CN107246037A - A kind of rectifying of leaned building structure and method for stake end sandy soil supporting course - Google Patents
A kind of rectifying of leaned building structure and method for stake end sandy soil supporting course Download PDFInfo
- Publication number
- CN107246037A CN107246037A CN201710674891.2A CN201710674891A CN107246037A CN 107246037 A CN107246037 A CN 107246037A CN 201710674891 A CN201710674891 A CN 201710674891A CN 107246037 A CN107246037 A CN 107246037A
- Authority
- CN
- China
- Prior art keywords
- stake
- regions
- classes
- region
- rectifying
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
- 239000002689 soil Substances 0.000 title claims abstract description 19
- 238000000034 method Methods 0.000 title claims abstract description 11
- 238000010276 construction Methods 0.000 claims abstract description 19
- 239000000463 material Substances 0.000 claims abstract description 16
- 238000004062 sedimentation Methods 0.000 claims abstract description 14
- 239000004567 concrete Substances 0.000 claims abstract description 12
- XLYOFNOQVPJJNP-UHFFFAOYSA-N water Substances O XLYOFNOQVPJJNP-UHFFFAOYSA-N 0.000 claims abstract description 11
- 238000005266 casting Methods 0.000 claims abstract description 7
- 230000003068 static effect Effects 0.000 claims abstract description 5
- 238000013461 design Methods 0.000 claims description 4
- 238000012544 monitoring process Methods 0.000 claims description 3
- 230000006835 compression Effects 0.000 claims 1
- 238000007906 compression Methods 0.000 claims 1
- 238000012937 correction Methods 0.000 abstract description 12
- 230000000694 effects Effects 0.000 abstract description 7
- 238000002347 injection Methods 0.000 abstract description 3
- 239000007924 injection Substances 0.000 abstract description 3
- 238000010586 diagram Methods 0.000 description 4
- 230000009286 beneficial effect Effects 0.000 description 2
- 238000006243 chemical reaction Methods 0.000 description 1
- 238000005516 engineering process Methods 0.000 description 1
- 238000004519 manufacturing process Methods 0.000 description 1
- 238000005728 strengthening Methods 0.000 description 1
- 238000013519 translation Methods 0.000 description 1
Classifications
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D35/00—Straightening, lifting, or lowering of foundation structures or of constructions erected on foundations
Landscapes
- Engineering & Computer Science (AREA)
- Structural Engineering (AREA)
- Life Sciences & Earth Sciences (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Mining & Mineral Resources (AREA)
- Paleontology (AREA)
- Civil Engineering (AREA)
- General Engineering & Computer Science (AREA)
- Foundations (AREA)
Abstract
The present invention relates to a kind of rectifying of leaned building structure for stake end sandy soil supporting course, the plane of building bottom plate is divided into tri- regions of A, B, C, a-quadrant is that position region occurs for larger sedimentation, B regions are that position region occurs for smaller sedimentation, and C regions are the regions being located between A, B region;Bottom plate, which is provided with to be uniformly provided with piling hole, each piling hole, is equipped with anchor jacked pile;Prestressing apparatus, and casting concrete are provided with the top of the A classes anchor jacked pile of a-quadrant;A classes anchor jacked pile stake end remains for the permeable hole of water filling in advance;Compressible material, and casting concrete are provided with the top of B, C class anchor jacked pile in B, C region.Building bottom plate is divided into three different regions, each region anchor rod static pressure pile driving construction is carried out in particular order by the present invention according to the situation of sedimentation, and uses different envelope piling method combination water injection methods, returns building and inclines, reaches the effect of correction.
Description
Technical field
It is a kind of building for stake sandy soil supporting course specifically the present invention relates to a kind of rectifying of leaned building structure
Thing error-correction structure, belongs to rectifying of leaned building technical field.
Background technology
The high-rise in weak soil or other unfavorable geologies area is built in, generally using pile foundation, due to reconnoitring, setting
The reason in terms of meter, construction or environment, when there is engineering pile damage or insufficient rigidity, building will be caused to produce uneven heavy
Drop, causes to tilt.
Conventional measure is that benefit sets anchor jacked pile progress strengthening of foundation, prevents it from further tilting, or using the side of soil digging
Formula is rectified a deviation, but the effect of prior art correction is not often good, is also difficult to during correction real-time according to actual conditions
Carry out construction adjustment, ensure while safety and reliability is also more difficult.
The content of the invention
The technical problem to be solved in the invention is:Prior art is entangled by the way of anchor jacked pile to building
When partially, the effect of correction is not so good as people's will, is also difficult to carry out construction adjustment in real time according to actual conditions during correction, together
When safety and reliability is also more difficult ensures.
The present invention takes following technical scheme:
A kind of rectifying of leaned building structure for stake end sandy soil supporting course, the plane of the building bottom plate 11 is divided into
Tri- regions of A, B, C, the a-quadrant is that position region occurs for larger sedimentation, and the B regions are that position occurs for smaller sedimentation
Region, the C regions are the regions being located between A, B region;Bottom plate 11 is each to press provided with piling hole 8 is uniformly provided with
Stake is equipped with anchor jacked pile 1 at hole 8;Prestressing apparatus 6 is provided with the top of the A classes anchor jacked pile of a-quadrant, and is poured
Concrete seven;The A classes anchor jacked pile stake end remains for the permeable hole of water filling in advance;B, C class anchor rod static pressure positioned at B, C region
Stake top portion is provided with compressible material 9, and casting concrete 7.
Further, the a-quadrant and B regions are two relative regions, respectively positioned at C regions both sides.
Further, the area equation of the a-quadrant and B regions.
Further, the lower section of building bottom plate 11 is additionally provided with former engineering pile 10.
It is used for the method for correcting error of the rectifying of leaned building structure of stake end sandy soil supporting course described in a kind of claim 1, including
Following steps:
A bottom plate 11) is distributed according to building superstructure load assignment, differential settlement situation and former engineering pile 10
Region opens up piling hole, then divides the class of A, B, C tri- stake subregion;
B) construction A classes stake, piling completes to carry out envelope stake using prestressing apparatus 6 at once, then carries out the stake piling of B classes, complete
Stake wouldn't be sealed after into piling, the permeable hole reserved by stake end carries out water filling, disturbance stake end sandy soil makes the relatively rapid production in the side
Raw certain sedimentation;At the same time, crossed construction C classes stake, sets certain thickness compressible material 9, and use in time in stake top
Concrete seven carries out envelope stake;
C) according to monitoring materials, after the building time amount of inclining meets design requirement, certain thickness is set to B classes stake stake top
Compressible material 9, and carry out envelope stake.
Further, step B is carried out) and step C) when, the thickness of the compressible material 9 in the piling hole of B classes is big
In the stake of C classes.
The beneficial effects of the present invention are:
1) according to the situation of sedimentation, building bottom plate is divided into three different regions, each region anchor rod static pressure pile driving construction
Carry out in particular order, and use different envelope piling method combination water injection methods, return building and incline, reach the effect of correction
Really;
2) rectifying of leaned building effect preferably, can be implemented to carry out construction adjustment during correction according to actual conditions;
3) while the safety and reliability of Deviation Correction Construction is higher.
Brief description of the drawings
Fig. 1 is the plan of the rectifying of leaned building structure for stake end sandy soil supporting course.
Fig. 2 is the schematic diagram that the stake piling of A classes and horse back prestressing force seal stake.
Fig. 3 is B classes pile driving construction and wouldn't seal the schematic diagram of stake.
Fig. 4 is the stake water filling of B classes, while the schematic diagram of C class pile driving constructions.
Fig. 5 is the schematic diagram of B classes stake envelope stake.
In figure, 1. anchor jacked piles, 2. different type pile bluelines, 3.A classes stake subregion, 4.B classes stake subregion, the stake point of 5.C classes
Area, 6. prestressing apparatus, 7. envelope pile concretes, 8. piling holes, 9. compressible materials, 10. former engineering piles, 11. bottom plates.
Embodiment
The present invention is further described with specific embodiment below in conjunction with the accompanying drawings.
Referring to Fig. 1-Fig. 5, a kind of rectifying of leaned building structure for stake end sandy soil supporting course, by the building bottom plate
11 plane is divided into tri- regions of A, B, C, and the a-quadrant is that position region occurs for larger sedimentation, and the B regions are smaller
Position region occurs for sedimentation, and the C regions are the regions being located between A, B region;Bottom plate 11 is provided with and is uniformly provided with pressure
Anchor jacked pile 1 is equipped with stake hole 8, each piling hole 8;Prestressing force is provided with the top of the A classes anchor jacked pile of a-quadrant
Device 6, and casting concrete 7;The A classes anchor jacked pile stake end remains for the permeable hole of water filling in advance;B positioned at B, C region,
Compressible material 9, and casting concrete 7 are provided with the top of C classes anchor jacked pile.
In this embodiment, referring to Fig. 1, the a-quadrant and B regions are two relative regions, respectively positioned at C regions two
Side.
In this embodiment, referring to Fig. 1, the area equation of the a-quadrant and B regions.
In this embodiment, referring to Fig. 2, the lower section of building bottom plate 11 is additionally provided with former engineering pile 10.
When carrying out the Specific construction of rectifying of leaned building, comprise the following steps:
A bottom plate 11) is distributed according to building superstructure load assignment, differential settlement situation and former engineering pile 10
Region opens up piling hole, then divides the class of A, B, C tri- stake subregion;B) construction A classes stake, piling completes to use prestressing apparatus at once
6 carry out envelope stake, then carry out the stake piling of B classes, stake wouldn't be sealed after completing piling, the permeable hole reserved by stake end carries out water filling,
Stake end sandy soil is disturbed, makes the certain sedimentation of the relatively rapid generation in the side;At the same time, crossed construction C classes stake, one is set in stake top
Determine the compressible material 9 of thickness, and envelope stake is carried out using concrete seven in time;C) according to monitoring materials, treat that building returns the amount of inclining and expired
After sufficient design requirement, certain thickness compressible material 9 is set to B classes stake stake top, and carry out envelope stake.
The beneficial effects of the present invention are:According to the situation of sedimentation, building bottom plate is divided into three different regions, respectively
Region anchor rod static pressure pile driving construction is carried out in particular order, and uses different envelope piling method combination water injection methods, makes building
Thing, which is returned, to incline, and reaches the effect of correction;Rectifying of leaned building effect preferably, can be implemented to carry out during correction according to actual conditions
Construction adjustment;The safety and reliability of Deviation Correction Construction is higher simultaneously.
Above is the preferred embodiments of the present invention, those of ordinary skill in the art can also enter on this basis line translation or
Improve, on the premise of the total design of the present invention is not departed from, these conversion or improvement should all belong to claimed
Within the scope of.
Claims (6)
1. a kind of rectifying of leaned building structure for stake end sandy soil supporting course, it is characterised in that:
The plane of the building bottom plate (11) is divided into tri- regions of A, B, C, the a-quadrant is that position institute occurs for larger sedimentation
In region, the B regions are that position region occurs for smaller sedimentation, and the C regions are the regions being located between A, B region;
Bottom plate (11) is provided with piling hole (8) is uniformly provided with, and each piling hole (8) place is equipped with anchor jacked pile (1);
Prestressing apparatus (6), and casting concrete (7) are provided with the top of the A classes anchor jacked pile of a-quadrant;The A classes anchor pole
Static pressed pile stake end remains for the permeable hole of water filling in advance;
Compressible material (9), and casting concrete (7) are provided with the top of B, C class anchor jacked pile in B, C region.
2. it is used for the rectifying of leaned building structure of stake end sandy soil supporting course as claimed in claim 1, it is characterised in that:The A
Region and B regions are two relative regions, respectively positioned at C regions both sides.
3. it is used for the rectifying of leaned building structure of stake end sandy soil supporting course as claimed in claim 2, it is characterised in that:The A
The area equation in region and B regions.
4. it is used for the rectifying of leaned building structure of stake end sandy soil supporting course as claimed in claim 1, it is characterised in that:It is described to build
Build and be additionally provided with former engineering pile (10) below thing bottom plate (11).
5. it is used for the method for correcting error of the rectifying of leaned building structure of stake end sandy soil supporting course, its feature described in a kind of claim 1
It is, comprises the following steps:
A bottom plate (11)) is distributed according to building superstructure load assignment, differential settlement situation and former engineering pile (10)
Region opens up piling hole, then divides the class of A, B, C tri- stake subregion;
B) construction A classes stake, piling completes to carry out envelope stake using prestressing apparatus (6) at once, then carries out the stake piling of B classes, completes
Stake wouldn't be sealed after piling, the permeable hole reserved by stake end carries out water filling, disturbance stake end sandy soil makes the relatively rapid generation in the side
Certain sedimentation;At the same time, crossed construction C classes stake, sets certain thickness compressible material (9), and use in time in stake top
Concrete (7) carries out envelope stake;
C) according to monitoring materials, after the building time amount of inclining meets design requirement, certain thickness press is set to B classes stake stake top
Compression material (9), and carry out envelope stake.
6. it is used for the method for correcting error of the rectifying of leaned building structure of stake end sandy soil supporting course, its feature as claimed in claim 5
It is:Carry out step B) and step C) when, the thickness of the compressible material (9) in the piling hole of B classes stake is more than C classes.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201710674891.2A CN107246037A (en) | 2017-08-09 | 2017-08-09 | A kind of rectifying of leaned building structure and method for stake end sandy soil supporting course |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201710674891.2A CN107246037A (en) | 2017-08-09 | 2017-08-09 | A kind of rectifying of leaned building structure and method for stake end sandy soil supporting course |
Publications (1)
Publication Number | Publication Date |
---|---|
CN107246037A true CN107246037A (en) | 2017-10-13 |
Family
ID=60013375
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201710674891.2A Pending CN107246037A (en) | 2017-08-09 | 2017-08-09 | A kind of rectifying of leaned building structure and method for stake end sandy soil supporting course |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN107246037A (en) |
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN109653187A (en) * | 2018-12-25 | 2019-04-19 | 上海勘察设计研究院(集团)有限公司 | A method of reducing the uneven traction sedimentation of anchor jacked pile |
CN109653265A (en) * | 2018-12-25 | 2019-04-19 | 上海勘察设计研究院(集团)有限公司 | A kind of pile-raft foundation building joint method for correcting error |
CN109881723A (en) * | 2019-03-20 | 2019-06-14 | 上海华铸地基技术有限公司 | A kind of comprehensive controllable method for correcting error of anchor jacked pile |
Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN204590107U (en) * | 2015-04-17 | 2015-08-26 | 上海岩土工程勘察设计研究院有限公司 | Building bidirectional deviation correction ruggedized construction |
CN105971039A (en) * | 2016-05-10 | 2016-09-28 | 山东建筑大学 | Method for rectifying deflection of building by digging out soil and pouring water |
CN205999947U (en) * | 2016-08-30 | 2017-03-08 | 中国建筑西南勘察设计研究院有限公司 | Thin stake reinforcement soil digging rectification composite foundation |
CN106592615A (en) * | 2016-11-17 | 2017-04-26 | 叶香雄 | Deviation rectification construction method for inclined sink |
CN207121940U (en) * | 2017-08-09 | 2018-03-20 | 上海岩土工程勘察设计研究院有限公司 | A kind of rectifying of leaned building structure for stake end sandy soil supporting course |
-
2017
- 2017-08-09 CN CN201710674891.2A patent/CN107246037A/en active Pending
Patent Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN204590107U (en) * | 2015-04-17 | 2015-08-26 | 上海岩土工程勘察设计研究院有限公司 | Building bidirectional deviation correction ruggedized construction |
CN105971039A (en) * | 2016-05-10 | 2016-09-28 | 山东建筑大学 | Method for rectifying deflection of building by digging out soil and pouring water |
CN205999947U (en) * | 2016-08-30 | 2017-03-08 | 中国建筑西南勘察设计研究院有限公司 | Thin stake reinforcement soil digging rectification composite foundation |
CN106592615A (en) * | 2016-11-17 | 2017-04-26 | 叶香雄 | Deviation rectification construction method for inclined sink |
CN207121940U (en) * | 2017-08-09 | 2018-03-20 | 上海岩土工程勘察设计研究院有限公司 | A kind of rectifying of leaned building structure for stake end sandy soil supporting course |
Non-Patent Citations (1)
Title |
---|
王建中: "既有建筑的迫降纠倾", 《山西建筑》, 28 February 2007 (2007-02-28), pages 144 - 145 * |
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN109653187A (en) * | 2018-12-25 | 2019-04-19 | 上海勘察设计研究院(集团)有限公司 | A method of reducing the uneven traction sedimentation of anchor jacked pile |
CN109653265A (en) * | 2018-12-25 | 2019-04-19 | 上海勘察设计研究院(集团)有限公司 | A kind of pile-raft foundation building joint method for correcting error |
CN109881723A (en) * | 2019-03-20 | 2019-06-14 | 上海华铸地基技术有限公司 | A kind of comprehensive controllable method for correcting error of anchor jacked pile |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN107090860B (en) | Deviation rectifying and reinforcing structure of shallow foundation building and construction method thereof | |
CN110080318B (en) | Deviation rectifying method for local settlement of pile foundation building | |
CN108343102B (en) | Pile foundation settlement reinforcement jacking leveling structure and construction method thereof | |
CN208996025U (en) | A kind of double casing pile foundation construction structures of thick silt layer | |
CN107246037A (en) | A kind of rectifying of leaned building structure and method for stake end sandy soil supporting course | |
CN202416195U (en) | Pier deviation correcting and reinforcing system | |
CN104294769B (en) | A kind of piling and the construction method increasing the built bridge abutment structure of platform cap composite reinforcement | |
CN206408657U (en) | Integrated bored concrete pile for static test | |
CN109138011A (en) | Existing building foundation stabilization and method for correcting error | |
CN201770942U (en) | Support for soft soil foundation cast-in-place concrete continuous beam bridge | |
CN207121940U (en) | A kind of rectifying of leaned building structure for stake end sandy soil supporting course | |
CN201581394U (en) | Large pile toe grout-injection precast pile | |
CN101418574B (en) | Construction method for reinforcing grade beam | |
CN104762967A (en) | Improved anchor rod static pressure pile sealing device and construction method | |
CN204097889U (en) | A kind of piling and the built bridge abutment structure of increase platform cap composite reinforcement | |
CN203768914U (en) | Foundation pit bracing diagonal support pile structure | |
CN105821887A (en) | Installing method for stand column pile constructed in pebble bed | |
CN108360369A (en) | The road and bridge end of the bridge engaging portion structure of pre- anti-jump vehicle phenomenon | |
CN111305182A (en) | Soft foundation reinforcement construction method | |
CN110258191B (en) | Deviation rectifying and reinforcing method for transverse displacement of high-speed railway roadbed | |
CN108532624B (en) | Chemical tank raft foundation reinforcing structure | |
CN110820817A (en) | Bridge pier stud pile foundation combination deviation rectifying method | |
CN110685287A (en) | Double-row pile foundation pit supporting system with drainage ditch and retaining wall and construction method | |
CN206829136U (en) | A kind of anchor jacked pile envelope pilework of high cushion cap foundation | |
CN206829147U (en) | A kind of combined type shaped steel, slip casting steel pipe bearing diagonal foundation pit enclosure structure |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
RJ01 | Rejection of invention patent application after publication | ||
RJ01 | Rejection of invention patent application after publication |
Application publication date: 20171013 |