CN107355233B - A kind of underground chamber and Cavity Construction method - Google Patents
A kind of underground chamber and Cavity Construction method Download PDFInfo
- Publication number
- CN107355233B CN107355233B CN201710763002.XA CN201710763002A CN107355233B CN 107355233 B CN107355233 B CN 107355233B CN 201710763002 A CN201710763002 A CN 201710763002A CN 107355233 B CN107355233 B CN 107355233B
- Authority
- CN
- China
- Prior art keywords
- gallery
- cavern
- periphery
- main
- main cavern
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH DRILLING; MINING
- E21D—SHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
- E21D9/00—Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries
- E21D9/14—Layout of tunnels or galleries; Constructional features of tunnels or galleries, not otherwise provided for, e.g. portals, day-light attenuation at tunnel openings
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH DRILLING; MINING
- E21D—SHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
- E21D11/00—Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
- E21D11/04—Lining with building materials
- E21D11/10—Lining with building materials with concrete cast in situ; Shuttering also lost shutterings, e.g. made of blocks, of metal plates or other equipment adapted therefor
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH DRILLING; MINING
- E21D—SHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
- E21D20/00—Setting anchoring-bolts
- E21D20/003—Machines for drilling anchor holes and setting anchor bolts
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH DRILLING; MINING
- E21F—SAFETY DEVICES, TRANSPORT, FILLING-UP, RESCUE, VENTILATION, OR DRAINING IN OR OF MINES OR TUNNELS
- E21F16/00—Drainage
Abstract
The present invention relates to rich groundwaters, the construction method of the large underground hole of wall rock geology condition difference, advance water discharge is carried out using underground gallery, the main surrounding rock of chamber of advance reinforcement, advance exploration, the multipurpose layout pattern and method monitored in advance, i.e. Main Underground cavern crown and with abutment wall periphery arranging multiplayer underground gallery, it first constructs before main cavern excavation the gallery of crown and abutment wall periphery, main cavern periphery groundwater level is reduced in advance using the underground gallery after construction, preconsolidation grouting is carried out to main cavern's crown country rock using top layer gallery and abutment wall periphery gallery simultaneously, prestress anchorage cable drilling construction and monitoring instrument it is pre-buried.This layout pattern and method, both influence of the underground water to surrounding rock of chamber had been can effectively reduce, it again can be by carrying out consolidation by grouting country rock to main cavern in advance, shorten anchor cable construction time performance anchor cable immediate support effect, and pass through advanced pre-buried monitoring instrument, the deformation measurement data for promptly and accurately acquiring and grasping country rock during main cavern excavation comes design and construction, the powerful guarantee safety and stability of Cavity Construction phase and runtime.
Description
Technical field
The invention belongs to underground engineering field, it is related to a kind of underground chamber and Cavity Construction method more particularly to ground
It is lauched the large underground hole and its construction method of abundant wall rock geology condition difference.
Background technique
Currently, the Cavity Construction poor for rich groundwater, wall rock condition, is mainly arranged on underground chamber periphery
Underground gallery is permanently drained;In terms of supporting on the basis of using bolt-spary supports, it is also necessary to which arrangement prestress anchor cable is controlled
The surrouding rock deformation of cavity preparation room.In conventional way, the arrangement of underground gallery is solely for permanently draining, and underground gallery construct it is past
Toward main cavern con struction is lagged behind, the groundwater level for reducing main cavern periphery in advance is not considered, construction time main surrounding rock of chamber is often
Easily there is phenomena such as landslide due to being influenced by underground water;Prestress anchorage cable mostly uses end anchor cable, anchor cable construction and monitor
When device embedded will often wait main cavern excavation, then row construction, such cable bolting timeliness is poor, the number that monitoring instrument is collected into
According to lag, it can not really reflect the case where surrouding rock deformation, cable bolting often occur not in time, cause to go out during main cavern excavation
The case where showing excessive surrouding rock deformation and unstability occurs, and also usually can not be grasped in time cavern due to the embedded lag of monitoring instrument and be enclosed
The deformation of rock leads to not the stable case for prejudging surrounding rock of chamber, and landslide phenomenon occurs, influences construction time safety, and
Cause construction delay.
Summary of the invention
In view of the deficiencies of the prior art, the present invention provides a kind of structurally stable underground chamber and its construction method.
The technical solution of the present invention is as follows: a kind of underground chamber, including main cavern, the vault of the main cavern are equipped with grouting and add
Gu Qu, the top in consolidation by grouting area are equipped with the row's of filling gallery, are equipped with prestress anchorage cable between filling row's gallery and consolidation by grouting area;
The two sides of the main cavern be respectively equipped with it is a plurality of be from top to bottom arranged successively periphery gallery, a plurality of periphery gallery and main cavern
Abutment wall between be equipped with prestress anchorage cable.
Generally, consolidation by grouting area, which is directed toward in the rock stratum of corresponding region, injects the materials such as Grouting Cement, is somebody's turn to do with playing to reinforce
The effect in region.
In the present invention, pass through the setting in consolidation by grouting area, it is ensured that the intensity of main cavern crown area country rock prevents out
Occurs cave in accident when digging;Meanwhile setting fills row's gallery above consolidation by grouting area, can facilitate grouting on the one hand to form grouting
Stabilization zone, on the other hand, it is convenient to prestress anchorage cable be set between the row's of filling gallery and consolidation by grouting area, constrain corresponding country rock
Deformation, improve the structural stability of main cavern, while prestress anchorage cable generates draw to consolidation by grouting area, reduce grouting
Pressure of the stabilization zone to main cavern's abutment wall position;It, can be to main cavern by the setting of periphery gallery and related prestress anchorage cable
Country rock near abutment wall generates support action, and limiting surrouding rock deformation with the soundness of the main cavern of comprehensive promotion prevents main hole
There is cave in accident in room excavation and subsequent use process.
Further, two filling are equipped with above main cavern's vault and arrange gallerys, two fillings are set and arrange gallerys, it is corresponding can
Mostly two prestress anchorage cables of setting, to increase the restraining force to vault country rock.
Further, the row's of filling gallery, which is equipped with to filling, arranges the drainage hole curtain extended above gallery.
Further, it is connected between the adjacent periphery gallery by drainage hole curtain.
By the setting of drainage hole curtain, main cavern periphery level of ground water can be reduced, reduces underground water to main cavern excavation
It influences, stablizes conducive to the excavation of main cavern;It after the completion of excavation, can play a protective role to main cavern, reduce water to main cavern
Infiltration.
Further, the main cavern includes multiple sub- caverns, and periphery gallery, this week are equipped between the adjacent sub- cavern
It is respectively equipped with prestress anchorage cable between side corner road and the abutment wall of adjacent each sub- cavern, improves the stable degree of cavern's abutment wall.
Further, the prestress anchorage cable is prestressing force two-ended cables.
Further, the filling row gallery is 10 ~ 35m at a distance from main cavern's vault;The periphery gallery and main cavern
The distance between abutment wall is 30 ~ 60m.Preferably, the filling row gallery is 20 ~ 30m at a distance from main cavern's vault;The periphery
The distance between gallery and main cavern's abutment wall are 40 ~ 50m.
In order to obtain the information such as main surrounding rock of chamber deformation, monitoring is embedded between the periphery gallery and the abutment wall of main cavern
Instrument;Monitor is embedded between filling row's gallery and main cavern's vault.Preferably, the monitor is multipoint displacement meter.
Based on the same inventive concept, the present invention also provides a kind of construction methods of underground chamber, include the following steps:
S1, before excavating main cavern, filling row's gallery is being dug above main cavern's vault wait excavate;Meanwhile wait excavate
The abutment wall two sides of main cavern dig the 1st layer of periphery gallery respectively, which is located at the depth model that main cavern's vault is crossed over
In enclosing, top layer gallery is dug above the periphery gallery;
S2, each top layer gallery and filling arrange what the rock stratum being arranged above corresponding gallery on gallery extended in step sl respectively
Drainage hole curtain is arranged in drainage hole curtain between top layer gallery and the 1st layer of periphery gallery;
S3, the country rock progress preconsolidation grouting construction for excavating main cavern's vault excavation line or more is treated by the row's of filling gallery,
Consolidation by grouting area is obtained above main cavern's vault;
S4, the pore-creating and the prestressed anchor that excavate main cavern and carry out prestress anchorage cable are treated by periphery gallery and the row's of filling gallery
The construction of pier;Then, start to excavate main cavern, after excavating prestress anchorage cable corresponding site, be reeved and to prestressing force
Anchor cable carries out tensioning fixation;While excavating main cavern, digs below the 1st layer of periphery gallery and successively from top to bottom to arrange
2nd layer ... n-th layer periphery gallery, and drainage hole curtain is set between upper and lower adjacent periphery gallery;Wherein, N be not less than
2 positive integer.
Further, it when carrying out excavation construction to periphery gallery and the row's of filling gallery, is mentioned by periphery gallery and the row's of filling gallery
It is preceding pre-buried for collecting the monitor of main surrounding rock of chamber geological information, such as multipoint displacement meter.In this way after main cavern excavation can and
When collect the information such as surrouding rock deformation, can be to evaluate and adjustment support parameters and working measure provide foundation, effectively control is led
The surrouding rock deformation of cavern, it is ensured that the safety and stability of main cavern excavation.
Using method of the invention, advanced excavation fills row's gallery, top layer gallery and the 1st layer of periphery gallery in step S1, and
Setting related drain hole curtain in step s 2, can reduce main cavern periphery level of ground water in advance, reduce underground water to main cavern
The influence of excavation, the excavation for being conducive to main cavern are stablized;In step S3, by grouting construction, main cavern's crown can be effectively improved
The integrity and stability of country rock avoids crown country rock when main cavern excavation from big landslide and chip off-falling occur;In step S4, opening
Just the pore-creating and the construction of prestressing force anchor pier that prestress anchorage cable is carried out before the cavern Wa Zhu, to main cavern excavation to anchor cable corresponding site
After certain distance, the effect of can quickly reeving and carry out the tensioning fixation of anchor cable, anchor cable immediate support can be given full play to, in time about
The deformation of beam country rock, to ensuring that it is highly beneficial that the excavation of main cavern is stablized.
After constructing in advance to underground galleries such as periphery gallery, top layer gallerys, collects underground gallery and excavate the geology disclosed
Situation is deduced the country rock information of main cavern by this, is conducive to check supporting parameter and arrangement and method for construction.
The present invention is constructed in advance in underground chamber building process, using underground gallery, and combines advance water discharge, advanced right
Main cavern's consolidation by grouting, advance exploration and the multipurpose layout pattern and construction method monitored in advance are realized advanced to main cavern
Draining, advance grouting reinforcing, advance exploration and advanced monitoring.This layout pattern and method utilize main cavern's crown and periphery cloth
It sets multi-layer underground gallery (top layer gallery, the row's of filling gallery and periphery gallery) and construction is completed in advance before main cavern excavation, first benefit
The main cavern region of excavation is treated with the underground gallery after construction and neighbouring rock stratum carries out advance water discharge, i.e., is reduced by gallery wait open
The groundwater level on the cavern Wa Zhu periphery effectively reduces influence of the underground water to main cavern excavation, guarantees the excavation of main cavern
Stablize;It recycles the row's of filling gallery to carry out preconsolidation grouting advance reinforcement to main cavern, improves the integrality of main cavern's crown country rock
And stability, avoid crown country rock when main cavern excavation from big landslide and chip off-falling occur;Then the underground corridor after construction is recycled
Road in advance drills the construction of (anchor pier) to prestress anchorage cable, can give full play to the timeliness of cable bolting, constraint is enclosed in time
The deformation of rock, it is ensured that the excavation of main cavern is stablized;It collects geological information and mentions in related underground gallery after finally recycling construction
Preceding pre-buried monitoring instrument, thus it is speculated that the cavern Chu Zhu geological information and in time acquisition monitoring data can be evaluation and adjustment design of its support ginseng
Several and working measure provides foundation, to efficiently control the surrouding rock deformation of main cavern and ensuring that the safety and stability of main cavern excavation mentions
For favorably ensureing.
Underground chamber stabilized structure of the invention, runtime safety and stability;The construction method of offer through the invention, can
It realizes and the safety and stability of main cavern is excavated, save the construction time, the safety of effective guarantee Cavity Construction phase and runtime
Stablize.
Detailed description of the invention
Fig. 1 is the gallery and drainage hole curtain arrangement schematic diagram of the first embodiment of the invention.
Fig. 2 is main cavern's crown preconsolidation grouting arrangement schematic diagram of the first embodiment of the invention.
Fig. 3 is the prestress anchorage cable arrangement schematic diagram of the first embodiment of the invention.
Fig. 4 is that the underground gallery monitor of the first embodiment of the invention buries situation schematic diagram.
Wherein: 1-top layer gallery;2-the row's of filling gallerys;3-periphery gallerys;4-drainage hole curtains;5-consolidation by grouting areas;
6-prestress anchorage cables;7-monitoring instruments;8-main caverns;801, the sub- cavern 802-.
Specific embodiment
For sake of convenience, such as there are "upper", "lower", "left", "right" printed words in the present invention, only indicate and attached drawing itself
Upper and lower, left and right direction is consistent, does not play restriction effect to structure.
Next by taking the building of the underground chamber of certain hydroenergy storage station as an example below invention is further explained, the power station
Underground Powerhouse condition is poor, and surrounding rock category is III~IV class, and V class of part, country rock is relatively more broken, and underground water ten
Divide abundant.
The vault of the underground chamber, including main cavern 8, the main cavern 8 is equipped with consolidation by grouting area 5, consolidation by grouting area 5
Top is equipped with the row's of filling gallery 2, is equipped with prestress anchorage cable 6 between filling row's gallery 2 and consolidation by grouting area 5;The main cavern 8
Two sides are respectively equipped with 3 and are from top to bottom arranged successively periphery gallery 3, the side of first layer and second layer periphery gallery 3 and main cavern 8
Prestress anchorage cable 6 is equipped between wall.
Wherein, the main cavern 8 includes cavern's 801 and sub- cavern 802, and two filling rows are equipped with above each sub- cavern's vault
Gallery 2(is shown in Fig. 2).
The row's of filling gallery 2, which is equipped with to filling, arranges the drainage hole curtain 4 extended above gallery;The adjacent periphery gallery 3 it
Between by drainage hole curtain 4 be connected to (see figure 1).
Be equipped with a periphery gallery 3 between the adjacent sub- cavern, the abutment wall of the periphery gallery 3 and adjacent each sub- cavern it
Between be respectively equipped with prestress anchorage cable 6(and see Fig. 3).
The prestress anchorage cable 6 is prestressing force two-ended cables.
Monitor 7 is embedded between the periphery gallery 3 and the abutment wall of main cavern 8;Filling row's gallery 2 and main cavern 8
It is embedded with monitor 7(between vault and sees Fig. 4).
For the overall stability for improving workshop surrounding rock of chamber, 4 are arranged in the above 25m of workshop crown and away from the periphery abutment wall 45m
Layer underground gallery (is from top to bottom followed successively by top layer gallery 1 and filling the row gallery 2, periphery gallery 3 concordant with top layer gallery), underground
Gallery arrangement, which fully considers, reduces workshop underground water, preconsolidation grouting can be carried out to main building and main transformer hole crown country rock not only but also
The rapid construction and many-sided comprehensive function such as pre-buried monitoring instrument in advance for facilitating prestress anchorage cable, in underground gallery layout design
When fully consider that the suitable elevation of gallery and position and top layer fill row's gallery cross dimensions etc., underground gallery arrangement should have
The standby condition constructed in advance, has carry out mentioning for preconsolidation grouting, prestress anchorage cable 6 and monitor 7 to main cavern's crown again
The condition and method of preceding construction.The underground gallery multipurpose layout pattern and method had both successfully solved underground water and had opened workshop
The influence of digging makes the entire digging process of workshop be substantially at dry environment construction, further through preconsolidation grouting, prestress anchorage cable
Immediate support and monitoring instrument shift to an earlier date pre-buried accurate grasp workshop surrouding rock deformation data, adjust supporting parameter in time and construction is arranged
It applies, efficiently controls the deformation of workshop surrounding rock of chamber, smoothly ensure that the safety and stability of workshop cavern excavation process.It is imitated from implementation
From the point of view of fruit, effect is more satisfactory, and main cavern excavation process does not occur landslide, chip off-falling phenomenon, and engineering carries out very smooth;Runtime
In, main cavern's structure performance is stablized, and does not occur abnormal phenomenon.
Claims (8)
1. a kind of construction method of underground chamber, which comprises the steps of:
S1, before excavating main cavern, filling row gallery (2) is being dug above main cavern's vault wait excavate;Meanwhile in master to be excavated
The abutment wall two sides of cavern dig the 1st layer of periphery gallery (3) respectively, which is located at the depth that main cavern's vault is crossed over
It spends in range, digs top layer gallery (1) above the periphery gallery (3);
S2, the rock stratum extension being arranged above corresponding gallery on gallery (2) is arranged in each top layer gallery (1) and filling in step sl respectively
Drainage hole curtain (4), between top layer gallery (1) and the 1st layer of periphery gallery (3) be arranged drainage hole curtain (4);
S3, the country rock that main cavern (8) the vault excavation line of excavation or more is treated by the row of filling gallery (2) carry out preconsolidation grouting and apply
Work obtains consolidation by grouting area (5) above main cavern's vault;
S4, the pore-creating and prestressing force anchor pier for excavating main cavern's progress prestress anchorage cable are treated by periphery gallery and the row's of filling gallery
Construction;Then, start to excavate main cavern, after excavating prestress anchorage cable corresponding site, be reeved and to prestress anchorage cable
(6) tensioning fixation is carried out;While excavating main cavern, digs below the 1st layer of periphery gallery and successively from top to bottom to arrange
2nd layer ... n-th layer periphery gallery, and drainage hole curtain is set between upper and lower adjacent periphery gallery;Wherein, N be not less than
2 positive integer.
2. the construction method of underground chamber according to claim 1, which is characterized in that periphery gallery and fill row gallery into
When row excavation construction, shifted to an earlier date by periphery gallery and the row's of filling gallery pre-buried for collecting the monitoring of main surrounding rock of chamber geological information
Instrument.
3. the construction method of underground chamber according to claim 1, which is characterized in that above main cavern (8) vault
Gallery (2) are arranged equipped with two fillings.
4. the construction method of underground chamber according to claim 1, which is characterized in that the adjacent periphery gallery (3) it
Between by drainage hole curtain (4) be connected to.
5. the construction method of underground chamber according to claim 1, which is characterized in that the main cavern (8) includes multiple
Sub- cavern (801;802), periphery gallery (3) is set to the adjacent sub- cavern (801;802) between, the periphery gallery (3) with
Adjacent each sub- cavern (801;802) prestress anchorage cable (6) are respectively equipped between abutment wall.
6. the construction method of described in any item underground chambers according to claim 1 ~ 5, which is characterized in that the prestress anchorage cable
It (6) is prestressing force two-ended cables.
7. the construction method of described in any item underground chambers according to claim 1 ~ 5, which is characterized in that gallery is arranged in the filling
It (2) is 10 ~ 35m at a distance from main cavern (8) vault;The distance between the periphery gallery (3) and main cavern (8) abutment wall are 30
~60m。
8. the construction method of described in any item underground chambers according to claim 1 ~ 5, which is characterized in that the periphery gallery
(3) it is embedded between the abutment wall of main cavern (8) monitor (7);It is buried between described filling row gallery (2) and main cavern (8) vault
Equipped with monitor (7).
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201710763002.XA CN107355233B (en) | 2017-08-30 | 2017-08-30 | A kind of underground chamber and Cavity Construction method |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201710763002.XA CN107355233B (en) | 2017-08-30 | 2017-08-30 | A kind of underground chamber and Cavity Construction method |
Publications (2)
Publication Number | Publication Date |
---|---|
CN107355233A CN107355233A (en) | 2017-11-17 |
CN107355233B true CN107355233B (en) | 2019-03-22 |
Family
ID=60290351
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201710763002.XA Active CN107355233B (en) | 2017-08-30 | 2017-08-30 | A kind of underground chamber and Cavity Construction method |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN107355233B (en) |
Families Citing this family (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN109184761B (en) * | 2018-10-29 | 2020-03-17 | 河南大有能源股份有限公司耿村煤矿 | Method for solving problem of reinforcing integrity of surrounding rock by deformation of two rock masses |
CN112195883B (en) * | 2020-07-02 | 2022-03-18 | 中国电建集团华东勘测设计研究院有限公司 | Arrangement structure and construction method of pressure pipeline and drainage gallery suitable for TBM construction |
CN112982371A (en) * | 2021-02-08 | 2021-06-18 | 中国电建集团北京勘测设计研究院有限公司 | Seepage-proofing method for large underground cavern by adopting advanced grouting sealing |
CN113089705B (en) * | 2021-04-21 | 2022-07-19 | 中国电建集团中南勘测设计研究院有限公司 | Underground cavern drainage system |
Citations (8)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN102654055A (en) * | 2012-05-21 | 2012-09-05 | 乐贵平 | Construction method for compound construction of large-scale underground space structure by holes, groove and piles |
CN103306682A (en) * | 2013-06-26 | 2013-09-18 | 中国水电顾问集团中南勘测设计研究院 | Long-span and high-side-wall underground space building and excavation support method thereof |
CN103321653A (en) * | 2013-06-27 | 2013-09-25 | 中国水电顾问集团成都勘测设计研究院 | Method of treating lining after collapse of underground cavern crown |
CN104453950A (en) * | 2014-12-29 | 2015-03-25 | 中国电建集团中南勘测设计研究院有限公司 | Underground cavity hanging concrete structure |
CN105201001A (en) * | 2015-10-10 | 2015-12-30 | 中国电建集团贵阳勘测设计研究院有限公司 | Composite seepage preventing structure for large karst cave in karst region and construction method thereof |
CN106640117A (en) * | 2017-03-08 | 2017-05-10 | 中国电建集团中南勘测设计研究院有限公司 | Underground cavern top arc structure, underground cavern and construction method of underground cavern |
CN106640118A (en) * | 2017-03-08 | 2017-05-10 | 中国电建集团中南勘测设计研究院有限公司 | Underground cavity arch crown structure, underground cavity and underground cavity construction method |
CN107044287A (en) * | 2017-03-06 | 2017-08-15 | 刘冲 | Colliery shaft station and the reinforcement means of track main entry |
-
2017
- 2017-08-30 CN CN201710763002.XA patent/CN107355233B/en active Active
Patent Citations (8)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN102654055A (en) * | 2012-05-21 | 2012-09-05 | 乐贵平 | Construction method for compound construction of large-scale underground space structure by holes, groove and piles |
CN103306682A (en) * | 2013-06-26 | 2013-09-18 | 中国水电顾问集团中南勘测设计研究院 | Long-span and high-side-wall underground space building and excavation support method thereof |
CN103321653A (en) * | 2013-06-27 | 2013-09-25 | 中国水电顾问集团成都勘测设计研究院 | Method of treating lining after collapse of underground cavern crown |
CN104453950A (en) * | 2014-12-29 | 2015-03-25 | 中国电建集团中南勘测设计研究院有限公司 | Underground cavity hanging concrete structure |
CN105201001A (en) * | 2015-10-10 | 2015-12-30 | 中国电建集团贵阳勘测设计研究院有限公司 | Composite seepage preventing structure for large karst cave in karst region and construction method thereof |
CN107044287A (en) * | 2017-03-06 | 2017-08-15 | 刘冲 | Colliery shaft station and the reinforcement means of track main entry |
CN106640117A (en) * | 2017-03-08 | 2017-05-10 | 中国电建集团中南勘测设计研究院有限公司 | Underground cavern top arc structure, underground cavern and construction method of underground cavern |
CN106640118A (en) * | 2017-03-08 | 2017-05-10 | 中国电建集团中南勘测设计研究院有限公司 | Underground cavity arch crown structure, underground cavity and underground cavity construction method |
Also Published As
Publication number | Publication date |
---|---|
CN107355233A (en) | 2017-11-17 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN107355233B (en) | A kind of underground chamber and Cavity Construction method | |
CN102606162B (en) | Quick construction method for weak surrounding rock shallowly-buried easily-collapsed area of tunnel | |
CN102021911B (en) | Side slope reinforcing method and structure | |
CN105888703B (en) | Super Shallow Covered Metro Station construction method under lateral canopy lid is performed in micro- pilot tunnel | |
CN202969392U (en) | Complex geology deep excavation pit combined support | |
CN201991017U (en) | Subway large-span station body structure based on arch cover method construction forming | |
CN101922302A (en) | Fault processing method of high pressure water enrichment area | |
CN105257301A (en) | Method for reinforcing collapse of weak surrounding rock of shallow embedded and mining tunnel | |
CN102226403A (en) | Construction method of large-span subway station main body by using arched cover method and station main body structure | |
CN107609241A (en) | Weak rheology surrounding rock tunnel secondary liner structure rigidity and its decision design method for applying opportunity | |
CN102966108A (en) | Construction method of deep foundation pit close to building and adopting underground structure as internal support | |
Chen et al. | Recent advances in high slope reinforcement in China: Case studies | |
CN103362513A (en) | Transformation and construction method for existing cavity in underground excavation region | |
CN108035733A (en) | A kind of perpendicular support partial excavation method of rock matter large section tunnel steelframe dike combination | |
CN110206038A (en) | Supporting construction and construction method at a kind of concave foundation pit external corner | |
CN104141500B (en) | One hardens sand and gravel stratum cavern con struction method | |
CN103114595A (en) | Support method and device of support pile preformed core-soil double-buttress inclined inner-strut foundation ditch | |
CN107327306A (en) | Tunnel excavation construction method is superimposed under the conditions of the shallow embedding of city | |
CN106351215A (en) | Method for supporting aeolian sand tunnel entrance arch door frame type jet grouting pile | |
CN203229955U (en) | Foundation pit enclosure structure allowing supporting while excavating | |
CN108914954A (en) | Slope support method of the pre support in conjunction with permanent support | |
CN102587385A (en) | Foundation pit supporting method for sludge-exchanged and filled soft soil | |
CN109403349A (en) | A kind of upper flexible and lower rigid system of deep foundation pit support and its construction method | |
CN209323533U (en) | It is a kind of it is upper just under soft system of deep foundation pit support | |
CN201908313U (en) | Side slope reinforcement structure |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
GR01 | Patent grant | ||
GR01 | Patent grant |