CN107254882A CN201710624973.6A CN201710624973A CN107254882A CN 107254882 A CN107254882 A CN 107254882A CN 201710624973 A CN201710624973 A CN 201710624973A CN 107254882 A CN107254882 A CN 107254882A
Authority
CN
China
Prior art keywords
grout
pipe
scall
highly permeable
hole
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201710624973.6A
Other languages
Chinese (zh)
Other versions
CN107254882B (en
Inventor
郭国华
邹爱明
杨志清
杨齐
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Sinohydro Bureau 8 Co Ltd
Original Assignee
Sinohydro Bureau 8 Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Sinohydro Bureau 8 Co Ltd filed Critical Sinohydro Bureau 8 Co Ltd
Priority to CN201710624973.6A priority Critical patent/CN107254882B/en
Publication of CN107254882A publication Critical patent/CN107254882A/en
Application granted granted Critical
Publication of CN107254882B publication Critical patent/CN107254882B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D19/00Keeping dry foundation sites or other areas in the ground
    • E02D19/06Restraining of underground water
    • E02D19/12Restraining of underground water by damming or interrupting the passage of underground water
    • E02D19/16Restraining of underground water by damming or interrupting the passage of underground water by placing or applying sealing substances
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D15/00Handling building or like materials for hydraulic engineering or foundations
    • E02D15/02Handling of bulk concrete specially for foundation or hydraulic engineering purposes
    • E02D15/04Placing concrete in mould-pipes, pile tubes, bore-holes or narrow shafts
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2250/00Production methods
    • E02D2250/0023Cast, i.e. in situ or in a mold or other formwork

Landscapes

  • Engineering & Computer Science (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Environmental & Geological Engineering (AREA)
  • Hydrology & Water Resources (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • Consolidation Of Soil By Introduction Of Solidifying Substances Into Soil (AREA)
  • Lining And Supports For Tunnels (AREA)

Abstract

The invention discloses a kind of highly permeable scall Quick leak stoppage apparatus and blocking method, device includes for the drilling tool for boring grout hole, combination floral tube and carries out sealed seal plug body to the aperture of grout hole after floral tube insertion grout hole for combining, combining floral tube includes at least one set of grout pipe group, every group of grout pipe group includes two grout pipes, the mouth of pipe closing of grout pipe lower end, and the aperture of grout hole is stretched out in upper end, grout pipe lower end surface or lower end side face are provided with grouting presbyopia, and the height for combining the lower surface of all grout pipes in floral tube is differed.Method includes:Bore grout hole and insert combination floral tube;The aperture of grout hole is poured using accelerated cement mortar;Each grout pipe is filled with cement-bentonite stable grout;To a grout pipe cement injection slurries in every group of grout pipe group, to another grout pipe priming petock glass pulp, make two kinds of slurries in highly permeable scall condensation by mixing filling space, quick blocking leakage passage.

Description

A kind of highly permeable scall Quick leak stoppage apparatus and blocking method
Technical field
The present invention relates to plasma pouring constructing skill field, more particularly to a kind of highly permeable scall Quick leak stoppage apparatus and stifled Leakage method.
Background technology
In engineering construction, highly permeable scall is primarily referred to as native stone accumulation body, original overburden layer, native stone Fill the big soil layer of the infiltration coefficients such as layer, there is water proof loading layer above general highly permeable scall, lower section have it is relative every Water layer.For the seepage of highly permeable scall, it is more effective, succinct mode to take two-shot grouting technology impervious leakage-stopping, Existing relatively advanced technology mainly has mini-valve tube two-shot grouting technology and the pure pressure type two-shot grouting technology of pipe laying shadoof, and both are double Liquid grouting technique common feature is that single Grouting Pipe is used in hole, cement grout and waterglass slurries are both needed in slurry bucket, The mouth of pipe or pipe in mixed, it is very high to Mortar mix proportion and human users' level requirement, it is careless slightly easily cause it is stifled Pipe or range of scatter can not meet the defects such as impervious leakage-stopping requirement very well.
The content of the invention
The technical problem to be solved in the present invention is to overcome the deficiencies in the prior art there is provided one kind by cement grout and waterglass In the earth formation mix, condense rapidly can quick blocking leakage passage highly permeable scall Quick leak stoppage apparatus and leak stopping side Method.
In order to solve the above technical problems, the present invention uses following technical scheme:
A kind of highly permeable scall Quick leak stoppage apparatus, including for boring the drilling tool of grout hole, combining floral tube and for group Close and sealed seal plug body is carried out to the aperture of grout hole after the floral tube insertion grout hole, the combination floral tube includes at least one Group grout pipe group, every group of grout pipe group includes two grout pipes, the closing of the grout pipe lower end mouth of pipe, and grout hole is stretched out in upper end Aperture, the grout pipe lower end surface or lower end side face are provided with grouting presbyopia, all grout pipes in the combination floral tube Height of the lower surface in the grout hole is differed.
It is used as the further improvement of above-mentioned technical proposal:
The grout hole passes through water proof loading layer, highly permeable scall, and extends to relative water resisting layer.
Lower surface highly minimum grout pipe extends to relative water resisting layer.
The device for plugging also includes being placed on the protection casing outside drilling tool during drilling.
The grout pipe upper end is provided with the grouting joint for being used for being connected with grouting pipeline.
The grout pipe is steel pipe or PRP pipes or PE pipes.
The length of each grout pipe is differed in the combination floral tube, and each grout pipe upper end is concordant, lower end edge grout hole It is staggeredly arranged above and below depth.
A kind of blocking method of the highly permeable scall Quick leak stoppage apparatus based on described in any of the above-described, including it is following Step:
S1, grout hole is drilled with, will be in combination floral tube insertion grout hole;
S2, the aperture for pouring using accelerated cement mortar grout hole form seal plug body;
S3, cement-each grout pipe of bentonite stable grout filling with high-consistency;
S4, to a grout pipe cement injection slurries in every group of grout pipe group, to another grout pipe priming petock glass pulp, Make two kinds of slurries in highly permeable scall condensation by mixing filling space, quick blocking leakage passage.
It is used as the further improvement of above-mentioned technical proposal:
Before step S1 is carried out, each grout pipe is bundled into a branch of, upper end alignment, and the grouting presbyopia of grout pipe uses adhesive tape Winding.
In step sl, protection casing is arranged while being drilled with grout hole outside drilling tool, after drilling terminates, drilling tool is taken out, Protection casing is stayed in grout hole, when floral tube to be combined is along protection casing insertion grout hole, extracts protection casing.
Compared with prior art, the advantage of the invention is that:
The highly permeable scall Quick leak stoppage apparatus of the present invention, during grouting, a grout pipe is used to fill in every group of grout pipe group Cementing slurries, another is used for priming petock glass pulp, and it is empty that two kinds of slurries are mixed and condensed in filling in highly permeable scall Gap, quick blocking leakage passage is realized and fills the highly permeables such as layer pine to native stone accumulation body, original overburden layer, native stone Dissipate stratum fast blockage;The present invention point make use of the loose big absorbent formation space of highly permeable it is big, it is connective good the characteristics of, cement mortar Liquid and waterglass slurry are mixed in the earth formation, are condensed rapidly after being mixed in the loose bottom of highly permeable, have both been not in plugging phenomenon, Again can be by adjusting the control of flow and pressure range of scatters of two kinds of slurries, it is ensured that quick effectively plugging effect;Meanwhile, overcome Prior art cement grout and waterglass slurries are in slurry bucket, the mouth of pipe or pipe in mixed, easily cause plugging or Range of scatter can not meet the defects such as impervious leakage-stopping requirement very well;In addition, requiring relatively low to operating personnel, it is only necessary to pass through Brief training can meet site operation requirement.
The highly permeable scall rapid plugging method for fiberglass of the present invention, is equally had cement grout using above-mentioned device for plugging Mixed in the earth formation with waterglass, condense it is rapid, can quick blocking leakage passage advantage.
Brief description of the drawings
Fig. 1 is the structural representation of Quick leak stoppage apparatus of the present invention.
Fig. 2 is the structural representation of combination floral tube in Quick leak stoppage apparatus of the present invention.
Fig. 3 is the structural representation of the grouting presbyopia of Quick leak stoppage apparatus of the present invention.
Fig. 4 is Quick leak stoppage apparatus drilling schematic diagram of the present invention.
Fig. 5 is the pre-buried combination floral tube schematic diagram of Quick leak stoppage apparatus of the present invention.
Fig. 6 is that Quick leak stoppage apparatus of the present invention fills combination floral tube schematic diagram temporarily.
Fig. 7 is Quick leak stoppage apparatus cement injection slurries of the present invention and waterglass slurries schematic diagram(One).
Fig. 8 is Quick leak stoppage apparatus cement injection slurries of the present invention and waterglass slurries schematic diagram(Two).
Fig. 9 is the flow chart of highly permeable scall rapid plugging method for fiberglass of the present invention.
Each label is represented in figure:
1st, grout hole;2nd, drilling tool;3rd, floral tube is combined;31st, grout pipe;311st, grouting presbyopia;312nd, bottom bulkhead;32nd, adhesive tape;4、 Seal plug body;51st, water proof loading layer;52nd, highly permeable scall;53rd, relative water resisting layer;6th, protection casing;7th, be in the milk pipeline; 8th, be in the milk joint;9th, grouting control valve.
Embodiment
The present invention is described in further detail below in conjunction with Figure of description and specific embodiment.
As shown in Figure 1 to Figure 3, the highly permeable scall Quick leak stoppage apparatus of the present embodiment, including for boring grout hole 1 Drilling tool 2, combination floral tube 3 and for sealedly being sealed to the aperture of grout hole 1 after combining the insertion grout hole 1 of floral tube 3 Stifled body 4, combination floral tube 3 includes at least one set of grout pipe group, and every group of grout pipe group includes two grout pipes 31, the lower end of grout pipe 31 The mouth of pipe is closed, and the aperture of grout hole 1 is stretched out in upper end, and the lower end surface of grout pipe 31 or lower end side face are provided with grouting presbyopia 311, Height of the lower surface of all grout pipes 31 in grout hole 1 is differed.
In concrete application example, grouting presbyopia 311, this reality can be set in the lower end surface of grout pipe 31 or lower end side face Apply in example, the lower end surface of grout pipe 31 is blocked by bottom bulkhead 312, grouting presbyopia 311 is arranged on the side face of lower end, beneficial to slurry Liquid enters highly permeable scall 52.
In the present embodiment, two groups of grout pipe groups are set, every group of grout pipe group includes the different grout pipe 31 of two pairs of length, one Individual to be used for cement injection slurries A, another is used for priming petock glass pulp B.The length of four grout pipes 31 is differed, each to fill Starch and be staggeredly arranged above and below the alignment of the upper end of pipe 31, the depth of lower end edge grout hole 1(Namely four grout pipes 31 are in grout hole 1 Height is differed), sufficiently uniformly enter highly permeable scall 52 beneficial to slurries.
Using the Quick leak stoppage apparatus of the present embodiment, during grouting, a grout pipe 31 is used to irrigate in every group of grout pipe group Cement grout A, another is used for priming petock glass pulp B, and two kinds of slurries are mixed and condensed in filling in highly permeable scall 52 Space, quick blocking leakage passage is realized and fills the highly permeables such as layer to native stone accumulation body, original overburden layer, native stone Scall fast blockage.The present invention take full advantage of the loose big absorbent formation space of highly permeable it is big, it is connective good the characteristics of, water Slurry liquid A and waterglass slurry B are mixed in the earth formation, are condensed rapidly after being mixed in highly permeable scall 52, are both not in Plugging phenomenon;Meanwhile, overcome prior art cement grout and waterglass slurries in slurry bucket, the mouth of pipe or pipe in mixed Close, the defects such as impervious leakage-stopping requirement can not be met very well by easily causing plugging or range of scatter;In addition, requiring operating personnel It is relatively low, it is only necessary to can to meet site operation requirement by brief training.
In the present embodiment, grout hole 1 passes through water proof loading layer 51, highly permeable scall 52, and extends to relative water proof Layer 53.The insertion relative water resisting layer 53 of grout hole 1 about 1m~2m, the length of most long grout pipe 31 is more than the depth of grout hole 1, That is lower surface highly minimum grout pipe 31 extends to relative water resisting layer 53, it is ensured that most long grout pipe 31 is loose through highly permeable Stratum 52, so that it is guaranteed that the bottom of highly permeable scall 52 can be in the milk.
In the present embodiment, device for plugging also includes being placed on the protection casing 6 outside drilling tool 2 during drilling.Drilling tool 2 is in drilling When, protection casing 6 is enclosed on outside drilling tool 2, advanced simultaneously with drilling tool 2.After drilling terminates, drilling tool 2 is taken out, protection casing 6 is stayed in In grout hole 1, when floral tube 3 to be combined is along the insertion grout hole 1 of protection casing 6, protection casing 6, protection combination floral tube 3 are extracted.
In the present embodiment, the upper end of grout pipe 31 is provided with the grouting joint 8 for being used for being connected with grouting pipeline 7.Be in the milk joint 8 Provided with grouting control valve 9 between grouting pipeline 7.Two kinds of slurries are irrigated by independent grouting pipeline 7.
In concrete application example, grout pipe 31 is steel pipe or PRP pipes or PE is managed or other can bear certain grouting pressure The tubing of power.In the present embodiment, grout pipe 31 is steel pipe, after grouting terminates, and grout pipe 31 is embedded in the earth formation.Combine floral tube 3 Material is disposable, relative to blender special in the prior art(In aperture or hole), mini-valve tube, two-shot grouting core Pipe, grouting nozzle etc., process easy maintenance, and in the market is easy to purchase and cheap, it is easy to realize that large area is quickly applied Work.
As shown in Fig. 4 to Fig. 9, highly permeable scall rapid plugging method for fiberglass of the invention comprises the following steps:
S1, grout hole 1 is drilled with, combination floral tube 3 is inserted in grout hole 1;
S2, the aperture for pouring using accelerated cement mortar grout hole 1 form seal plug body 4;
S3, each grout pipe 31 of cement-bentonite stable grout C fillings with high-consistency;
S4, to a cement injection slurries A of grout pipe 31 in every group of grout pipe group, to another priming petock glass paste of grout pipe 31 Liquid B, makes two kinds of slurries in the condensation by mixing filling of highly permeable scall 52 space, quick blocking leakage passage.
Each grout pipe 31 is filled using the cement-bentonite stable grout C of high-consistency, so as to ensure each grout pipe before grouting 31 are filled, during grouting, when most long grout pipe 31 is in the milk, and other grout pipes 31 are not when being in the milk, it is to avoid slurries are never filled The grouting presbyopia 311 of the grout pipe 31 of slurry enters, so as to block presbyopia 311 of not being in the milk.Using the technology to highly permeable loosely Layer 52 carries out impervious leakage-stopping two-shot groutings, and filling process does not need rig to coordinate, and does not need special two-shot grouting pump, Large area rapid construction used device relative populations are few and are worth low.
In concrete application example, in every group of grout pipe group, the relatively low grout pipe 31 in lower surface can cement injection slurries A or Waterglass slurries B, the present embodiment, by taking the relatively low cement injection slurries A of grout pipe 31 in lower surface as an example, because lower surface is relatively low The grouting presbyopia 311 of the grouting presbyopia 311 of grout pipe 31 grout pipe 31 higher less than lower surface, it is ensured that cement grout A It is sufficiently mixed from top to bottom with waterglass slurries B, accelerates to condense filling space, quick blocking leakage passage.
Carry out step S1 before, at least two grout pipes 31 are bundled into it is a branch of, in the present embodiment, by two groups four fill Slurry pipe 31 is bundled into a branch of, upper end alignment, and the grouting presbyopia 311 of grout pipe 31 is wound always using adhesive tape 32.The adhesive tape 32 In grouting, it can be punctured by slurries.The adhesive tape 32 is used to protect grouting presbyopia 311, it is to avoid grouting presbyopia 311 is not in the milk for a long time When block.
In step sl, protection casing 6 is arranged while being drilled with grout hole 1 outside drilling tool 2, after drilling terminates, takes out and bores Tool 2, protection casing 6 is stayed in grout hole 1, when floral tube 3 to be combined is along the insertion grout hole 1 of protection casing 6, extracts protection casing 6.
In concrete application example, two groups of grout pipes 31 of combination floral tube 3 can be in the milk simultaneously, can also separate and be in the milk, i.e., and one It is secondary to fill one group, filling another group after one group of filling is complete.In the present embodiment, two groups of grout pipe groups are in the milk simultaneously.
Although the present invention is disclosed above with preferred embodiment, but is not limited to the present invention.It is any to be familiar with ability The technical staff in domain, in the case where not departing from technical solution of the present invention scope, all using the technology contents pair of the disclosure above Technical solution of the present invention makes many possible variations and modification, or is revised as the equivalent embodiment of equivalent variations.Therefore, it is every Without departing from the content of technical solution of the present invention, according to the technology of the present invention essence to any simple modification made for any of the above embodiments, Equivalent variations and modification, all should fall in the range of technical solution of the present invention protection.

Claims (10)

1. a kind of highly permeable scall Quick leak stoppage apparatus, it is characterised in that:Including for boring grout hole(1)Drilling tool(2)、 Combine floral tube(3)And for combining floral tube(3)Insert the grout hole(1)Afterwards to grout hole(1)Aperture carry out it is sealed Seal plug body(4), the combination floral tube(3)Including at least one set of grout pipe group, every group of grout pipe group includes two grout pipes (31), the grout pipe(31)Lower end mouth of pipe closing, and grout hole is stretched out in upper end(1)Aperture, the grout pipe(31)Lower end End face or lower end side face are provided with grouting presbyopia(311), the combination floral tube(3)In all grout pipes(31)Lower surface in institute State grout hole(1)Interior height is differed.
2. highly permeable scall Quick leak stoppage apparatus according to claim 1, it is characterised in that:The grout hole(1) Through water proof loading layer(51), highly permeable scall(52), and extend to relative water resisting layer(53).
3. highly permeable scall Quick leak stoppage apparatus according to claim 2, it is characterised in that:Lower surface is highly minimum Grout pipe(31)Extend to relative water resisting layer(53).
4. highly permeable scall Quick leak stoppage apparatus according to claim 1, it is characterised in that:The device for plugging is also Drilling tool is placed on during including drilling(2)Outside protection casing(6).
5. the highly permeable scall Quick leak stoppage apparatus according to Claims 1-4 any one, it is characterised in that:Institute State grout pipe(31)Upper end, which is provided with, to be used for and grouting pipeline(7)The grouting joint of connection(8).
6. the highly permeable scall Quick leak stoppage apparatus according to Claims 1-4 any one, it is characterised in that:Institute State grout pipe(31)For steel pipe or PRP pipes or PE pipes.
7. the highly permeable scall Quick leak stoppage apparatus according to Claims 1-4 any one, it is characterised in that:Institute State combination floral tube(3)In each grout pipe(31)Length differ, each grout pipe(31)Upper end is concordant, lower end edge grout hole (1)Depth above and below be staggeredly arranged.
8. a kind of blocking method of the highly permeable scall Quick leak stoppage apparatus based on described in claim 1 to 7 any one, It is characterised in that it includes following steps:
S1, it is drilled with grout hole(1), floral tube will be combined(3)Insert grout hole(1)It is interior;
S2, grout hole poured using accelerated cement mortar(1)Aperture formed seal plug body(4);
S3, each grout pipe of cement-bentonite stable grout filling with high-consistency(31);
S4, to a grout pipe in every group of grout pipe group(31)Cement injection slurries, to another grout pipe(31)Priming petock Glass pulp, makes two kinds of slurries in highly permeable scall(52)Condensation by mixing filling space, quick blocking leakage passage.
9. highly permeable scall rapid plugging method for fiberglass according to claim 8, it is characterised in that carry out step S1 it Before, by each grout pipe(31)It is bundled into a branch of, upper end alignment, and grout pipe(31)Grouting presbyopia(311)Using adhesive tape(32) Winding.
10. highly permeable scall rapid plugging method for fiberglass according to claim 8, it is characterised in that:In step sl, bore If grout hole(1)While in drilling tool(2)It is arranged protection casing outside(6), after drilling terminates, take out drilling tool(2), protection casing (6)Stay in grout hole(1)It is interior, floral tube to be combined(3)Along protection casing(6)Insert grout hole(1)When, extract protection casing(6).
CN201710624973.6A 2017-07-27 2017-07-27 Rapid plugging device and method for high-permeability unconsolidated formation Active CN107254882B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710624973.6A CN107254882B (en) 2017-07-27 2017-07-27 Rapid plugging device and method for high-permeability unconsolidated formation

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710624973.6A CN107254882B (en) 2017-07-27 2017-07-27 Rapid plugging device and method for high-permeability unconsolidated formation

Publications (2)

Publication Number Publication Date
CN107254882A true CN107254882A (en) 2017-10-17
CN107254882B CN107254882B (en) 2022-11-18

Family

ID=60026078

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710624973.6A Active CN107254882B (en) 2017-07-27 2017-07-27 Rapid plugging device and method for high-permeability unconsolidated formation

Country Status (1)

Country Link
CN (1) CN107254882B (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111775298A (en) * 2020-07-07 2020-10-16 上海建工四建集团有限公司 Method for pouring concrete of prefabricated stand column

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2000212961A (en) * 1999-01-22 2000-08-02 East Japan Railway Co Construction method for cast-in-place concrete pile
CN103132526A (en) * 2013-03-15 2013-06-05 中国水利水电第七工程局成都水电建设工程有限公司 Two-fluid-process grouting plug and grouting method using the same
CN103145381A (en) * 2013-03-14 2013-06-12 中国水利水电第七工程局成都水电建设工程有限公司 Double-liquid process grouting material and grouting process using grouting material
CN103362548A (en) * 2013-07-09 2013-10-23 淮南矿业(集团)有限责任公司 Grouting device
CN105386435A (en) * 2015-12-07 2016-03-09 中交第三航务工程局有限公司南京分公司 Double-liquid grouting system used for cement and water glass solution and construction process of double-liquid grouting system
CN105951749A (en) * 2016-05-11 2016-09-21 中国水利水电第十四工程局有限公司 Construction method for reinforcement treatment of soft foundation steel pipe pile in confined space

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2000212961A (en) * 1999-01-22 2000-08-02 East Japan Railway Co Construction method for cast-in-place concrete pile
CN103145381A (en) * 2013-03-14 2013-06-12 中国水利水电第七工程局成都水电建设工程有限公司 Double-liquid process grouting material and grouting process using grouting material
CN103132526A (en) * 2013-03-15 2013-06-05 中国水利水电第七工程局成都水电建设工程有限公司 Two-fluid-process grouting plug and grouting method using the same
CN103362548A (en) * 2013-07-09 2013-10-23 淮南矿业(集团)有限责任公司 Grouting device
CN105386435A (en) * 2015-12-07 2016-03-09 中交第三航务工程局有限公司南京分公司 Double-liquid grouting system used for cement and water glass solution and construction process of double-liquid grouting system
CN105951749A (en) * 2016-05-11 2016-09-21 中国水利水电第十四工程局有限公司 Construction method for reinforcement treatment of soft foundation steel pipe pile in confined space

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111775298A (en) * 2020-07-07 2020-10-16 上海建工四建集团有限公司 Method for pouring concrete of prefabricated stand column

Also Published As

Publication number Publication date
CN107254882B (en) 2022-11-18

Similar Documents

Publication Publication Date Title
CN101864778B (en) Method for leaking stoppage of external wall of underground structure
CN109098213A (en) A kind of basement blocking method
CN100510274C (en) Construction method of enclosing level rotary-jet pile hole-mouth using double-liquid slip jection method
CN106013259A (en) Method for plugging deformation joint of underground engineering concrete structure in vibration disturbing environment
CN105735364B (en) Concrete joint waterproof system, construction method and the protection component for the system
CN108517899A (en) Mouth high-pressure grouting leak stopping processing method is buried in the leakage drilling of deep basal pit diaphram wall
CN207739264U (en) A kind of Grouting Pipe
CN106592614B (en) The method for blocking of leakage point in foundation pit waterproof of man
CN105386435B (en) It is a kind of to be used for the double-liquid grouting system and its construction technology of cement and water glass solution
CN103866762A (en) Pile body longitudinal multipoint grouting device
CN108374567A (en) A kind of biliquid single system air pressure energy storage slip casting machine and grouting process
CN105484266B (en) The grouting equipment and its construction method of a kind of multifunctional information
CN109853633A (en) A kind of external sealing treatment process of basement bottom board leakage
JP5289639B1 (en) Chemical injection method and chemical injection structure in the ground during chemical injection
CN106320728A (en) Double-fluid grouting bag type rapid hole sealing device
CN206328766U (en) A kind of pipe well well-sealing device
CN207017282U (en) A kind of highly permeable scall Quick leak stoppage apparatus
CN107254882A (en) A kind of highly permeable scall Quick leak stoppage apparatus and blocking method
CN104452751A (en) Secondary pouring pile forming device and pile forming method for bored piles
CN108677959A (en) A kind of grouting tube and grouting construction method suitable for mortar depositing construction under the conditions of limited space
CN110453672B (en) Loose shallow earth covering double-liquid grouting reinforcement method
CN104712145A (en) Grouting method for middle embedded grouting water stop belt
CN107630452A (en) Construction method of the bedrock fracture development rich in the underwater slip casting of underground water anti-float anchor rod
CN108915705B (en) A kind of baffle grouting construction method blocked for shield export & import leak
CN205531429U (en) Quick hole sealing device of biliquid slip casting bag pocket type

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant