- CN104712145A CN104712145A CN201510086122.1A CN201510086122A CN104712145A CN 104712145 A CN104712145 A CN 104712145A CN 201510086122 A CN201510086122 A CN 201510086122A CN 104712145 A CN104712145 A CN 104712145A
- Authority
- CN
- China
- Prior art keywords
- grouting
- grouting pipe
- slip casting
- buried
- waterstop
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
- XLYOFNOQVPJJNP-UHFFFAOYSA-N water Substances O XLYOFNOQVPJJNP-UHFFFAOYSA-N 0.000 title abstract description 5
- 238000007569 slipcasting Methods 0.000 claims description 63
- 210000001503 Joints Anatomy 0.000 claims description 7
- 239000007788 liquid Substances 0.000 claims description 7
- 125000003700 epoxy group Chemical group 0.000 claims description 6
- 239000000463 material Substances 0.000 claims description 5
- 230000000903 blocking Effects 0.000 claims description 3
- 230000000694 effects Effects 0.000 abstract description 9
- 239000011440 grout Substances 0.000 abstract description 6
- 238000010276 construction Methods 0.000 abstract description 4
- 239000002002 slurry Substances 0.000 description 10
- 238000007789 sealing Methods 0.000 description 8
- 230000001808 coupling Effects 0.000 description 4
- 238000010168 coupling process Methods 0.000 description 4
- 238000005859 coupling reaction Methods 0.000 description 4
- 230000003487 anti-permeability Effects 0.000 description 2
- 230000000149 penetrating Effects 0.000 description 2
- 210000004911 Serous fluid Anatomy 0.000 description 1
- 239000000084 colloidal system Substances 0.000 description 1
- 238000010192 crystallographic characterization Methods 0.000 description 1
- 238000005516 engineering process Methods 0.000 description 1
Abstract
The invention relates to the field of buildings and discloses a grouting method for a middle embedded grouting water stop belt. The grouting method comprises the steps that the middle embedded grouting water stop belt is installed at the pipe joint seam of two adjacent concrete members, pre-embedded grouting pipes are arranged on the two sides of the middle embedded grouting water stop belt respectively, and a plurality of grouting guide pipes communicated with the pre-embedded grouting pipes are arranged; grouting is started from the first grouting guide pipe and is stopped when grout comes out of the second grouting guide pipe adjacent to the first grouting guide pipe and the third grouting guide pipe, the first grouting guide pipe is sealed at the moment, then grouting is started from the second grouting guide pipe and the third grouting guide pipe, and the second grouting guide pipe and the third grouting guide pipe are sealed when grout comes out of the fourth grouting guide pipe adjacent to the second grouting guide pipe and the fifth grouting guide pipe adjacent to the third grouting guide pipe, the rest is done in the same manner until grout comes out of the last grouting guide pipe, and grouting is stopped. According to the grouting method, the grouting effect is good, the grout utilization rate is high, and construction is simple.
Description
Technical field
The present invention relates to technical field of buildings, particularly relate to a kind of in buried can the grouting method of slip casting waterstop.
Background technology
The long 180m of huge concrete structure single standard tube coupling, is made up of the sections of 8 long 22.5m.Tube coupling adopts holes one piping lane section form, wide 3795cm, high 1140cm, and single tube coupling weight is about 9000T, 8 sections gross weight 72000T; Leaking probably appears in two the sections places connecting so large concrete component, so can install a circle waterstop at sections section before building, but this can not accomplish the effect of complete sealing, slip casting therefore can be adopted to carry out detecting, sealing; But, also there is no a kind of convenient, effective grouting method at present.
Summary of the invention
(1) technical problem that will solve
The object of this invention is to provide that a kind of slip casting effect is good, slurries utilization rate is high, construction simple in buried can the grouting method of slip casting waterstop.
(2) technical scheme
In order to solve the problems of the technologies described above, the invention provides a kind of in buried can the grouting method of slip casting waterstop, it comprises the steps:
S1, to install at the joints of segment place of adjacent two concrete components buried together can slip casting waterstop, buriedly in described the both sides of slip casting waterstop can be respectively equipped with pre-buried type Grouting Pipe, and buriedly in described the many grouting pipe be communicated with described pre-buried type Grouting Pipe can be set respectively for the both sides of slip casting waterstop;
Spacing between S2, adjacent two grouting pipe is 5-6m;
S3, choose wherein a grouting pipe as the first grouting pipe, first from the first grouting pipe slip casting, when second grouting pipe adjacent with described first grouting pipe and the 3rd grouting pipe pulp, stop slip casting, now close the first grouting pipe, then slip casting from the second grouting pipe and the 3rd grouting pipe, after four grouting pipe adjacent with described second grouting pipe and the five grouting pipe pulp adjacent with described 3rd grouting pipe, close described second grouting pipe and the 3rd grouting pipe, subsequently by that analogy, until after last root grouting pipe pulp, stop slip casting, and close last root grouting pipe.
Wherein, in S3, injecting paste material is modified epoxy grouting liquid.
Wherein, in S3, if centre have indivedual grouting pipe because of blocking cannot pulp time, keep pressure after 10-15 minute, proceed next root grouting pipe slip casting.
Wherein, in S3, the grouting pressure of every root grouting pipe controls between 0.5MPa ~ 1MPa.
Wherein, in S3, the grouting pressure of last root grouting pipe reaches 0.6MPa and keeps pressure to stop slip casting without when obviously reducing in 3-5 minute.
Preferably, in S1, buriedly in described 24 grouting pipe can be set respectively for the both sides of slip casting waterstop.
Wherein, in S1, be also provided with rubber strip at the joints of segment place of adjacent two concrete components.
(3) beneficial effect
Compared with prior art, the present invention has the following advantages:
Provided by the invention a kind of in buried can the grouting method of slip casting waterstop, install at the joints of segment place of adjacent two concrete components buried together can slip casting waterstop, buriedly in described the both sides of slip casting waterstop can be respectively equipped with pre-buried type Grouting Pipe, and buriedly in described the many grouting pipe be communicated with described pre-buried type Grouting Pipe can be set respectively for the both sides of slip casting waterstop, choose wherein a grouting pipe as the first grouting pipe, first from the first grouting pipe slip casting, when second grouting pipe adjacent with described first grouting pipe and the 3rd grouting pipe pulp, stop slip casting, now close the first grouting pipe, then slip casting from the second grouting pipe and the 3rd grouting pipe, after four grouting pipe adjacent with described second grouting pipe and the five grouting pipe pulp adjacent with described 3rd grouting pipe, close described second grouting pipe and the 3rd grouting pipe, subsequently by that analogy, until after last root grouting pipe pulp, stop slip casting, and close last root grouting pipe, the method adopts circulating mud jacking, can accomplish to fill slurries completely in whole sealing zone circle, and high in conjunction with slurry consolidation intensity, and the feature of good penetrability, perfectly accomplishes the feature of waterproof, sealing, grout mixing can be allowed large, to concrete and waterstop slip casting effect good, the consolidation strength of slip casting is high, the method better economy, and construction is also simpler.
Accompanying drawing explanation
Fig. 1 be the present invention a kind of in buried can the integral layout figure of grouting method of slip casting waterstop;
Fig. 2 be the present invention a kind of in buried can the structure sectional view of grouting method of slip casting waterstop.
In figure: 1: the first grouting pipe; 2: the second grouting pipe; 3: the three grouting pipe; 4: the four grouting pipe; 5: the five grouting pipe; 6: in buried can slip casting waterstop; 7: pre-buried type Grouting Pipe; 8: grouting pipe; 9: rubber strip.
Detailed description of the invention
Below in conjunction with drawings and Examples, the specific embodiment of the present invention is described in further detail.Following instance for illustration of the present invention, but is not used for limiting the scope of the invention.
In describing the invention, it should be noted that, term " " center ", " longitudinal direction ", " transverse direction ", " on ", D score, " front ", " afterwards ", " left side ", " right side ", " vertically ", " level ", " top ", " end " " interior ", orientation or the position relationship of the instruction such as " outward " are based on orientation shown in the drawings or position relationship, only the present invention for convenience of description and simplified characterization, instead of indicate or imply that the device of indication or element must have specific orientation, with specific azimuth configuration and operation, therefore limitation of the present invention can not be interpreted as.In addition, term " first ", " second ", " the 3rd " etc. only for describing object, and can not be interpreted as instruction or hint relative importance.
In addition, in describing the invention, except as otherwise noted, the implication of " multiple ", " many ", " many groups " is two or more.
As depicted in figs. 1 and 2, for provided by the invention a kind of in buried can the grouting method of slip casting waterstop, it comprises the steps:
S1, to install at the joints of segment place of adjacent two concrete components buried together can slip casting waterstop 6, buriedly in described the both sides of slip casting waterstop 6 can be respectively equipped with pre-buried type Grouting Pipe, and buriedly in described the many grouting pipe 8 be communicated with described pre-buried type Grouting Pipe 7 can be set respectively for the both sides of slip casting waterstop 6; The method to concrete and waterstop slip casting effect good; The consolidation strength of slip casting is high, can direction and location, and grouting serous fluid all enters seam, and the utilization rate of slurries is high; The method better economy, and construction is also simpler;
S2, particularly, the spacing between adjacent two grouting pipe can be 5-6m;
S3, injecting treatment is made after concrete intensity reaches 45MPa, grouting pipe 8 is one by one adopted to carry out slip casting during slip casting, choose wherein a grouting pipe as the first grouting pipe 1, first from the first grouting pipe 1 slip casting, when second grouting pipe 2 adjacent with described first grouting pipe 1 and the 3rd grouting pipe 3 pulp (or after first grouting pipe 1 pressure to 1MPa), stop slip casting, now close the first grouting pipe 1 with plug, then slip casting from the second grouting pipe 2 and the 3rd grouting pipe 3, after four grouting pipe 4 adjacent with described second grouting pipe 2 and five grouting pipe 5 pulp adjacent with described 3rd grouting pipe 3, plug is utilized to close described second grouting pipe 2 and the 3rd grouting pipe 3, subsequently by that analogy, until after last root grouting pipe pulp, stop slip casting, and close last root grouting pipe.The method adopts circulating mud jacking, can accomplish to fill slurries completely in whole sealing zone circle, and high in conjunction with slurry consolidation intensity, and the feature of good penetrability, perfectly accomplishes the feature of waterproof, sealing.
Wherein, in S3, injecting paste material is modified epoxy grouting liquid, and this material initial viscosity is little, and penetrating power is strong, adhesion strength and compressive strength high, anti-permeability performance is good.Particularly, (1) this material main performance index 1. viscosity: <200mPa.s; 2. the initial setting time: 8 ~ 24 hours; 3. pure colloid compressive strength: >=40MPa; 4. compress variation: 40 ~ 60%; 5. adhesion strength: >2.5MPa.(2) match ratio: Sui Jin section SJK-02 modified epoxy grouting liquid: Sui Jin section SJK-02 modified epoxy grouting liquid is 25:2, grouting pipe preferably settles 24 altogether, and the arrangement distance controlling of each grouting pipe is within the 5-6m scope of code requirement, adopt circulating slip casting one by one, simple to operate.Adopt modified epoxy grouting liquid initial viscosity little, penetrating power is strong, adhesion strength and compressive strength high, the features such as anti-permeability performance is good, can fabulous the coupling together by very trickle gap, and utilize its adhesion strength high feature waterstop and concrete can be combined, play sealing effect.
Wherein, in S3, if centre have indivedual grouting pipe 8 because of blocking cannot pulp time, keep pressure after 10-15 minute, proceed next root grouting pipe 8 slip casting.
Wherein, in S3, the grouting pressure of every root grouting pipe 8 controls between 0.5MPa ~ 1MPa, and the slip casting duration should control at 7 ~ 15 minutes.
Wherein, in S3, the grouting pressure of last root grouting pipe 8 reaches 0.6MPa and keeps pressure preferably within 5 minutes, can stop slip casting without when obviously reducing in 3-5 minute.If grout outlet does not flow out slurries smoothly, grouting pressure can be strengthened, but pressure should not more than 1MPa.After whole grouting completes, according to drawing the liquid level height exposing conduit slurries, determine whether to need back-grouting.
Wherein, in S1, be also provided with rubber strip 9 at the joints of segment place of adjacent two concrete components, it is inflatable that described rubber strip 9 meets water, thus when slurries are noted in seam, described rubber strip 9 preferably by joint sealing, thus can play good hermetic seal effect after expanding.
Slip casting effect of the present invention is good, and the utilization rate of slurries is high; And better economy, construct also simpler.
The foregoing is only preferred embodiment of the present invention, not in order to limit the present invention, within the spirit and principles in the present invention all, any amendment done, equivalent replacement, improvement etc., all should be included within protection scope of the present invention.
Claims (7)
1. buried in can the grouting method of slip casting waterstop, it is characterized in that, comprise the steps:
S1, to install at the joints of segment place of adjacent two concrete components buried together can slip casting waterstop, buriedly in described the both sides of slip casting waterstop can be respectively equipped with pre-buried type Grouting Pipe, and buriedly in described the many grouting pipe be communicated with described pre-buried type Grouting Pipe can be set respectively for the both sides of slip casting waterstop;
Spacing between S2, adjacent two grouting pipe is 5-6m;
S3, choose wherein a grouting pipe as the first grouting pipe, first from the first grouting pipe slip casting, when second grouting pipe adjacent with described first grouting pipe and the 3rd grouting pipe pulp, stop slip casting, now close the first grouting pipe, then slip casting from the second grouting pipe and the 3rd grouting pipe, after four grouting pipe adjacent with described second grouting pipe and the five grouting pipe pulp adjacent with described 3rd grouting pipe, close described second grouting pipe and the 3rd grouting pipe, subsequently by that analogy, until after last root grouting pipe pulp, stop slip casting, and close last root grouting pipe.
2. buried in as claimed in claim 1 can the grouting method of slip casting waterstop, it is characterized in that, in S3, injecting paste material is modified epoxy grouting liquid.
3. buried in as claimed in claim 1 can the grouting method of slip casting waterstop, it is characterized in that, in S3, if centre have indivedual grouting pipe because of blocking cannot pulp time, keep pressure after 10-15 minute, proceed next root grouting pipe slip casting.
4. buried in as claimed in claim 1 can the grouting method of slip casting waterstop, it is characterized in that, in S3, the grouting pressure of every root grouting pipe controls between 0.5MPa ~ 1MPa.
5. buried in as claimed in claim 1 can the grouting method of slip casting waterstop, it is characterized in that, in S3, the grouting pressure of last root grouting pipe reaches 0.6MPa and keeps pressure to stop slip casting without when obviously reducing in 3-5 minute.
6. buried in as claimed in claim 1 can the grouting method of slip casting waterstop, it is characterized in that, in S1, buriedly in described 24 grouting pipe can be set respectively for the both sides of slip casting waterstop.
7. buried in as claimed in claim 1 can the grouting method of slip casting waterstop, it is characterized in that, in S1, be also provided with rubber strip at the joints of segment place of adjacent two concrete components.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201510086122.1A CN104712145B (en) | 2015-02-16 | 2015-02-16 | In a kind of it is buried can slip casting waterstop grouting method |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201510086122.1A CN104712145B (en) | 2015-02-16 | 2015-02-16 | In a kind of it is buried can slip casting waterstop grouting method |
Publications (2)
Publication Number | Publication Date |
---|---|
CN104712145A true CN104712145A (en) | 2015-06-17 |
CN104712145B CN104712145B (en) | 2017-08-25 |
Family
ID=53411832
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201510086122.1A Active CN104712145B (en) | 2015-02-16 | 2015-02-16 | In a kind of it is buried can slip casting waterstop grouting method |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN104712145B (en) |
Cited By (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN106638710A (en) * | 2017-02-17 | 2017-05-10 | 四川省第六建筑有限公司 | New and old underground building joint construction seam waterproof processing technology |
CN107237408A (en) * | 2017-07-12 | 2017-10-10 | 中国二十冶集团有限公司 | It is a kind of to prevent the construction method of expansion joint position seepage |
CN107237507A (en) * | 2016-03-28 | 2017-10-10 | 中国二十冶集团有限公司 | New and old concrete structures to form device and construction method in improvement project |
CN113310872A (en) * | 2021-05-25 | 2021-08-27 | 北京中煤矿山工程有限公司 | Elastic wave-assisted cement grouting water-stopping model test device |
Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
DE19715366A1 (en) * | 1997-04-14 | 1998-10-22 | Tricosal Gmbh | Sealing strip used in concrete construction to form expansion- or structural joints |
CN2613530Y (en) * | 2003-05-15 | 2004-04-28 | 韩君国 | Intermediate set grout injection waterstop |
CN2718073Y (en) * | 2004-06-25 | 2005-08-17 | 李树奎 | Ejection rubber water plugging band |
CN101372840A (en) * | 2007-08-21 | 2009-02-25 | 上海市建筑科学研究院(集团)有限公司 | Mounting method with detachable rubber water stop mounted inside |
US20110277413A1 (en) * | 2010-05-13 | 2011-11-17 | Emmons Peter H | System and method for leaking crack repair |
-
2015
- 2015-02-16 CN CN201510086122.1A patent/CN104712145B/en active Active
Patent Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
DE19715366A1 (en) * | 1997-04-14 | 1998-10-22 | Tricosal Gmbh | Sealing strip used in concrete construction to form expansion- or structural joints |
CN2613530Y (en) * | 2003-05-15 | 2004-04-28 | 韩君国 | Intermediate set grout injection waterstop |
CN2718073Y (en) * | 2004-06-25 | 2005-08-17 | 李树奎 | Ejection rubber water plugging band |
CN101372840A (en) * | 2007-08-21 | 2009-02-25 | 上海市建筑科学研究院(集团)有限公司 | Mounting method with detachable rubber water stop mounted inside |
US20110277413A1 (en) * | 2010-05-13 | 2011-11-17 | Emmons Peter H | System and method for leaking crack repair |
Cited By (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN107237507A (en) * | 2016-03-28 | 2017-10-10 | 中国二十冶集团有限公司 | New and old concrete structures to form device and construction method in improvement project |
CN106638710A (en) * | 2017-02-17 | 2017-05-10 | 四川省第六建筑有限公司 | New and old underground building joint construction seam waterproof processing technology |
CN107237408A (en) * | 2017-07-12 | 2017-10-10 | 中国二十冶集团有限公司 | It is a kind of to prevent the construction method of expansion joint position seepage |
CN113310872A (en) * | 2021-05-25 | 2021-08-27 | 北京中煤矿山工程有限公司 | Elastic wave-assisted cement grouting water-stopping model test device |
Also Published As
Publication number | Publication date |
---|---|
CN104712145B (en) | 2017-08-25 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN107060116B (en) | A kind of high-pressure slip-casting blocking method for building settlement seam | |
CN101864778B (en) | Method for leaking stoppage of external wall of underground structure | |
CN106761835B (en) | A kind of Karst Tunnel leak segmenting slip casting construction method | |
CN104712145A (en) | Grouting method for middle embedded grouting water stop belt | |
CN106013259A (en) | Method for plugging deformation joint of underground engineering concrete structure in vibration disturbing environment | |
CN103898873A (en) | Water seepage plugging construction method of shaft construction seams under high water head | |
CN108104865B (en) | A kind of concordant drilling Anti-air-leakage gas pumping method | |
CN105780781A (en) | Fast plugging method for deep foundation pit | |
CN110748350A (en) | Method for quickly treating collapse of urban subway tunnel passing through water-rich sand layer section | |
CN104314106A (en) | Underground diaphragm wall with joint water stop and filling vacancy structure and construction method thereof | |
CN102002950A (en) | Liquid division slip casting reinforcing method for subsurface structure construction joints | |
CN102174818A (en) | Controlled impermeable leaking stoppage grout-extruding water-stopping technology of strong water permeable stratum of quaternary system | |
CN103205986A (en) | Concrete raft foundation construction-joint grouting device and construction method | |
CN201424658Y (en) | Water leakage detection of underground continuous wall groove seams and block repair device | |
CN103174428B (en) | A kind of applied chemistry slurries implement the method for grouting for water blocking to vertical shaft | |
CN109403914B (en) | Water column grout stopping double-liquid grouting method in mine underground ultra-deep borehole | |
CN204343286U (en) | A kind of steel pipe pile support | |
CN203866777U (en) | Grouting treatment structure used after water stopping of cross joints of concrete dam fails | |
CN103161166B (en) | Wind-guiding chemical grouting device and grouting method of the same | |
CN114197403A (en) | Elevation and extension seepage-proofing system for grouted stone gravity dam and construction method | |
CN204282366U (en) | A kind of diaphragm wall seam grouting device | |
CN203924150U (en) | EPR deformation joint is repaired water-stopping structure | |
CN206110124U (en) | Bored concrete pile stake end post grouting device | |
CN102296617A (en) | Post-grouting reinforcement construction method of flexible joints of diaphragm walls | |
CN105089551A (en) | Casing pipe running reinforcing process of grouting hole opening pipe |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
GR01 | Patent grant | ||
GR01 | Patent grant |