CN107165626A - A kind of coal-face floods prevention method with cranny development country rock top plate - Google Patents

A kind of coal-face floods prevention method with cranny development country rock top plate Download PDF

Info

Publication number
CN107165626A
CN107165626A CN201710520654.0A CN201710520654A CN107165626A CN 107165626 A CN107165626 A CN 107165626A CN 201710520654 A CN201710520654 A CN 201710520654A CN 107165626 A CN107165626 A CN 107165626A
Authority
CN
China
Prior art keywords
rock
top plate
face
coal
water
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201710520654.0A
Other languages
Chinese (zh)
Inventor
索可歆
周鹏
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Xuzhou Naili Macromolecule Technology Co Ltd
Original Assignee
Xuzhou Naili Macromolecule Technology Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Xuzhou Naili Macromolecule Technology Co Ltd filed Critical Xuzhou Naili Macromolecule Technology Co Ltd
Priority to CN201710520654.0A priority Critical patent/CN107165626A/en
Publication of CN107165626A publication Critical patent/CN107165626A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21BEARTH DRILLING, e.g. DEEP DRILLING; OBTAINING OIL, GAS, WATER, SOLUBLE OR MELTABLE MATERIALS OR A SLURRY OF MINERALS FROM WELLS
    • E21B49/00Testing the nature of borehole walls; Formation testing; Methods or apparatus for obtaining samples of soil or well fluids, specially adapted to earth drilling or wells
    • GPHYSICS
    • G01MEASURING; TESTING
    • G01VGEOPHYSICS; GRAVITATIONAL MEASUREMENTS; DETECTING MASSES OR OBJECTS; TAGS
    • G01V11/00Prospecting or detecting by methods combining techniques covered by two or more of main groups G01V1/00 - G01V9/00

Abstract

The invention discloses a kind of coal-face floods prevention method with cranny development country rock top plate, including adopt preceding detection, bore detecting checking, security evaluation, floods threat assessment, dynamic and monitor, adopt the steps such as rear water flowing fractured zone development observation and site operation.This has the coal-face floods prevention method of cranny development country rock top plate due to carrying out overall merit to working face hydrogeologic condition, Spray water way according to physical prospecting, drilling situation, by a series of detections such as rock mechanics experiment, physical prospecting, numerical simulation, height of water flowing fractured zone detections and overall merit is carried out to detection data, therefore, it is possible to effectively prevent the floods of coal-face in same exploiting field, the coal-face with cranny development country rock top plate is particularly suitable for use in.

Description

A kind of coal-face floods prevention method with cranny development country rock top plate
Technical field
It is specifically a kind of that there is crack hair suitable for underground coal mine the present invention relates to a kind of roof fracture water detection method The coal-face floods prevention method of country rock top plate is educated, belongs to Safety of Coal Mine Production technical field.
Background technology
Crevice water is underground water of the preservation in rock cranny, by the origin cause of formation in water-bearing media crack, can be divided into weathering fissures Water, diagenesis crevice water and structural fissured water.By mode of occurence, it can be diving or artesian water, be compared with pore water, crack moisture Cloth is uneven, and hydraulic connection is bad, and the permeability of medium has inhomogeneity and anisotropy.
It is frequently encountered in mine, tunnel, underground engineering in cranny development country rock, weak surrounding rock and infiltration country rock, country rock Containing obvious weak intercalated layer, siltized intercalation, all kinds of structural planes, and all kinds of composite constructions, wherein, soft surrounding rock containing mudstone foundation With strong dilatancy and it is efflorescence properties the characteristics of, especially for coal mining, as seam mining is constantly deepened, big thickness coal seam Exploitation is mined using the modernization that three machines are supporting or four machines are supporting equip at present, is adopted depth, is adopted thickness, balkstone lithology, work Face inclination angle, push to adopt the factors such as speed, working face span and coal winning technology directly affects the water guide of cranny development country rock top plate and split Gap band development mechanism and height.
Mine is in construction and production process, and the surface water and underground water are gushed by the various passages such as crack, tomography, subsidence area Enter mine, when swallet exceedes proper drainage ability, result in mine water disaster, it is also commonly referred to as permeable;Caving zone, which refers to, to be adopted Destruction is directly caving caused by after ore deposit working face caving, the band is not only permeable but also saturating sand;Fissure zone refers to big on caving zone What amount occurred cut layer, absciss layer and fracture gap or fracture extension zone, the band will not sand but energy is permeable thoroughly;Caving zone and fissure zone are collectively referred to as Water flowing fractured zone, water flowing fractured zone development height, mining exploitation and roof rock migration etc. influence factor to preventing and treating crack hair Educate wall-rock crack water most important.
Current cranny development wall-rock crack floods administer cranny development country rock at present mostly with rear goaf delaying water bursting The method of crevice water is also normally only to adopt preceding physical prospecting, drill unrestrained water, but to roof water migration, coal-getter in exploitation process Making face water flowing fractured zone development mechanism does not have pertinent literature to discuss record.
The content of the invention
In view of the above-mentioned problems, the present invention provides a kind of coal-face floods prevention side with cranny development country rock top plate Method, overall merit is carried out according to physical prospecting, drilling situation to working face hydrogeologic condition, Spray water way etc., can be effectively pre- The generation of anti-floods, is particularly suitable for use in the coal-face with cranny development country rock top plate.
To achieve the above object, there is the coal-face floods prevention method of cranny development country rock top plate to be according to thing for this Visit, drilling situation carries out overall merit to working face hydrogeologic condition, Spray water way, comprise the following steps that:
A. preceding detection is adopted:After coal-face is formed, using underground VHD 3 D resistivity method on working face Cover, tunnel lateral wall top country rock water-bearing layer water enrichment area is detected, and according to the resistivity detected, demarcates mining face top Roof rock water-bearing layer rich water exceptions area above plate, rib;
B. bore detecting is verified:Hydrology drilling verification is carried out to Geophysical Anomalies area, it is synchronous to obtain profit after top plate core rock sample Wall-rock crack water-bearing layer hydrous fluids are carried out with three axle rock mechanics experiment machines unrestrained;
C. security evaluation:Rock mechanics experiment is carried out to top plate core rock sample, carried out according to the rock mechanics parameters of acquirement Stope stope roof and floor numerical simulation, designs the detection of top plate height of water flowing fractured zone using numerical simulation result and drills, Observe the original fractured situation of stope top plate;
D. floods threat assessment:According to physical prospecting, results of drilling, wall-rock crack is evaluated using conventional water damage threat assessment method Water-bearing layer is evaluated by working face mining danger;
E. dynamic monitoring:Working face is often pushed to adopt after setpoint distance using VHD 3 D resistivity method to coal work Side, rear goaf top plate country rock watery are detected in front, and monitoring roof rock hydrous fluids change with pressure from surrounding rock is adopted And the migration occurred, prevent the delayed water burst in goaf;
F. rear water flowing fractured zone development observation and site operation are adopted:Stope is pushed to adopt to stopping adopting after line, is stopping adopting line Outside utilizes numerical simulation result in step c to design water flowing fractured zone development bore detecting again;Moved and managed according to roof rock By above goaf rock stratum being divided into caving zone, fissure zone, warp damage, according to adopting upper the three of country rock motion theory Band is theoretical, and design bore direction points to above goaf, and inclination angle is determined according to back production country rock motion value simulated test, and is utilized Double-end sealing leak detection carries out site operation.
Compared with prior art, this has the coal-face floods prevention method of cranny development country rock top plate due to basis Physical prospecting, drilling situation carry out overall merit to working face hydrogeologic condition, Spray water way, pass through rock mechanics experiment, thing A series of detections such as spy, numerical simulation, height of water flowing fractured zone detection simultaneously carry out overall merit to detection data, therefore, it is possible to have Imitate and the floods of coal-face in same exploiting field are prevented, be particularly suitable for use in the coal-getter with cranny development country rock top plate Make face.
Embodiment
There is the coal-face floods prevention method of cranny development country rock top plate to be to work according to physical prospecting, drilling situation for this Make face hydrogeologic condition, Spray water way and carry out overall merit, comprise the following steps that:
A. preceding detection is adopted:After coal-face is formed, using underground VHD 3 D resistivity method on working face Cover, tunnel lateral wall top country rock water-bearing layer water enrichment area is detected, and according to the resistivity detected, demarcates mining face top Roof rock water-bearing layer rich water exceptions area above plate, rib;
B. bore detecting is verified:Hydrology drilling verification is carried out to Geophysical Anomalies area, it is synchronous to obtain profit after top plate core rock sample Wall-rock crack water-bearing layer hydrous fluids are carried out with three axle rock mechanics experiment machines it is unrestrained, when water-bearing layer water yield be more than 3m3During/h By water drainage;
C. security evaluation:Rock mechanics experiment is carried out to top plate core rock sample, carried out according to the rock mechanics parameters of acquirement Stope stope roof and floor numerical simulation, designs the detection of top plate height of water flowing fractured zone using numerical simulation result and drills, Observe the original fractured situation of stope top plate;
D. floods threat assessment:According to physical prospecting, results of drilling, wall-rock crack is evaluated using conventional water damage threat assessment method Water-bearing layer is evaluated by working face mining danger;
E. dynamic monitoring:Working face often push to adopt after 200m using VHD 3 D resistivity method to coal work in face of Side, rear goaf top plate country rock watery are detected, and monitoring roof rock hydrous fluids are sent out with pressure from surrounding rock change is adopted Raw migration, prevents the delayed water burst in goaf;
F. rear water flowing fractured zone development observation and site operation are adopted:Stope is pushed to adopt to stopping adopting after line, is stopping adopting line Outside utilizes numerical simulation result in step c to design water flowing fractured zone development bore detecting again;Moved and managed according to roof rock By above goaf rock stratum being divided into caving zone, fissure zone, warp damage, according to adopting upper the three of country rock motion theory Band is theoretical, and design bore direction points to above goaf, and inclination angle is determined according to back production country rock motion value simulated test, and is utilized Double-end sealing leak detection carries out site operation.
This has the coal-face floods prevention method of cranny development country rock top plate due to according to physical prospecting, drilling situation pair Working face hydrogeologic condition, Spray water way carry out overall merit, pass through rock mechanics experiment, physical prospecting, numerical simulation, water guide A series of detections such as fissure zone height detecting simultaneously carry out overall merit to detection data, therefore, it is possible to effectively to being adopted in same exploiting field The floods of coal working face are prevented, and are particularly suitable for use in the coal-face with cranny development country rock top plate.

Claims (1)

1. a kind of coal-face floods prevention method with cranny development country rock top plate, it is characterised in that according to physical prospecting, bore Spy situation carries out overall merit to working face hydrogeologic condition, Spray water way, comprises the following steps that:
A. preceding detection is adopted:After coal-face is formed, using underground VHD 3 D resistivity method to working face overlying, lane Country rock water-bearing layer water enrichment area is detected above road lateral wall, according to the resistivity detected, demarcates mining face top plate, coal Roof rock water-bearing layer rich water exceptions area above wall;
B. bore detecting is verified:Hydrology drilling verification is carried out to Geophysical Anomalies area, synchronous obtain utilizes three after top plate core rock sample Axle rock mechanics experiment machine carries out unrestrained to wall-rock crack water-bearing layer hydrous fluids;
C. security evaluation:Rock mechanics experiment is carried out to top plate core rock sample, back production is carried out according to the rock mechanics parameters of acquirement Working face stope roof and floor numerical simulation, designs the detection of top plate height of water flowing fractured zone using numerical simulation result and drills, observation The original fractured situation of stope top plate;
D. floods threat assessment:According to physical prospecting, results of drilling, wall-rock crack is evaluated using conventional water damage threat assessment method aqueous Layer is evaluated working face mining danger;
E. dynamic monitoring:Working face often push to adopt after setpoint distance using VHD 3 D resistivity method to coal work in face of Side, rear goaf top plate country rock watery are detected, and monitoring roof rock hydrous fluids are sent out with pressure from surrounding rock change is adopted Raw migration, prevents the delayed water burst in goaf;
F. rear water flowing fractured zone development observation and site operation are adopted:Stope is pushed to adopt to stopping adopting after line, is stopping adopting on the outside of line Water flowing fractured zone development bore detecting is designed again using numerical simulation result in step c;, will according to roof rock motion theory Above goaf rock stratum is divided into caving zone, fissure zone, warp damage, is managed according to upper three band for adopting country rock motion theory By design bore direction points to above goaf, and inclination angle is determined according to back production country rock motion value simulated test, and utilizes both-end Block the carry out site operation that leaks hunting.
CN201710520654.0A 2017-06-30 2017-06-30 A kind of coal-face floods prevention method with cranny development country rock top plate Pending CN107165626A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710520654.0A CN107165626A (en) 2017-06-30 2017-06-30 A kind of coal-face floods prevention method with cranny development country rock top plate

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710520654.0A CN107165626A (en) 2017-06-30 2017-06-30 A kind of coal-face floods prevention method with cranny development country rock top plate

Publications (1)

Publication Number Publication Date
CN107165626A true CN107165626A (en) 2017-09-15

Family

ID=59828102

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710520654.0A Pending CN107165626A (en) 2017-06-30 2017-06-30 A kind of coal-face floods prevention method with cranny development country rock top plate

Country Status (1)

Country Link
CN (1) CN107165626A (en)

Cited By (11)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107622164A (en) * 2017-09-25 2018-01-23 中国煤炭地质总局勘查研究总院 A kind of method for porecasting water upwelling amount of mine well and device
CN110221357A (en) * 2019-05-20 2019-09-10 深圳市勘察研究院有限公司 A kind of long-span and shallowly buried limestone goaf integrated survey method
CN110501473A (en) * 2019-09-19 2019-11-26 六盘水师范学院 A kind of goaf leting speeper experimental provision and its working method
CN110675273A (en) * 2019-10-15 2020-01-10 神华神东煤炭集团有限责任公司 Method for judging water and sand bursting disasters of coal face
CN111140229A (en) * 2020-01-23 2020-05-12 中国矿业大学 Simulation system for roof destruction process after water-soluble mining of layered salt rock
CN111764837A (en) * 2020-07-06 2020-10-13 中国矿业大学 Double-end water plugging detection rod, overburden fracture drilling and measuring integrated device and drilling and measuring method
CN111997688A (en) * 2020-07-15 2020-11-27 陕西麟北煤业开发有限责任公司 Method for preventing and controlling water damage of coal seam roof separation layer
CN113404484A (en) * 2021-07-27 2021-09-17 中国矿业大学 Ground double-bare-hole combined monitoring method for internal movement of water-rich stratum mining rock stratum
CN114397421A (en) * 2021-11-29 2022-04-26 中煤科工开采研究院有限公司 Mining coal seam floor damage depth monitoring method
CN114415260A (en) * 2022-01-19 2022-04-29 中国矿业大学 Detection and evaluation method for water inrush accident of reservoir above goaf
CN110501473B (en) * 2019-09-19 2024-04-30 六盘水师范学院 Goaf water exploring and draining experiment device and working method thereof

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103628914A (en) * 2013-11-13 2014-03-12 陕西煤业化工技术研究院有限责任公司 Low-permeability thick-layer bedrock aquifer exploring and draining method for low-angle coal seam slicing mining
CN104181611A (en) * 2014-08-28 2014-12-03 山东科技大学 Mine working face top board and bottom board mining breaking fracture development dynamic monitoring method
CN104481587A (en) * 2014-11-10 2015-04-01 山东科技大学 Large-mining depth and long-span fully-mechanized top-coal caving face roof sandstone fracture water detecting and preventing method
CN104963721A (en) * 2015-05-26 2015-10-07 安徽建筑大学 Downhole stereo rapid water drainage method through the combination of horizontal drilling holes and vertical drilling holes
CN106528707A (en) * 2016-10-26 2017-03-22 中国矿业大学 Coal seam roof sandstone aquifer water-abundance evaluation method
CN106703883A (en) * 2016-12-29 2017-05-24 山东科技大学 Method for determining floor water inrush danger level of coal mining working faces in personalized manner

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103628914A (en) * 2013-11-13 2014-03-12 陕西煤业化工技术研究院有限责任公司 Low-permeability thick-layer bedrock aquifer exploring and draining method for low-angle coal seam slicing mining
CN104181611A (en) * 2014-08-28 2014-12-03 山东科技大学 Mine working face top board and bottom board mining breaking fracture development dynamic monitoring method
CN104481587A (en) * 2014-11-10 2015-04-01 山东科技大学 Large-mining depth and long-span fully-mechanized top-coal caving face roof sandstone fracture water detecting and preventing method
CN104963721A (en) * 2015-05-26 2015-10-07 安徽建筑大学 Downhole stereo rapid water drainage method through the combination of horizontal drilling holes and vertical drilling holes
CN106528707A (en) * 2016-10-26 2017-03-22 中国矿业大学 Coal seam roof sandstone aquifer water-abundance evaluation method
CN106703883A (en) * 2016-12-29 2017-05-24 山东科技大学 Method for determining floor water inrush danger level of coal mining working faces in personalized manner

Cited By (15)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107622164A (en) * 2017-09-25 2018-01-23 中国煤炭地质总局勘查研究总院 A kind of method for porecasting water upwelling amount of mine well and device
CN110221357A (en) * 2019-05-20 2019-09-10 深圳市勘察研究院有限公司 A kind of long-span and shallowly buried limestone goaf integrated survey method
CN110221357B (en) * 2019-05-20 2020-10-09 深圳市勘察研究院有限公司 Large-span shallow-buried limestone goaf comprehensive exploration method
CN110501473A (en) * 2019-09-19 2019-11-26 六盘水师范学院 A kind of goaf leting speeper experimental provision and its working method
CN110501473B (en) * 2019-09-19 2024-04-30 六盘水师范学院 Goaf water exploring and draining experiment device and working method thereof
CN110675273A (en) * 2019-10-15 2020-01-10 神华神东煤炭集团有限责任公司 Method for judging water and sand bursting disasters of coal face
CN110675273B (en) * 2019-10-15 2022-08-12 神华神东煤炭集团有限责任公司 Method for judging water and sand bursting disasters of coal face
CN111140229B (en) * 2020-01-23 2021-09-24 中国矿业大学 Simulation system for roof destruction process after water-soluble mining of layered salt rock
CN111140229A (en) * 2020-01-23 2020-05-12 中国矿业大学 Simulation system for roof destruction process after water-soluble mining of layered salt rock
CN111764837A (en) * 2020-07-06 2020-10-13 中国矿业大学 Double-end water plugging detection rod, overburden fracture drilling and measuring integrated device and drilling and measuring method
CN111997688A (en) * 2020-07-15 2020-11-27 陕西麟北煤业开发有限责任公司 Method for preventing and controlling water damage of coal seam roof separation layer
CN113404484A (en) * 2021-07-27 2021-09-17 中国矿业大学 Ground double-bare-hole combined monitoring method for internal movement of water-rich stratum mining rock stratum
CN114397421A (en) * 2021-11-29 2022-04-26 中煤科工开采研究院有限公司 Mining coal seam floor damage depth monitoring method
CN114415260A (en) * 2022-01-19 2022-04-29 中国矿业大学 Detection and evaluation method for water inrush accident of reservoir above goaf
CN114415260B (en) * 2022-01-19 2023-02-21 中国矿业大学 Detection and evaluation method for water inrush accident of reservoir above goaf

Similar Documents

Publication Publication Date Title
CN107165626A (en) A kind of coal-face floods prevention method with cranny development country rock top plate
CN107044289B (en) A kind of bored grouting blocks the water damage control method of overlying strata water producing fractures main channel
Lu et al. Improvement of methane drainage in high gassy coal seam using waterjet technique
CN104989403B (en) Method for reconstructing floor limestone aquifer into natural-artificial composite integrated aquiclude
CN106014407B (en) Utilize the roof fracture water method that reduction master control coal rock layer controls disaster in situ
CN106089296B (en) A kind of prevention and treatment method of roof absciss layer water
Adams et al. Differentiating applications of hydraulic fracturing
CN104314610A (en) Coal road stripe region burst-preventing method
CN109162731B (en) Water inrush grouting treatment method for deep mining of iron mine area
CN106150501B (en) The method for weakening master control coal rock layer using Overburden gob area situ waste water
CN107816365A (en) A kind of quick-fried pumping integration anti-burst method of coal seam drilling
CN108086977A (en) A kind of coal seam prevents water-resisting floor coal-mining method for water-bearing layer
Meng et al. In situ investigation and numerical simulation of the failure depth of an inclined coal seam floor: a case study
Liang et al. Field research: measuring water pressure resistance in a fault-induced fracture zone
Kang et al. Application of large-scale hydraulic fracturing for reducing mining-induced stress and microseismic events: A comprehensive case study
Wang et al. Coupling technology of deep-hole presplitting blasting and hydraulic fracturing enhance permeability technology in low-permeability and gas outburst coal seam: a case study in the no. 8 mine of Pingdingshan, China
Zhang et al. A simple and efficient way to detect the mining induced water-conducting fractured zone in overlying strata
CN106194185B (en) The lower thick aqueous soil layer sand control coal and rock pillar for safety of hydraulic pressure effect stays equipment, method
Khave Delineating subterranean water conduits using hydraulic testing and machine performance parameters in TBM tunnel post-grouting
Zhou et al. Geological barrier–a natural rock stratum for preventing confined karst water from flowing into mines in North China
Du et al. Influence of key strata on the gas downward leakage law in dual-system of coal seam
CN113622952A (en) Comprehensive treatment method for water damage of mountain green coal in structurally complex area
Hu et al. Evaluation Method of Water Hazard Control Effect of Coal Seam Floor in Deep Mining: Sequence Verification Evaluation
Shang et al. Permeability enhancement technology for soft and low-permeability coal seams combined with hydraulic perforation and hydraulic fracturing
CN113550754B (en) Method and system for performing advanced drilling of coal seam roadway based on bottom suction roadway cross-layer drilling

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20170915