CN107237500A - Concrete vibrating method - Google Patents

Concrete vibrating method Download PDF

Info

Publication number
CN107237500A
CN107237500A CN201710491222.1A CN201710491222A CN107237500A CN 107237500 A CN107237500 A CN 107237500A CN 201710491222 A CN201710491222 A CN 201710491222A CN 107237500 A CN107237500 A CN 107237500A
Authority
CN
China
Prior art keywords
concrete
vibrating
reinforcing bar
auxiliary member
vibrated
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201710491222.1A
Other languages
Chinese (zh)
Inventor
孔维
孔维一
刘家亮
宋赛中
孙恺
常涌琛
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China MCC20 Group Corp Ltd
Original Assignee
China MCC20 Group Corp Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China MCC20 Group Corp Ltd filed Critical China MCC20 Group Corp Ltd
Priority to CN201710491222.1A priority Critical patent/CN107237500A/en
Publication of CN107237500A publication Critical patent/CN107237500A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G21/00Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
    • E04G21/02Conveying or working-up concrete or similar masses able to be heaped or cast
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G21/00Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
    • E04G21/02Conveying or working-up concrete or similar masses able to be heaped or cast
    • E04G21/06Solidifying concrete, e.g. by application of vacuum before hardening
    • E04G21/08Internal vibrators, e.g. needle vibrators

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Mechanical Engineering (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • On-Site Construction Work That Accompanies The Preparation And Application Of Concrete (AREA)

Abstract

The invention provides a kind of concrete vibrating method.This method includes:Following steps:The position respectively vibrated a little according to the spacing treated between assembling reinforcement, vibrate rod outside diameter and the determination of vibrating spear operating radius;In reinforcing bar process of binding or after reinforcing bar colligation is finished, into reinforcing bar before casting concrete, in the pre-buried auxiliary member in position a little that vibrates;After the casting concrete into reinforcing bar, the side that vibrating spear is attached to auxiliary member is vibrated, and the opposite side that vibrating spear is attached to auxiliary member again after vibration compacting is vibrated, and vibrates and auxiliary member is extracted after finishing.In the present invention, in the pre-buried auxiliary member in position a little that vibrates so that inconsistent phenomenon will not occur in process of binding for each layer reinforcing bar, it is to avoid cause because reinforcing bar colligation time interval is too small vibrating spear to be difficult to the phenomenon for inserting armored concrete;In process of vibrating, vibrating spear is vibrated close to auxiliary member so that uniform force inside reinforcing bar, can prevent vibrating spear from colliding reinforcing bar when vibrating, it is ensured that the quality of vibrating of concrete.

Description

Concrete vibrating method
Technical field
The present invention relates to architectural engineering construction technique field, in particular to a kind of concrete vibrating method.
Background technology
China's major part buildings or structures use reinforced concrete structure, when the component such as basis, beam or post in design drawing Reinforcing bar it is excessively intensive when, inevitably occur that local bar spacing is too small in reinforcing bar process of binding, cause concrete to shake Tamper can not be inserted inside reinforcing bar, it is impossible to which vibrate lower concrete, reduced concrete vibrating quality, caused hidden danger of quality, influenceed Delivery receiving acceptance.
Solving the problems, such as the method for concrete vibrating under intensive reinforcing rod part at present mainly has following several:
(1) Reinforcement Replacement.Minor diameter reinforcing bar changes Large-size rebar into, reduces reinforcing bar radical, increases bar spacing.The method Need designer to recalculate arrangement of reinforcement, delay the construction period, effect is limited.
(2) pea gravel concreten is poured.The obstruction that can reduce coarse aggregate to vibrating spear is poured using pea gravel concreten, but not Obstruction of the reinforcing bar to vibrating spear can be reduced.
(3) reinforcing bar is haled using crowbar or iron wire.Force to pry open reinforcing bar using crowbar or forced to pull open reinforcing bar with iron wire, so Insertion vibrating spear vibrates afterwards, and such method easily causes reinforcing bar dislocation, violates job specfication, influence structure safety.
The content of the invention
In consideration of it, the present invention proposes a kind of concrete vibrating method, it is intended to solve in the prior art due to local reinforcing bar Spacing is too small, causes concrete vibration stick can not insert the problem of concrete vibrating caused by reinforcing bar inside is second-rate.
On one side, the present invention proposes a kind of concrete vibrating method, comprises the following steps:Vibrate and to determine a step, The position respectively vibrated a little according to the spacing treated between assembling reinforcement, vibrate rod outside diameter and the determination of vibrating spear operating radius;Reinforcing bar colligation Step, before casting concrete, vibrates a little in reinforcing bar process of binding or after reinforcing bar colligation is finished, into reinforcing bar described The pre-buried auxiliary member in position;Pour and vibrated concrete step, after the casting concrete into reinforcing bar, the vibrating spear is attached to The side of the auxiliary member is vibrated, and the opposite side that the vibrating spear is attached to the auxiliary member again after vibration compacting is shaken Smash, vibrate and the auxiliary member is extracted after finishing.
Further, in above-mentioned concrete vibrating method, in a determination step of vibrating, vibrated a little described in each two Spacing is not more than 1.5 times of the vibrating spear operating radius.
Further, in above-mentioned concrete vibrating method, in the assembling reinforcement step, the auxiliary member is steel pipe.
Further, in above-mentioned concrete vibrating method, the external diameter of the steel pipe for the rod outside diameter that vibrates 1.1~ 1.2 again.
Further, in above-mentioned concrete vibrating method, the bottom of the steel pipe is cone.
Further, it is described to pour and in vibrated concrete step, work as placement layer by layer in above-mentioned concrete vibrating method When, lower-layer concrete pour and vibrate finish after the auxiliary member pulled out with default unpluging amount upwards;Continue to pour upper strata coagulation Soil, after pouring, first inserts the vibrating spear and is vibrated at the predetermined depth in the lower-layer concrete of the auxiliary member side, Vibrating spear is inserted again and vibrated at the predetermined depth in the lower-layer concrete of the auxiliary member opposite side, the like until Pour and vibrate finish after extract the auxiliary member.
Further, in above-mentioned concrete vibrating method, the predetermined depth is 50mm~100mm.
Further, in above-mentioned concrete vibrating method, the unpluging amount pours thickness equal to the lower-layer concrete.
In the present invention, in the pre-buried auxiliary member in position a little that vibrates so that mistake will not occur in process of binding for each layer reinforcing bar Position phenomenon, it is to avoid cause because reinforcing bar colligation time interval is too small vibrating spear to be difficult to the phenomenon for inserting armored concrete;Vibrating During, vibrating spear is vibrated close to auxiliary member so that uniform force inside reinforcing bar, can prevent vibrating spear from being collided when vibrating Reinforcing bar, it is ensured that the quality of vibrating of concrete.
Brief description of the drawings
By reading the detailed description of hereafter preferred embodiment, various other advantages and benefit is common for this area Technical staff will be clear understanding.Accompanying drawing is only used for showing the purpose of preferred embodiment, and is not considered as to the present invention Limitation.And in whole accompanying drawing, identical part is denoted by the same reference numerals.In the accompanying drawings:
Fig. 1 is the flow chart of concrete vibrating method provided in an embodiment of the present invention;
Fig. 2 be concrete vibrating method provided in an embodiment of the present invention in, the position view between respectively vibrating a little;
Fig. 3 be concrete vibrating method provided in an embodiment of the present invention in, the position view of vibrating spear and auxiliary member.
Embodiment
The exemplary embodiment of the disclosure is more fully described below with reference to accompanying drawings.Although showing the disclosure in accompanying drawing Exemplary embodiment, it being understood, however, that may be realized in various forms the disclosure without should be by embodiments set forth here Limited.On the contrary, these embodiments are provided to facilitate a more thoroughly understanding of the present invention, and can be by the scope of the present disclosure Complete conveys to those skilled in the art.It should be noted that in the case where not conflicting, embodiment in the present invention and Feature in embodiment can be mutually combined.Describe the present invention in detail below with reference to the accompanying drawings and in conjunction with the embodiments.
Referring to Fig. 1, the flow chart of concrete vibrating method provided in an embodiment of the present invention is shown in figure.As illustrated, The vibrating method comprises the following steps:
Vibrate and to determine a step S1, according to the spacing treated between assembling reinforcement, vibrate rod outside diameter and vibrating spear operating radius it is true The fixed position respectively vibrated a little.
Specifically, the spacing that each two is vibrated a little is not more than 1.5 times of vibrating spear operating radius 2.
For example, when the spacing of each transverse steel 3 is 70mm, the external diameter of live vibrating spear 5 is 50mm, and operating radius is During 250mm, then the maximum spacing L=250*1.5mm=375mm that each two is vibrated a little between 1, that is to say, that each two is vibrated The spacing of point 1 can be adjusted according to the position of reinforcing bar colligation, but not should be greater than 375mm.
Reinforcing bar step of ligation S2, in reinforcing bar process of binding or after reinforcing bar colligation is finished, the casting concrete into reinforcing bar Before, in the pre-buried auxiliary member in position a little that vibrates.
Specifically, auxiliary member can be steel pipe, and the external diameter of steel pipe 7 can be 1.1~1.2 times of vibrating spear external diameter.For example, Outside diameter d=50mm of vibrating spear 5, the outer diameter D of steel pipe 7 can be 50mm*1.2=60mm.
When it is implemented, during assembling reinforcement, steel pipe 7 is placed on to vibrating on a little 1 position of having determined, steel The lower end of pipe 7 and bottom template contacts, upper end can slightly fixation not be toppled over thin wire.
, can be by when steel pipe 7 is difficult to insertion and vibrated caused by bar spacing is too small during assembling reinforcement The lower end of steel pipe 7 is tapered with gas flame cuttiug, i.e., the bottom of steel pipe is cone.In transverse steel 3 and the colligation of vertical reinforcement 4 Afterwards, before concrete 6 is poured, steel pipe 7 is inserted to vibrating a little on 1 of having determined.Wherein, in order to prevent the mistake in casting concrete Cheng Zhong, concrete is fallen into steel pipe 7, the upper end open of steel pipe 7 can be covered with capping or directly in the upper end open of steel pipe 7 Place's welding capping.
Pour and vibrated concrete step S3, after the casting concrete into reinforcing bar, vibrating spear is attached to auxiliary member Side is vibrated, and the opposite side that vibrating spear is attached to auxiliary member again after vibration compacting is vibrated, and vibrating, it is auxiliary to be extracted after finishing Assistant piece.
Specifically, when concrete, which is integrated, to be poured, the side that vibrating spear 5 is attached to steel pipe 7 is vibrated, vibration compacting The opposite side that vibrating spear 5 is attached to steel pipe 7 again afterwards is vibrated, and vibrates and steel pipe 7 is extracted after finishing, then steel pipe 7 is positioned over separately One vibrates a little 1, proceeds operation of vibrating.
When placement layer by layer, lower-layer concrete pour and vibrate finish after auxiliary member pulled out with default unpluging amount upwards;After It is continuous to pour layer concrete, after pouring, first vibrating spear is inserted and entered at the predetermined depth in the lower-layer concrete of auxiliary member side Row vibrate, then vibrating spear insert auxiliary member opposite side lower-layer concrete in predetermined depth at vibrated, the like Auxiliary member is extracted after being finished up to pouring and vibrating.When it is implemented, after lower-layer concrete 6 is vibrated and finished, slowly pulling out upwards Steel pipe 7, the height that steel pipe 7 is pulled out upwards is equal to the thickness that lower-layer concrete 6 is poured, and the bottom of steel pipe 7 is located at lower-layer concrete Top surface;Lower-layer concrete was reached after the intermittent time, poured layer concrete, was poured after finishing with vibrating spear 5 close to the one of steel pipe 7 Is vibrated in side insertion lower-layer concrete after 50mm~100mm, it is preferable that the depth that vibrating spear 5 inserts lower-layer concrete is 50mm;After vibration compacting again vibrating spear 5 close to steel pipe 7 opposite side insert concrete in vibrated, the like up to Concreting to default absolute altitude and vibrating extracts steel pipe 7 after finishing.
In the present embodiment, in the pre-buried auxiliary member in position a little that vibrates so that each layer reinforcing bar will not occur in process of binding Inconsistent phenomenon, it is to avoid cause because reinforcing bar colligation time interval is too small vibrating spear to be difficult to the phenomenon for inserting armored concrete;Shaking During smashing, vibrating spear is vibrated close to auxiliary member so that uniform force inside reinforcing bar, can prevent vibrating spear from being touched when vibrating Hit reinforcing bar, it is ensured that the quality of vibrating of concrete;Meanwhile, also solve in the prior art because designer again arrangement of reinforcement causes Construction time limit long-delayed problem, saved the construction period.
Obviously, those skilled in the art can carry out the essence of various changes and modification without departing from the present invention to the present invention God and scope.So, if these modifications and variations of the present invention belong to the scope of the claims in the present invention and its equivalent technologies Within, then the present invention is also intended to comprising including these changes and modification.

Claims (8)

1. a kind of concrete vibrating method, it is characterised in that comprise the following steps:
Vibrate and to determine a step, according to the spacing treated between assembling reinforcement, vibrate rod outside diameter and vibrating spear operating radius determines respectively to shake Smash position a little;
Reinforcing bar step of ligation, in reinforcing bar process of binding or after reinforcing bar colligation is finished, into reinforcing bar before casting concrete, The pre-buried auxiliary member in the position vibrated a little;
Pour and vibrated concrete step, after the casting concrete into reinforcing bar, the vibrating spear is attached to the auxiliary member Side vibrated, the opposite side that the vibrating spear is attached to the auxiliary member again after vibration compacting is vibrated, and has been vibrated The auxiliary member is extracted after finishing.
2. concrete vibrating method according to claim 1, it is characterised in that in a determination step of vibrating, every two The individual spacing vibrated a little is not more than 1.5 times of the vibrating spear operating radius.
3. concrete vibrating method according to claim 1, it is characterised in that described auxiliary in the assembling reinforcement step Assistant piece is steel pipe.
4. concrete vibrating method according to claim 3, it is characterised in that the external diameter of the steel pipe is the vibrating spear 1.1~1.2 times of external diameter.
5. concrete vibrating method according to claim 4, it is characterised in that the bottom of the steel pipe is cone.
6. concrete vibrating method according to claim 1, it is characterised in that described to pour and vibrated concrete step In, when placement layer by layer, lower-layer concrete pour and vibrate finish after the auxiliary member pulled out with default unpluging amount upwards;Continue Layer concrete is poured, after pouring, the default the depth first vibrating spear inserted in the lower-layer concrete of the auxiliary member side Vibrated at degree, then vibrating spear inserted shaken at the predetermined depth in the lower-layer concrete of the auxiliary member opposite side Smash, the like until pour and vibrate finish after extract the auxiliary member.
7. concrete vibrating method according to claim 6, it is characterised in that the predetermined depth is 50mm~100mm.
8. concrete vibrating method according to claim 6, it is characterised in that the unpluging amount is equal to lower floor's coagulation Native pours thickness.
CN201710491222.1A 2017-06-26 2017-06-26 Concrete vibrating method Pending CN107237500A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710491222.1A CN107237500A (en) 2017-06-26 2017-06-26 Concrete vibrating method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710491222.1A CN107237500A (en) 2017-06-26 2017-06-26 Concrete vibrating method

Publications (1)

Publication Number Publication Date
CN107237500A true CN107237500A (en) 2017-10-10

Family

ID=59987949

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710491222.1A Pending CN107237500A (en) 2017-06-26 2017-06-26 Concrete vibrating method

Country Status (1)

Country Link
CN (1) CN107237500A (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111946067A (en) * 2020-09-07 2020-11-17 上海建工二建集团有限公司 Concrete vibrating device and construction method thereof
CN112431356A (en) * 2020-11-27 2021-03-02 中国十七冶集团有限公司 Large-slope inclined column concrete vibrating auxiliary method
CN113585766A (en) * 2021-08-31 2021-11-02 中国二十二冶集团有限公司 Concrete vibrating device and vibrating method
CN113882679A (en) * 2021-11-01 2022-01-04 中国水利水电第三工程局有限公司 Vertical state control method of vibrating rod in thin-wall high-wall cast-in-place concrete

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2005076371A (en) * 2003-09-02 2005-03-24 Shimizu Corp Concrete vibrator
CN103669875A (en) * 2012-09-24 2014-03-26 五冶集团上海有限公司 Tamping assist device for concrete pouring and manufacture method thereof
CN104533094A (en) * 2014-12-03 2015-04-22 浙江省火电建设公司 Vibration rod guiding device
CN106760546A (en) * 2017-02-03 2017-05-31 山东科技大学 Vibrating method and tamping equipment are poured when large volume concrete structural thing is constructed

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2005076371A (en) * 2003-09-02 2005-03-24 Shimizu Corp Concrete vibrator
CN103669875A (en) * 2012-09-24 2014-03-26 五冶集团上海有限公司 Tamping assist device for concrete pouring and manufacture method thereof
CN104533094A (en) * 2014-12-03 2015-04-22 浙江省火电建设公司 Vibration rod guiding device
CN106760546A (en) * 2017-02-03 2017-05-31 山东科技大学 Vibrating method and tamping equipment are poured when large volume concrete structural thing is constructed

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111946067A (en) * 2020-09-07 2020-11-17 上海建工二建集团有限公司 Concrete vibrating device and construction method thereof
CN112431356A (en) * 2020-11-27 2021-03-02 中国十七冶集团有限公司 Large-slope inclined column concrete vibrating auxiliary method
CN113585766A (en) * 2021-08-31 2021-11-02 中国二十二冶集团有限公司 Concrete vibrating device and vibrating method
CN113882679A (en) * 2021-11-01 2022-01-04 中国水利水电第三工程局有限公司 Vertical state control method of vibrating rod in thin-wall high-wall cast-in-place concrete
CN113882679B (en) * 2021-11-01 2022-05-17 中国水利水电第三工程局有限公司 Vertical state control method of vibrating rod in thin-wall high-wall cast-in-place concrete

Similar Documents

Publication Publication Date Title
CN107237500A (en) Concrete vibrating method
CN104847014B (en) The vertical connecting structure of assembly concrete shear wall and construction method
CN104895092B (en) The method that a kind of interim lattice column of inner support is used as permanent structure post
CN102383628B (en) Construction device and construction method for post construction of depressing cone of silo structure
CN107605177A (en) The construction method of efficient precast floor slab and its independent support frame
CN207177303U (en) Rail mounted vibrating spear
CN109610341A (en) A kind of solid section constructing method of Thin-wall Hollow Pier pier top
CN108005255A (en) A kind of construction method of wall
CN207003723U (en) High-rise assembled single row of holes precast shear wall and its assembling structure
CN205976167U (en) Based on cast -in -place floor structures of detachable positioning control spare
CN108544655A (en) The curved beam prefabricated construction method of curved bridge
CN108638322A (en) Prefabricated post concreting method in a kind of assembled architecture
CN106968398A (en) A kind of process that support column is poured below balcony
KR102120647B1 (en) Composite blocks of stone and concrete and manufacturing method thereof
CN112609986A (en) Method for controlling pouring forming quality of concrete batter post
CN105971196B (en) The embedded Concrete-Filled Square Steel Tube ring beam and construction column method of construction of masonry structure
CN105755979A (en) Process for constructing cement concrete guardrails
CN108532939A (en) Shear wall single side formwork method
CN109441190A (en) A kind of orlop heap slope structure and its construction method
CN107939094A (en) Conical concrete construction of funnel method
CN106760487A (en) A kind of cast-in-place concrete exterior wall crack resistence Slate hanging construction method
CN102561692A (en) Method and template for pouring concrete beam or column with embedded part at top
CN106638672B (en) A kind of construction method effectively reducing piping lane haunch area concrete formation bubble
CN111560940A (en) Treatment method of karst tunnel
CN208329639U (en) A kind of steel reinforced concrete auxiliary tamping equipment

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20171010