CN107194831A - BIM and application process of the Quick Response Code in construction management - Google Patents
BIM and application process of the Quick Response Code in construction management Download PDFInfo
- Publication number
- CN107194831A CN107194831A CN201710405631.5A CN201710405631A CN107194831A CN 107194831 A CN107194831 A CN 107194831A CN 201710405631 A CN201710405631 A CN 201710405631A CN 107194831 A CN107194831 A CN 107194831A
- Authority
- CN
- China
- Prior art keywords
- quick response
- code
- response code
- bim
- application process
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
- 238000000034 method Methods 0.000 title claims abstract description 19
- 238000009430 construction management Methods 0.000 title claims abstract description 16
- 238000005516 engineering process Methods 0.000 claims abstract description 13
- 239000000178 monomer Substances 0.000 claims description 3
- 238000007639 printing Methods 0.000 claims description 3
- 238000004891 communication Methods 0.000 abstract description 11
- 238000010276 construction Methods 0.000 abstract description 3
- 238000012545 processing Methods 0.000 description 2
- 238000004088 simulation Methods 0.000 description 2
- 230000009286 beneficial effect Effects 0.000 description 1
- 229910002056 binary alloy Inorganic materials 0.000 description 1
- 230000007812 deficiency Effects 0.000 description 1
- 230000014759 maintenance of location Effects 0.000 description 1
- 238000005457 optimization Methods 0.000 description 1
- 238000011160 research Methods 0.000 description 1
- 238000012800 visualization Methods 0.000 description 1
Classifications
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06Q—INFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
- G06Q50/00—Information and communication technology [ICT] specially adapted for implementation of business processes of specific business sectors, e.g. utilities or tourism
- G06Q50/08—Construction
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06K—GRAPHICAL DATA READING; PRESENTATION OF DATA; RECORD CARRIERS; HANDLING RECORD CARRIERS
- G06K19/00—Record carriers for use with machines and with at least a part designed to carry digital markings
- G06K19/06—Record carriers for use with machines and with at least a part designed to carry digital markings characterised by the kind of the digital marking, e.g. shape, nature, code
- G06K19/06009—Record carriers for use with machines and with at least a part designed to carry digital markings characterised by the kind of the digital marking, e.g. shape, nature, code with optically detectable marking
- G06K19/06037—Record carriers for use with machines and with at least a part designed to carry digital markings characterised by the kind of the digital marking, e.g. shape, nature, code with optically detectable marking multi-dimensional coding
Landscapes
- Physics & Mathematics (AREA)
- General Physics & Mathematics (AREA)
- Engineering & Computer Science (AREA)
- Theoretical Computer Science (AREA)
- Business, Economics & Management (AREA)
- Health & Medical Sciences (AREA)
- Economics (AREA)
- General Health & Medical Sciences (AREA)
- Human Resources & Organizations (AREA)
- Marketing (AREA)
- Primary Health Care (AREA)
- Strategic Management (AREA)
- Tourism & Hospitality (AREA)
- General Business, Economics & Management (AREA)
- Management, Administration, Business Operations System, And Electronic Commerce (AREA)
- Stored Programmes (AREA)
- Mobile Radio Communication Systems (AREA)
Abstract
The invention discloses a kind of BIM and application process of the Quick Response Code in construction management, comprise the following steps:A, clearly manage object;B, code system living are made;C, BIM model link Quick Response Code;D, scene patch code;E, mobile terminal are used;F, problem joint examination.It is of the invention to utilize BIM+ planar bar code technologies well, realize the information sharing in project construction process, cooperate, significantly there is provided communication efficiency, improve the instantaneity and intuitive of communication.
Description
Technical field
The present invention relates to architectural engineering information communication technical field, specially a kind of BIM is with Quick Response Code in construction management
Application process.
Background technology
BIM, BIM(Building Information Modeling)Or architecture information management
(Building Information Management)Be based on every relevant information data of construction-engineering project,
Set up the BUILDINGS MODELS of three-dimensional, the real information having by digital information analogue simulation building.[1]It has letter
Cease completeness, information relevance, consistency on messaging, visualization, harmony, simulation, optimization property and the big spy of figure eight can be gone out
Point.
Two-dimensional bar code/Quick Response Code(2-dimensional bar code)It is by a set pattern with certain specific geometric figure
Rule is in plane(On two-dimensional directional)The chequered with black and white graphic recording data symbol information of distribution;On coding dexterously
It is corresponding with binary system several using several using the concept of " 0 ", " 1 " bit stream for constituting computer-internal logical foundations
What body represents word numerical information, by image input device or photoelectric scanning device automatically identifying and reading to realize that information is automatic
Processing:It has some general character of barcode technology:Every kind of code system has its specific character set;Each character occupies certain width
Degree;With certain verifying function etc..Also there is the information automatic identification function to not going together and processing figure rotation to become simultaneously
Change point.
In project sites, the situation for needing multidisciplinary collaboration to link up can be usually run into, and is limited to field condition, it is right
The problem found in scene, it is multidisciplinary while the chance linked up of showing up is few.Traditional communication way is to adopt
Linked up with the modes such as phone contact, the QQ groups of message and other departments, instantaneity, intuitive and trackability are all big to give a discount
Button.
Therefore, how BIM technology to be combined with planar bar code technology, to aid in the communication management at scene, being one is worth
The problem of research.
The content of the invention
In order to overcome above-mentioned deficiency of the prior art, the invention provides one kind by BIM and Quick Response Code in construction management
In simultaneously application process, significantly there is provided communication efficiency, improve the instantaneity and intuitive of communication.
The object of the present invention is achieved like this:
BIM and application process of the Quick Response Code in construction management, comprise the following steps:A, clearly manage object;B, code system living are made;
C, BIM model link Quick Response Code;D, scene patch code;E, mobile terminal are used;F, problem joint examination.
Described clearly management object is the discussion by all departments' early stage, determines that plan takes " BIM+ bis- in BIM models
The object of dimension code " information management;Then object's position is marked in BIM models using Autodesk Navisworks softwares;
Described object is monomer, floor, room, some component or equipment, depending on the demand of project management;
Described work code system is made to be by network two-dimension code generator, generation one " code living ";
So-called code living, is that after Quick Response Code is generated and is determined, a kind of Quick Response Code that content is modified is connected to this yard;
Described BIM models link Quick Response Code refers to the understanding by the principle to Quick Response Code, it is found that each Quick Response Code is actual
It is the link of a website form;
Described scene patch code refers to the two-dimentional code position in reference model, and two-dimension code image printing is pasted into live corresponding positions
Put;
Described mobile terminal is live to a certain location point barcode scanning using referring to, checks a series of procedural informations of the object;
Described the problem of, makes a joint checkup, and refers in the engineering in project, technology, quality regular meeting, is marked with before being opened using computer end
The model file of Quick Response Code location point, clickthrough can browse to the work progress information record of relevant position, including progress,
Quality, technology contents, meanwhile, during produce the problem of and counte-rplan it is also very clear.
Positive beneficial effect:It is of the invention to utilize BIM+ planar bar code technologies well, realize the information in project construction process
Shared, collaborative work, significantly there is provided communication efficiency, improves the instantaneity and intuitive of communication.
Embodiment
The present invention is described further below:
BIM and application process of the Quick Response Code in construction management, comprise the following steps:A, clearly manage object;B, code system living are made;
C, BIM model link Quick Response Code;D, scene patch code;E, mobile terminal are used;F, problem joint examination.
Described clearly management object is the discussion by all departments' early stage, determines that plan takes " BIM+ bis- in BIM models
The object of dimension code " information management;Then object's position is marked in BIM models using Autodesk Navisworks softwares;
Described object is monomer, floor, room, some component or equipment, depending on the demand of project management;
Described work code system is made to be by network two-dimension code generator, generation one " code living ";
So-called code living, is that after Quick Response Code is generated and is determined, a kind of Quick Response Code that content is modified is connected to this yard.It
It is to meet the real-time retention to work progress information so the such Quick Response Code of selection.
Described BIM models link Quick Response Code refers to the understanding by the principle to Quick Response Code, it is found that each Quick Response Code is real
Border is all the link of a website form;(Example:http://biz.cli.im/Rec/S57hJZ#!/ ).Therefore, pass through
The linking functions of Autodesk Navisworks softwares, can be by " website links " corresponding to the Quick Response Code of generation, correspondingly
It is added in the location point marked in prior model.
Described scene patch code refers to the two-dimentional code position in reference model, and two-dimension code image printing is pasted into live phase
Answer position;
Described mobile terminal is live to a certain location point barcode scanning using referring to, checks a series of procedural informations of the object;
Described the problem of, makes a joint checkup, and refers in the engineering in project, technology, quality regular meeting, is marked with before being opened using computer end
The model file of Quick Response Code location point, clickthrough can browse to the work progress information record of relevant position, including progress,
Quality, technology contents, meanwhile, during produce the problem of and counte-rplan it is also very clear.
It is of the invention to utilize BIM+ planar bar code technologies well, realize the information sharing in project construction process, cooperate,
Communication efficiency is provided significantly, improves the instantaneity and intuitive of communication.
Moreover, it will be appreciated that this narrating mode of specification is only that for clarity, those skilled in the art should
Using specification as an entirety, the technical solutions in the various embodiments may also be suitably combined, forms those skilled in the art
It may be appreciated other embodiment.
Claims (9)
1.BIM and application process of the Quick Response Code in construction management, it is characterised in that:Comprise the following steps:A, clearly management pair
As;B, code system living are made;C, BIM model link Quick Response Code;D, scene patch code;E, mobile terminal are used;F, problem joint examination.
2. BIM according to claim 1 and application process of the Quick Response Code in construction management, it is characterised in that:Described
Clearly management object is the discussion by all departments' early stage, determines that plan takes " BIM+ Quick Response Codes " information management in BIM models
Object;Then object's position is marked in BIM models using Autodesk Navisworks softwares.
3. BIM according to claim 2 and application process of the Quick Response Code in construction management, it is characterised in that:Described
Object is monomer, floor, room, some component or equipment, depending on the demand of project management.
4. BIM according to claim 1 and application process of the Quick Response Code in construction management, it is characterised in that:Described
Code system living is made to be by network two-dimension code generator, generation one " code living ".
5. BIM according to claim 1 and application process of the Quick Response Code in construction management, it is characterised in that:So-called work
Code, is that after Quick Response Code is generated and is determined, a kind of Quick Response Code that content is modified is connected to this yard.
6. BIM according to claim 1 and application process of the Quick Response Code in construction management, it is characterised in that:Described
BIM models link Quick Response Code refers to the understanding by the principle to Quick Response Code, it is found that each Quick Response Code reality is a network address
The link of form.
7. BIM according to claim 1 and application process of the Quick Response Code in construction management, it is characterised in that:Described
Scene patch code refers to the two-dimentional code position in reference model, and two-dimension code image printing is pasted into live relevant position.
8. BIM according to claim 1 and application process of the Quick Response Code in construction management, it is characterised in that:Described
Mobile terminal is live to a certain location point barcode scanning using referring to, checks a series of procedural informations of the object.
9. BIM according to claim 1 and application process of the Quick Response Code in construction management, it is characterised in that:Described
Problem is made a joint checkup, and refers in the engineering in project, technology, quality regular meeting, two-dimentional code position is marked with before being opened using computer end
The model file of point, clickthrough can browse to the work progress information record of relevant position, including progress, quality, technology
Content, meanwhile, during produce the problem of and counte-rplan it is also very clear.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201710405631.5A CN107194831A (en) | 2017-06-01 | 2017-06-01 | BIM and application process of the Quick Response Code in construction management |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201710405631.5A CN107194831A (en) | 2017-06-01 | 2017-06-01 | BIM and application process of the Quick Response Code in construction management |
Publications (1)
Publication Number | Publication Date |
---|---|
CN107194831A true CN107194831A (en) | 2017-09-22 |
Family
ID=59876748
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201710405631.5A Pending CN107194831A (en) | 2017-06-01 | 2017-06-01 | BIM and application process of the Quick Response Code in construction management |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN107194831A (en) |
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN109360123A (en) * | 2018-10-22 | 2019-02-19 | 上海建工四建集团有限公司 | A kind of multi-specialized execution management method therefor and system based on room |
CN112990401A (en) * | 2021-04-19 | 2021-06-18 | 北京天润建设有限公司 | Display method of actual measurement data |
US11386364B1 (en) | 2019-10-24 | 2022-07-12 | Eci Software Solutions, Inc. | Construction project information and document access system |
Citations (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN104463950A (en) * | 2014-10-29 | 2015-03-25 | 中冶天工集团有限公司 | Two-dimension code information identification method of furnace kiln refractory 3D model |
CN105160466A (en) * | 2015-08-26 | 2015-12-16 | 中交第二航务工程局有限公司 | Method for applying two-dimensional code to highway engineering |
CN105654318A (en) * | 2016-01-13 | 2016-06-08 | 上海振华重工(集团)股份有限公司 | Production internet of things management method |
CN105888248A (en) * | 2016-04-27 | 2016-08-24 | 河北建筑工程学院 | Construction method of guiding informationization prefabricated member based on BIM (Building Information Modeling)) technology |
CN105933362A (en) * | 2016-07-13 | 2016-09-07 | 北京恒华伟业科技股份有限公司 | Project progress monitoring method, device, and system |
CN106777751A (en) * | 2016-12-30 | 2017-05-31 | 译筑信息科技(上海)有限公司 | Architecture information processing method and processing device |
-
2017
- 2017-06-01 CN CN201710405631.5A patent/CN107194831A/en active Pending
Patent Citations (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN104463950A (en) * | 2014-10-29 | 2015-03-25 | 中冶天工集团有限公司 | Two-dimension code information identification method of furnace kiln refractory 3D model |
CN105160466A (en) * | 2015-08-26 | 2015-12-16 | 中交第二航务工程局有限公司 | Method for applying two-dimensional code to highway engineering |
CN105654318A (en) * | 2016-01-13 | 2016-06-08 | 上海振华重工(集团)股份有限公司 | Production internet of things management method |
CN105888248A (en) * | 2016-04-27 | 2016-08-24 | 河北建筑工程学院 | Construction method of guiding informationization prefabricated member based on BIM (Building Information Modeling)) technology |
CN105933362A (en) * | 2016-07-13 | 2016-09-07 | 北京恒华伟业科技股份有限公司 | Project progress monitoring method, device, and system |
CN106777751A (en) * | 2016-12-30 | 2017-05-31 | 译筑信息科技(上海)有限公司 | Architecture information processing method and processing device |
Cited By (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN109360123A (en) * | 2018-10-22 | 2019-02-19 | 上海建工四建集团有限公司 | A kind of multi-specialized execution management method therefor and system based on room |
CN109360123B (en) * | 2018-10-22 | 2021-07-27 | 上海建工四建集团有限公司 | Multi-professional construction management method and system based on room |
US11386364B1 (en) | 2019-10-24 | 2022-07-12 | Eci Software Solutions, Inc. | Construction project information and document access system |
CN112990401A (en) * | 2021-04-19 | 2021-06-18 | 北京天润建设有限公司 | Display method of actual measurement data |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
Maher et al. | Understanding virtual design studios | |
CN101124582B (en) | Automated derivative view rendering system | |
Kan et al. | QR code based augmented reality applications | |
CN107194831A (en) | BIM and application process of the Quick Response Code in construction management | |
CN104732182B (en) | Communication method based on two-dimensional code on webpage | |
CN110930486A (en) | Rendering method and device of virtual grass in game and electronic equipment | |
Song et al. | Build a secure smart city by using blockchain and digital twin | |
CN105139056A (en) | Intelligent 2-dimensional bar code capable of being edited by user | |
CN104463950A (en) | Two-dimension code information identification method of furnace kiln refractory 3D model | |
CN102713963A (en) | Interworking system among a plurality of distributed virtual worlds using a universally unique distributed object ID and method for same | |
US20180025547A1 (en) | 2d graphical coding to create a 3d image | |
CN103795967A (en) | Multi-person multi-dimensional remote sensing consultation collaborative studying and judging method and device | |
McDonough et al. | Saving Second Life: Issues in archiving a complex, multi-user virtual world | |
Liu et al. | A study of digital exhibition visual design led by digital twin and VR technology | |
CN105429866A (en) | Private message code product and application assembly | |
CN106095975A (en) | A kind of Quick Response Code based on electronic chart generates system and two-dimensional code generation method thereof | |
Stefan et al. | Prototyping 3D virtual learning environments with X3D-based content and visualization tools | |
CN111462343B (en) | Data processing method and device, electronic equipment and storage medium | |
CN117083626A (en) | Generating and using tokens to request services and access to a product collaboration platform | |
CN106339907A (en) | Data tracing interaction method | |
CN107273961A (en) | A kind of method that color 2 D code is automatically generated according to template | |
Rostam | Education Needs to Support Architecture, Engineering, and Construction Collaboration Using Building Information Modeling | |
CN110175952A (en) | A kind of automatic generation method and device of the jade machining path based on target detection | |
Bui | Implementation of Building Information Modeling in Infrastructure Construction: Lessons from Norway and Vietnam | |
Zhou et al. | Construction method of multi-source Dougong point cloud dataset |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
WD01 | Invention patent application deemed withdrawn after publication |
Application publication date: 20170922 |
|
WD01 | Invention patent application deemed withdrawn after publication |