CN107327314B - Construction method of ultra-thick backfill layer pile foundation - Google Patents

Construction method of ultra-thick backfill layer pile foundation Download PDF

Info

Publication number
CN107327314B
CN107327314B CN201710443680.8A CN201710443680A CN107327314B CN 107327314 B CN107327314 B CN 107327314B CN 201710443680 A CN201710443680 A CN 201710443680A CN 107327314 B CN107327314 B CN 107327314B
Authority
CN
China
Prior art keywords
steel pipe
backfill layer
ultra
pile
hammering
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201710443680.8A
Other languages
Chinese (zh)
Other versions
CN107327314A (en
Inventor
胡碧海
马国新
张佩军
屠永安
张敏
刘向荣
张巧
吴广
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Sinochem Zhoushan Xinghai Construction Co Ltd
Original Assignee
Sinochem Zhoushan Xinghai Construction Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Sinochem Zhoushan Xinghai Construction Co Ltd filed Critical Sinochem Zhoushan Xinghai Construction Co Ltd
Priority to CN201710443680.8A priority Critical patent/CN107327314B/en
Publication of CN107327314A publication Critical patent/CN107327314A/en
Application granted granted Critical
Publication of CN107327314B publication Critical patent/CN107327314B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21FSAFETY DEVICES, TRANSPORT, FILLING-UP, RESCUE, VENTILATION, OR DRAINING IN OR OF MINES OR TUNNELS
    • E21F15/00Methods or devices for placing filling-up materials in underground workings

Abstract

The invention relates to a construction method of an ultra-thick backfill layer pile foundation, which comprises the following steps: excavating a foundation pit for embedding the steel pipe pile casing on the ultra-thick backfill layer by adopting machinery, wherein the depth of the foundation pit exceeds 5 m; the backfill material contains blocky stones with the particle size larger than 500mm, and the thickness of the backfill layer is more than 11 m; filling a clay layer into the bottom of the foundation pit, and then arranging the steel pipe pile casing into the foundation pit along the vertical direction, wherein the thickness of the clay layer is more than 500 mm; exposing the top end of the backfilled steel pipe pile casing out of the ground; preparing mud by stirring clay and water, wherein the specific gravity of the mud is more than 1.35; pouring the prepared slurry into the steel pipe protective cylinder, and filling the steel pipe protective cylinder with the slurry; and hammering the backfill layer in the steel pipe protective cylinder by adopting a hammering pile, and forming holes by using the slurry protective wall. The method for constructing the pile foundation of the ultra-thick backfill layer can improve the hole forming quality of the pile foundation of the ultra-thick backfill layer, enables the hole forming of the pile foundation of the ultra-thick backfill layer to be more convenient, efficient and rapid, further can shorten the construction period and reduce the construction cost.

Description

Construction method of ultra-thick backfill layer pile foundation
Technical Field
The invention relates to a construction method of an ultra-thick backfill layer pile foundation.
Background
The coastal region adopts mountain-opening backfill to form a project of a land area, the backfill material contains more large-particle-size rock blocks, the field is not subjected to dynamic compaction, and the backfill layer structure is relatively loose; the formal seawall is not formed generally when the sea area is backfilled, and the sea surface tide level has obvious influence on the underground water level of the field area; because the basic level of the original sea area is low, a large amount of mountain-digging muck needs to be backfilled to form an ultra-thick backfill layer in part of projects; the problems cause a plurality of adverse effects on project construction, particularly pile foundation construction, cause problems of pile foundation hole wall collapse, overlarge hole diameter, necking, wall protection slurry loss, incapability of normally drilling a pile machine and the like, and cause irreparable harm to construction quality.
For the pile foundation construction of an ultra-thick backfill layer, the current common method mainly comprises the following steps:
1. hammering pile pore-forming
Adopting an impact hammer to form a hole, and utilizing high-specific gravity slurry to form a hole wall support so as to penetrate through a backfill layer to form a hole; the process has the advantages that: large equipment investment is not needed, the requirement on the site is low, and the vibration is small; the disadvantages are as follows: the construction period is long, and the underground water level has great influence on the forming of the retaining wall.
2. Adopting all-steel casing and hammering penetration backfill layer
The inner mold pipe is hammered through the backfill layer by the large-scale hammering pile driver in the form of the inner mold pipe and the outer mold pipe, the outer mold pipe sinks along with the outer mold pipe in the full thickness, the inner mold pipe is taken out after hole forming, and the outer mold pipe is taken out in a vibration mode after pile forming. The process has the advantages that: the steel pipe can be circulated, and the construction speed is high; the disadvantages are as follows: large-scale mechanical equipment is required for construction, and the requirement on the site is high; strong noise, large vibration and easy soil squeezing effect during construction; the cost is high.
Disclosure of Invention
The invention aims to provide the construction method of the pile foundation of the ultra-thick backfill layer, which can improve the hole forming quality of the pile foundation of the ultra-thick backfill layer, enables the hole forming of the pile foundation of the ultra-thick backfill layer to be more convenient, efficient and rapid, further shortens the construction period and reduces the construction cost.
The invention discloses a construction method of an ultra-thick backfill layer pile foundation, which comprises the following steps:
A. excavating a foundation pit for embedding the steel pipe pile casing on the ultra-thick backfill layer by adopting machinery, wherein the depth of the foundation pit exceeds 5 m;
the ultra-thick backfill layer is a field formed by digging a mountain and backfilling the ground, which is close to a sea wall, and the surface water of the field is influenced by the sea surface tide level, the field is not subjected to dynamic compaction, the backfill layer is compacted through natural sedimentation, and the internal structure is relatively loose; the backfill material contains blocky stones with the particle size larger than 500mm, and the thickness of the backfill layer is more than 11 m;
B. filling a clay layer into the bottom of the foundation pit, and then arranging the steel pipe pile casing into the foundation pit along the vertical direction, wherein the thickness of the clay layer is more than 500 mm;
C. exposing the top end of the backfilled steel pipe pile casing out of the ground;
D. preparing mud by stirring clay and water, wherein the specific gravity of the mud is more than 1.35;
E. pouring the prepared slurry into the steel pipe protective cylinder, and filling the steel pipe protective cylinder with the slurry;
F. hammering a backfill layer in the steel pipe pile casing by adopting a hammering pile, forming a hole by using a slurry protecting wall, and hammering the hole to be below an underground water level influence line;
G. adding Portland cement into the steel pipe casing filled with the slurry, fully stirring the Portland cement and the slurry to form cement slurry, standing for more than 12 hours, and continuously hammering the pile to hammer the backfill layer in the steel pipe casing until the hammering hole forms and penetrates through the ultra-thick backfill layer.
Furthermore, the penetration rate of the hammering hole forming is controlled to be 0.5-1.25m every 30 minutes, and the penetration rate is controlled to be 0.1-0.35m every 30 minutes when the hammering hole forming meets large-particle-size rock blocks;
further, the internal diameter of the steel pipe casing is 800mm, the diameter of the hammer head of the hammering pile is 600mm, the length of the hammer head is 2.7 meters, and the weight of the hammer head is 3 tons.
Further, when the hole is formed by hammering and penetrates through a ballast layer, the mud retaining wall drilling operation is carried out by using a rotary pile machine.
The construction method of the ultra-thick backfill layer pile foundation adopts the special process of the invention, so that the hole forming of the ultra-thick backfill layer pile foundation is more convenient, efficient and rapid, the construction period can be further shortened, and the construction cost can be reduced. Therefore, the construction method of the ultra-thick backfill layer pile foundation has prominent substantive characteristics and remarkable progress.
The foregoing is a summary of the present invention, and in order to provide a clear understanding of the technical means of the present invention and to be implemented in accordance with the present specification, the following is a detailed description of the preferred embodiments of the present invention.
Detailed Description
The following examples are given to further illustrate the embodiments of the present invention. The following examples are intended to illustrate the invention but are not intended to limit the scope of the invention.
The invention is suitable for the situation that dynamic compaction is not carried out, the backfill layer naturally settles and is compact, and the structure is relatively loose; the backfill material contains blocky stones with the particle size larger than 500mm, and the thickness of the backfill layer is more than 11 m; the operation site is close to a seawall, and the surface water of the site is greatly influenced by sea surface tide level; the pile foundation type is drilling bored concrete pile, and the pile foundation interval is greater than 9 m.
The invention discloses a construction method of an ultra-thick backfill layer pile foundation, which comprises the following steps:
A. excavating a foundation pit for embedding the steel pipe pile casing on the ultra-thick backfill layer by adopting machinery, wherein the depth of the foundation pit exceeds 5 m;
the ultra-thick backfill layer is a field formed by digging a mountain and backfilling the ground, which is close to a sea wall, and the surface water of the field is influenced by the sea surface tide level, the field is not subjected to dynamic compaction, the backfill layer is compacted through natural sedimentation, and the internal structure is relatively loose; the backfill material contains blocky stones with the particle size larger than 500mm, and the thickness of the backfill layer is more than 11 m;
B. filling a clay layer into the bottom of the foundation pit, and then arranging the steel pipe pile casing into the foundation pit along the vertical direction, wherein the thickness of the clay layer is more than 500 mm;
C. exposing the top end of the backfilled steel pipe pile casing out of the ground;
D. preparing mud by stirring clay and water, wherein the specific gravity of the mud is more than 1.35;
E. pouring the prepared slurry into the steel pipe protective cylinder, and filling the steel pipe protective cylinder with the slurry;
F. hammering a backfill layer in the steel pipe pile casing by adopting a hammering pile, forming a hole by using a slurry protecting wall, and hammering the hole to be below an underground water level influence line;
G. adding Portland cement into the steel pipe casing filled with the slurry, fully stirring the Portland cement and the slurry to form cement slurry, standing for more than 12 hours, and continuously hammering the pile to hammer the backfill layer in the steel pipe casing until the hammering hole forms and penetrates through the ultra-thick backfill layer.
As a further improvement of the invention, the penetration rate of the hammering hole forming is controlled to be 0.5-1.25m every 30 minutes, and the penetration rate is controlled to be 0.1-0.35m every 30 minutes when meeting the large-particle-size rock block;
as a further improvement of the invention, the inner diameter of the steel pipe casing is 800mm, the diameter of the hammerhead of the hammering pile is 600mm, the length of the hammerhead is 2.7 meters, and the hammerhead weighs 3 tons.
As a further improvement of the invention, when the hammer is used for drilling holes to penetrate through the slag layer, the rotary pile machine is used for carrying out mud wall protection drilling operation.
The above description is only a preferred embodiment of the present invention and is not intended to limit the present invention, it should be noted that, for those skilled in the art, many modifications and variations can be made without departing from the technical principle of the present invention, and these modifications and variations should also be regarded as the protection scope of the present invention.

Claims (2)

1. The construction method of the ultra-thick backfill layer pile foundation is characterized by comprising the following steps:
A. excavating a foundation pit for embedding the steel pipe pile casing on the ultra-thick backfill layer by adopting machinery, wherein the depth of the foundation pit exceeds 5 m;
the ultra-thick backfill layer is a field formed by digging a mountain and backfilling the ground, which is close to a sea wall, and the surface water of the field is influenced by the sea surface tide level, the field is not subjected to dynamic compaction, the backfill layer is compacted through natural sedimentation, and the internal structure is relatively loose; the backfill material contains blocky stones with the particle size larger than 500mm, and the thickness of the backfill layer is more than 11 m;
B. filling a clay layer into the bottom of the foundation pit, and then arranging the steel pipe pile casing into the foundation pit along the vertical direction, wherein the thickness of the clay layer is more than 500 mm;
C. exposing the top end of the backfilled steel pipe pile casing out of the ground;
D. preparing mud by stirring clay and water, wherein the specific gravity of the mud is more than 1.35;
E. pouring the prepared slurry into the steel pipe protective cylinder, and filling the steel pipe protective cylinder with the slurry;
F. hammering a backfill layer in the steel pipe pile casing by adopting a hammering pile, forming a hole by using a slurry protecting wall, and hammering the hole to be below an underground water level influence line; the penetration rate of the hammering hole forming is controlled to be 0.5-1.25m every 30 minutes, and the penetration rate is controlled to be 0.1-0.35m every 30 minutes when the hammering hole forming meets the large-particle-size rock block; when the hole is formed by hammering and penetrates through a slag layer of the pond, the mud retaining wall drilling operation is carried out by using a rotary pile machine;
G. adding Portland cement into the steel pipe casing filled with the slurry, fully stirring the Portland cement and the slurry to form cement slurry, standing for more than 12 hours, and continuously hammering the pile to hammer the backfill layer in the steel pipe casing until the hammering hole forms and penetrates through the ultra-thick backfill layer.
2. The construction method of the ultra-thick backfill layer pile foundation according to the claim 1, characterized in that: the internal diameter of a steel pipe protects a section of thick bamboo is 800mm, the tup diameter of hammering stake is 600mm, and the tup is long 2.7 meters, and the tup is heavy 3 tons.
CN201710443680.8A 2017-06-13 2017-06-13 Construction method of ultra-thick backfill layer pile foundation Active CN107327314B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710443680.8A CN107327314B (en) 2017-06-13 2017-06-13 Construction method of ultra-thick backfill layer pile foundation

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710443680.8A CN107327314B (en) 2017-06-13 2017-06-13 Construction method of ultra-thick backfill layer pile foundation

Publications (2)

Publication Number Publication Date
CN107327314A CN107327314A (en) 2017-11-07
CN107327314B true CN107327314B (en) 2020-06-05

Family

ID=60194239

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710443680.8A Active CN107327314B (en) 2017-06-13 2017-06-13 Construction method of ultra-thick backfill layer pile foundation

Country Status (1)

Country Link
CN (1) CN107327314B (en)

Family Cites Families (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP3672304B1 (en) * 2004-10-28 2005-07-20 株式会社高特 Filling method of existing buried hollow pipe and backfilling method of existing structure
CN101289861B (en) * 2008-04-10 2010-08-11 中交三航局第二工程有限公司 Pile foundation construction method for foundation ditch in water
CN102518130B (en) * 2011-12-29 2014-12-17 中铁上海工程局集团华海工程有限公司 Manufacturing method of and construction process of reinforcement cage cement plaster pile casing
CN104120716A (en) * 2013-04-28 2014-10-29 杨哲 Slurry wall protection construction method for bored pile
CN104818712B (en) * 2015-04-07 2017-01-18 浙江大华建设集团有限公司 Construction method of cast-in-situ bored pile suitable for karst cave geology

Also Published As

Publication number Publication date
CN107327314A (en) 2017-11-07

Similar Documents

Publication Publication Date Title
Smoltczyk Geotechnical Engineering Handbook, Procedures
WO2018210019A1 (en) Pile formation method for down-the-hole impact rotary jet composite piles
CN102011391B (en) Reinforcement processing method of soft foundation
CN102733378B (en) Construction method of concrete pile
CN101487252A (en) Construction process of cast-in-situ bored pile
CN103485336A (en) Drilling pile drilling construction method of bead-type karst area
CN109385992B (en) Construction method for forming hole in artificial stone-filling layer
CN104612179B (en) Through the construction method of the diaphram wall of super thick silty sand ground
CN111042116A (en) Karst cave stratum pile foundation construction method
CA2942801C (en) Method for installing metal piles in permafrost soil
CN106812149A (en) A kind of construction method of pile foundation
CN109518677A (en) Punching Borehole Cast-in-place Concrete Pile karst cave treatment method
CN104746505A (en) Method for treating miscellaneous fill foundation combing dynamic consolidation and compaction grouting
CN106522191A (en) Transformer substation foundation treatment method and application thereof
CN101225664A (en) Caisson dock structure and construction method therefor
CN110761265A (en) Karst cave disposal method for deep foundation pit pile foundation construction in karst area
CN102912789A (en) Mechanical hole forming technology applied to karst landform
CN110397056A (en) A kind of deep building pit piping method for blocking
CN101481913A (en) Construction method of rock-socketed underground continuous wall punching slot section
CN101899827B (en) Broken soil vibration and compaction treatment method by utilizing impact hammer in immersed tube in riprap filled foundation
CN107327314B (en) Construction method of ultra-thick backfill layer pile foundation
CN106869153A (en) A kind of method of the quick soft soil foundation treatment of well-points dewatering
CN205776209U (en) The construction equipment of concrete-pile
RU121275U1 (en) REINFORCED GROUND-CEMENT WALL FOR PROTECTION OF BUILDINGS AND STRUCTURES FROM THE DIGGED NEAR THE CROWDED
CN109113054A (en) A kind of reclaimation area complex geological condition cast-in-situ bored pile multimachine combined construction method

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant