CN107217670A - 一种提高灌注桩沉渣质量的施工控制方法 - Google Patents
一种提高灌注桩沉渣质量的施工控制方法 Download PDFInfo
- Publication number
- CN107217670A CN107217670A CN201710324304.7A CN201710324304A CN107217670A CN 107217670 A CN107217670 A CN 107217670A CN 201710324304 A CN201710324304 A CN 201710324304A CN 107217670 A CN107217670 A CN 107217670A
- Authority
- CN
- China
- Prior art keywords
- sediment
- disk
- bored concrete
- concrete pile
- improving
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D13/00—Accessories for placing or removing piles or bulkheads, e.g. noise attenuating chambers
- E02D13/08—Removing obstacles
Landscapes
- Engineering & Computer Science (AREA)
- Life Sciences & Earth Sciences (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Mining & Mineral Resources (AREA)
- Paleontology (AREA)
- Civil Engineering (AREA)
- General Engineering & Computer Science (AREA)
- Structural Engineering (AREA)
- Piles And Underground Anchors (AREA)
Abstract
本发明属于建筑施工领域,为了解决传统清渣方式存在的清渣效率低、清渣不彻底的问题,本发明提供了一种提高灌注桩沉渣质量的施工控制方法,采用化学沉淀和沉渣盘配合施工的方式控制沉渣质量,灌注桩钻孔施工后首先下放沉渣盘,然后利用聚丙烯酰胺对桩孔内泥浆进行脱水分离,对分离后的水进行抽排循环使用,分离后的沉渣随沉渣盘上拉一次性清除。沉渣盘的加工应用,提升了传统的旋挖钻清孔工效,且确保沉渣厚度满足质量要求。根据桩基检测结果分析对比,简易检测盘能快速检测沉渣厚度并数据准确。
Description
技术领域
本发明属于建筑施工领域,具体涉及一种提高灌注桩沉渣质量的施工控制方法。
背景技术
灌注桩在钻孔施工后需要下放钢筋笼,最后灌注混凝土成型,因此,灌注桩的钻孔深度、直径、垂直度等会直接影响最终质量,但钻孔和清孔过程中会因沉淀或塌孔留下较大颗粒的沉渣,此类沉渣不容易被循环泥浆带走,需要进行清渣处理,但由于孔内泥浆、粗渣混合,利用传统的捞砂钻头清孔器对砂岩地层段进行清孔处理时,往往需要反复循环抽排泥浆-清理沉渣-测量沉渣厚度才能最终完成对孔内沉渣的处理,循环清渣次数多,施工效率低,且多次清孔后仍然存在清渣不彻底的现象。
发明内容
本发明为了解决传统清渣方式存在的清渣效率低、清渣不彻底的问题,进而提供了一种提高灌注桩沉渣质量的施工控制方法。
本发明采用如下技术方案:
一种提高灌注桩沉渣质量的施工控制方法,采用化学沉淀和沉渣盘配合施工的方式控制沉渣质量,灌注桩钻孔施工后首先下放沉渣盘,然后利用聚丙烯酰胺对桩孔内泥浆进行脱水分离,对分离后的水进行抽排循环使用,分离后的沉渣随沉渣盘上拉一次性清除。
所述聚丙烯酰胺的浓度不小于0.1%,加入聚丙烯酰胺后的沉淀分离时间不少于半小时(一般为1-2小时),保证能快速且充分脱水分离。
灌注桩钻孔施工时采用检测盘测量沉渣厚度,钻进成孔后测量的孔深与检测盘测量孔深的高程差为沉渣厚度。
所述沉渣盘包括盘体钢护筒,钢护筒顶端敞口、底端封闭,钢护筒的顶端穿拉有若干钢绞绳,钢护筒底板上安装有若干水压平衡阀,钢护筒内外有压差时水压平衡阀常开,钢护筒内外水压平衡时水压平衡阀闭合。
所述钢护筒直径至少比灌注桩直径小20cm。
所述检测盘的盘体上开有若干泄水孔,利用泄水孔可减小水阻力,快速下放检测盘。
本发明具有如下有益效果:
1、本发明利用聚丙烯酰胺实现化学沉淀,然后利用沉渣盘将沉淀后的沉渣一次上提清除,只需要一次即可完成清孔作业,作业时间为三小时左右,相比传统的多次清孔方式,一个桩孔至少节省半天;
2、化学沉淀后的沉渣完全置于沉渣盘内,可全部上提外排,,不会出现反渣的现象,清渣更彻底;
3、沉渣厚度采用检测盘替代传统的重锤测量,能快速检测沉渣厚度且测量数据更准确。
附图说明
图1为沉渣盘的结构示意图;
图2为检测盘的结构示意图;
图中:1-钢绞绳、2-钢护筒、3-稳固杆、4-水压平衡阀、5-盘体、6-泄水孔、7-拉绳。
具体实施方式
结合附图,对本发明的具体实施方式作进一步说明:
本发明采用 “化学沉淀+自行加工沉渣盘”的方法进行沉渣控制,该方法沉渣分离速度快,加速清渣;清渣彻底,且可减少循环清渣次数,有利于提高工效和确保质量。
灌注桩钻孔施工后首先下放沉渣盘,然后利用聚丙烯酰胺对桩孔内泥浆进行脱水分离,对分离后的水进行抽排循环使用,分离后的沉渣随沉渣盘上拉一次性清除。
(1)采用化学剂迅速分离沉渣中泥浆
添加0.1%-0.5%参量的聚丙烯酰胺对沉渣泥浆进行脱水分离,加快了沉渣清理速度。聚丙烯酰胺(PAM)是一种较好的凝聚剂,具有良好的絮凝性,可以降低液体之间的摩擦阻力,可使混合泥浆中的粗颗粒快速沉淀。考虑聚丙烯酰胺的化学特性,当其浓度过大时,反而会造成泥浆液浑浊,无法分离脱水,因此,聚丙烯酰胺的浓度优选值为0.1%-0.5%。
(2)自行加工沉渣盘用于清渣
选用比设计桩径小约20㎝的废旧钢护筒加工成沉渣盘,钢护筒顶端敞口、底端封闭,钢护筒的顶端穿拉有若干钢绞绳,方便下放或上拉,为减少沉渣盘下放的阻力,钢护筒底板上安装有若干水压平衡阀,钢护筒内外有压差时水压平衡阀常开,钢护筒内外水压平衡时水压平衡阀闭合。平衡阀的原理类似朝钢护筒内开的合页,刚下放沉渣盘时,钢护筒内的水压明显小于筒外的水压,则桩孔内的泥浆液自流进入钢护筒,当钢护筒内的泥浆液满后,钢护筒内外无冥想压差,该合页在内外平衡力作用下始终闭合,进而使混合泥浆液在钢护筒内沉淀分离。
(3)自行加工简易的沉渣厚度检测设备
采用5mm厚钢板加工一个φ50㎝的检测盘,为减少下放时的水阻力,在检测盘上四周对称切割4个φ3㎝泄水孔,检测盘下放后测量高程,改盘的表面积大,不会明显下陷于软质的沉渣内,可避免测量误差,钻进成孔后测量的孔深-检测盘测量孔深,两者高程差即为沉渣厚度。施工时,可以下放重2kg采用钢皮尺连接的尖锐钢筋头(即检测锤),并测量高程,将该测量高程与检测盘测得高程进行比较可知,由于检测锤的尖头易插入沉渣中,因此检测锤的测量值大于检测盘的测量值,导致利用检测锤测得的沉渣厚度小于理论值。
沉渣盘的加工应用,提升了传统的旋挖钻清孔工效,且确保沉渣厚度满足质量要求。根据桩基检测结果分析对比,简易检测盘能快速检测沉渣厚度并数据准确。
Claims (6)
1.一种提高灌注桩沉渣质量的施工控制方法,其特征在于:采用化学沉淀和沉渣盘配合施工的方式控制沉渣质量,灌注桩钻孔施工后首先下放沉渣盘,然后利用聚丙烯酰胺对桩孔内泥浆进行脱水分离,对分离后的水进行抽排循环使用,分离后的沉渣随沉渣盘上拉一次性清除。
2.根据权利要求1所述的提高灌注桩沉渣质量的施工控制方法,其特征在于:所述聚丙烯酰胺的浓度不小于0.1%,加入聚丙烯酰胺后的沉淀分离时间不少于半小时。
3.根据权利要求2所述的提高灌注桩沉渣质量的施工控制方法,其特征在于:灌注桩钻孔施工时采用检测盘测量沉渣厚度,钻进成孔后测量的孔深与检测盘测量孔深的高程差为沉渣厚度。
4.根据权利要求3所述的提高灌注桩沉渣质量的施工控制方法,其特征在于:所述沉渣盘包括盘体钢护筒(2),钢护筒(2)顶端敞口、底端封闭,钢护筒(2)的顶端穿拉有若干钢绞绳(1),钢护筒(2)底板上安装有若干水压平衡阀(4),钢护筒(2)内外有压差时水压平衡阀(4)常开,钢护筒(2)内外水压平衡时水压平衡阀(4)闭合。
5.根据权利要求4所述的提高灌注桩沉渣质量的施工控制方法,其特征在于:所述钢护筒(2)直径至少比灌注桩直径小20cm。
6.根据权利要求5所述的提高灌注桩沉渣质量的施工控制方法,其特征在于:所述检测盘的盘体(5)上开有若干泄水孔(6)。
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201710324304.7A CN107217670A (zh) | 2017-05-10 | 2017-05-10 | 一种提高灌注桩沉渣质量的施工控制方法 |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201710324304.7A CN107217670A (zh) | 2017-05-10 | 2017-05-10 | 一种提高灌注桩沉渣质量的施工控制方法 |
Publications (1)
Publication Number | Publication Date |
---|---|
CN107217670A true CN107217670A (zh) | 2017-09-29 |
Family
ID=59944058
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201710324304.7A Pending CN107217670A (zh) | 2017-05-10 | 2017-05-10 | 一种提高灌注桩沉渣质量的施工控制方法 |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN107217670A (zh) |
Cited By (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN108517867A (zh) * | 2018-04-26 | 2018-09-11 | 中冶建工集团有限公司 | 一种深孔桩孔底清渣方法 |
CN108517868A (zh) * | 2018-04-26 | 2018-09-11 | 中冶建工集团有限公司 | 深孔桩清渣桶 |
CN108643852A (zh) * | 2018-04-26 | 2018-10-12 | 中冶建工集团有限公司 | 一种深孔桩清渣系统 |
CN111733801A (zh) * | 2020-06-28 | 2020-10-02 | 中冶地集团西北岩土工程有限公司 | 一种松软地质中旋挖孔灌注桩的施工工艺 |
Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH08120674A (ja) * | 1994-10-24 | 1996-05-14 | Mitsubishi Constr Co Ltd | 場所打ちコンクリート杭用スライム処置バケット及びこのスライム処置バケットを利用するリフトアップスライム処置方法 |
CN102425389A (zh) * | 2011-09-19 | 2012-04-25 | 中铁十二局集团第七工程有限公司 | 地下暗河中的灌注桩孔孔底清渣方法及掏渣桶和吹送清渣系统 |
CN204571894U (zh) * | 2014-01-24 | 2015-08-19 | 中铁二十四局集团有限公司 | 孔桩沉渣桶 |
CN205314140U (zh) * | 2015-12-01 | 2016-06-15 | 中国一冶集团有限公司 | 灌注桩孔底沉渣厚度检测装置 |
-
2017
- 2017-05-10 CN CN201710324304.7A patent/CN107217670A/zh active Pending
Patent Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH08120674A (ja) * | 1994-10-24 | 1996-05-14 | Mitsubishi Constr Co Ltd | 場所打ちコンクリート杭用スライム処置バケット及びこのスライム処置バケットを利用するリフトアップスライム処置方法 |
CN102425389A (zh) * | 2011-09-19 | 2012-04-25 | 中铁十二局集团第七工程有限公司 | 地下暗河中的灌注桩孔孔底清渣方法及掏渣桶和吹送清渣系统 |
CN204571894U (zh) * | 2014-01-24 | 2015-08-19 | 中铁二十四局集团有限公司 | 孔桩沉渣桶 |
CN205314140U (zh) * | 2015-12-01 | 2016-06-15 | 中国一冶集团有限公司 | 灌注桩孔底沉渣厚度检测装置 |
Non-Patent Citations (1)
Title |
---|
左名麒等: "《桩基础工程 设计 施工 检测》", 31 May 1996 * |
Cited By (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN108517867A (zh) * | 2018-04-26 | 2018-09-11 | 中冶建工集团有限公司 | 一种深孔桩孔底清渣方法 |
CN108517868A (zh) * | 2018-04-26 | 2018-09-11 | 中冶建工集团有限公司 | 深孔桩清渣桶 |
CN108643852A (zh) * | 2018-04-26 | 2018-10-12 | 中冶建工集团有限公司 | 一种深孔桩清渣系统 |
CN108517867B (zh) * | 2018-04-26 | 2019-06-18 | 中冶建工集团有限公司 | 一种深孔桩孔底清渣方法 |
CN108517868B (zh) * | 2018-04-26 | 2019-06-18 | 中冶建工集团有限公司 | 深孔桩清渣桶 |
CN111733801A (zh) * | 2020-06-28 | 2020-10-02 | 中冶地集团西北岩土工程有限公司 | 一种松软地质中旋挖孔灌注桩的施工工艺 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN107217670A (zh) | 一种提高灌注桩沉渣质量的施工控制方法 | |
CN102704873B (zh) | 自带泥浆池及泥浆分离装置钻/冲孔灌注桩的施工设备 | |
CN105804059B (zh) | 钻孔灌注桩成孔装置及方法 | |
CN207260136U (zh) | 超深灌注桩清孔系统 | |
Wurpts et al. | 15 years experience with fluid mud: Definition of the nautical bottom with rheological parameters | |
CN102787815B (zh) | 超深钻孔灌注桩正、反循环相结合施工工艺 | |
CN108166485A (zh) | 旋挖式钻孔灌注桩施工方法 | |
CN105937377A (zh) | 一种气举反循环清孔方法 | |
CN107687171A (zh) | 地下连续墙双泵后注浆装置及施工方法 | |
CN106638579A (zh) | 一种珊瑚砂地基膨胀水泥砂浆注浆桩的施工方法 | |
CN204959757U (zh) | 一种护筒泥浆循环装置 | |
CN102409978B (zh) | 复杂地层灌注桩施工采用多级合金超前牙轮钻头回旋钻进成孔工法 | |
CN212656251U (zh) | 一种水中桩基础冲击钻施工用正循环泥浆清孔系统 | |
CN105257248A (zh) | 一种低渗透油田污水回注井负压返吐解堵方法 | |
CN202249851U (zh) | 灌注桩反循环成孔设备 | |
CN206438508U (zh) | 分体式快速清孔装置 | |
CN110485925A (zh) | 一种适用于狭窄空间内高强度斜岩面的钻孔装置及其方法 | |
CN107503349A (zh) | 旋挖孔底沉碴和泥浆清理方法 | |
CN113931572B (zh) | 复合地层大直径桩基的施工方法及钻头系统 | |
CN205605155U (zh) | 一种桩基清孔冲击钻捞渣桶 | |
CN204532167U (zh) | 一种桩孔冲洗抽砂淸孔装置 | |
CN204456094U (zh) | 钻孔灌注桩环保护筒 | |
CN209324259U (zh) | 一种用于长螺旋挤密成孔灌注桩的钻具 | |
CN208309574U (zh) | 一种钻孔灌注桩多级钻杆 | |
CN202969388U (zh) | 桩位孔底沉渣排除系统 |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
RJ01 | Rejection of invention patent application after publication | ||
RJ01 | Rejection of invention patent application after publication |
Application publication date: 20170929 |