CN107227829A - A kind of quick levelling hanging structure of metope - Google Patents
A kind of quick levelling hanging structure of metope Download PDFInfo
- Publication number
- CN107227829A CN107227829A CN201710226300.5A CN201710226300A CN107227829A CN 107227829 A CN107227829 A CN 107227829A CN 201710226300 A CN201710226300 A CN 201710226300A CN 107227829 A CN107227829 A CN 107227829A
- Authority
- CN
- China
- Prior art keywords
- suspension member
- horizontal
- oblique
- face
- groove
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04F—FINISHING WORK ON BUILDINGS, e.g. STAIRS, FLOORS
- E04F13/00—Coverings or linings, e.g. for walls or ceilings
- E04F13/07—Coverings or linings, e.g. for walls or ceilings composed of covering or lining elements; Sub-structures therefor; Fastening means therefor
- E04F13/08—Coverings or linings, e.g. for walls or ceilings composed of covering or lining elements; Sub-structures therefor; Fastening means therefor composed of a plurality of similar covering or lining elements
- E04F13/0801—Separate fastening elements
- E04F13/0832—Separate fastening elements without load-supporting elongated furring elements between wall and covering elements
- E04F13/0833—Separate fastening elements without load-supporting elongated furring elements between wall and covering elements not adjustable
- E04F13/0835—Separate fastening elements without load-supporting elongated furring elements between wall and covering elements not adjustable the fastening elements extending into the back side of the covering elements
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04F—FINISHING WORK ON BUILDINGS, e.g. STAIRS, FLOORS
- E04F13/00—Coverings or linings, e.g. for walls or ceilings
- E04F13/07—Coverings or linings, e.g. for walls or ceilings composed of covering or lining elements; Sub-structures therefor; Fastening means therefor
- E04F13/08—Coverings or linings, e.g. for walls or ceilings composed of covering or lining elements; Sub-structures therefor; Fastening means therefor composed of a plurality of similar covering or lining elements
- E04F13/0801—Separate fastening elements
- E04F13/0832—Separate fastening elements without load-supporting elongated furring elements between wall and covering elements
- E04F13/0858—Separate fastening elements without load-supporting elongated furring elements between wall and covering elements fixed by means of spring action
Abstract
The present invention relates to building decoration field, it is simple in construction there is provided one kind, easy construction, dismounting is time saving and energy saving, integrate the quick levelling hanging structure of the metope of positioning and leveling, solve metope present in prior art it is levelling mount construction it is loaded down with trivial details, long construction period, difficulty is big, the technical problem wasted time and energy etc., it includes being fixed on the decoration panel of surface of wall, surface of wall corresponding with the decoration panel is provided with L-shaped suspension member, the longitudinal surface of L-shaped suspension member is smooth to be fixed on surface of wall, it is horizontal for outer extension, and the outer end of longitudinal surface stretches out to form oblique importing clamp upwardly, the outer face in horizontal face extends downwardly and inwardly to form down oblique elastic card plate, suspension member mounting groove is correspondingly provided with decoration panel, the upper oblique importing upward interworking of clamp is connected in the corresponding oblique groove in suspension member mounting groove upper end, under oblique elastic card plate be elastically engaged at the opening edge of suspension member mounting groove along upper.
Description
Technical field
The present invention relates to building decoration field, more particularly to it is a kind of simple in construction, it is time saving and energy saving to dismount, and positioning and leveling are same
Walk the quick levelling hanging structure of the metope completed.
Background technology
Existing metope is levelling to have mounted three kinds of techniques, the levelling method of cement mortar screeding method, keel, the levelling method of basic unit, three kinds
Technique respectively has quality, wherein using, most, technology is most ripe, it is simplest to operate, and cement mortar screeding method is first that basic unit is clear
Reason is clean, by 1:The cement mortar that 3 ratios have been converted is layered on above, and fragment of brick is laid in above, reality, the method are beaten out with skin hammer
Although simple to operate, price is relatively low, there is also following defect:Complex process, from the preparation before laying to last
Maintenance waxing, laying process is more complicated;Cycle is longer, because the curing time of cement mortar is no less than 7 days, so applying
The work cycle is long;Pollution is larger, because traditional handicraft is to carry out paving, one side binding material meeting using cement mortar mode
To mating formation, plate is polluted, and influences paving quality, on the other hand, binding material is easily caused during paving to construction environment
Pollution;It is difficult to change and reuses, combination during laying between floor tile and metope is permanent using media such as cement mortar
Bond, once needing to change, can only be carried out in the way of damage type is removed, general is difficult to reuse, and causes material and artificial
Expend big;Easily there is mass defect, in process of deployment for various reasons, hollowing easily occur, ftracture, come off etc. to lack
Fall into, influence construction quality and use;Difficulty of construction is big, high to construction technical requirement, and rawness or the workman lacked experience hold
Easily cause the problems such as construction quality is not up to standard.Other two kinds of levelling modes are also to compare waste of materials, and technique is relative complex can not
Realize industrialized construction.
The content of the invention
The present invention mainly provides a kind of simple in construction, convenient and quick construction, and it is time saving and energy saving to dismount, and positioning and leveling are same
The quick levelling hanging structure of the metope completed is walked, levelling loaded down with trivial details, the construction that mounts construction of metope present in prior art is solved
Cycle length, difficulty are big, the technical problem wasted time and energy etc..
The above-mentioned technical problem of the present invention is mainly what is be addressed by following technical proposals:A kind of metope is quickly levelling
Hanging structure, including it is fixed on by fixing bolt the decoration panel of surface of wall, wall table corresponding with the decoration panel
Face is provided with L-shaped suspension member, and the longitudinal surface of L-shaped suspension member is smooth to be fixed on surface of wall, is horizontal for outer extension, and longitudinal surface
Outer end stretches out to form oblique importing clamp upwardly, and the outer face in horizontal face extends downwardly and inwardly to form down oblique elasticity
Clamp, is correspondingly provided with suspension member mounting groove on decoration panel, and the upper oblique importing upward interworking of clamp is connected on suspension member mounting groove
Hold in corresponding oblique groove, under oblique elastic card plate be elastically engaged at the opening edge of suspension member mounting groove along upper.Pass through fixed spiral shell
Bolt is horizontally disposed with L-shaped suspension member on surface of wall, and L-shaped suspension member interworking is connected in the mounting groove of decoration panel medial surface, wherein L
Shape suspension member is slidably inserted into mounting groove in corresponding oblique groove by the upper oblique importing clamp of upper end, lower end in insertion process
Under be folded upward at after oblique elastic card plate elastic deformation, until in the upper complete interworking insertion oblique groove of oblique importing clamp,
Under oblique elastic card plate recover to deform and be elastically engaged at the opening edge of suspension member mounting groove along upper so that L-shaped suspension member is firm
It is connected in mounting groove, decoration panel is fixed on wall, integrates positioning and leveling, simple in construction, easy construction, tear open
It is time saving and energy saving to fill.
Preferably, the outboard end level of oblique elastic card plate extends inwardly to form horizontal resiliency clamp, level under described
The inwall that elastic clamp carries over suspension member mounting groove is extended outwardly and is vertically connected on surface of wall.Pass through the oblique elasticity under
The outboard end of clamp extends horizontal resiliency clamp, stress of the oblique elastic card plate in dismounting and fixation under improvement,
And increase under oblique elastic card plate intensity, improve location and installation reliability.
Preferably, being respectively equipped with lateral direction penetrating groove in the middle part of the longitudinal surface and horizontal face.By in longitudinal surface and
The middle part in horizontal face sets lateral direction penetrating groove respectively, L-shaped suspension member is turned into hollow frame structure, on the one hand saves former material
Material, reduces weight, on the other hand also improves the bulk strength and elasticity of L-shaped suspension member.
Preferably, being provided with positioning hole, the connection end of fixing bolt close to the longitudinal surface lower side both sides in the horizontal face
Spin and be fixed on surface of wall through positioning hole.The left and right two ends of L-shaped suspension member are fixed on wall by fixing bolt, Gu
Determine mode simple and reliable, fixation is conveniently leveling.
Preferably, it is described it is it is oblique import clamp and under the angle of oblique elastic card plate and surface of wall be 45 ゜ ± 5
゜.Upper oblique importing clamp oblique elastic card plate with keeps suitable extension angle, not only can guarantee that it has enough bullets
Property, it can guarantee that it has enough intensity and deformability again.
Preferably, the top insertion in the positioning hole is connected with horizontal location with the screw rod interworking on fixing bolt
Groove, the outboard end of horizontal location groove is connected on neighbouring L-shaped suspension member end face by end face apical pore, is set in end face apical pore
There is a horizontal push rod, horizontal push rod extends internally and screw rod is clamped in the medial extremity of horizontal location groove.By in positioning hole
Top insertion connection horizontal location groove, further through end face apical pore and neighbouring L on the extended line direction of horizontal location groove
Shape suspension member end face is connected, and first fixing bolt can be horizontally fixed on wall during installation, then by the positioning hole pair on L-shaped suspension member
That answers is sleeved on fixing bolt, then pulls L-shaped suspension member now, and screw rod enters horizontal location groove, then unidirectional level pulls L-shaped
Suspension member, makes screw rod be located at the medial extremity of horizontal location groove, horizontal push rod is then placed in end face apical pore, screw rod is clamped in
The medial extremity of horizontal location groove, the bolt that is finally tightened positioning, due to installing fixing bolt in advance, it is thus ensured that fixed
Bolt is in horizontality and easily realized, the screw rod on fixing bolt is by clamping and positioning, reverse operating during dismounting, and positioning is adjusted
Flat synchronous realization, it is convenient and swift, it is time saving and energy saving.
Horizontal push rod can be screwed in end face apical pore, as it is further preferred that the horizontal push rod interworking is slidably connected at end
In the apical pore of face, and flexible plug is being encapsulated in corresponding end face apical pore on the outside of horizontal push rod.Pass through elastic plug restriction level
Push rod position, prevents horizontal push rod from left and right play, simple in construction, convenient disassembly occurring under external force.
As it is further preferred that bolt head interworking on the positioning hole and fixing bolt, and positioning hole be oriented to by inclined-plane it is logical
Groove connects the outboard end in horizontal location groove.By setting inclined-plane guide groove, L-shaped suspension member can be in Action of Gravity Field during installation
It is lower automatic downward, screw rod is slipped into horizontal location groove, installation process is more time saving and energy saving.
Therefore, a kind of quick levelling hanging structure tool of metope of the invention has the advantage that:It is horizontally fixed on the L on wall
Shape suspension member makes the upper oblique importing clamp interworking of its upper end be caught in decorative cover by the elastic deformation of oblique elastic card plate under lower end
The mounting groove of plate, under oblique elastic card plate recover deformation and interworking is connected to the opening edge of suspension member mounting groove along upper so that dress
Decoration panel is firmly fixed on wall by L-shaped suspension member, integrates positioning and leveling, simple in construction, easy construction, dismounting
It is time saving and energy saving;Extend to form horizontal resiliency clamp by the outboard end of the oblique elastic card plate under, improve down oblique elastic card
The intensity of oblique elastic card plate under stress of the plate in dismounting and fixation, and increase;L-shaped suspension member uses hollow framework
Structure, lightweight, intensity is high;Horizontal location groove and end face apical pore are connected by the top insertion in positioning hole, during installation
First fixing bolt can be horizontally fixed on wall and be set with L-shaped suspension member again, therefore can be by the horizontally disposed reality of fixing bolt
The horizontal positioned of existing L-shaped suspension member, positioning leveling synchronously realizes that installation process is convenient and swift, time saving and energy saving.
Brief description of the drawings:
Fig. 1 is a kind of structural representation of the quick levelling hanging structure of metope of the invention;
Fig. 2 is the partial structurtes enlarged drawing of the present invention;
Fig. 3 is the partial structural diagram of positioning hole in the present invention.
Embodiment:
Below by embodiment, and with reference to accompanying drawing, technical scheme is described in further detail.
Embodiment:
As depicted in figs. 1 and 2, the quick levelling hanging structure of a kind of metope of the invention, including be fixed on the decoration on the surface of wall 1
Pass through the left and right fixed L-shaped suspension member 3, L of two fixing bolts 6 level on panel 2, the surface of wall 1 corresponding with decoration panel 2
The longitudinal surface 31 of shape suspension member 3 is upper, and horizontal face 32 is under, the lower side both sides of longitudinal surface 31 close to the horizontal face 32 of L-shaped suspension member 3
A positioning hole 5 is had, the connection end of fixing bolt 6 spins through positioning hole 5 to be fixed on the surface of wall 1, hangs L-shaped
The longitudinal surface 31 of part 3 is smooth to be fixed on the surface of wall 1, and horizontal face 32 is extended perpendicularly outward, and longitudinal surface 31 outer end towards
Upper outside 45 ゜ extends to form oblique importing clamp 33, and inside 45 ゜ extends to form down oblique bullet downwards for the outer end in horizontal face 32
Property clamp 34, corresponding on the medial surface of decoration panel 2 to be provided with suspension member mounting groove 4, the upper oblique importing upward interworking of clamp 33
In the oblique groove 41 for being connected to the inner top side of suspension member mounting groove 4, under oblique elastic card plate 34 be elastically engaged at suspension member mounting groove 4
On the internal face of downside, under oblique elastic card plate 34 outboard end again along the internal face of suspension member mounting groove 4 towards the surface direction water of wall 1
Flat extension forms horizontal resiliency clamp 35, until the outboard end of horizontal resiliency clamp 35 is vertically connected on the surface of wall 1, vertical
Lateral direction penetrating groove 36 is respectively provided with again to the middle part in face 31 and horizontal face 32, and the cross section of lateral direction penetrating groove 36 is rectangle, and square
The lateral direction penetrating groove 36 of shape is respectively facing the bearing of trend extension in longitudinal surface 31 and horizontal face 32.As shown in figure 3, positioning hole 5
Diameter is than the circular big 2mm of diameter of bolt head 62 on fixing bolt 6, and the top of positioning hole 5 is further through inclined-plane guide groove 11
Insertion is connected to the right-hand end of horizontal location groove 7, and the forward end level of horizontal location groove 7 extends to the left, and horizontal location
The width of groove 7 is than the big 1mm of diameter of screw rod 61 on fixing bolt 6, and inclined-plane guide groove 11 is up-small and down-big, inclined-plane guide groove
11 upper port is consistent with the width of horizontal location groove 7, and the lower port and positioning hole 5 of inclined-plane guide groove 11 are tangent, wherein
The right-hand end level of the horizontal location groove 7 on right side extends to the right and connected forms end face top on the end face of L-shaped suspension member 3 on right side
Hole 8, interworking is slidably connected dampening flat-top bar 9 in end face apical pore 8, and horizontal push rod 9 extends internally and screw rod 61 is clamped in into water
Calm down the medial extremity of a groove 7, the flexible plug 10 of encapsulation, elastic plug in the corresponding end face apical pore 8 in the horizontal outside of push rod 9
10 end face outside and the corresponding end face flush of L-shaped suspension member 3.
Specific embodiment described herein is only the design explanation for example to the present invention.Technology belonging to of the invention
The technical staff in field can make various modifications or supplement to described specific embodiment or use similar mode
Substitute, but without departing from the spiritual of the present invention or surmount scope defined in appended claims.
Claims (8)
1. a kind of quick levelling hanging structure of metope, including pass through fixing bolt(6)It is fixed on wall(1)The decoration panel on surface
(2), it is characterised in that:With the decoration panel(2)Corresponding wall(1)Surface is provided with L-shaped suspension member(3), L-shaped suspension member(3)
Longitudinal surface(31)It is smooth to be fixed on wall(1)On surface, horizontal face(32)Stretch out, and longitudinal surface(31)Outer end towards
On stretch out to form oblique importing clamp(33), horizontal face(32)Outer face extend downwardly and inwardly to form down oblique elasticity
Clamp(34), in decoration panel(2)On be correspondingly provided with suspension member mounting groove(4), upper oblique importing clamp(33)Upward interworking clamping
In suspension member mounting groove(4)The corresponding oblique groove in upper end(41)It is interior, under oblique elastic card plate(34)It is elastically engaged at suspension member installation
Groove(4)Opening edge along upper.
2. a kind of quick levelling hanging structure of metope according to claim 1, it is characterised in that:Oblique elastic card under described
Plate(34)Outboard end level extend inwardly to form horizontal resiliency clamp(35), horizontal resiliency clamp(35)Carry over suspension member mounting groove
(4)Inwall extend outwardly and be vertically connected to wall(1)On surface.
3. a kind of quick levelling hanging structure of metope according to claim 1 or 2, it is characterised in that:In the longitudinal surface
(31)With horizontal face(32)Middle part be respectively equipped with lateral direction penetrating groove(36).
4. a kind of quick levelling hanging structure of metope according to claim 1 or 2, it is characterised in that:Close to the transverse direction
Face(32)Longitudinal surface(31)Lower side both sides are provided with positioning hole(5), fixing bolt(6)Connection end pass through positioning hole(5)Rotation
Connect and be fixed on wall(1)On surface.
5. a kind of quick levelling hanging structure of metope according to claim 1 or 2, it is characterised in that:It is described oblique to lead
Enter clamp(33)The oblique elastic card plate with(34)With wall(1)The angle on surface is the ゜ of 45 ゜ ± 5.
6. a kind of quick levelling hanging structure of metope according to claim 1 or 2, it is characterised in that:In the positioning hole
(5)Top insertion be connected with and fixing bolt(6)On screw rod(61)The horizontal location groove of interworking(7), horizontal location lead to
Groove(7)Outboard end pass through end face apical pore(8)Connection is in neighbouring L-shaped suspension member(3)On end face, in end face apical pore(8)Inside it is provided with
Horizontal push rod(9), horizontal push rod(9)Extend internally and by screw rod(61)It is clamped in horizontal location groove(7)Medial extremity.
7. a kind of quick levelling hanging structure of metope according to claim 6, it is characterised in that:The horizontal push rod(9)
Interworking is slidably connected at end face apical pore(8)It is interior, and in horizontal push rod(9)The corresponding end face apical pore in outside(8)Interior encapsulation is flexible
Plug(10).
8. a kind of quick levelling hanging structure of metope according to claim 6, it is characterised in that:The positioning hole(5)With
Fixing bolt(6)On bolt head(62)Interworking, and positioning hole(5)Pass through inclined-plane guide groove(11)Connection is logical in horizontal location
Groove(7)Outboard end.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201710226300.5A CN107227829B (en) | 2017-04-08 | 2017-04-08 | A kind of quick levelling hanging structure of metope |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201710226300.5A CN107227829B (en) | 2017-04-08 | 2017-04-08 | A kind of quick levelling hanging structure of metope |
Publications (2)
Publication Number | Publication Date |
---|---|
CN107227829A true CN107227829A (en) | 2017-10-03 |
CN107227829B CN107227829B (en) | 2019-01-25 |
Family
ID=59933611
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201710226300.5A Active CN107227829B (en) | 2017-04-08 | 2017-04-08 | A kind of quick levelling hanging structure of metope |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN107227829B (en) |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN108868035A (en) * | 2018-07-13 | 2018-11-23 | 永嘉县博宇建设有限公司 | A kind of wall floor decoration module |
CN114051561A (en) * | 2020-05-04 | 2022-02-15 | 斯维斯佩尔集团股份公司 | Panel fastening system |
Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US5107641A (en) * | 1988-06-10 | 1992-04-28 | Cerline Ceramic Corporation | Ceramic brick |
CN2303888Y (en) * | 1997-03-03 | 1999-01-13 | 许鸿泉 | Dry construction ceramic tile |
CN203867018U (en) * | 2014-06-20 | 2014-10-08 | 中机中联工程有限公司 | Grooved stone curtain wall connecting element and mounting structure thereof |
CN205577329U (en) * | 2016-03-18 | 2016-09-14 | 翁元水 | Wall fastener |
CN206737336U (en) * | 2017-04-08 | 2017-12-12 | 浙江亚厦装饰股份有限公司 | A kind of levelling hanging structure of metope |
-
2017
- 2017-04-08 CN CN201710226300.5A patent/CN107227829B/en active Active
Patent Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US5107641A (en) * | 1988-06-10 | 1992-04-28 | Cerline Ceramic Corporation | Ceramic brick |
CN2303888Y (en) * | 1997-03-03 | 1999-01-13 | 许鸿泉 | Dry construction ceramic tile |
CN203867018U (en) * | 2014-06-20 | 2014-10-08 | 中机中联工程有限公司 | Grooved stone curtain wall connecting element and mounting structure thereof |
CN205577329U (en) * | 2016-03-18 | 2016-09-14 | 翁元水 | Wall fastener |
CN206737336U (en) * | 2017-04-08 | 2017-12-12 | 浙江亚厦装饰股份有限公司 | A kind of levelling hanging structure of metope |
Cited By (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN108868035A (en) * | 2018-07-13 | 2018-11-23 | 永嘉县博宇建设有限公司 | A kind of wall floor decoration module |
CN108868035B (en) * | 2018-07-13 | 2020-01-14 | 永嘉县博宇建设有限公司 | Wall and floor decoration module |
CN114051561A (en) * | 2020-05-04 | 2022-02-15 | 斯维斯佩尔集团股份公司 | Panel fastening system |
CN114051561B (en) * | 2020-05-04 | 2023-11-07 | 斯维斯佩尔集团股份公司 | Panel fastening system |
Also Published As
Publication number | Publication date |
---|---|
CN107227829B (en) | 2019-01-25 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN208401455U (en) | A kind of cable bearer for building | |
CN107227829A (en) | A kind of quick levelling hanging structure of metope | |
KR101060587B1 (en) | Construction stair tile construction mold and stair tile construction method | |
CN206737336U (en) | A kind of levelling hanging structure of metope | |
CN105155794B (en) | The wet hanging method of stone material and its structure of a kind of gypsum aerating brick wall | |
CN207512990U (en) | A kind of suspended ceiling structure | |
CN210217063U (en) | Plate joint filling device for light wall plate | |
CN201962924U (en) | Putty scraping machine | |
CN109630947B (en) | Subway top linkage | |
CN214696641U (en) | Ground overhead leveling structure | |
CN113882565B (en) | Assembly type unit ceramic brick dry-hanging curtain wall system and construction method thereof | |
CN202500296U (en) | Embedded prearranged pipe locking pin used for fixing veneer | |
CN215594693U (en) | Steel pipe pull rod hollow ceramic archaized brick combined wall | |
CN201428212Y (en) | Improved dry-hang device | |
CN209990060U (en) | Monomer large unit building decorative board | |
CN211080715U (en) | Wall light composite stone hangs structure futilely in assembled | |
CN204919356U (en) | Mould platform is hung in construction of steel longeron concrete bridge panel | |
CN109025230B (en) | Construction platform for building | |
CN208473262U (en) | A kind of decorative engineering ceramic tile installation supplementary structure | |
CN107299696B (en) | A kind of heat-preserving building wall and production method | |
CN2365322Y (en) | Fast setting glazed tiles machine | |
CN213837440U (en) | Detachable wall decorative panel | |
CN206521928U (en) | A kind of multi-functional accessory of mating formation | |
CN215670752U (en) | Wallboard installation kit free of detachable bottom plate | |
CN214697038U (en) | Novel concrete floor construction device |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
GR01 | Patent grant | ||
GR01 | Patent grant |