CN109322315A - A kind of retaining structure and its construction method for high Steep Slope Embankment location - Google Patents

A kind of retaining structure and its construction method for high Steep Slope Embankment location Download PDF

Info

Publication number
CN109322315A
CN109322315A CN201811324974.XA CN201811324974A CN109322315A CN 109322315 A CN109322315 A CN 109322315A CN 201811324974 A CN201811324974 A CN 201811324974A CN 109322315 A CN109322315 A CN 109322315A
Authority
CN
China
Prior art keywords
section
cantilever segment
pile
steep slope
anchor pile
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201811324974.XA
Other languages
Chinese (zh)
Inventor
李传宝
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Railway Siyuan Survey and Design Group Co Ltd
Original Assignee
China Railway Siyuan Survey and Design Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Railway Siyuan Survey and Design Group Co Ltd filed Critical China Railway Siyuan Survey and Design Group Co Ltd
Priority to CN201811324974.XA priority Critical patent/CN109322315A/en
Publication of CN109322315A publication Critical patent/CN109322315A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D17/00Excavations; Bordering of excavations; Making embankments
    • E02D17/20Securing of slopes or inclines
    • E02D17/207Securing of slopes or inclines with means incorporating sheet piles or piles

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Pit Excavations, Shoring, Fill Or Stabilisation Of Slopes (AREA)

Abstract

The invention discloses a kind of retaining structures for high Steep Slope Embankment location, including the anchor pile and breast boards being arranged along embankment longitudinal gap, the anchor pile includes the anchoring section of the cantilever segment and subsurface on ground, it is characterized in that, the cantilever segment, anchoring section coaxial arrangement, the cross section of the cantilever segment be rectangle, anchoring section cross section be it is round, the breast boards is hung between the cantilever segment of each adjacent anchor pile.The present invention is using large-diameter circular, the anchor pile of rectangular section combination form.The section of this pile-type below ground pile body anchoring section uses large-diameter circular, and rotary drilling rig or percussive drill is facilitated to construct, and the section of the above pile body cantilever segment in ground uses rectangle, builds method construction with traditional mould.

Description

A kind of retaining structure and its construction method for high Steep Slope Embankment location
Technical field
The present invention relates to geotechnical engineering reinforcing side slope technique fields, in particular to a kind of branch for high Steep Slope Embankment location Keep off structure and its construction method.
Background technique
Traffic of mountain area and piece of smooth land construction field are often arranged greatly in high abrupt slope embankment embankment location to improve embankment stability Section rectangle anchor pile (friction pile)+earth-retaining board combining structure pattern carries out supporting and retaining system.It is anti-that pile body below ground part provides anchoring Railway embankment after power, pile body and breast boards undertakes sliding force and pressure of banketing.The China of Publication No. CN 206873487U is real Disclose a kind of rib stake formula peg board retaining wall with new patent, including pile body anchoring section, pile body cantilever segment, in adjacent pile body cantilever Longitudinally disposed breast boards between section.The pile body anchoring section of anchor pile, the barrette that pile body cantilever segment is size uniformity.
There are two kinds of rectangle and circle in traditional anchoring stake body section, and existing major defect is as follows:
(1) circular cross-section anchor pile can not carry out Slate hanging construction between stake and stake, be unable to satisfy applying of banketing after stake Work requirement.
(2) rectangular section anchor pile can hang breast boards after stake or hang breast boards in pile body setting bracket, then Carry out fill construction;But it does not have corresponding construction machinery, and big section rectangle anchor pile under ground portion uses manually digging hole operation, Work efficiency is low, and high Steep Slope Embankment sets a position and is normally at hypsography low-lying location, and often underground water is relatively abundant, needs manually to drop Water, and when broken rock and soil, there is very big personal safety hidden danger in the easy collapse hole under groundwater seepage and acting by external hydrostatic pressure.
More than summary, circular cross-section anchor pile is not suitable for embankment filled soil location after stake;There are nothings for rectangular section anchor pile Corresponding construction machinery, manually digging hole work efficiency be low, be not suitable for broken rock and soil or underground water development location, personal safety hidden danger are big etc. Disadvantage.
Therefore, it is necessary to develop it is a kind of construct convenient, operation efficiently, pile conveniently, safely hanging plate for high abrupt slope road The retaining structure and its construction method in dike location.
Summary of the invention
The purpose of the present invention is to solve the deficiency of the above background technology, provide a kind of convenient, operation of construction efficiently, at The retaining structure and its construction method for high Steep Slope Embankment location of stake conveniently, safely hanging plate.
The technical solution of the present invention is as follows: a kind of retaining structure for high Steep Slope Embankment location, including between embankment longitudinal direction Every the anchor pile and breast boards of setting, the anchor pile includes the anchoring section of the cantilever segment and subsurface on ground, feature It is,
The cantilever segment, anchoring section coaxial arrangement, the cross section of the cantilever segment be rectangle, anchoring section cross section be round Shape, the breast boards are hung between the cantilever of each adjacent anchor pile.
Preferably, the anchoring section cross sectional radius is greater than or equal to cantilever segment cross section circumradius.
Preferably, the cantilever segment includes a pair of along the longitudinally disposed the first side wall of embankment and a pair of along embankment laterally setting Second sidewall.
Further, the first side wall length d≤second sidewall length h on the cross section of the cantilever segment.
Further, the breast boards longitudinally hang on adjacent anchor pile and closes on the first side wall on the inside of embankment.
Further, the breast boards is longitudinally hung on the bracket for the second sidewall setting that adjacent anchor pile closes on.
Preferably, the anchor pile is integrally formed.
The present invention also provides a kind of construction method of above-mentioned retaining structure for high Steep Slope Embankment location, steps are as follows:
A. below ground utilizes rotary drilling rig or percussive drill pore-forming at anchor pile design;
B. the circle pile cages of prefabricated anchoring section, then the welding binding cantilever segment above circle pile cages are transferred in hole Rectangle steel reinforcement cage, one-piece casting anchoring section, cantilever section concrete after installation template;
C., prefabricated breast boards is installed between cantilever segment after concrete reaches intensity.
The invention has the benefit that
1. using large-diameter circular+rectangular section combination form anchor pile.This pile-type below ground pile body anchoring section Section uses large-diameter circular, and rotary drilling rig or percussive drill is facilitated to construct, and the section of the above pile body cantilever segment in ground uses square Shape builds method construction with traditional mould.
2. lower pile body anchoring section diameter of section is greater than or equal to upper pile body cantilever segment rectangular section circumscribed circle diameter, make lower stake Body anchoring section is as the embedded stabilization that is built on the rock, to be conducive to the stability of upper pile body after banketing;It adopts in upper pile body cantilever segment section With rectangle, it is convenient for seamless installation between breast boards and anchor pile.
3. anchor pile is formed using one-time-concreting, make anchor pile good integrity, binding force is strong between upper pile body, lower pile body.
Detailed description of the invention
Fig. 1 is retaining structure schematic diagram of the present invention for high Steep Slope Embankment location (along embankment transverse direction)
Fig. 2 is retaining structure schematic diagram of the present invention for high Steep Slope Embankment location (along embankment longitudinal direction)
Fig. 3 is anchor pile top view
Fig. 4 is anchor pile perspective view
Wherein: 1- anchor pile 2- breast boards 3- cantilever segment 4- anchoring section 5- the first side wall 6- second sidewall 7- embankment.
Specific embodiment
The present invention is described in further detail for specific embodiment below.
As shown in Figs 1-4, a kind of retaining structure for high Steep Slope Embankment location provided by the invention, including along embankment 7 The anchor pile 1 and breast boards 2 of longitudinal gap setting, anchor pile 1 include the anchoring section 4 of the cantilever segment 3 and subsurface on ground, Cantilever segment 3, anchoring section 4 are coaxially disposed, the cross section of cantilever segment 3 be rectangle, anchoring section 4 cross section be it is round, by breast boards 2 It hang between the cantilever segment 3 of each adjacent anchor pile 1.
4 cross sectional radius of anchoring section is greater than or equal to the circumradius of 3 cross section of cantilever segment.Anchoring section in the present embodiment 4 is along the uniform square pile of axial cross section, cantilever segment 3 are the circle stake uniform along axial cross section, 4 cross sectional radius of anchoring section etc. Circumradius in 3 cross section of cantilever segment obtains cantilever segment 3 in 4 cross-sectional extent of anchoring section with this larger-size Rectangular cross section.
Cantilever segment 3 includes a pair of along the longitudinally disposed the first side wall 5 of embankment 7 and a pair of second be laterally arranged along embankment 7 Side wall 6.5 length d of the first side wall is less than or equal to 6 length h of second sidewall on the cross section of cantilever segment 3.Breast boards 2 is longitudinal to be hung It is arranged on the first side wall 5 that adjacent anchor pile 1 is located at 7 laterally inboard of embankment, or in the second sidewall 6 of adjacent anchor pile 1 Breast boards 2 is hung after bracket.
Anchor pile 1 is integrally formed in the present embodiment, and the axial direction of anchor pile 1 is vertical direction.4 cross sectional radius R of anchoring section 1.0~1.5m generally can be used;1.5~2.5m generally can be used in 5 length d of the first side wall on the cross section of cantilever segment 3;Cantilever segment 1.5~2.75m generally can be used in 6 length h of second sidewall on 3 cross section;3 axial length L of cantilever segment18m is usually no more than, 4 axial length L of anchoring section2It is determined by Structure Calculation, typically no less than length L1;High Steep Slope Embankment slope gradient generally takes 1:1.5 ~1:2;Away from S in the stake of the anchoring section 4 of two adjacent anchor piles 1,3~6m generally can be used.
The construction method of the above-mentioned retaining structure for high Steep Slope Embankment location, step are as follows:
A. below ground utilizes rotary drilling rig or percussive drill pore-forming to answer core in pore forming process at 1 design of anchor pile To landform, geologic information, it is found that when geological conditions and design data are misfitted (such as Limestone pavement develops solution cavity, rate of decay changes, Native stone interface variation, formation variation etc.), should be contacted in time with designing unit, to be verified in time according to practical geological conditions or Adjusted design;
B. the circle pile cages of prefabricated anchoring section 4, then the welding binding cantilever above circle pile cages are transferred in hole The rectangle steel reinforcement cage of section 3 installs whole continuous placing anchoring section 4,3 concrete of cantilever segment after 3 outboard template of cantilever;
C. after concrete reaches intensity between cantilever segment the prefabricated breast boards 2 of installation template, then banket after carrying out stake Construction.

Claims (8)

1. a kind of retaining structure for high Steep Slope Embankment location, including the anchor pile (1) that is arranged along embankment (7) longitudinal gap with And breast boards (2), the anchor pile (1) include the anchoring section (4) of the cantilever segment (3) and subsurface on ground, which is characterized in that
The cantilever segment (3), anchoring section (4) coaxial arrangement, the cross section of the cantilever segment (3) are the cross of rectangle, anchoring section (4) Section is circle, and the breast boards (2) hang between the cantilever segment (3) of each adjacent anchor pile (1).
2. being used for the retaining structure in high Steep Slope Embankment location as described in claim 1, which is characterized in that the anchoring section (4) Cross sectional radius is greater than or equal to cantilever segment (3) cross section circumradius.
3. being used for the retaining structure in high Steep Slope Embankment location as described in claim 1, which is characterized in that the cantilever segment (3) Including a pair along the longitudinally disposed the first side wall (5) of embankment (7) and a pair of second sidewall (6) being laterally arranged along embankment (7).
4. being used for the retaining structure in high Steep Slope Embankment location as claimed in claim 3, which is characterized in that the cantilever segment (3) Cross section on the first side wall (5) length d≤second sidewall (6) length h.
5. being used for the retaining structure in high Steep Slope Embankment location as claimed in claim 3, which is characterized in that the breast boards (2) Longitudinal direction hang on adjacent anchor pile (1) and closes on the first side wall (5) on the inside of embankment (7).
6. being used for the retaining structure in high Steep Slope Embankment location as claimed in claim 3, which is characterized in that the breast boards (2) Longitudinal direction is hung on the bracket for second sidewall (6) setting that adjacent anchor pile (1) is closed on.
7. being used for the retaining structure in high Steep Slope Embankment location as described in claim 1, which is characterized in that the anchor pile (1) It is integrally formed.
8. a kind of construction method for the retaining structure for being used for high Steep Slope Embankment location as described in claim 1, which is characterized in that Step are as follows:
A. below ground utilizes rotary drilling rig or percussive drill pore-forming at anchor pile (1) design;
B. the circle pile cages of prefabricated anchoring section (4), then the welding binding cantilever segment above circle pile cages are transferred in hole (3) rectangle steel reinforcement cage, one-piece casting anchoring section (4), cantilever segment (3) concrete after installation template;
C., prefabricated breast boards (2) are installed between cantilever segment after concrete reaches intensity.
CN201811324974.XA 2018-11-08 2018-11-08 A kind of retaining structure and its construction method for high Steep Slope Embankment location Pending CN109322315A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201811324974.XA CN109322315A (en) 2018-11-08 2018-11-08 A kind of retaining structure and its construction method for high Steep Slope Embankment location

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201811324974.XA CN109322315A (en) 2018-11-08 2018-11-08 A kind of retaining structure and its construction method for high Steep Slope Embankment location

Publications (1)

Publication Number Publication Date
CN109322315A true CN109322315A (en) 2019-02-12

Family

ID=65260531

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201811324974.XA Pending CN109322315A (en) 2018-11-08 2018-11-08 A kind of retaining structure and its construction method for high Steep Slope Embankment location

Country Status (1)

Country Link
CN (1) CN109322315A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113216216A (en) * 2021-03-24 2021-08-06 云南省交通规划设计研究院有限公司 Active reinforcing method for built-in anti-slide pile suitable for unstable slope
CN114482091A (en) * 2022-02-09 2022-05-13 中铁二十三局集团第四工程有限公司 Construction method of side slope anchoring pile

Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101298780A (en) * 2008-06-23 2008-11-05 云南省公路规划勘察设计院 High and light anchorage cable pile panel wall and construction method thereof
CN201224889Y (en) * 2008-06-20 2009-04-22 云南省公路规划勘察设计院 High and light type anchoring plate retaining wall in high filling branch block engineering
CN101838998A (en) * 2010-04-27 2010-09-22 中国科学院武汉岩土力学研究所 Prestressed anchor cable pile sliding wall along river road shoulder and construction method thereof
CN205954640U (en) * 2016-07-12 2017-02-15 中铁二院昆明勘察设计研究院有限责任公司 Stake siding wall
CN207512752U (en) * 2017-10-31 2018-06-19 甘肃中建市政工程勘察设计研究院 A kind of tall earth fill supporting construction
CN207672558U (en) * 2017-12-14 2018-07-31 中铁二院工程集团有限责任公司 A kind of railroad embankment Pile slab-wall structure
CN108532397A (en) * 2018-06-19 2018-09-14 云南建投中航建设有限公司 It is a kind of that the method for roadbed and combined friction pile are consolidated using combined friction pile
CN210031852U (en) * 2018-11-08 2020-02-07 中铁第四勘察设计院集团有限公司 A a fender structure for high abrupt slope embankment section

Patent Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN201224889Y (en) * 2008-06-20 2009-04-22 云南省公路规划勘察设计院 High and light type anchoring plate retaining wall in high filling branch block engineering
CN101298780A (en) * 2008-06-23 2008-11-05 云南省公路规划勘察设计院 High and light anchorage cable pile panel wall and construction method thereof
CN101838998A (en) * 2010-04-27 2010-09-22 中国科学院武汉岩土力学研究所 Prestressed anchor cable pile sliding wall along river road shoulder and construction method thereof
CN205954640U (en) * 2016-07-12 2017-02-15 中铁二院昆明勘察设计研究院有限责任公司 Stake siding wall
CN207512752U (en) * 2017-10-31 2018-06-19 甘肃中建市政工程勘察设计研究院 A kind of tall earth fill supporting construction
CN207672558U (en) * 2017-12-14 2018-07-31 中铁二院工程集团有限责任公司 A kind of railroad embankment Pile slab-wall structure
CN108532397A (en) * 2018-06-19 2018-09-14 云南建投中航建设有限公司 It is a kind of that the method for roadbed and combined friction pile are consolidated using combined friction pile
CN210031852U (en) * 2018-11-08 2020-02-07 中铁第四勘察设计院集团有限公司 A a fender structure for high abrupt slope embankment section

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
张发春;: "一种新型高大锚定板挡土墙的设计与施工", 中外公路, no. 05, pages 45 - 50 *

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113216216A (en) * 2021-03-24 2021-08-06 云南省交通规划设计研究院有限公司 Active reinforcing method for built-in anti-slide pile suitable for unstable slope
CN114482091A (en) * 2022-02-09 2022-05-13 中铁二十三局集团第四工程有限公司 Construction method of side slope anchoring pile
CN114482091B (en) * 2022-02-09 2024-06-04 中铁二十三局集团第四工程有限公司 Construction method of slope anchoring pile

Similar Documents

Publication Publication Date Title
CN107313431B (en) Close on not contour foundation pit method for synchronously constructing
CN104612143B (en) Composite pile constructed in drilled hole structure under a kind of solution cavity/soil cave geological conditions
CN106930321B (en) The construction method of underground structure is built in a kind of stake of pipe-jacking with large diameter combination hole
CN105672348A (en) Construction method for cropping bridge pile foundation at sandy gravel stratum of abyssal region
CN105464074B (en) A kind of artificial digging pile high polymer grouting safeguard structure and its construction method
CN102953341A (en) Overhead trestle structure built on non-covering steep bare rocks in deep rapids
CN206308569U (en) It is a kind of to reinforce the road structure for punishing the solution cavity that underlies
CN102979039B (en) Elevated trestle bridge construction method on covering-free steep bare rock in deepwater and rapid stream
CN108532586A (en) A kind of construction method of garage parking diaphram wall
CN104389320A (en) Construction method of pile foundation anchor rope prestress high retaining wall
CN107503362A (en) A kind of compound antiskid piling wall retaining structure and construction method suitable for reservoir stability
CN101838957B (en) Integral type T-shaped outer cantilever roads and construction method thereof
CN103572764A (en) Ultra-deep manual hole digging pile dado water stop structure and construction method thereof
CN113174958A (en) Construction method for foundation pit of adjacent road under poor ground condition
CN104131566B (en) A kind of basement is without the construction method of horizontal support foundation ditch
CN109322315A (en) A kind of retaining structure and its construction method for high Steep Slope Embankment location
CN202644591U (en) A reinforced bridge pile foundation in tunnel construction under the geological condition of water-rich quicksand
CN102995647B (en) Underground water control method used for grouting and seepage insulation of pile hole
CN105369800B (en) One-step forming construction method for inserting steel pipe column into cast-in-situ bored pile in pilot tunnel
CN104196488B (en) Underwater exploration hole hole-sealing technology
CN106050239A (en) Construction method for retaining structure of deep and large vertical shaft in water-abundant upper-soft lower-hard stratum
CN212104124U (en) Landslide prevention and control construction unit and system
CN205576990U (en) Cross section and wear bridge pier tunnel slip casting supporting construction
CN107476315A (en) A kind of prefabricated component and its construction method being directed to close to type foundation ditch
CN112878315A (en) End-bearing rotary-digging hole-forming cast-in-place pile based on Civil 3D technology and construction method

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination