CN113202137A - Row pile retaining wall with permanent retaining structure and construction method - Google Patents

Row pile retaining wall with permanent retaining structure and construction method Download PDF

Info

Publication number
CN113202137A
CN113202137A CN202010416672.6A CN202010416672A CN113202137A CN 113202137 A CN113202137 A CN 113202137A CN 202010416672 A CN202010416672 A CN 202010416672A CN 113202137 A CN113202137 A CN 113202137A
Authority
CN
China
Prior art keywords
pile
concrete
cast
reinforcing
bored
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202010416672.6A
Other languages
Chinese (zh)
Inventor
苏伟
崔维孝
黄建川
张青波
曹佳宁
周斌
张凤维
朱洪伟
张高帅
李文才
白昱
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Railway Design Corp
Original Assignee
China Railway Design Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Railway Design Corp filed Critical China Railway Design Corp
Priority to CN202010416672.6A priority Critical patent/CN113202137A/en
Publication of CN113202137A publication Critical patent/CN113202137A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D29/00Independent underground or underwater structures; Retaining walls
    • E02D29/02Retaining or protecting walls
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D29/00Independent underground or underwater structures; Retaining walls
    • E02D29/02Retaining or protecting walls
    • E02D29/0258Retaining or protecting walls characterised by constructional features
    • E02D29/0275Retaining or protecting walls characterised by constructional features cast in situ
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D3/00Improving or preserving soil or rock, e.g. preserving permafrost soil
    • E02D3/02Improving by compacting
    • E02D3/10Improving by compacting by watering, draining, de-aerating or blasting, e.g. by installing sand or wick drains
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2300/00Materials
    • E02D2300/0004Synthetics
    • E02D2300/0018Cement used as binder
    • E02D2300/002Concrete

Landscapes

  • Engineering & Computer Science (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • Structural Engineering (AREA)
  • Environmental & Geological Engineering (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Agronomy & Crop Science (AREA)
  • Soil Sciences (AREA)
  • Bulkheads Adapted To Foundation Construction (AREA)

Abstract

The invention provides a row pile retaining wall with a permanent retaining structure, which comprises cast-in-situ bored piles, wherein the cast-in-situ bored piles are of a cylindrical structure, a crown beam is arranged at the top of each cast-in-situ bored pile, a reverse filtering layer is arranged between every two adjacent cast-in-situ bored piles, concrete panels are vertically arranged on the outer sides of the cast-in-situ bored piles and the outer sides of the reverse filtering layers, concrete cushions are horizontally arranged at the bottoms of the reverse filtering layers and the concrete panels, reinforcing mesh sheets are vertically arranged inside the concrete panels, a plurality of reinforcing ribs are equidistantly arranged on the reinforcing mesh sheets, water drainage holes are formed in the concrete panels and between every two adjacent cast-in-situ bored piles, and expansion joints are arranged on the concrete cushions, the concrete panels and the crown beam at intervals of about 10m and between the cast-in-situ bored piles. The reinforcing mesh is provided with a plurality of reinforcing ribs at equal intervals from top to bottom. The invention enables a user to use conventional equipment to carry out mechanical construction, has the characteristics of safety, reliability, high construction efficiency and low construction risk, and has popularization and application values.

Description

Row pile retaining wall with permanent retaining structure and construction method
Technical Field
The invention belongs to the field of retaining walls, and particularly relates to a row pile retaining wall with a permanent retaining structure and a construction method.
Background
The expansive rock soil is a special rock soil with the characteristics of repeated expansion and contraction, lower strength, more cracks and the like, has poor engineering properties, has extremely large change of mechanical properties after meeting water, and is very easy to cause disasters such as collapse, landslide and the like. According to the design specification of railway subgrade, the design of the expansive soil cutting slope follows the principle of combining the slope slowing rate, the wide platform, the reinforced slope toe and the proper slope protection. Usually, the toe reinforcement retaining structure is a rectangular sheet pile wall or a gravity retaining wall.
The gravity type retaining wall has no pre-reinforcing effect, a foundation pit needs to be excavated during construction, a temporary side slope is easy to collapse, and groove jumping excavation or temporary reinforcing measures need to be taken. The sheet pile wall has the pre-reinforcing effect, generally needs to adopt the mode construction of manual hole digging, and construction safety risk is higher relatively.
Disclosure of Invention
The invention aims to provide a row pile retaining wall with a permanent retaining structure and a construction method, which are particularly suitable for a user to use conventional equipment for construction and have the characteristics of safety, reliability, high construction efficiency and low construction risk.
In order to solve the technical problems, the invention adopts the technical scheme that: the row pile retaining wall comprises bored piles, each bored pile is of a cylindrical structure, a crown beam is arranged at the top of each bored pile, a reverse filter layer is arranged between every two adjacent bored piles, concrete panels are vertically arranged on the outer sides of the bored piles and the outer sides of the reverse filter layers, concrete cushions are horizontally arranged at the bottoms of the reverse filter layers and the concrete panels, reinforcing mesh sheets are vertically arranged inside the concrete panels and are positioned in the concrete panels, the free ends of the bottoms of the reinforcing mesh sheets are inserted into the concrete cushions, the tops of the reinforcing mesh sheets extend into the crown beams and are bound and connected with the reinforcing bars of the crown beams, a plurality of implanted reinforcing bars are arranged on the bored piles at equal intervals, a plurality of reinforcing ribs are arranged on the reinforcing mesh sheets at equal intervals, a water drainage hole is arranged on each concrete panel and between every two adjacent bored piles, each concrete cushion layer is formed by connecting the concrete panels, Expansion joints are arranged on the concrete panel and the crown beam every 10m or so and between the cast-in-situ bored piles. Reinforcing bar net piece from top to bottom the equidistance is provided with a plurality of strengthening ribs, and each implantation reinforcing bar all is located the strengthening rib by. The inverted filter layer is 0.5m thick sand filled with pebbles. The filling material in the expansion joint is asphalt reinforcement, and the filling amount of the asphalt reinforcement is at least 0.2 m. The filling material in the expansion joint is an asphalt wood board, and the filling amount of the asphalt wood board is at least 0.2 m.
The concrete construction method comprises the following steps:
firstly, excavating cutting side slopes and pile top platforms;
step two, constructing a cast-in-situ bored pile;
excavating the soil above the pile top to 10cm below the pile top, and excavating the soil before and among the piles to the bottom of the concrete cushion;
step four, constructing a concrete cushion layer between the piles;
step five, filling a reverse filtering layer from bottom to top in a layered manner;
step six, drilling holes at the designed position, implanting reinforcing steel bars, installing reinforcing steel bar meshes, and pre-burying drainage holes;
step seven, pouring panel concrete after the pile body deforms stably;
and step eight, constructing the crown beam to enable the crown beam to be flush with the wall top platform.
In the using process, after a user excavates the pile top platform, a cutting slope is excavated on one side of the pile top platform, firstly, a conventional machine is adopted to construct a bored pile, then, a soil body in front of the pile is excavated, and the bored pile can play a role in pre-reinforcement, so that the safety risk during construction is reduced, and the construction efficiency is improved; a bagged sand-pebble inverted filter layer with the thickness of 0.5m arranged between the cast-in-situ bored piles can effectively buffer the expansion and contraction deformation of expansive soil; the steel bar net piece in the concrete panel is connected with the cast-in-situ bored pile through the embedded steel bars of the pile body, so that the cast-in-situ formwork can be erected and poured, the appearance is ensured to be neat, and the steel bar net piece is bound and connected with the crown beam steel bars, so that the integrity is good; drainage holes are formed in the concrete panel between the bored piles to ensure smooth drainage; the expansion joint and the water drainage hole are arranged in a staggered mode, and good using effect is guaranteed.
The invention has the advantages and positive effects that: by adopting the technical scheme, a user can use conventional equipment to carry out mechanical construction, and the method has the characteristics of safety, reliability, high construction efficiency and low construction risk and has popularization and application values; the invention has simple structure, convenient maintenance and low processing cost.
Drawings
FIG. 1 is a schematic cross-sectional structural view of the present invention;
FIG. 2 is a schematic top view of the present invention;
fig. 3 is a schematic view of the connection structure of the steel mesh and the implanted steel bar according to the present invention.
In the figure:
1. cast-in-situ bored pile 2, crown beam 3 and inverted filter
4. Concrete panel 5, water drainage hole 6 and concrete cushion layer
7. Implanted steel bar 8, steel bar net piece 9 and side ditch platform
10. Side ditch 11, wall top platform 12, cutting slope
13. Expansion joint 14 and reinforcing rib
Detailed Description
As shown in figures 1-3, the invention relates to a row pile retaining wall with a permanent retaining structure and a construction method thereof, the row pile retaining wall comprises bored piles 1, the bored piles 1 are of a cylindrical structure, a crown beam 2 is arranged at the top of the bored piles 1, an inverted filter layer 3 is arranged between adjacent bored piles 1, concrete panels 4 are vertically arranged at the outer sides of the bored piles 1 and the outer sides of the inverted filter layers 3, concrete cushions 6 are horizontally arranged at the bottoms of the inverted filter layers 3 and the concrete panels 4, reinforcing mesh sheets 8 are vertically arranged in the concrete panels 4, the reinforcing mesh sheets 8 are positioned in the concrete panels 4, the free ends of the bottoms of the reinforcing mesh sheets 8 are inserted into the concrete cushions 6, the tops of the reinforcing mesh sheets 8 extend into the crown beam 2 and are bound and connected with the reinforcing steel bars of the crown beam 2, a plurality of implanted reinforcing steel bars 7 are equidistantly arranged on the bored piles 1, a plurality of reinforcing mesh sheets 14 are equidistantly arranged on the reinforcing mesh sheets 8, and a water drainage hole 5 is formed in the concrete panel 4 and between the adjacent cast-in-situ bored piles 1, and expansion joints 13 are formed in the concrete cushion 6, the concrete panel 4 and the crown beam 2 every 10m or so and between the cast-in-situ bored piles 1. The reinforcing mesh 8 is provided with a plurality of reinforcing ribs 14 from top to bottom at equal intervals, and each implanted reinforcing steel bar 7 is positioned beside the reinforcing rib 14. The inverted filter layer 3 is 0.5m thick bagged sand with pebbles. The filling material in the expansion joint 13 is asphalt reinforcement, and the filling amount of the asphalt reinforcement is at least 0.2 m. The filling material in the expansion joint 13 is asphalt wood plate, and the filling amount of the asphalt wood plate is at least 0.2 m.
In the using process, after a user excavates the pile top platform 11, a cutting slope 12 is excavated on one side of the pile top platform 11, the bored pile 1 is constructed by adopting a conventional machine, then the soil body in front of the pile is excavated, and the bored pile 1 can play a role of pre-reinforcement, so that the safety risk during construction is reduced, and the construction efficiency is improved; a bagged sand-pebble inverted filter layer 3 with the thickness of 0.5m arranged between the cast-in-situ bored piles 1 can effectively buffer the expansion and contraction deformation of expansive soil; the reinforcing mesh 8 in the concrete panel 4 is connected with the cast-in-situ bored pile 1 through the embedded reinforcing steel bars 7 of the pile body, so that the cast-in-situ formwork erection can be performed, the appearance is ensured to be neat, and the reinforcing mesh 8 is bound and connected with the reinforcing steel bars of the crown beam 2, so that the integrity is good; drainage holes 5 are formed in the concrete panels 4 among the cast-in-situ bored piles 1, so that smooth drainage is ensured; the expansion joint 13 and the drainage hole 5 are arranged in a staggered mode, and good using effect is guaranteed.
While one embodiment of the present invention has been described in detail, the description is only a preferred embodiment of the present invention and should not be taken as limiting the scope of the invention. All equivalent changes and modifications made within the scope of the present invention shall fall within the scope of the present invention.

Claims (6)

1.一种永久支挡结构的排桩挡土墙,其特征在于:包括钻孔灌注桩(1),所述钻孔灌注桩(1)为圆柱体结构,所述钻孔灌注桩(1)顶部设置有一冠梁(2),相邻的所述钻孔灌注桩(1)之间设置有反滤层(3),所述钻孔灌注桩(1)的外侧及所述反滤层(3)外侧竖向设置有混凝土面板(4),所述反滤层(3)和所述混凝土面板(4)底部均水平设置有混凝土垫层(6),所述混凝土面板(4)内部竖直设置有钢筋网片(8),所述钢筋网片(8)位于所述混凝土面板(4)内,所述钢筋网片(8)底部自由端插入所述混凝土垫层(6)中,且所述钢筋网片(8)顶部伸入所述冠梁(2)内,并与所述冠梁(2)钢筋绑扎连接,所述钻孔灌注桩(1)上等间距设置若干植入钢筋(7),所述钢筋网片(8)上等距设置有若干加强筋(14),所述混凝土面板(4)上且位于相邻的所述钻孔灌注桩(1)之间设置有泄水孔(5),所述混凝土垫层(6)、所述混凝土面板(4)及所述冠梁(2)上每隔10m左右且位于所述钻孔灌注桩(1)之间设置有伸缩缝(13)。1. a pile row retaining wall of a permanent retaining structure is characterized in that: comprise bored cast-in-place pile (1), described bored cast-in-place pile (1) is a cylindrical structure, and described bored cast-in-situ pile (1) ) is provided with a crown beam (2) at the top, a reverse filter layer (3) is provided between the adjacent bored piles (1), the outer side of the bored pile (1) and the reverse filter layer (3) A concrete panel (4) is arranged vertically on the outside, a concrete cushion (6) is horizontally arranged at the bottom of the filter layer (3) and the concrete panel (4), and a concrete cushion (6) is arranged inside the concrete panel (4). A reinforcing mesh sheet (8) is vertically arranged, the reinforcing mesh sheet (8) is located in the concrete panel (4), and the bottom free end of the reinforcing mesh sheet (8) is inserted into the concrete cushion (6) , and the top of the reinforced mesh (8) extends into the crown beam (2), and is connected with the crown beam (2) by reinforcing bars, and several plantings are arranged at equal intervals on the bored pile (1). Reinforcing steel bars (7), several reinforcing bars (14) are provided at equal distances on the reinforcing bar mesh (8), and the concrete panels (4) are located between the adjacent bored piles (1). Drain holes (5) are provided, and the concrete cushion (6), the concrete panel (4) and the crown beam (2) are located at intervals of about 10m and are located between the bored piles (1). An expansion joint (13) is arranged between them. 2.根据权利要求1所述的永久支挡结构的排桩挡土墙,其特征在于:所述钢筋网片(8)由上至下等距设置有若干加强筋(14),各个所述植入钢筋(7)均位于所述加强筋(14)旁。2. The pile-row retaining wall of a permanent retaining structure according to claim 1, characterized in that: the steel mesh (8) is provided with a plurality of reinforcing ribs (14) equidistantly from top to bottom, and each said The implanted reinforcing bars (7) are all located beside the reinforcing bars (14). 3.根据权利要求1所述的永久支挡结构的排桩挡土墙,其特征在于:所述反滤层(3)为0.5m厚袋装砂夹卵石。3 . The pile-row retaining wall of a permanent retaining structure according to claim 1 , wherein the anti-filter layer ( 3 ) is 0.5 m thick bagged sand with pebbles. 4 . 4.根据权利要求1所述的永久支挡结构的排桩挡土墙,其特征在于:所述伸缩缝(13)内填充物为沥青麻筋,且所述沥青麻筋填入至少为0.2m。4. The pile-row retaining wall of the permanent retaining structure according to claim 1, characterized in that: the filler in the expansion joint (13) is asphalt hemp, and the asphalt hemp is filled with at least 0.2 m. 5.根据权利要求1所述的永久支挡结构的排桩挡土墙,其特征在于:所述伸缩缝(13)内填充物为沥青木板,且所述沥青木板填入至少为0.2m。5 . The pile-row retaining wall of a permanent retaining structure according to claim 1 , wherein the filler in the expansion joint ( 13 ) is an asphalt board, and the asphalt board is filled in at least 0.2 m. 6 . 6.根据权利要求1-5所述的永久支挡结构的排桩挡土墙的施工方法,其特征在于:步骤如下:6. the construction method of the pile row retaining wall of permanent support structure according to claim 1-5, is characterized in that: step is as follows: 步骤一,开挖路堑边坡(12)及桩顶平台(11);Step 1, excavate the cutting slope (12) and the pile top platform (11); 步骤二,施做钻孔灌注桩(1);Step 2, make a bored cast-in-place pile (1); 步骤三,开挖桩顶以上土体至桩顶以下10cm,开挖桩前及桩间土体至混凝土垫层(6)底部;Step 3, excavate the soil above the top of the pile to 10cm below the top of the pile, and excavate the soil before and between the piles to the bottom of the concrete cushion (6); 步骤四,施做桩间的混凝土垫层(6);Step 4, make concrete cushion (6) between piles; 步骤五,由下至上分层填充反滤层(3);Step 5, fill the reverse filter layer (3) in layers from bottom to top; 步骤六,在设计位置钻孔植入钢筋(7),并安装钢筋网片,预埋泄水孔(5);Step 6: Drilling holes and implanting steel bars (7) at the design positions, installing steel mesh sheets, and pre-embedding the scuppers (5); 步骤七,桩体变形稳定后,浇筑面板混凝土;Step 7: After the pile body is deformed and stabilized, the face concrete is poured; 步骤八,施做冠梁(2),使得冠梁与墙顶平台平齐。Step 8, make crown beams (2) so that the crown beams are flush with the platform on the top of the wall.
CN202010416672.6A 2020-05-16 2020-05-16 Row pile retaining wall with permanent retaining structure and construction method Pending CN113202137A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202010416672.6A CN113202137A (en) 2020-05-16 2020-05-16 Row pile retaining wall with permanent retaining structure and construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202010416672.6A CN113202137A (en) 2020-05-16 2020-05-16 Row pile retaining wall with permanent retaining structure and construction method

Publications (1)

Publication Number Publication Date
CN113202137A true CN113202137A (en) 2021-08-03

Family

ID=77024936

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202010416672.6A Pending CN113202137A (en) 2020-05-16 2020-05-16 Row pile retaining wall with permanent retaining structure and construction method

Country Status (1)

Country Link
CN (1) CN113202137A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113482012A (en) * 2021-08-20 2021-10-08 中亿丰建设集团股份有限公司 Wall-mounted wing wall combined with cast-in-situ bored pile foundation pit support and construction method thereof

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN201762710U (en) * 2010-06-30 2011-03-16 中国京冶工程技术有限公司 Pile-wall combined enclosing structure for offshore deep foundation pit
CN104727302A (en) * 2015-03-30 2015-06-24 中铁七局集团第三工程有限公司 Cast-in-place construction process for inter-pile board wall between slide-resistant piles
CN207672558U (en) * 2017-12-14 2018-07-31 中铁二院工程集团有限责任公司 A kind of railroad embankment Pile slab-wall structure
CN109914445A (en) * 2019-04-11 2019-06-21 中铁第六勘察设计院集团有限公司 A kind of level of ground water alternately changes the construction method of location expensive soil cutting
CN110258587A (en) * 2019-05-07 2019-09-20 中铁第四勘察设计院集团有限公司 The branch mark structure and construction method of side slope
CN212561606U (en) * 2020-05-16 2021-02-19 中国铁路设计集团有限公司 Row pile retaining wall with permanent retaining structure

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN201762710U (en) * 2010-06-30 2011-03-16 中国京冶工程技术有限公司 Pile-wall combined enclosing structure for offshore deep foundation pit
CN104727302A (en) * 2015-03-30 2015-06-24 中铁七局集团第三工程有限公司 Cast-in-place construction process for inter-pile board wall between slide-resistant piles
CN207672558U (en) * 2017-12-14 2018-07-31 中铁二院工程集团有限责任公司 A kind of railroad embankment Pile slab-wall structure
CN109914445A (en) * 2019-04-11 2019-06-21 中铁第六勘察设计院集团有限公司 A kind of level of ground water alternately changes the construction method of location expensive soil cutting
CN110258587A (en) * 2019-05-07 2019-09-20 中铁第四勘察设计院集团有限公司 The branch mark structure and construction method of side slope
CN212561606U (en) * 2020-05-16 2021-02-19 中国铁路设计集团有限公司 Row pile retaining wall with permanent retaining structure

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113482012A (en) * 2021-08-20 2021-10-08 中亿丰建设集团股份有限公司 Wall-mounted wing wall combined with cast-in-situ bored pile foundation pit support and construction method thereof

Similar Documents

Publication Publication Date Title
CN212561606U (en) Row pile retaining wall with permanent retaining structure
AU2016221315B2 (en) A retaining wall method of precast block to prevent landslide
CN102966119A (en) Geogrid reinforced wall and construction method thereof
CN207003499U (en) A kind of anti-floating lifting device of underground tunnel upper excavation of foundation pit
CN110777806B (en) Multi-connecting-rod plane frame permanent supporting structure and construction process thereof
KR101041274B1 (en) Synthetic Grouting Fixture Structure and Construction Method
CN114775352A (en) A kind of widening structure and construction method of existing roadbed and embankment section near the river
CN209855277U (en) Conversion layer structure for underground added layer of existing building
CN111236259A (en) Combined lattice-shaped prefabricated pile wall supporting structure and construction method thereof
CN204753262U (en) A fender structure on high embankment of existing railway
WO2011009219A1 (en) Shoring free excavation and basement construction apparatus and method
CN110644297A (en) A kind of anti-bulge support structure and construction method of ballastless track high-speed railway
CN113202137A (en) Row pile retaining wall with permanent retaining structure and construction method
CN212375698U (en) An ultra-high composite reinforced soil abutment combined with prestressed anchor cables
CN118461623A (en) Foundation pit supporting method close to existing building
CN112323816A (en) Unloading type combined retaining structure and construction method thereof
CN110685287A (en) Double-row pile foundation pit supporting system with drainage ditch and retaining wall and construction method
CN220486172U (en) Reinforcing structure suitable for mountain area highway bank section disaster damage roadbed
CN109137887B (en) An underground continuous wall structure, construction method and support device passing through a karst cave
CN217629947U (en) Foundation pit support structure
CN215483000U (en) Combined foundation pit supporting structure
CN116607562A (en) Grouting sheet stone retaining wall body grouting reinforcement structure and construction method thereof
CN214061687U (en) Flexible water-permeable cutting retaining wall
CN218373887U (en) Unloading type combined retaining structure
CN107447794A (en) The anti-floating of excavation pit plays construction method in a kind of subway protection region

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination