CN107322157B - A kind of exothermic welding method being grounded in Amazon tropic rain forest - Google Patents

A kind of exothermic welding method being grounded in Amazon tropic rain forest Download PDF

Info

Publication number
CN107322157B
CN107322157B CN201710684313.7A CN201710684313A CN107322157B CN 107322157 B CN107322157 B CN 107322157B CN 201710684313 A CN201710684313 A CN 201710684313A CN 107322157 B CN107322157 B CN 107322157B
Authority
CN
China
Prior art keywords
mold
welded
connector
welding
plumb joint
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201710684313.7A
Other languages
Chinese (zh)
Other versions
CN107322157A (en
Inventor
宋维洋
庞继勇
邵国栋
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
SEPCO1 Electric Power Construction Co Ltd
Original Assignee
SEPCO1 Electric Power Construction Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by SEPCO1 Electric Power Construction Co Ltd filed Critical SEPCO1 Electric Power Construction Co Ltd
Priority to CN201710684313.7A priority Critical patent/CN107322157B/en
Publication of CN107322157A publication Critical patent/CN107322157A/en
Application granted granted Critical
Publication of CN107322157B publication Critical patent/CN107322157B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • BPERFORMING OPERATIONS; TRANSPORTING
    • B23MACHINE TOOLS; METAL-WORKING NOT OTHERWISE PROVIDED FOR
    • B23KSOLDERING OR UNSOLDERING; WELDING; CLADDING OR PLATING BY SOLDERING OR WELDING; CUTTING BY APPLYING HEAT LOCALLY, e.g. FLAME CUTTING; WORKING BY LASER BEAM
    • B23K23/00Alumino-thermic welding

Abstract

The present invention relates to the exothermic welding method being grounded in a kind of Amazon tropic rain forest, include the following steps: that cutting pincers with circular arc is all whittled into the cone that cone angle is α for the connector to be welded being grounded at docking;The connector to be welded of ground line is stopped up with iron wire and is dried;Connector to be welded is wiped with cotton gauze until removing oxide layer is completely exposed metallic luster;Connector to be welded, which is put into mold welding booth, to be made at plumb joint face and mold diversion trench central outlet to be formed;Mold and connector to be welded are heated;Mold will integrally be heated again after mold clamping;The supporting spring of mold is placed on to the bottom of hot melt room;Suitable welding powder pours into the hot melt room with scale mark, is spilled into a small amount of pyrophoric powder, the one end for rope of igniting is inserted into pyrophoric powder, other end extraction mold, and the rope of igniting outside mold is lighted after fastening die cover;Cooling 30-50s after having welded opens mold and takes out plumb joint and to its dress watch, it is qualified after on plumb joint anticorrosion with painting paint.

Description

A kind of exothermic welding method being grounded in Amazon tropic rain forest
Technical field
The invention belongs to the welding techniques of ground line, and in particular to the welding side being grounded in a kind of Amazon tropic rain forest Method.
Background technique
Earthed system mainly selects the i.e. common galvanized strand wires of flexible ground line in Amazon tropic rain forest grounding construction. The segmentation laying of flexible ground line, connector is more, and connector is bolted using generic connectivity fitting.Such connection type is not Only cause flexible ground line can not robust connection, work progress center tap part zinc coat repeatedly worn, and Since junction portion is directly contacted with soil so that the accelerated corrosion in the environment of Amazon tropic rain forest humidity of flexible ground line, Greatly shorten earthed system service life, seriously affects earthed system safe and stable operation.
Therefore, this flexible ground line is bolted technology, can not connect the ground line robust of segmentation, conductive Reliability is poor;Vulnerable to abrasion, junction portion is directly exposed to be contacted work progress center tap part zinc coat with soil, is made The corrosion for accelerating earthed system in Amazon tropic rain forest wet environment is obtained, earthed system safe and stable operation is unfavorable for.It connects Ground system reduced service life, increase later period operation maintenance personnel to ground connection system maintenance, transformation working strength, increase O&M at This.
In the prior art, there are also one is with heat release welding technology, heat release weldering is also referred to as chamotte for the connection of ground line or grounded screen Thermofussion welding is that two or more connectors to be welded of ground line are placed on the high fever generated in specific weld mold using chemical reaction Can, it fuses into one to form molecule combination at place to be welded, this technology welding effect in copper ground line is preferable.On the one hand it is directed to It is different to put heat weldable welding powder dosage welding quality to welding end and weld mold and have direct influence, on the other hand in such as sub- horse This high temperature in inferior rainforest, in the adverse circumstances of high humility, galvanized strand wires plumb joint surface oxidation, corrosion rate are fast, institute With at present be to be bolted.How to guarantee heat release weldering normal construction and how to improve the machinery of the junction after welding by force Degree and corrosion resistance are urgent problems to be solved in the prior art.
Summary of the invention
To solve the above-mentioned problems, the present invention provides the exothermic weld sides being grounded in a kind of Amazon tropic rain forest Earthed system service life is greatly improved in method, and technique is accurate and reliable, reduces the maintenance work to earthed system, reduces production Cost.
The technical solution adopted by the invention is as follows:
The exothermic welding method being grounded in a kind of Amazon tropic rain forest, includes the following steps:
S1, pincers are cut with circular arc the connector to be welded being grounded at docking is all whittled into the cone that cone angle is α, the α is 50 ° ≤α≤70°;
S2, the connector to be welded of ground line is stopped up with iron wire, mold and connector to be welded are dried with flame gun, The pre-heat treatment;
S3, connector to be welded is wiped with cotton gauze until removing oxide layer is completely exposed metallic luster, while cleaning out mould Tool;
S4, connector to be welded is put into mold welding booth makes plumb joint face and mold diversion trench central outlet to be formed Place;
S5, mold and connector to be welded are heated with flame gun;
S6, mold will integrally be heated again after mold clamping;
Diversion trench upper port is blocked in S7, the bottom that the supporting spring of mold is placed on to hot melt room;
S8, suitable welding powder is poured into the hot melt room with scale mark, is spilled into a small amount of pyrophoric powder, by the one end for rope of igniting It is inserted into pyrophoric powder, other end extraction mold, the rope of igniting outside mold is lighted after fastening die cover;
S9, cooling 30-50s after having welded open mold and take out plumb joint and to its dress watch, it is qualified after in plumb joint Upper anticorrosion with painting paint.
In above-mentioned steps S5, when heating to mold and connector to be welded, real time temperature measurement is carried out to the two with infrared temperature measurement gun, Guarantee that the two temperature is all not less than 165 DEG C and the state continues 18-30s;In above-mentioned steps S6, make outside mold when being heated after molding The temperature of wall is not less than 180 DEG C and continues 30-60s.
In above-mentioned steps S8, the dosage of the welding powder is [0.0089L π r2+1200 °/α] g, and wherein L is two groups to be welded The total length and unit of head are mm, and r is ground line radius and unit mm.
In above-mentioned steps S1, the joint length to be welded of the cone is the 1/3-1/2 of mold welding booth length;Above-mentioned step In rapid S4, the group of the connector to be welded is 1-2mm to gap.
The invention has the benefit that
Segmentation treats welding end, mold is heated and controls acid extraction, forms the copper with high mechanical strength Envelope connection, plumb joint appearance are in ellipticity, and processing quality is beautiful;Implement to prove on the one hand postwelding cooling a period of time facilitates Plumb joint cooled and solidified and surface formation have the oxidation film of corrosion-resisting function, have delayed ground line in moist hot environment Corrosion rate;On the other hand vigorous reaction influences weldering after steam being contacted to avoid the plumb joint of high temperature in the big environment of humidity It connects effect and even forms point on surface;
Room graduation mark mark is heated, welding powder additional amount, entire sweat soldering operation are accurately controlled by welding powder dosage formula It is safe and efficient;
Plumb joint is not easy to relax, and welded joint does not have surface and residual stress, stable as grounded conductive body, reliable, subtracts Few later maintenance service work, greatly reduction production cost;
Plumb joint sprays the anti-decaying paint made by two-part epoxy with gas tank, further extends the use of earthed system Service life.
Detailed description of the invention
Fig. 1 is the mold structure diagram used in exothermic welding method of the present invention,
In figure: 1 be die cover, 2 for ignite rope, 3 be hot melt room, 4 be supporting spring, 5 be diversion trench, 6 be welding booth, 7 for Plumb joint.
Specific embodiment
The present invention relates to the exothermic welding methods being grounded in a kind of Amazon tropic rain forest, include the following steps:
S1, circular arc cut pincers and the connector to be welded 7 being grounded at docking are all whittled into cone, the connector to be welded of the cone 7 length are the 1/3-1/2 of 6 length of mold welding booth, and the cone angle of the connector to be welded 7 of the cone is 50-70 °;
S2, the connector to be welded 7 of ground line is stopped up with iron wire, mold and connector to be welded 7 is dried with flame gun Dry, the pre-heat treatment;
S3, it is completely exposed metallic luster until removing oxide layer with cotton gauze wiping connector 7 to be welded, while cleans out mould Tool;
S4, connector 7 to be welded is put into mold welding booth 6 goes out plumb joint face and mold water conservancy diversion groove center to be formed At mouthful, the group of the connector to be welded is 1-2mm to gap;
S5, mold and connector to be welded are heated with flame gun, real time temperature measurement is carried out to the two with infrared temperature measurement gun, is guaranteed The two temperature is all not less than 165 DEG C and continues 18-30s;
S6, mold will integrally be heated again after mold clamping, make the temperature of outer mold wall not less than 180 DEG C and continues 30- 60s;
5 upper port of diversion trench is blocked in S7, the bottom that the supporting spring 4 of mold is placed on to hot melt room;
S8, suitable welding powder is poured into the hot melt room 3 with scale mark, is spilled into a small amount of pyrophoric powder, will ignite the one of rope 2 End is inserted into pyrophoric powder, the other end draws mold, and the rope 6 of igniting outside mold is lighted after fastening die cover 1;The dosage of the welding powder For [0.0089L π r2+1200 °/α] g, wherein L is the total length of two groups of connectors 7 to be welded and unit is mm, and r is ground line radius And unit mm;
S9, cooling 30-50s after having welded open mold and take out plumb joint and to its dress watch, it is qualified after in plumb joint Upper anticorrosion with painting paint.
Beautiful mountain ± 800kV the extra-high voltage direct-current of the first extra high voltage line engineering built outside China sea below i.e. Brazil In work transmission line, further explained by each embodiment and comparative example present invention.
All embodiment and comparative examples are all using the weld part of 30 "-" types as object, and pilot project is also to extract phase With the sample of quantity.Embodiment 1 to 3 is to carry out constructing operation using above-mentioned exothermic welding method provided by the invention, is specifically shown in Each embodiment.Under the premise of being grounded with the same welding surroundings of embodiment, comparative example 1 is to utilize existing general copper-clad copper The exothermic welding method of welding carries out constructing operation, and comparative example 2 is to be bolted ground line using in the prior art.
Embodiment 1
S1,30 are treated plumb joint 7 and is divided into three groups every group and treat plumb joint 7 for 10, cut pincers for three groups of ground lines with circular arc It is first group 50 °, second group 60 ° and 70 ° of third group of cone that connector to be welded 7 at docking is whittled into cone angle respectively, each to The conus portion length of plumb joint 7 is the 1/2 of 6 length of mold welding booth;
S2, the connector to be welded 7 of ground line is stopped up with iron wire, mold and connector to be welded 7 is dried with flame gun Dry, the pre-heat treatment;
S3, it is completely exposed metallic luster until removing oxide layer with cotton gauze wiping connector 7 to be welded, while cleans out mould Tool;
S4, connector 7 to be welded is put into mold welding booth 6 makes 5 center of plumb joint face and mold diversion trench to be formed Exit, the group between the connector 7 to be welded is 1-2mm to gap;
S5, mold and connector to be welded 7 are heated with flame gun, real time temperature measurement is carried out to the two with infrared temperature measurement gun, is protected Both cards temperature is at 200 DEG C or so and continues 18s;
S6, mold will integrally be heated again after mold clamping, made between 185-200 DEG C of temperature of outer mold wall and continued 60s;
5 upper port of diversion trench is blocked in S7, the bottom that the supporting spring 4 of mold is placed on to hot melt room 3;
S8, suitable welding powder is poured into the hot melt room 3 with scale mark, specific dosage is shown in Table lattice 1;It is spilled into later a small amount of The one end for rope 2 of igniting is inserted into pyrophoric powder, other end extraction mold, lights drawing outside mold after fastening die cover 1 by pyrophoric powder Fiery rope 2;
S9, rear three group welding portions cooling 30s, 40s, 50s respectively have been welded, has opened mold taking-up plumb joint and simultaneously it is cleared up It checks, the detection of technological effect is carried out according to the test parameters of table 1 and 2.
Embodiment 2
S1, to treat plumb joint 7 by 30 to be all whittled into cone angle be 60 ° of cone, and the conus portion length of each connector 7 to be welded is The 1/2 of 6 length of mold welding booth;
S2, the connector to be welded 7 of ground line is stopped up with iron wire, mold and connector to be welded 7 is dried with flame gun Dry, the pre-heat treatment;
S3, it is completely exposed metallic luster until removing oxide layer with cotton gauze wiping connector 7 to be welded, while cleans out mould Tool;
S4, connector 7 to be welded is put into mold welding booth 6 makes 5 center of plumb joint face and mold diversion trench to be formed Exit, the group between the connector 7 to be welded is 1-2mm to gap;
S5, mold and connector to be welded 7 are heated with flame gun, real time temperature measurement is carried out to the two with infrared temperature measurement gun, is protected Both cards temperature is all between 180-190 DEG C and continues 25s;
S6, mold will integrally be heated again after mold clamping, made between 220-240 DEG C of temperature of outer mold wall and continued 40s;
5 upper port of diversion trench is blocked in S7, the bottom that the supporting spring 4 of mold is placed on to hot melt room 3;
S8, suitable welding powder is poured into the hot melt room 3 with scale mark, is spilled into a small amount of pyrophoric powder, will ignite the one of rope 2 End is inserted into pyrophoric powder, the other end draws mold, and the rope 2 of igniting outside mold is lighted after fastening die cover 1;
S9, cooling 40s after having welded, opening mold takes out plumb joint and to its dress watch, according to the examination of table 1 and 2 Test the detection that parameter carries out technological effect.
Embodiment 3
S1, to treat plumb joint by 30 to be whittled into cone angle be 60 ° of cone, and the conus portion length of each connector 7 to be welded is mould Has the 1/2 of 6 length of welding booth;
S2, the connector to be welded 7 of ground line is stopped up with iron wire, mold and connector to be welded 7 is dried with flame gun Dry, the pre-heat treatment;
S3, it is completely exposed metallic luster until removing oxide layer with cotton gauze wiping connector 7 to be welded, while cleans out mould Tool;
S4, connector 7 to be welded is put into mold welding booth 6 makes 5 center of plumb joint face and mold diversion trench to be formed Exit, the group between the connector 7 to be welded is 1-2mm to gap;
S5, mold and connector to be welded 7 are heated with flame gun, real time temperature measurement is carried out to the two with infrared temperature measurement gun, is protected Both cards temperature is between 165-180 DEG C and continues 30s;
S6, mold will integrally be heated again after mold clamping, make between 300 DEG C of temperature of outer mold wall and continues 30s;
5 upper port of diversion trench is blocked in S7, the bottom that the supporting spring 4 of mold is placed on to hot melt room 3;
S8, suitable welding powder is poured into the hot melt room 3 with scale mark, is spilled into a small amount of pyrophoric powder, will ignite the one of rope 2 End is inserted into pyrophoric powder, the other end draws mold, and the rope 2 of igniting outside mold is lighted after fastening die cover 1;
S9, welding cool down 50s respectively after having reacted, opening mold takes out plumb joint and to its dress watch, according to table 1 Test parameters with 2 carries out the detection of technological effect.
Comparative example 1
S1, to treat plumb joint by 30 to be whittled into cone angle be 60 ° of cone, and the conus portion length of each connector 7 to be welded is mould Has the 1/2 of 6 length of welding booth;
S2, the connector to be welded 7 of ground line is stopped up with iron wire, mold and connector to be welded 7 is dried with flame gun Dry-cure;
S3, it is completely exposed metallic luster until removing oxide layer with cotton gauze wiping connector 7 to be welded, while cleans out mould Tool;
S4, connector 7 to be welded is put into mold welding booth 6 makes 5 center of plumb joint face and mold diversion trench to be formed Exit, the group between the connector 7 to be welded is 1-2mm to gap;
5 upper port of diversion trench is blocked in S5, the bottom that the supporting spring 4 of mold is placed on to hot melt room 3;
S6, suitable welding powder is poured into the hot melt room 3 with scale mark, is spilled into a small amount of pyrophoric powder, will ignite the one of rope 2 End is inserted into pyrophoric powder, the other end draws mold, and the rope 2 of igniting outside mold is lighted after fastening die cover 1;
S7, mold is directly opened after having welded take out plumb joint and to its dress watch, joined according to the test of table 1 and 2 Number carries out the detection of technological effect.
Comparative example 2
Attachment cap with holes is set in ground line end using the prior art, tightening attachment cap with bolt makes ground line each other Connection.
Table 1 is the technological effect after the completion of welding to weld part:
Project name Embodiment 1 Embodiment 2 Embodiment 3 Comparative example 1 Comparative example 2
It is grounded linear diameter (mm) Φ9.52 Φ9.52 Φ9.52 Φ9.52 Φ9.52
The cone angle of connector 7 to be welded First group is 50 °, and second group is 60 °, the Three groups are 70 ° 60° 60° 60° Nothing
The length of connector 7 to be welded L/2(mm) 75 70 75 75 Nothing
Welding powder dosage (g) First group is 119, and second group is 115, the Three groups are 112 109 115 120 Nothing
Weld part resistivity becomes Change value (* 10-3Ω· Mm2/m) First group be ± 0.05, second group for- 0.01 ~+0.02, third group is ± 0.03 ±0.01 0~+0.03 -0.08~+0.10 ±0.15
Weld part outer surface matter Amount Three groups are all the smooth no welding slag in surface, solderless Tumor, whole uniform, the both ends radian of weld part Smoothly The smooth no welding slag in surface, without overlap, weldering Socket part is whole uniformly, both ends radian is smooth Non-welding surface slag, without overlap, the whole uniformly both ends arc of weld part There are the fiber crops of slight convex at smooth, the intermediate face diversion trench 5 of degree Point Face of weld at face diversion trench 5 has bright Aobvious welding slag, weld part both ends are thicker and can see To slight weld seam Nothing
Weld cross section matter Amount If the visible section of three group welding portion naked eyes has The dry identical minute bubbles of size, and uniformly divide Cloth Naked eye is visible only close to outer surface Section on have several minute bubbles and Even distribution Naked eye it is visible only close to outer surface section on have it is several Minute bubbles and be uniformly distributed, and 4 on section at or so it is light Micro- point Naked eye can see that there is non-uniform gas in section Bubble and apparent point at 4-7 Nothing
The weld part embedment underground normal ground that remaining not test (N.T.) cross section is destroyed works three months, and table 2 below is Situation after the buried work of weld part three months:
Embodiment 1 Embodiment 3 Embodiment 3 Comparative example 1 Comparative example 2
Weld part change in resistance value (* 10-3Ω mm2/m) ±0.25 ±0.12 ±0.20 ±1.00 ±1.20
Weld part outer surface quality The a small amount of rust staining in surface, cleaning rear surface have If the dry corrosion concave point of lax distribution Surface without rust staining, has lax substantially If the dry corrosion concave point of distribution The a small amount of rust staining in surface, cleaning rear surface have ratio If the slightly more dry corrosion concave point of embodiment 1 Surface is completely covered by rust staining and rust staining thickness is in 1-2mm Degree, cleaning rear surface largely corrode concave point Bolt gets rusty seriously, twists It completely can not be again after lower With
Weld part whether desoldering It is no It is no It is no The both ends of weld part are serious to intermediate direction desoldering Attachment cap and ground line Connection loosens
By above-mentioned Tables 1 and 2 as it can be seen that when being cooled down before weldering to mold and connector heating temperature to be welded, the dosage of welding powder, postwelding Between etc. composite factors all have an impact to weld part quality and change in resistance.

Claims (3)

1. the exothermic welding method being grounded in a kind of Amazon tropic rain forest, which comprises the steps of:
S1, pincers are cut with circular arc the connector to be welded being grounded at docking is all whittled into the cone that cone angle is α, the α is 50 °≤α ≤70°;
S2, the connector to be welded of ground line is stopped up with iron wire, mold and connector to be welded is dried with flame gun, preheated Processing;
S3, connector to be welded is wiped with cotton gauze until removing oxide layer is completely exposed metallic luster, while cleaning out mold;
S4, connector to be welded is put into mold welding booth makes at plumb joint face and mold diversion trench central outlet to be formed;
S5, mold and connector to be welded are heated with flame gun;
S6, mold will integrally be heated again after mold clamping;
Diversion trench upper port is blocked in S7, the bottom that the supporting spring of mold is placed on to hot melt room;
S8, suitable welding powder is poured into the hot melt room with scale mark, is spilled into a small amount of pyrophoric powder, the one end for rope of igniting is inserted into In pyrophoric powder, the other end draw mold, light rope of igniting outside mold after fastening die cover;The dosage of the welding powder is [0.0089L π r2+1200 °/α] g, wherein L is the total length of two groups of connectors to be welded and unit is mm, r be ground line radius and Unit is mm;
S9, cooling 30-50s after having welded, opening mold take out plumb joint and to its dress watch, spray on plumb joint after qualified Apply anti-decaying paint.
2. exothermic welding method according to claim 1, it is characterised in that: in above-mentioned steps S5, to mold and to be welded When head heating, real time temperature measurement is carried out to the two with infrared temperature measurement gun, guarantees that the two temperature is all not less than 165 DEG C and the state is held Continuous 18-30s;In above-mentioned steps S6, makes the temperature of outer mold wall not less than 180 DEG C when heating after molding and continue 30-60s.
3. exothermic welding method according to claim 1, it is characterised in that: in above-mentioned steps S1, it is described cone to Plumb joint length is the 1/3-1/2 of mold welding booth length;In above-mentioned steps S4, the group of the connector to be welded is 1- to gap 2mm。
CN201710684313.7A 2017-08-11 2017-08-11 A kind of exothermic welding method being grounded in Amazon tropic rain forest Active CN107322157B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710684313.7A CN107322157B (en) 2017-08-11 2017-08-11 A kind of exothermic welding method being grounded in Amazon tropic rain forest

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710684313.7A CN107322157B (en) 2017-08-11 2017-08-11 A kind of exothermic welding method being grounded in Amazon tropic rain forest

Publications (2)

Publication Number Publication Date
CN107322157A CN107322157A (en) 2017-11-07
CN107322157B true CN107322157B (en) 2019-08-20

Family

ID=60200283

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710684313.7A Active CN107322157B (en) 2017-08-11 2017-08-11 A kind of exothermic welding method being grounded in Amazon tropic rain forest

Country Status (1)

Country Link
CN (1) CN107322157B (en)

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2019033223A1 (en) * 2017-08-14 2019-02-21 山东电力建设第一工程公司 Exothermic welding method for welding grounding wires in amazon rainforest

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH06106367A (en) * 1991-10-30 1994-04-19 Erico Internatl Corp Aluminum welding method and reaction agent mixture for use in said method
EP0802013A1 (en) * 1996-04-18 1997-10-22 Erico International Corporation Welding mold and method
CN102000894A (en) * 2010-11-05 2011-04-06 中国建筑第八工程局有限公司 Exothermic thermofussion welding construction method of airport terminal lightningproof grounding copper clad steel conductor
CN102049625A (en) * 2010-11-17 2011-05-11 国家电网公司直流建设分公司 Heat release welding process for grounding electrode facility of power grid direct current engineering
CN103264222A (en) * 2013-05-24 2013-08-28 合肥荣事达三洋电器股份有限公司 Welding method for aluminium wire and copper wire for motor
CN103506755A (en) * 2013-10-14 2014-01-15 湖北威达电气有限公司 Iron-based nonelectric welding device
CN104209670A (en) * 2014-08-19 2014-12-17 李立志 Construction method of grounding system heat release welding

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH06106367A (en) * 1991-10-30 1994-04-19 Erico Internatl Corp Aluminum welding method and reaction agent mixture for use in said method
EP0802013A1 (en) * 1996-04-18 1997-10-22 Erico International Corporation Welding mold and method
CN102000894A (en) * 2010-11-05 2011-04-06 中国建筑第八工程局有限公司 Exothermic thermofussion welding construction method of airport terminal lightningproof grounding copper clad steel conductor
CN102049625A (en) * 2010-11-17 2011-05-11 国家电网公司直流建设分公司 Heat release welding process for grounding electrode facility of power grid direct current engineering
CN103264222A (en) * 2013-05-24 2013-08-28 合肥荣事达三洋电器股份有限公司 Welding method for aluminium wire and copper wire for motor
CN103506755A (en) * 2013-10-14 2014-01-15 湖北威达电气有限公司 Iron-based nonelectric welding device
CN104209670A (en) * 2014-08-19 2014-12-17 李立志 Construction method of grounding system heat release welding

Non-Patent Citations (2)

* Cited by examiner, † Cited by third party
Title
凯维放热焊接法在某近海核电站接地网中的应用;李勇;《科技信息》;20110825(第24期);第5-6节
铝热焊接在苏丹上阿特巴拉电站接地施工中的应用;殷高翔;《四川水力发电》;20160615;第35卷(第03期);第55、56和101页

Also Published As

Publication number Publication date
CN107322157A (en) 2017-11-07

Similar Documents

Publication Publication Date Title
CN102303178B (en) Semi-automatic gas shield welding construction technology for aluminum conductors
CN107322157B (en) A kind of exothermic welding method being grounded in Amazon tropic rain forest
CN106270965A (en) A kind of welding procedure of X80 level pipe line steel circular weld
CN105479122B (en) A kind of composite welded pipe production technology of on-line continuous outer galvanizing and interior coating
CN108180325A (en) A kind of production method of band injection electric heating melting bell and spigot joint internal-rib bellows and its connector
CN104588964B (en) Dissimilar metal tubing and its preparation method and application
CN109622939A (en) Copper alloy surface wear-resistant coating and preparation method are prepared with CuMnNi
CN102049625A (en) Heat release welding process for grounding electrode facility of power grid direct current engineering
CN205342165U (en) Anti -corrosion overlay of tube sheet large tracts of land and have its tube sheet
CN203696258U (en) Device for heat-released welding
CN103372641A (en) Steel wire rope head casting method
CN104209670A (en) Construction method of grounding system heat release welding
CN105149742A (en) T23 steel pipe welding process
CN104625477A (en) Passive self-breeding high-heat pasty fluid for automatic stainless steel welding and preparation and using methods thereof
CN206393077U (en) A kind of mould for being used to weld copper-plated ground line
CN205583166U (en) Improve ground net and prevent corrosive effects's device
CN212560404U (en) Tin frock is warded off with electrically conductive copper bar of positive pole roof beam to hydrometallurgy
CN209632363U (en) A kind of online gas shield device of welded tube welding seam
CN207145836U (en) A kind of heavy antisepsis elbow bend pipe
CN208841889U (en) A kind of heat-shrink tube shrinkage apparatus
WO2019033223A1 (en) Exothermic welding method for welding grounding wires in amazon rainforest
CN102059468A (en) Nano-scale splash-preventing propellent solution
KR101670396B1 (en) Hose connection manifold and the fuel supply hose manufacturing method of automatic gas cutting machine using the same
CN205817062U (en) Welding wire preheating lance
CN104439756A (en) Passive self-breeding high-heat carbon steel metal automatic welding pasty fluid and preparing method and using method of passive self-breeding high-heat carbon steel metal automatic welding pasty fluid

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant