CN106351215A - Method for supporting aeolian sand tunnel entrance arch door frame type jet grouting pile - Google Patents

Method for supporting aeolian sand tunnel entrance arch door frame type jet grouting pile Download PDF

Info

Publication number
CN106351215A
CN106351215A CN201610888918.3A CN201610888918A CN106351215A CN 106351215 A CN106351215 A CN 106351215A CN 201610888918 A CN201610888918 A CN 201610888918A CN 106351215 A CN106351215 A CN 106351215A
Authority
CN
China
Prior art keywords
pile
tunnel
construction
rotary churning
hole
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201610888918.3A
Other languages
Chinese (zh)
Inventor
苗广营
郝军洲
刘宁
刘德忠
李金龙
伏亚峰
李慧赞
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Highway Scientific Research Surveying And Designing Institute Of Qinghai Province
THIRD ENGINEERING Co Ltd OF CCCC SECOND HIGHWAY ENGINEERING BUREAU
Highway Construction In Qinghai Province Management Board
Original Assignee
Highway Scientific Research Surveying And Designing Institute Of Qinghai Province
THIRD ENGINEERING Co Ltd OF CCCC SECOND HIGHWAY ENGINEERING BUREAU
Highway Construction In Qinghai Province Management Board
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Highway Scientific Research Surveying And Designing Institute Of Qinghai Province, THIRD ENGINEERING Co Ltd OF CCCC SECOND HIGHWAY ENGINEERING BUREAU, Highway Construction In Qinghai Province Management Board filed Critical Highway Scientific Research Surveying And Designing Institute Of Qinghai Province
Priority to CN201610888918.3A priority Critical patent/CN106351215A/en
Publication of CN106351215A publication Critical patent/CN106351215A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/22Piles
    • E02D5/34Concrete or concrete-like piles cast in position ; Apparatus for making same
    • E02D5/46Concrete or concrete-like piles cast in position ; Apparatus for making same making in situ by forcing bonding agents into gravel fillings or the soil
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D9/00Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries
    • E21D9/001Improving soil or rock, e.g. by freezing; Injections

Landscapes

  • Engineering & Computer Science (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Structural Engineering (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Civil Engineering (AREA)
  • Paleontology (AREA)
  • General Engineering & Computer Science (AREA)
  • Soil Sciences (AREA)
  • Environmental & Geological Engineering (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Geology (AREA)
  • Excavating Of Shafts Or Tunnels (AREA)

Abstract

The invention provides a method for supporting an aeolian sand tunnel entrance arch door frame type jet grouting pile and relates to the technical field of tunnel construction. The method comprises the steps of laying off jet grouting piles on the earth's surface of a hidden hole entrance, performing vertical jet grouting pile construction, and excavating an open cut tunnel and the hidden hole. The method has the advantages that the vertical jet grouting pile are snapped with each other, so that an arch door frame type continuous concrete structure is formed at the hidden hole entrance of a tunnel, stable side upward slopes and hidden hole advance support conditions are provided for tunnel hidden hole and open cut tunnel construction, large scale landside during construction is avoided, and it is guaranteed that the tunnel hidden hole construction is performed smoothly and safely. According to the technical scheme, the key problem of hidden hole entrance construction of the aeolian sand tunnel is solved; the method is very favorable for reducing project cost and project construction period, the method is wide in technical adaptive range, the structural stress is scientific, design parameters can be flexibly adjusted according to the tunnel entrance geological and geomorphological conditions, and the construction is convenient and safe.

Description

A kind of method of wind-blown sand tunnel hole arch form door case type rotary churning pile supporting
First, technical field
The present invention relates to technical field of tunnel construction, a kind of more particularly to wind-blown sand tunnel hole arch form door case type rotary churning pile props up The method of shield.
2nd, background technology
It is distributed with the drift-sand geology and geomorphology situation of vast area on China Qinghai, Xinjiang, Inner Mongol, Ningxia, Shaanxi and other places.? Under the conditions of this geology, tunnel construction faces great difficulty.One of major issue is exactly under drift-sand geological conditions how The dark hole in tunnel is made safely and smoothly to enter dark hole.The dark hole of wind-blown sand tunnel cannot be stablized after excavation, almost surely caves in Situations such as, it is that constructing tunnel brings major safety risks.
3rd, content of the invention
In order to overcome the above-mentioned deficiencies of the prior art, the invention provides a kind of wind-blown sand tunnel hole arch form door case type rotary churning pile The method of supporting: wind-blown sand tunnel dark hole hole vault arranges vertical rotary churning pile, is made adjacent by timber pile footpath Small Distance mode The close bonding of rotary churning pile, thus form underground continuous concrete to pay protection structure in advance it is ensured that wind-blown sand tunnel open cut tunnel and secretly wide open dig When face-upward slope and dark hole structure safety.
It is completed by following steps: dark hole hole earth's surface rotary churning pile setting-out → vertical jet grouting pile construction → cut-and-cover tunnel and dark Wide open dig → dark hole structure construction;
Dark hole hole earth's surface rotary churning pile setting-out: this stake is calculated according to every pile earth's surface elevation and the relative position with tunnel Long, according to design drawing with the dark hole pile No. that designs as starting point, extend 10~15m, horizontal 17~20m to longitudinal barrel direction, Carry out vertical jet grouting pile construction;Rotary churning pile stake top height is 2m height on arch ring top, calculates the length of every rotary churning pile;
The process conditions of rotary churning pile pile driving construction operation are: carry out jet grouting pile construction from drift-sand earth's surface, churning drill bit of pile machine is drilled into Projected depth starts churning, steps up high to design rotary churning pile top mark, forms a complete rotary churning pile, in rotary churning pile pile body Intensity reaches and is carrying out jet grouting pile construction again every stake position during 10 more than mpa, finally carries out rotary churning pile two centres and applies Work so that underground rotary churning pile pile body is connected, rotary churning pile foundation pile footpath 80cm, horizontal and vertical spacing be 60cm, rotary churning pile Strength of the mixing pile should be not less than 15mpa;
The process conditions of cut-and-cover tunnel and dark hole excavating sequences are: after the completion for the treatment of dark hole hole top jet grouting pile construction, strength of the mixing pile reaches To the excavation that can carry out hole open cut tunnel and dark hole during 15 more than mpa.
Points for attention: 1, arch door case type advance support length and width can specific aim according to tunnel portal geology, landforms Adjustment.2nd, after the completion of jet grouting pile construction, strength of the mixing pile reaches the excavation that can carry out hole open cut tunnel and dark hole when more than 75%.3rd, revolve Spray stake must measure by stake and setting-out, and calculates length and the depth of every pile.4th, rotary churning pile pile diameter domination is very crucial, Must assure that rotary churning pile reaches design stake footpath.5th, it is necessary to carry out rotary churning pile test pile under the conditions of identical geology before jet grouting pile construction Construction, to determine the Specific construction parameter under this geological conditions.6th, rotary churning pile serosity can be adjusted according to live stratum water content Whole.
Technical characterstic: 1, adjacent rotary churning pile is closely engaged mutually is the key of the technical program.2nd, accurately control every rotation The stake footpath of spray stake and length, depth.3rd, rotary churning pile strength of the mixing pile should be not less than 15mpa.4th, this method can be used for wind-blown sand tunnel, Saturated soft soil tunnel etc..
The beneficial effects of the present invention is: engaged using vertical rotary churning pile, form an arch at tunnel An Dong hole Shape door case type underground continuous concrete structure, is the dark hole in tunnel and open cut tunnel construction provides stable face-upward slope and dark hole advance support Condition, it is to avoid there is large scale landside or landslide situation in construction it is ensured that the smooth safe construction in the dark hole in tunnel, this technical side Case solves a key difficult problem for wind-blown sand tunnel dark hole entrance construction;It is advantageous to save construction costs and reduce engineering work Phase;
This technology wide accommodation, structure stress science, design parameter can be adjusted flexibly according to tunnel portal geology and geomorphology condition, Construction Portable safety.This technology passes through the arch door case type that rotary churning pile pile body is engaged, is formed in advance in drift-sand stratum Buried concrete overall structure, it is to avoid wind-blown sand tunnel secretly wide open digging and the face-upward slope slump situation that produces, is wind-blown sand tunnel Dark hole hole is excavated and is created conditions.
4th, brief description
Fig. 1 is wind-blown sand tunnel hole arch form doorframe profile;
Fig. 2 is the rotary churning pile partial enlargement a-a sectional view of Fig. 1;
5th, specific embodiment
Embodiment 1
A kind of method of wind-blown sand tunnel hole arch form door case type rotary churning pile supporting:
Wind-blown sand tunnel dark hole hole vault arranges vertical rotary churning pile, makes adjacent rotary churning pile close by timber pile footpath Small Distance mode Cut bonding, thus forming underground continuous concrete to pay protection structure in advance it is ensured that wind-blown sand tunnel open cut tunnel and secretly wide open face-upward slope when digging And the safety of dark hole structure.
It is completed by following steps: dark hole hole earth's surface rotary churning pile setting-out → vertical jet grouting pile construction → cut-and-cover tunnel and dark Wide open dig → dark hole structure construction;
Dark hole hole earth's surface rotary churning pile setting-out: this stake is calculated according to every pile earth's surface elevation and the relative position with tunnel Long, according to design drawing with the dark hole pile No. that designs as starting point, extend 10m, horizontal 17m to longitudinal barrel direction, carry out vertical Jet grouting pile construction;Rotary churning pile stake top height is 2m height on arch ring top, calculates the length of every rotary churning pile;
The process conditions of rotary churning pile pile driving construction operation are: carry out jet grouting pile construction from drift-sand earth's surface, churning drill bit of pile machine is drilled into Projected depth starts churning, steps up high to design rotary churning pile top mark, forms a complete rotary churning pile, in rotary churning pile pile body Intensity reaches and is carrying out jet grouting pile construction again every stake position during 10 more than mpa, finally carries out rotary churning pile two centres and applies Work so that underground rotary churning pile pile body is connected, rotary churning pile foundation pile footpath 80cm, horizontal and vertical spacing be 60cm, rotary churning pile Strength of the mixing pile should be not less than 15mpa;
The process conditions of cut-and-cover tunnel and dark hole excavating sequences are: after the completion for the treatment of dark hole hole top jet grouting pile construction, strength of the mixing pile reaches To the excavation that can carry out hole open cut tunnel and dark hole during 15 more than mpa.
Embodiment 2
The method of a kind of wind-blown sand tunnel hole arch form door case type rotary churning pile supporting: vault setting in wind-blown sand tunnel dark hole hole is perpendicular To rotary churning pile, the close bonding of adjacent rotary churning pile is made by timber pile footpath Small Distance mode, thus it is pre- to form underground continuous concrete Supporting construction is it is ensured that the safety of wind-blown sand tunnel open cut tunnel and secretly wide open face-upward slope and dark hole structure when digging.
It is completed by following steps: dark hole hole earth's surface rotary churning pile setting-out → vertical jet grouting pile construction → cut-and-cover tunnel and dark Wide open dig → dark hole structure construction;
Dark hole hole earth's surface rotary churning pile setting-out: this stake is calculated according to every pile earth's surface elevation and the relative position with tunnel Long, according to design drawing with the dark hole pile No. that designs as starting point, extend 13m, horizontal 18m to longitudinal barrel direction, carry out vertical Jet grouting pile construction;Rotary churning pile stake top height is 2m height on arch ring top, calculates the length of every rotary churning pile;
The process conditions of rotary churning pile pile driving construction operation are: carry out jet grouting pile construction from drift-sand earth's surface, churning drill bit of pile machine is drilled into Projected depth starts churning, steps up high to design rotary churning pile top mark, forms a complete rotary churning pile, in rotary churning pile pile body Intensity reaches and is carrying out jet grouting pile construction again every stake position during 10 more than mpa, finally carries out rotary churning pile two centres and applies Work so that underground rotary churning pile pile body is connected, rotary churning pile foundation pile footpath 80cm, horizontal and vertical spacing be 60cm, rotary churning pile Strength of the mixing pile should be not less than 15mpa;
The process conditions of cut-and-cover tunnel and dark hole excavating sequences are: after the completion for the treatment of dark hole hole top jet grouting pile construction, strength of the mixing pile reaches To the excavation that can carry out hole open cut tunnel and dark hole during 15 more than mpa.
Embodiment 3
The method of a kind of wind-blown sand tunnel hole arch form door case type rotary churning pile supporting: vault setting in wind-blown sand tunnel dark hole hole is perpendicular To rotary churning pile, the close bonding of adjacent rotary churning pile is made by timber pile footpath Small Distance mode, thus it is pre- to form underground continuous concrete Supporting construction is it is ensured that the safety of wind-blown sand tunnel open cut tunnel and secretly wide open face-upward slope and dark hole structure when digging.It is complete by following steps Become: dark hole hole earth's surface rotary churning pile setting-out → vertical jet grouting pile construction → cut-and-cover tunnel and secretly wide open dig → secretly hole structure construction;
Dark hole hole earth's surface rotary churning pile setting-out: this stake is calculated according to every pile earth's surface elevation and the relative position with tunnel Long, according to design drawing with the dark hole pile No. that designs as starting point, extend 15m, horizontal 20m to longitudinal barrel direction, carry out vertical Jet grouting pile construction;Rotary churning pile stake top height is 2m height on arch ring top, calculates the length of every rotary churning pile;
The process conditions of rotary churning pile pile driving construction operation are: carry out jet grouting pile construction from drift-sand earth's surface, churning drill bit of pile machine is drilled into Projected depth starts churning, steps up high to design rotary churning pile top mark, forms a complete rotary churning pile, in rotary churning pile pile body Intensity reaches and is carrying out jet grouting pile construction again every stake position during 10 more than mpa, finally carries out rotary churning pile two centres and applies Work so that underground rotary churning pile pile body is connected, rotary churning pile foundation pile footpath 80cm, horizontal and vertical spacing be 60cm, rotary churning pile Strength of the mixing pile should be not less than 15mpa;
The process conditions of cut-and-cover tunnel and dark hole excavating sequences are: after the completion for the treatment of dark hole hole top jet grouting pile construction, strength of the mixing pile reaches To the excavation that can carry out hole open cut tunnel and dark hole during 15 more than mpa.

Claims (1)

1. the method for a kind of wind-blown sand tunnel hole arch form door case type rotary churning pile supporting: it is characterized in that: it is complete by following steps Become: dark hole hole earth's surface rotary churning pile setting-out → vertical jet grouting pile construction → cut-and-cover tunnel and secretly wide open dig;
Dark hole hole earth's surface rotary churning pile setting-out: this stake is calculated according to every pile earth's surface elevation and the relative position with tunnel Long, according to design drawing with the dark hole pile No. that designs as starting point, extend 10~15m, horizontal 17~20m to longitudinal barrel direction, Carry out vertical jet grouting pile construction;Rotary churning pile stake top height is 2m height on arch ring top, calculates the length of every rotary churning pile;
The process conditions of rotary churning pile pile driving construction operation are: carry out jet grouting pile construction from drift-sand earth's surface, churning drill bit of pile machine is drilled into Projected depth starts churning, steps up high to design rotary churning pile top mark, forms a complete rotary churning pile, in rotary churning pile pile body Intensity reaches and is carrying out jet grouting pile construction again every stake position during 10 more than mpa, finally carries out rotary churning pile two centres and applies Work so that underground rotary churning pile pile body is connected, rotary churning pile foundation pile footpath 80cm, horizontal and vertical spacing be 60cm, rotary churning pile Strength of the mixing pile should be not less than 15mpa;
The process conditions of cut-and-cover tunnel and dark hole excavating sequences are: after the completion for the treatment of dark hole hole top jet grouting pile construction, strength of the mixing pile reaches To the excavation that can carry out hole open cut tunnel and dark hole during 15 more than mpa.
CN201610888918.3A 2016-10-12 2016-10-12 Method for supporting aeolian sand tunnel entrance arch door frame type jet grouting pile Pending CN106351215A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201610888918.3A CN106351215A (en) 2016-10-12 2016-10-12 Method for supporting aeolian sand tunnel entrance arch door frame type jet grouting pile

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201610888918.3A CN106351215A (en) 2016-10-12 2016-10-12 Method for supporting aeolian sand tunnel entrance arch door frame type jet grouting pile

Publications (1)

Publication Number Publication Date
CN106351215A true CN106351215A (en) 2017-01-25

Family

ID=57866065

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201610888918.3A Pending CN106351215A (en) 2016-10-12 2016-10-12 Method for supporting aeolian sand tunnel entrance arch door frame type jet grouting pile

Country Status (1)

Country Link
CN (1) CN106351215A (en)

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107366282A (en) * 2017-07-11 2017-11-21 北京市政建设集团有限责任公司 A kind of tunnel arch foot partial high pressure rotary churning pile reinforcement technique
CN107524144A (en) * 2017-07-28 2017-12-29 同济大学 A kind of hardened system and reinforcement means for soft soil foundation before tunnel excavation
CN109026057A (en) * 2018-07-25 2018-12-18 西南交通大学 A kind of tunnel combined support structure suitable for drift-sand stratum
CN109209448A (en) * 2018-08-28 2019-01-15 北京瑞威世纪铁道工程有限公司 Tunnel surface grouting blocks water construction method
CN109487640A (en) * 2018-10-15 2019-03-19 西南交通大学 A kind of closed conduit develops regional consolidation roadbed of high-speed structure and construction method
CN114109394A (en) * 2021-10-22 2022-03-01 西南交通大学 Method for determining pile length of tunnel shallow-buried weak surrounding rock high-pressure jet grouting pile method ground surface reinforcement

Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
EP1757771A2 (en) * 2005-08-23 2007-02-28 Trevi S.p.A. Method for consolidating and impermeabilizing the ground around a tunnel
CN105909263A (en) * 2016-06-13 2016-08-31 中交第公路勘察设计研究院有限公司 Eolian sand stratum highway tunnel structure and construction method thereof

Patent Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
EP1757771A2 (en) * 2005-08-23 2007-02-28 Trevi S.p.A. Method for consolidating and impermeabilizing the ground around a tunnel
CN105909263A (en) * 2016-06-13 2016-08-31 中交第公路勘察设计研究院有限公司 Eolian sand stratum highway tunnel structure and construction method thereof

Non-Patent Citations (3)

* Cited by examiner, † Cited by third party
Title
徐智等: "旋喷桩加固技术在某隧道风积砂地层中的应用", 《现代隧道技术》 *
潘振武: "建筑工程地基基础变形分析与加固处理", 《广东公路交通》 *
高成梁等: "旋喷桩在盾构法隧道端头井洞口土体加固工程中的应用", 《探矿工程(岩土钻掘工程)》 *

Cited By (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107366282A (en) * 2017-07-11 2017-11-21 北京市政建设集团有限责任公司 A kind of tunnel arch foot partial high pressure rotary churning pile reinforcement technique
CN107524144A (en) * 2017-07-28 2017-12-29 同济大学 A kind of hardened system and reinforcement means for soft soil foundation before tunnel excavation
CN109026057A (en) * 2018-07-25 2018-12-18 西南交通大学 A kind of tunnel combined support structure suitable for drift-sand stratum
CN109209448A (en) * 2018-08-28 2019-01-15 北京瑞威世纪铁道工程有限公司 Tunnel surface grouting blocks water construction method
CN109487640A (en) * 2018-10-15 2019-03-19 西南交通大学 A kind of closed conduit develops regional consolidation roadbed of high-speed structure and construction method
CN109487640B (en) * 2018-10-15 2020-11-17 西南交通大学 High-speed railway roadbed reinforcing structure in underdrain development area and construction method
CN114109394A (en) * 2021-10-22 2022-03-01 西南交通大学 Method for determining pile length of tunnel shallow-buried weak surrounding rock high-pressure jet grouting pile method ground surface reinforcement
CN114109394B (en) * 2021-10-22 2022-07-15 西南交通大学 Method for determining pile length of tunnel shallow-buried weak surrounding rock high-pressure jet grouting pile method ground surface reinforcement

Similar Documents

Publication Publication Date Title
CN106351215A (en) Method for supporting aeolian sand tunnel entrance arch door frame type jet grouting pile
CN105257301B (en) A kind of shallow-depth-excavation tunnel weak surrounding rock landslide reinforcing and processing method
CN102606162B (en) Quick construction method for weak surrounding rock shallowly-buried easily-collapsed area of tunnel
CN104047623B (en) A kind of big across cavern excavation construction method
CN102966108B (en) Construction method of deep foundation pit close to building and adopting underground structure as internal support
CN106049532B (en) A kind of pipe gallery open-cut branch blocking means and its construction method
CN110685698B (en) Climbing reverse construction method for newly building large-section tunnel in existing cavern side direction
CN102660955B (en) Quick construction method for foundation pit slope support
CN103835729A (en) Ground pre-grouting strengthening technology for deep long-distance roadway surrounding rock
CN103775110A (en) Underground excavation construction method for multilayer underground space of soft soil area
CN108532586A (en) A kind of construction method of garage parking diaphram wall
CN203334300U (en) Root pile supporting structure
CN108457670B (en) Construction method for large-section tunnel to penetrate through upper-hard lower-soft water-rich stratum
CN114319388A (en) Construction method of foundation pit enclosure structure in existing building in karst area
CN105909262B (en) A kind of bored tunnel driving method
CN203821414U (en) Structure of protecting wall of hole-digging pile
CN103243721B (en) Highrise Building With Raft Foundation and Core Walls Structure excavation construction method under Unfavorable geology condition
KR101021915B1 (en) A method for constructing cut-off temporary structure for sheathing work
CN105442614A (en) Construction method for foundation pit support
CN105040705A (en) Ground foundation treatment construction technology under multi-karst-cave geological conditions
CN113026757A (en) Rapid excavation and support construction method for complex stratum pipe-jacking comprehensive well
CN103046556B (en) Without inner support annular space enclosing structure and preparation method thereof
CN111927320A (en) Ultra-deep large-diameter pile hole forming method
CN102678127B (en) Method for constructing weakly consolidated non-stratified sandstone tunnel
CN109322315A (en) A kind of retaining structure and its construction method for high Steep Slope Embankment location

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20170125

RJ01 Rejection of invention patent application after publication