CN107218179B - The construction method of offshore wind generating partial installation - Google Patents

The construction method of offshore wind generating partial installation Download PDF

Info

Publication number
CN107218179B
CN107218179B CN201710618852.0A CN201710618852A CN107218179B CN 107218179 B CN107218179 B CN 107218179B CN 201710618852 A CN201710618852 A CN 201710618852A CN 107218179 B CN107218179 B CN 107218179B
Authority
CN
China
Prior art keywords
assistance platform
auxiliary
platform
blower
pile
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201710618852.0A
Other languages
Chinese (zh)
Other versions
CN107218179A (en
Inventor
胡金雄
黄延琦
叶修煜
尹剑锋
吴春林
管鹏程
王建勇
司天宇
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Ningbo Branch Cccc No3 Harbor Engineering Co ltd
CCCC Third Harbor Engineering Co Ltd
Original Assignee
Cccc Third Harbor Engineering Co Ltd Ningbo Branch
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Cccc Third Harbor Engineering Co Ltd Ningbo Branch filed Critical Cccc Third Harbor Engineering Co Ltd Ningbo Branch
Priority to CN201710618852.0A priority Critical patent/CN107218179B/en
Priority to CN201711116097.2A priority patent/CN107795438B/en
Publication of CN107218179A publication Critical patent/CN107218179A/en
Application granted granted Critical
Publication of CN107218179B publication Critical patent/CN107218179B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F03MACHINES OR ENGINES FOR LIQUIDS; WIND, SPRING, OR WEIGHT MOTORS; PRODUCING MECHANICAL POWER OR A REACTIVE PROPULSIVE THRUST, NOT OTHERWISE PROVIDED FOR
    • F03DWIND MOTORS
    • F03D13/00Assembly, mounting or commissioning of wind motors; Arrangements specially adapted for transporting wind motor components
    • F03D13/20Arrangements for mounting or supporting wind motors; Masts or towers for wind motors
    • F03D13/25Arrangements for mounting or supporting wind motors; Masts or towers for wind motors specially adapted for offshore installation
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02EREDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
    • Y02E10/00Energy generation through renewable energy sources
    • Y02E10/70Wind energy
    • Y02E10/72Wind turbines with rotation axis in wind direction
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02EREDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
    • Y02E10/00Energy generation through renewable energy sources
    • Y02E10/70Wind energy
    • Y02E10/727Offshore wind turbines
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02PCLIMATE CHANGE MITIGATION TECHNOLOGIES IN THE PRODUCTION OR PROCESSING OF GOODS
    • Y02P70/00Climate change mitigation technologies in the production process for final industrial or consumer products
    • Y02P70/50Manufacturing or production processes characterised by the final manufactured product

Landscapes

  • Engineering & Computer Science (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • Sustainable Development (AREA)
  • Sustainable Energy (AREA)
  • Chemical & Material Sciences (AREA)
  • Combustion & Propulsion (AREA)
  • Mechanical Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Wind Motors (AREA)
  • Placing Or Removing Of Piles Or Sheet Piles, Or Accessories Thereof (AREA)

Abstract

The present invention relates to a kind of construction methods of offshore wind generating partial installation, the wind-driven generator is located on the cushion cap of blower foundation, wherein the wind-driven generator includes pylon and the blower above the pylon, the wind-driven generator fission is lifted on blower foundation by assistance platform, to realize the partial installation of the wind-driven generator.The present invention is installed using the assistance platform by blower is split type, is effectively reduced the influence that stormy waves constructs to assembling, is improved installation efficiency.

Description

The construction method of offshore wind generating partial installation
Technical field
The present invention relates to technical field of wind power generation, refer in particular to a kind of construction party of offshore wind generating partial installation Method.
Background technique
China's oceanic area is vast, and offshore wind energy resource is abundant, and the potential using sea wind wind-power electricity generation is very big, but China Wind energy on the sea develop later, Oversea wind power generation indicating China formally since the completion of Donghai Bridge marine wind electric field.
Offshore wind farm is the open sea environment that offshore is more than 10 nautical miles, mesh as a kind of new energy, at present country's addressing There are mainly two types of modes for preceding offshore wind turbine installation, and one is use large-scale floating cranes directly to carry out integral hoisting, Second is that using the dedicated large scale equipment of assembling.Since sea situation is severe, especially natural conditions pair such as construction area wind, wave, stream No matter the influence of ship machine construction which kind of above-mentioned scheme is used, all had the disadvantage in that due to wind-driven generator entirety marine transportation Center of gravity is high, and the risk that causes to tumble is big;And in transport, the ability of transport and hanging device is not only increased substantially, is also wanted Integral installation buffer unit is considered in wind generator design to reduce the clashing and breaking rate of sea-freight and sea dress, thus caused marine big The installation difficulty of type wind-driven generator is big.
In order to overcome the above problem, Chinese invention patent (CN101985917A) discloses a kind of offshore wind turbine Tower crane is assembled in land, is refuted using the crane barge side of being hung to, then tower crane is mounted on by crane barge by partial installation construction method After on pier and it is fixed on pier;After tower crane is installed on pier, sequence installs three section towers of blower, lifting Blower host, wheel hub and blade;The tower that blower is unclamped using cohesion device is turned to upright position, withdraws cantilever crane and king-post, Tower crane is lifted on transport barge with crane barge.Above-mentioned offshore wind turbine partial installation construction method, although reducing Self weight, reduces costs, and facilitates the integral installation of tower crane, but due to the required precision of assembling height, causes to lifting The requirement of equipment is also very high, and still depositing leads to the problem of reducing construction efficiency vulnerable to wave influence during installation.
Summary of the invention
For this purpose, technical problem to be solved by the present invention lies in overcome in the prior art Wind turbines installation vulnerable to sea situation shadow Ring, the problem that causes construction efficiency low to provide it is a kind of influenced by sea situation small, guarantee that Wind turbines installation is steady to the full extent The construction method of qualitative offshore wind generating partial installation.
In order to solve the above technical problems, a kind of construction method of offshore wind generating partial installation of the invention, described Wind-driven generator is located on the cushion cap of blower foundation, wherein the wind-driven generator includes pylon and is located above the pylon Blower, include the following steps: step S1: pile sinking carried out to the pile foundation of the blower foundation;Step S2: manufacture assistance platform, And the assistance platform is mounted on by the blower foundation, make the assistance platform close to the blower foundation;Step S3: Suspender is set on the assistance platform, and continue under the suspender cooperation cable tube to the blower foundation, by ship facility, Anti-collision structure installation and cushion cap reinforcing bar, template and concrete structure are constructed;Step S4: it is utilized on the assistance platform The suspender on the tower hoisting to the cushion cap and will first be installed, and then again lift the blower to the pylon It goes up and is installed.
In one embodiment of the invention, the assistance platform uses jacket structure, whole spicing forming type.
In one embodiment of the invention, when the assistance platform is installed, in the lower end of the assistance platform, setting is anti- Heavy reinforcing rod, and go deep into the anti-settling reinforcing rod in mud.
In one embodiment of the invention, auxiliary pile is installed at the node location of the assistance platform, and institute is installed The method for stating auxiliary pile are as follows: be first inserted vertically into four auxiliary piles in the casing of four corner points of the assistance platform, pass through Vibration hammer turns four auxiliary piles to designed elevation, promotes the assistance platform and assists to designed elevation and by described four Stake is fixed in the auxiliary pipe casing, then hangs up and beats remaining auxiliary pile and remaining auxiliary pile is fixed in described sleeve pipe.
In one embodiment of the invention, four are inserted vertically into the casing of four corner points of the assistance platform The method of auxiliary pile are as follows: auxiliary pile is sling by crane ship, the auxiliary pile is sequentially inserted into the assistance platform casing, so Crane ship slings vibration hammer afterwards, makes the fixture of the vibration hammer close to the top of the auxiliary pile, and the fixture is caught in stake top And clamp, finally start the vibration hammer auxiliary pile successively shakes and is sink to designed elevation.
In one embodiment of the invention, the assistance platform is promoted to consolidate to designed elevation and by four auxiliary piles The method being scheduled in the assistance platform casing are as follows: after the assistance platform is promoted to designed elevation, in the assistance platform Beam is shelved in insertion in through-hole on casing, and four auxiliary piles is made to be located at the lower section for shelving beam.
In one embodiment of the invention, the method remaining auxiliary pile being fixed on the assistance platform are as follows: in institute It states equal aperture on remaining auxiliary pile and forms mounting hole, and the mounting hole on the remaining auxiliary pile is made to be directed at the assistance platform set Through-hole on pipe, then so that the remaining auxiliary pile is fixed on the assistance platform across the mounting hole on corresponding beam of shelving On.
In one embodiment of the invention, when the assistance platform is installed, the assistance platform is hung using crane ship To the position for performing label in advance, make the assistance platform close to the starboard of station keeping ship, the center line on the assistance platform When position is overlapped with the ship side outer center line of the station keeping ship, by slowly decentralization is high to designing after assistance platform leveling Journey broke off relations after the assistance platform is stablized, subsequently into the auxiliary pile construction stage.
In one embodiment of the invention, the pylon includes positioned at the tower of bottom, above the tower Middle tower and the head tower above the middle tower, after the completion of the bearing platform construction of the blower foundation, in the assistance platform On the tower is lifted on the cushion cap and installing, then sequentially lift the middle tower and head tower.
In one embodiment of the invention, the blower includes cabin above the pylon, is located at the machine Wheel hub on cabin and the three pieces blade on the wheel hub after installing pylon, utilize suspender on the assistance platform The combination of the cabin and wheel hub is first lifted, then the three pieces blade is lifted according to this again.
The above technical solution of the present invention has the following advantages over the prior art:
The construction method of offshore wind generating partial installation of the present invention, passes through the lifting on the assistance platform Equipment both can safe and efficient progress blower cushion cap cable tube, by ship facility, the installation of anti-collision structure and reinforcing bar, template and coagulation Soil construction, and the wind-driven generator fission can be installed, reduce influence of the marine stormy waves to construction, realizes to institute " land construction " for stating cushion cap top assembling effectively reduces the influence that stormy waves constructs to assembling, significantly improves peace Fill work efficiency.
Detailed description of the invention
In order to make the content of the present invention more clearly understood, it below according to specific embodiments of the present invention and combines Attached drawing, the present invention is described in further detail, wherein
Fig. 1 is the construction method flow chart of offshore wind generating partial installation of the present invention;
Fig. 2 is the top view of blower cushion cap and the assistance platform of the present invention;
Fig. 3 is the side view of assistance platform of the present invention.
Specific embodiment
As depicted in figs. 1 and 2, described the present embodiment provides a kind of construction method of offshore wind generating partial installation Wind-driven generator is located on the cushion cap of blower foundation 10, wherein the wind-driven generator includes pylon and is located on the pylon The blower of side, includes the following steps: step S1: carrying out pile sinking to the pile foundation of the blower foundation 10;Step S2: manufacture auxiliary is flat Platform 20, and the assistance platform 20 is mounted on by the blower foundation 10, make the assistance platform 20 close to the blower base Plinth 10;Step S3: suspender is set on the assistance platform 20, and is continued under suspender cooperation to the blower foundation 10 Cable tube, by ship facility, anti-collision structure installation and cushion cap reinforcing bar, template and concrete structure construct;Step S4: It on the tower hoisting to the cushion cap and will first be carried out on the assistance platform 20 using the suspender, then again by the wind Machine is lifted on the pylon and being installed.
The construction method of offshore wind generating partial installation described in the present embodiment, the wind-driven generator are located at blower base On the cushion cap of plinth 10, wherein the wind-driven generator includes pylon and the blower above the pylon, wherein the tower Frame is located on the cushion cap, in the step S1, pile sinking is carried out to the pile foundation of the blower foundation 10, thus by the blower base Plinth 10 is fixed at sea;In the step S2, assistance platform 20 is manufactured, and the assistance platform 20 is mounted on the blower base By plinth 10, make the assistance platform 20 close to the blower foundation 10, thus be conducive to it is right subsequently through the assistance platform 20 The wind-driven generator is constructed, and is realized " land construction " to cushion cap top assembling, is effectively reduced wind The influence that wave constructs to assembling, significantly improves installation effectiveness;In the step S3, it is arranged on the assistance platform 20 Suspender, and the suspender cooperation under continue the cable tube to the blower foundation 10, by ship facility, anti-collision structure installation and Cushion cap reinforcing bar, template and concrete structure are constructed, and are also accelerated the cable tube by the assistance platform 20 at this time, are leaned on Ship facility, the installation of anti-collision structure and cushion cap reinforcing bar, template and concrete construction effectively reduce stormy waves and apply to top cushion cap The influence of work;In the step S4, first the tower hoisting is held to described using the suspender on the assistance platform 20 On platform and installed, thus be conducive to for the pylon being mounted on the cushion cap, it then will on the assistance platform 20 The blower is lifted on the pylon and being installed, and is conducive to the assembling by the assistance platform described On pylon.
It please refers to shown in Fig. 3, the assistance platform 20 uses jacket structure, and whole spicing forming type is not only constructed in factory Convenient, operating condition is good, and processing progress can effective control, guarantee quality.Specifically, the assistance platform 20 includes conduit Frame 21, the jacket 21 are provided with first crossbar 22, second crossbar 23 and third according to this from top to bottom in the vertical direction Cross bar 24, wherein the second crossbar 23 be in design lowest stage hereinafter, so that the pile bearing capacity of the jacket 21, buoyancy, Buoyant unit weight uplift force just with it is dead-weight balanced;The third cross bar 24 is anti-settling reinforcing rod, and the jacket 21 is arranged in Lower end, and go deep into the anti-settling reinforcing rod in mud, stability when installation is advantageously ensured that by the anti-settling reinforcing rod.Separately Outside, diagonal brace is additionally provided between the jacket 21 and the first crossbar 22, the diagonal brace uses steel pipe.
In order to guarantee the stabilization of the assistance platform 20, it is separately installed at 9 node locations of the assistance platform 20 Auxiliary pile 25, and the method for installing the auxiliary pile 25 is as follows: it is equipped with casing at node 1, node 2 to node 9, each Auxiliary pile 25 is installed in described sleeve pipe, is bottomed out when wherein described sleeve pipe is installed.Specifically, first in the assistance platform 20 Four corner points casing in be inserted vertically into four auxiliary piles 25, the i.e. casing at node 1, node 3, node 7 and node 9 It is inside inserted into four auxiliary piles 25 respectively, four auxiliary piles 25 are turned to designed elevation by vibration hammer, promote the auxiliary Platform 20 is fixed in 20 casing of assistance platform to designed elevation and by four auxiliary piles 25, is then hung up and beaten remaining auxiliary It helps stake 25 and is fixed on remaining auxiliary pile 25 on the casing of the assistance platform 20, by the auxiliary for first installing four corner points Stake 25, then installs the auxiliary pile 25 at other positions, it can prevent the assistance platform 20 when above mentioning the auxiliary pile 25 with Described sleeve pipe is sprained jail, and advantageously reduces difficulty of construction, thus accelerate the progress of construction, the following detailed description of.
The method that four auxiliary piles 25 are inserted vertically into the casing of four corner points of the assistance platform 20 is as follows: logical It crosses crane ship and slings the auxiliary pile 25, the auxiliary pile is inserted into 20 casing of assistance platform, then crane ship is sling Vibration hammer makes the fixture of the vibration hammer that the fixture are caught in stake top and clamped, finally close to the top of the auxiliary pile 25 Starting vibration hammer, which successively shakes the auxiliary pile 25, is sink to designed elevation.It is flat in order to make the auxiliary pile 25 be fixed on the auxiliary In platform 20,20 platform of assistance platform is promoted to designed elevation and by four auxiliary piles 25 and is fixed on the assistance platform Method in 20 is as follows: the through-hole after the assistance platform 20 is promoted to designed elevation, on the casing of the assistance platform 20 Beam is shelved in interior insertion, so that four auxiliary piles 25 is shelved the lower section of beam positioned at described, to ensure that the position always of auxiliary pile 25 In in described sleeve pipe.
The method that remaining auxiliary pile 25 is fixed on the assistance platform 20 is as follows: on the remaining auxiliary pile 25 Aperture forms mounting hole, and it is logical on 20 inner sleeve of assistance platform to be directed at the mounting hole on the remaining auxiliary pile 25 Hole, i.e., by each auxiliary pile of through-hole alignment on the casing at node 2, node 8,6 position of node 4, node 5 and node Mounting hole on 25, then so that the remaining auxiliary pile 25 is fixed on the auxiliary across the mounting hole on corresponding beam of shelving On platform 20.Since four auxiliary piles 25 of four corner points do not need aperture, by promoting the assistance platform 20 to design Absolute altitude, by four auxiliary piles 25 be fixed on it is described shelve the lower section of beam, therefore reduce aperture time and the alignment of two holes Time so that construction is simple, effectively increases construction efficiency.It is wherein described to shelve existing height difference gap between beam and duct Place can use metal mat jail, to guarantee the stability of the auxiliary pile 25.
When the assistance platform 20 is installed, the assistance platform 20 is hung to the position for performing label in advance using crane ship Set, make the assistance platform 20 close to the starboard of station keeping ship, when on the assistance platform 20 position of center line and the positioning When the ship side outer center line of ship is overlapped, will slowly it transfer after the assistance platform 20 leveling to design altitude, to the auxiliary Platform 20 breaks off relations after stablizing, subsequently into 25 construction stage of auxiliary pile, to advantageously ensure that the stabilization of the assistance platform 20. In addition, traction cable wind rope is additionally provided in the two sides of the assistance platform 20, for preventing assistance platform 20 from occurring during installation Significantly shake.Wherein before the assistance platform 20 installation, need to position the assistance platform 20, it is specific to position Method are as follows: by two GPS instrument flow stations on the deck of the station keeping ship side of plunging into the commercial sea of the assistance platform 20 (station keeping ship lean on) Upper measuring goes out two installation sidelines of the assistance platform 20, and the straight line that two GPS centres are constituted is put down with ship side outer Row, instrument spacing are greater than steady stake platform size, measure the vertical range in described two installation sidelines and ship side outer, make station keeping ship The side of a ship is parallel with 20 side of assistance platform, in two GPS instrument centered positions, marks and ship side outer is perpendicular portrays Line measures two GPS centres to the vertical range for portraying line respectively.
In the present embodiment, the pylon includes positioned at tower, the middle tower above the tower and the position of bottom Head tower above the middle tower after the completion of the bearing platform construction of the blower foundation, utilizes suspender on the assistance platform 20 The tower is lifted on the cushion cap and installing, the middle tower and head tower are then sequentially lifted, by the middle tower It is fixed in the tower, the head tower is fixed on the middle tower.
The blower includes being located at the cabin above the pylon, the wheel hub in the cabin and positioned at the wheel Three pieces blade on hub after installing pylon, first lifts the cabin and wheel hub using suspender on the assistance platform 20 Combination, the cabin and wheel hub are fixed on the head tower, then lifted according to this to the three pieces blade again, will be described Three pieces blade is separately fixed on the wheel hub, to complete the installation of the wind-driven generator.
After the wind-driven generator is installed, then electrical system and warning system are installed, cooperate wind power generation set system Debugging, and after acceptance(check), just complete the installation of entire wind-driven generator.In addition, being provided on the assistance platform 20 big Heavy-duty hoisting equipment provides elevating capacity by the lifting equipment and guarantees working security, realizes to the wind-driven generator Lifting.
In the present embodiment, the suspender is large caterpillar.
To sum up, technical solution of the present invention has the advantage that
1. the construction method of offshore wind generating partial installation of the present invention, the wind-driven generator is located at blower base On the cushion cap of plinth, wherein the wind-driven generator includes pylon and the blower above the pylon, wherein the pylon On the cushion cap, in the step S1, pile sinking is carried out to the pile foundation of the blower foundation, so that the blower foundation be consolidated It is scheduled on sea;In the step S2, assistance platform is manufactured, and the assistance platform is mounted on by the blower foundation, make institute Assistance platform is stated close to the blower foundation, to be conducive to the wind-driven generator be carried out subsequently through the assistance platform Construction, realizes " land construction " to cushion cap top assembling, effectively reduces what stormy waves constructed to assembling It influences, significantly improves installation effectiveness;In the step S3, suspender is set on the assistance platform, and matches in the suspender Continue the cable tube to the blower foundation under conjunction, by ship facility, anti-collision structure installation and cushion cap reinforcing bar, template and concrete Structure is constructed, at this time by the assistance platform also accelerate the cable tube, by ship facility, anti-collision structure installation with And cushion cap reinforcing bar, template and concrete construction, effectively reduce influence of the stormy waves to top bearing platform construction;In the step S4, On the tower hoisting of the wind-driven generator to the cushion cap and it will first be pacified on the assistance platform using the suspender Dress, to be conducive to for the pylon being mounted on the cushion cap;Then by the wind-driven generator on the assistance platform Blower lift on the pylon and being installed, be conducive to the assembling by the assistance platform in the tower On frame.
2. the construction method of offshore wind generating partial installation of the present invention, four auxiliary piles of four corner points are not Aperture is needed, by promoting the assistance platform to designed elevation, four auxiliary piles are fixed on described shelve under beam Side, therefore reduce the time of aperture time and the alignment of two holes, so that construction is simple, effectively increases construction efficiency.
Obviously, the above embodiments are merely examples for clarifying the description, does not limit the embodiments.For For those of ordinary skill in the art, other different form variations can also be made on the basis of the above description or are become It is dynamic.There is no necessity and possibility to exhaust all the enbodiments.And obvious variation extended from this or change It moves still within the protection scope of the invention.

Claims (8)

1. a kind of construction method of offshore wind generating partial installation, the wind-driven generator are located at the cushion cap of blower foundation On, wherein the wind-driven generator includes pylon and the blower above the pylon, which is characterized in that including walking as follows It is rapid:
Step S1: pile sinking is carried out to the pile foundation of the blower foundation;
Step S2: manufacture assistance platform, and the assistance platform is mounted on by the blower foundation, lean on the assistance platform The nearly blower foundation, wherein the assistance platform uses jacket structure, whole spicing forming type, the node of the assistance platform Auxiliary pile, and the method for installing the auxiliary pile are installed are as follows: first in the set of four corner points of the assistance platform at position It is inserted vertically into four auxiliary piles in pipe, four auxiliary piles are turned to designed elevation by vibration hammer, it is flat to promote the auxiliary Platform is fixed in the assistance platform casing to designed elevation and by four auxiliary piles, is then hung up and beaten remaining auxiliary pile and is incited somebody to action Remaining auxiliary pile is fixed in described sleeve pipe;
Step S3: being arranged suspender on the assistance platform, and continues the electricity to the blower foundation under suspender cooperation Cable pipe is constructed by ship facility, anti-collision structure installation and cushion cap reinforcing bar, template and concrete structure;
Step S4: on the tower hoisting to the cushion cap and will first be pacified on the assistance platform using the suspender Then dress again lifts the blower on the pylon and installing.
2. the construction method of offshore wind generating partial installation according to claim 1, it is characterised in that: the auxiliary is flat When platform is installed, anti-settling reinforcing rod is set in the lower end of the assistance platform, and go deep into the anti-settling reinforcing rod in mud.
3. the construction method of offshore wind generating partial installation according to claim 1, it is characterised in that: in the auxiliary The method of four auxiliary piles is inserted vertically into the casing of four corner points of platform are as follows: auxiliary pile is sling by crane ship, by institute It states auxiliary pile to be sequentially inserted into the assistance platform casing, then crane ship slings vibration hammer, leans on the fixture of the vibration hammer The top of the nearly auxiliary pile, is caught in stake top for the fixture and clamps, finally start the vibration hammer by the auxiliary pile according to Secondary vibration is sink to designed elevation.
4. the construction method of offshore wind generating partial installation according to claim 1, it is characterised in that: promoted described auxiliary Platform is helped to be fixed on the method in the assistance platform casing to designed elevation and by four auxiliary piles are as follows: the auxiliary is flat After platform is promoted to designed elevation, beam is shelved in insertion in the through-hole on the casing of the assistance platform, makes four auxiliary piles Positioned at the lower section for shelving beam.
5. the construction method of offshore wind generating partial installation according to claim 1, it is characterised in that: assist residue Stake is fixed on the method in described sleeve pipe are as follows: aperture forms mounting hole on the remaining auxiliary pile, and keeps the residue auxiliary It helps the mounting hole in stake to be directed at the through-hole on the assistance platform casing, then corresponding beam of shelving is made across the mounting hole The remaining auxiliary pile is fixed on the assistance platform.
6. the construction method of offshore wind generating partial installation according to claim 1, it is characterised in that: the auxiliary is flat When platform is installed, the assistance platform is hung to the position for performing label in advance using crane ship, makes the assistance platform close to fixed The starboard of position ship will when the position of center line on the assistance platform is overlapped with the ship side outer center line of the station keeping ship It slowly transfers after the assistance platform leveling to design altitude, breaks off relations after the assistance platform is stablized, subsequently into auxiliary pile Construction stage.
7. the construction method of offshore wind generating partial installation according to claim 1, it is characterised in that: the pylon packet Include tower, the middle tower above the tower and the head tower above the middle tower positioned at bottom, the blower After the completion of the bearing platform construction on basis, the tower is lifted on the cushion cap and installing, so on the assistance platform The middle tower and head tower are sequentially lifted afterwards.
8. the construction method of offshore wind generating partial installation according to claim 1, it is characterised in that: the blower packet Include cabin, the wheel hub in the cabin and the three pieces blade on the wheel hub being located above the pylon, peace After installing pylon, the combination of the cabin and wheel hub is first lifted using suspender on the assistance platform, then again to described three Piece blade is successively lifted.
CN201710618852.0A 2017-07-26 2017-07-26 The construction method of offshore wind generating partial installation Active CN107218179B (en)

Priority Applications (2)

Application Number Priority Date Filing Date Title
CN201710618852.0A CN107218179B (en) 2017-07-26 2017-07-26 The construction method of offshore wind generating partial installation
CN201711116097.2A CN107795438B (en) 2017-07-26 2017-07-26 A kind of construction method of assistance platform

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710618852.0A CN107218179B (en) 2017-07-26 2017-07-26 The construction method of offshore wind generating partial installation

Related Child Applications (1)

Application Number Title Priority Date Filing Date
CN201711116097.2A Division CN107795438B (en) 2017-07-26 2017-07-26 A kind of construction method of assistance platform

Publications (2)

Publication Number Publication Date
CN107218179A CN107218179A (en) 2017-09-29
CN107218179B true CN107218179B (en) 2019-07-16

Family

ID=59953914

Family Applications (2)

Application Number Title Priority Date Filing Date
CN201711116097.2A Active CN107795438B (en) 2017-07-26 2017-07-26 A kind of construction method of assistance platform
CN201710618852.0A Active CN107218179B (en) 2017-07-26 2017-07-26 The construction method of offshore wind generating partial installation

Family Applications Before (1)

Application Number Title Priority Date Filing Date
CN201711116097.2A Active CN107795438B (en) 2017-07-26 2017-07-26 A kind of construction method of assistance platform

Country Status (1)

Country Link
CN (2) CN107795438B (en)

Families Citing this family (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109838351B (en) * 2017-11-24 2020-09-11 黄灿光 Floating type automatic wind-to-water wind power generation equipment with multiple wind power generators
CN109737013A (en) * 2019-01-25 2019-05-10 中国能源建设集团广东省电力设计研究院有限公司 Marine frame structure and assemble method
CN112921937A (en) * 2021-01-27 2021-06-08 中交第三航务工程局有限公司宁波分公司 Self-stabilizing offshore operation platform

Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2008084971A1 (en) * 2007-01-11 2008-07-17 Dong Taek Suh Method of establishing sea wind power generator using the leading rail
CN102535510A (en) * 2012-02-27 2012-07-04 广东明阳风电产业集团有限公司 Basic mounting method of offshore fan jacket and integrated jacket device

Family Cites Families (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2000073349A (en) * 1998-09-02 2000-03-07 Nippon Steel Corp Jacket with rotary press-in steel pipe pile and its execution method
US7530780B2 (en) * 2006-05-22 2009-05-12 General Electric Company Method and apparatus for wind power foundation
CN103850885B (en) * 2012-11-28 2016-08-24 财团法人船舶暨海洋产业研发中心 The offshore installation method of wind-driven generator and connecting structure thereof
CN105672317B (en) * 2014-11-21 2017-11-14 上海勘测设计研究院有限公司 Underwater jacket piling interpolation type positioner
CN106677995B (en) * 2016-07-12 2018-12-18 中交第三航务工程局有限公司 The construction method of off-lying sea blower partial installation
CN206034408U (en) * 2016-07-29 2017-03-22 中国电建集团华东勘测设计研究院有限公司 A back pitching pile formula jacket structure for marine booster station

Patent Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2008084971A1 (en) * 2007-01-11 2008-07-17 Dong Taek Suh Method of establishing sea wind power generator using the leading rail
CN102535510A (en) * 2012-02-27 2012-07-04 广东明阳风电产业集团有限公司 Basic mounting method of offshore fan jacket and integrated jacket device

Also Published As

Publication number Publication date
CN107218179A (en) 2017-09-29
CN107795438B (en) 2019-06-14
CN107795438A (en) 2018-03-13

Similar Documents

Publication Publication Date Title
CN103015445B (en) Neritic zone wind energy turbine set is without changeover portion single-pile foundation construction and Fan Equipment mounting process
CN101565091B (en) Installation equipment of above-water wind generator and construction method thereof
CN107218179B (en) The construction method of offshore wind generating partial installation
CN103939299B (en) The split type mounting process of a kind of offshore wind turbine
CN106828812B (en) Semi-submersible type deep-sea wind-powered electricity generation mounting platform and its wind power generating set integral installation method
KR20100055053A (en) (method of establishing sea wind power generator and apparatus thereof
CN102277878A (en) Floating foundation and construction method thereof
CN105201010B (en) Offshore wind turbine assembled taper pile basis
CN102817341B (en) Construction method for segmented installation of offshore anemometer tower and combination of high-altitude manufactured parts for assembly
CN103010413A (en) Working method for hoisting draught fan by barge
CN203128000U (en) Hoisting device for direct-driven wind power generator set
CN108946509A (en) A kind of large-scale wind driven generator is from rising tower crane construction method
CN202322091U (en) Lifting equipment
CN110158566A (en) Offshore wind power platform
CN201615033U (en) Flexible installing system of off-shore wind turbine generator system
CN103215956B (en) Multi-pile pile gripper and multi-pile guide pipe frame foundation construction method for shallow wind power farm
CN110173397A (en) A kind of installation method partly latent for refuting crawler crane sea large-scale wind driven generator
CN103243732A (en) Installing method of marine anemometer tower base structure
CN103807114A (en) Offshore wind power generation set horizontally-assembling and integrally-overturning-and-erecting installation system and method
CN103807115A (en) Offshore wind power generation set horizontally-assembling and integrally-overturning-and-erecting device and construction method thereof
CN106638530A (en) Process for lifting offshore booster station jacket in shallow water
KR101262089B1 (en) Sea establishment method of weather tower and wind turbine generator
CN205046567U (en) Marine wind turbine foundation structure
CN216241100U (en) But reuse's offshore anemometer tower system of rising certainly
CN207261176U (en) A kind of offshore wind power platform pitching pile fixing device

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant
TR01 Transfer of patent right

Effective date of registration: 20230913

Address after: 200032 No. 139, Xuhui District, Shanghai, Pingjiang Road

Patentee after: CCCC THIRD HARBOR ENGINEERING Co.,Ltd.

Patentee after: NINGBO BRANCH, CCCC NO.3 HARBOR ENGINEERING CO.,LTD.

Address before: No.462, Yanjiang East Road, Zhenhai District, Ningbo, Zhejiang 315000

Patentee before: NINGBO BRANCH, CCCC NO.3 HARBOR ENGINEERING CO.,LTD.

TR01 Transfer of patent right