CN107165306A - Construction wall construction method - Google Patents

Construction wall construction method Download PDF

Info

Publication number
CN107165306A
CN107165306A CN201710501063.9A CN201710501063A CN107165306A CN 107165306 A CN107165306 A CN 107165306A CN 201710501063 A CN201710501063 A CN 201710501063A CN 107165306 A CN107165306 A CN 107165306A
Authority
CN
China
Prior art keywords
wall
construction
concrete
building
build
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201710501063.9A
Other languages
Chinese (zh)
Other versions
CN107165306B (en
Inventor
虞和定
李鱼
陆基伟
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
HUAHENG CONSTRUCTION GROUP CO Ltd
Original Assignee
HUAHENG CONSTRUCTION GROUP CO Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by HUAHENG CONSTRUCTION GROUP CO Ltd filed Critical HUAHENG CONSTRUCTION GROUP CO Ltd
Priority to CN201710501063.9A priority Critical patent/CN107165306B/en
Publication of CN107165306A publication Critical patent/CN107165306A/en
Application granted granted Critical
Publication of CN107165306B publication Critical patent/CN107165306B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B2/00Walls, e.g. partitions, for buildings; Wall construction with regard to insulation; Connections specially adapted to walls
    • E04B2/02Walls, e.g. partitions, for buildings; Wall construction with regard to insulation; Connections specially adapted to walls built-up from layers of building elements

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Physics & Mathematics (AREA)
  • Electromagnetism (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Revetment (AREA)
  • On-Site Construction Work That Accompanies The Preparation And Application Of Concrete (AREA)

Abstract

The invention discloses a kind of construction wall construction method, its drip irrigation device is:Including surveying setting-out, build Kan Tai, laying built-in fitting, building wall, wall reinforcement, floorslab concrete construction, the indwelling of construction joint and processing, wall and floor reinforcing and external wall plastering;The present invention proposes corresponding solution in terms of quality of materials, technology, construction technology, reaches cheap, the masonry stability and construction quality of raising construction wall.

Description

Construction wall construction method
Technical field
The present invention relates to construction engineering technical field, more specifically, it relates to a kind of construction wall construction method.
Background technology
With the fast development of science and technology, construction material also develops to the direction of energy-saving and environmental protection, particularly building block material Material, also shows the increasingly flourishing impetus;Compared with other building wall materials, air-entrained concrete building block has the spy of itself Point, its energy consumption is low, lightweight, speed of application fast, and especially its heat preservation and energy conservation effects is good, there is good social benefit.
But in current building structure, the characteristics of due to air-entrained concrete building block, it is easily caused blockwork overlap joint Unstable and plaster cracking, so as to cause air-entrained concrete building block to be in a disadvantageous position in application and popularizations.
The content of the invention
In view of the deficienciess of the prior art, it is an object of the invention to provide a kind of construction wall construction method, having Improve the effect of building block building wall construction quality.
To achieve the above object, the invention provides following technical scheme:
A kind of construction wall construction method, comprises the following steps:
S1, surveying setting-out:Excavating sideline and the traverse point and bench mark of construction are measured on ground;
S2, build Kan Tai:Poured coagulation earth steps platform on ground, and coagulation earth steps platform and ground connect Cha Chu uniformly poured with Ground matches identical without stone cement mortar;
S3, laying built-in fitting:Horizontal prestressed pipe and vertical prestressing pipe are laid on coagulation earth steps platform;
S4, building wall:To be built below the center line of wall height using sealed concrete solid building block, more than the center line of wall height Using steam pressure sand aerated concrete block, and connector is preset with steam pressure sand aerated concrete block, pipeline is installed reserved And building wall and door and window, lintel, post, build gap between top by laying bricks or stones and coordinate and build;
S5, wall reinforcement:Strong position, which is shunk, in wall is equipped with seizing wire or the fiberglass gridding cloth of resistance to alkali lye;
S6, floorslab concrete construction;Floorslab concrete is divided into four sections and poured by flowing water section, and vibration board vibrates movement When, the edge that flat board covers jolt ramming part is not less than 100mm;
S7, construction joint indwelling and processing:
A) indwelling of construction joint:Every layer of top plate is divided by four flowing water sections and is retained in the range of span centre 1/3, is stayed per story shear wall Under the top plate at surface above 5mm;
B) treatment of construction joints:Concrete strength at construction joint is not less than 1.2Mpa, and first uniformly pouring a layer thickness before pouring is 50~100mm and subtract stone cement mortar with concrete composition identical;
S8, wall and floor are reinforced:Carbon cloth is equipped between the connector and floor that metope is reserved;
S9, external wall plastering.
Be arranged such, first clear the design drawing of construction wall, then place, ground are cleaned out, line setting, Provide good position and size;Simultaneously by concrete segment carry out selection, detection, will be up to standard after concrete segment lay, Improve the standard requirement and the quality control of concrete segment of filling wall base body;By to carrying out concrete bank before building wall Platform is built, and by improving connective stability and adhesive strength between wall and ground without stone cement mortar, is easy to Make wall contact with bottom of the building face and concrete segment is bonded with bottom of the building face by Kan Tai, improve concrete segment formation and build Stability during walling body, also reduces the effect that concrete segment is directly contacted with ground, and the use for improving construction wall is steady Qualitative energy;Strong position is shunk in wall and is equipped with seizing wire or the fiberglass gridding cloth of resistance to alkali lye, improves construction wall Overall structural strength and safety and stability performance;By construction wall and, the cooperation between window, beam, post and corresponding component, and Indwelling has preset slot, is easy to the filling built between near-end part in later stage;Constructing and check and accept simultaneously will according to engineering and specification Summation acceptance criteria, the strict live masonry project construction quality of control, steps up construction quality, finally after to construction Wall is reinforced with floor, by being equipped with carbon cloth between the connector and floor that metope is reserved, improves wall and floor Between stability;Finally External Wall is plastered again, completes preliminary construction to construction wall, reach raising construction total quality with And the overall safety and stability performance of construction wall, while also improving construction safety performance.
Further set:The coagulation earth steps platform is vibrated using placement layer by layer, and every layer pours thickness for 30cm, pours coagulation Earth steps platform is is carried out continuously, and interval time is no more than concrete final setting time, when pouring concrete at door-window opening, both sides pair Claim blanking, and vibrating spear is 15~20cm apart from hole side.
It is arranged such, coagulation earth steps platform is uniformly poured, improves the overall structural stability of coagulation earth steps platform.
Further set:When coagulation earth steps platform vibrates, depth is not less than 50mm in vibrating spear insertion lower-layer concrete, shakes The displacement of tamper is not more than 350mm, vibrates and laitance and not in degree of being settled into is presented with envelope, and posts on vibrating spear use In the adhesive tape of mark, coagulation earth steps platform is poured finish after, by the built-in fitting at suitable for reading, construction joint cleared up and will landing ash it is clear Reason is clean.
It is arranged such, improves the connective stability between adjacent layer, and be easy to record the height vibrated by adhesive tape, simultaneously Reserving corresponding built-in fitting is easy to the later stage to carry out corresponding constructing operation.
Further set:Block is taken using dislocation during building wall, sealed concrete solid building block takes block length and is more than concrete reality / 3rd of heart building block length, mortar joint is smooth vertical and horizontal to be set, and horizontal joint, perps saturation degree are all higher than being equal to 80%.
It is arranged such, the connective stability be conducive between neighbouring concrete segment is built in dislocation, makes the one of top Block concrete building block and the block concrete building block of lower section two are bonding, improve the overall stability of filling walling;Pass through simultaneously Mortar joint is smooth vertical and horizontal to be set, and improves the bonding stability between concrete segment.
Further set:Horizontal mortar joint degree and perps width are 3-4mm.
It is arranged such, the tight ness rating connected between raising concrete segment, cooperation when gap is built by laying bricks or stones between adjacent block, Adjacent concrete blocks are bonded by mortar again, the stability of filling walling is improved.
Further set:Building wall and door and window, lintel, post, build top by laying bricks or stones and build when, treating that cavity is built by laying bricks or stones completely should be extremely After being spaced 14 days less, then mended block jam-packed.
It is arranged such, after the wall masonry for building early stage by laying bricks or stones is stable, concrete segment is completely dried bonding, wall with mortar Entirety entered the period after finalize the design almost, then mended by the later stage build extruding make wall and beam, post, build by laying bricks or stones at the top of etc. stablize close Envelope connection, improves the integral sealing stability of wall.
Further set:Sealed concrete solid building block builds height by laying bricks or stones and is less than 1.5m daily, and when stopping building on the skin brick of highest one Beared down on one with 1 skin float block, taken away again when continuing to build by laying bricks or stones within the 2nd day.
It is arranged such, wall is uniformly dried stress, it is to avoid after disposable building is too high, the concrete segment and sand of bottom Starch contact excessive, cause mutually to bond illusive problem;Because upper strata does not have later stage building block pressure by itself and lower section Building block pressuring action, at the same by it is top have on a skin brick beared down on one with 1 skin float block, taken again when continuing to build by laying bricks or stones within the 2nd day Walk, can improve the firmness between later stage building block and early stage building block, and then improve the overall stability of filling wall.
Further set:Thickness is equipped between external wall plastering layer for 20mm, 1 in building wall:2 cement mortar and interior Mix the vertical damp-proof layer of the waterproofing agent of cement weight 5%.
It is arranged such, improves the humidity resistance of wall.
Further set:Thickness is equipped between coagulation earth steps platform and ground for 20mm, 1:2 cement mortar and interior water mixing mud The horizontal damp-proof course of the waterproofing agent of weight 5%.
It is arranged such, improves the humidity resistance between wall and ground, improve the stability of its wall.
Further set:Described is 50mm without stone cement mortar thickness.
It is arranged such, makes integrally formed thickness moderate, and makes wall and thickness that sealed concrete solid building block is formed moderate.
By using above-mentioned technical proposal, the present invention is compared compared with the prior art:By include surveying setting-out, build Kan Tai, Built-in fitting, building wall, wall reinforcement, floorslab concrete construction, the indwelling of construction joint and processing, wall and floor is laid to reinforce And external wall plastering;Corresponding solution is proposed in terms of quality of materials, technology, construction technology, reaches that raising construction is overall Quality and the overall safety and stability performance of construction wall, while also improving construction safety performance.
Embodiment
Construction wall construction method is described further below.
A kind of construction wall construction method, comprises the following steps:
Key points for operation before construction:
S1 surveying setting-outs:Be familiar with design drawing and acceptance specification requirement, specify quality of materials standard, check wall position line into Really, understand constructional column, collar tie beam, the setting requirements of drawknot beam, carry out the technical preparation of construction early stage;Side is excavated on ground Line and the traverse point and bench mark for measuring construction, cleaning ground remaining mortar, debris etc., line setting and vertical skin Number bar.
Raw material are marched into the arena requirement:
S2:Pre-processed before concrete segment selection, detection, placement and construction;
1)Concrete segment selection, should provide work certificate and properties of product examining report, and the material whole audience of marching into the arena is carried out Visual examination;
2)Concrete segment is loaded and unloaded using fork truck or crane, and is stacked at the hard smooth ground without ponding, and uses colour bar cloth Covering;
3)Inspection lot is a collection of by same kind, same specification, 10,000 pieces of ad eundem, and 80 pieces of sample surveys are extracted with accidental sampling Dimensional discrepancy, presentation quality;From outward appearance and dimensional discrepancy examine qualified sample, 5 groups of totally 15 pieces of progress intensity are randomly selected Detection, randomly selects 3 groups of totally 9 pieces of progress bulk density inspections;
4)During concrete masonry, product age should forbid throwing and incline more than 28 days, during material handling;After marching into the arena by Kind, specification are stacked neatly respectively;2m is not to be exceeded in stacking height, and prevents from drenching with rain;
5)Filling wall should shift to an earlier date 2 days structured base layer is watered moistening before building by laying bricks or stones, when aerated blocks are built by laying bricks or stones, should be on the day of building by laying bricks or stones to block Block bricklaying surface water spray moistening.
Building wall quality control points:
S2, build Kan Tai:
1)Coagulation earth steps platform has been poured on ground, and coagulation earth steps platform meets Cha Chu with ground and uniformly poured and ground proportioning phase Same and thickness is 50mm without stone cement mortar;It is being 20mm, 1 without thickness is equipped between stone cement mortar and ground:2 water Cement mortar and the interior horizontal damp-proof course for mixing the waterproofing agent of cement weight 5%;
2)Coagulation earth steps platform is vibrated using placement layer by layer, and every layer pours thickness for 30cm, and casting concrete Kan Tai is to be carried out continuously, And interval time is no more than concrete final setting time;
3)When pouring concrete at door-window opening, the symmetrical blanking in both sides, and vibrating spear is 15~20cm apart from hole side;
4)When coagulation earth steps platform vibrates, depth is not less than 50mm in vibrating spear insertion lower-layer concrete, the movement of vibrating spear away from From no more than 350mm, vibrate and laitance and not in degree of being settled into is presented with envelope, and post on vibrating spear the glue for mark Bar;
5)Coagulation earth steps platform is poured finish after, by the built-in fitting at suitable for reading, construction joint cleared up and by landing ash clean out.
S3, laying built-in fitting:Horizontal prestressed pipe and vertical prestressing pipe are laid on coagulation earth steps platform.
S4, building wall:To be built below the center line of wall height using sealed concrete solid building block, the center line of wall height Steam pressure sand aerated concrete block is used above, and is preset with connector on steam pressure sand aerated concrete block, pipeline is installed Reserved and building wall and door and window, lintel, post, build gap between top by laying bricks or stones and coordinate and build;
1)Block is taken using dislocation during concrete block masonry, concrete segment, which is taken, builds length is more than building block length 1/3rd, Mortar joint is smooth vertical and horizontal, and mortar is full;Mortar joint is smooth vertical and horizontal to be set, and horizontal joint, perps saturation degree are all higher than being equal to 80%;
2)Concrete block masonry gray seam thickness and width should be correct, when concrete segment uses steam pressure sand aerated concrete block During adhesive mortar, thickness of mortarat bed joint and vertical mortar joint width are preferably 3-4mm;
3)Concrete segment build to door, window, lintel, post, build by laying bricks or stones top build when, treating that cavity is built by laying bricks or stones should at least be spaced 14 days completely Afterwards, then mended block jam-packed.
4)Concrete block wall builds height by laying bricks or stones no more than 1.5m daily, and thickness of mortarat bed joint cannot be greater than 15mm, vertically Mortar joint cannot be greater than 20mm;And beared down on one when stopping building on the skin brick of highest 1 with 1 skin float block, taken again when continuing to build by laying bricks or stones within the 2nd day Walk;
5)Concrete block masonry mortar joint adhesive mortar building mortar layer thickness is 3-4mm;Steam pressure sand aerated concrete block wall 10-15mm gaps should be stayed between agent structure, 10-20mm gaps, gap PU foaming agents or polymerization are stayed between wall top and floor Thing mortar is filled;
6)Pipeline is installed to reserve, pipeline through walls is met, its position, size should be examined in advance;Based on reserved, chisel is picked in reduction afterwards Destroy wall stability.
S5, wall reinforcement:Strong position, which is shunk, in wall is equipped with seizing wire or the fiberglass gridding cloth of resistance to alkali lye; Such as the suitable position of the hinge point of beam column built from concrete and masonry wall, door-window opening, the turning point of architectural plane or long wall.
S6, floorslab concrete construction;Floorslab concrete is divided into four sections and poured by flowing water section, and vibration board vibrates shifting When dynamic, the edge that flat board covers jolt ramming part is not less than 100mm.
S7, construction joint indwelling and processing:
A) indwelling of construction joint:Every layer of top plate is divided by four flowing water sections and is retained in the range of span centre 1/3, is stayed per story shear wall Under the top plate at surface above 5mm;
B) treatment of construction joints:Concrete strength at construction joint is not less than 1.2Mpa, and first uniformly pouring a layer thickness before pouring is 50~100mm and subtract stone cement mortar with concrete composition identical.
S8, wall and floor are reinforced:Carbon cloth is equipped between the connector and floor that metope is reserved.
S9, external wall plastering;Thickness is equipped between external wall plastering layer for 20mm, 1 in building wall:2 cement mortar and Inside mix the vertical damp-proof layer of the waterproofing agent of cement weight 5%.
S10:The construction of curtain wall:Glass curtain wall mounting process is sequentially successively;
1)Preparation of construction:Prepare including personnel, material prepares, preparation at the construction site;
2)Inspect for acceptance glass plate:Whether specification quantity is correct, whether each interlayer has dislocation, and whether glass, glass stacking pacify Entirely, whether there is the overproof glass of error, be enough to have the glass damaged, three-dimensional error whether in control range, glass Whether whether glass aluminium frame have suitable bad, structure glue to have, and anomaly, sampling do the test of structure glue sticking, inspecting for acceptance will carry out in detail Record and bind into book form;
3)Glass plate is stacked by level:Son, which installs glass plate yuan, will say that glass cleaning is put well by level heap, simultaneously Stacked by erection sequence, stack appropriate tilt, it is to avoid topple;
4)Just install:Check and find glass, transport glass, adjustment direction, glass is lifted to installation position, two pieces of 10mm glass holders are installed Plate, to groove, enter groove, to glue-line;
5)Plate is adjusted after the completion of being filled at the beginning of adjustment glass plate, adjustment standard is put down for horizontal flat, vertical, face;Horizontal flat i.e. horizontal stroke Beam level, glue water shutoff are put down;Vertical and vertical beam is vertical, glue envelope is vertical;The flat i.e. each glass in face is in the same plane or in cambered surface;It is outdoor Adjust in rear inspection chamber and whether be in level, whether size reaches design requirement everywhere;
6)It is fixed:It is fixed, is fixed using block rubber, cushion block is just compressed after the completion of glass plate adjustment, prevents glass plate pine It is dynamic;
7)Check and accept:End is installed to from glass, whole process carries out quality control;Inside have:Whether plate itself is problematic, glue Whether seam size meets connecing between whether smooth vertical and horizontal design requirement, glue-line, the whether wrong face phenomenon of glass plate, indoor aluminium Whether mouth meets design requirement.
Described above is only the preferred embodiment of the present invention, and protection scope of the present invention is not limited merely to above-mentioned implementation Example, all technical schemes belonged under thinking of the present invention belong to protection scope of the present invention.It should be pointed out that for the art Those of ordinary skill for, some improvements and modifications without departing from the principles of the present invention, these improvements and modifications It should be regarded as protection scope of the present invention.

Claims (10)

1. a kind of construction wall construction method, it is characterised in that comprise the following steps:
S1, surveying setting-out:Excavating sideline and the traverse point and bench mark of construction are measured on ground;
S2, build Kan Tai:Poured coagulation earth steps platform on ground, and coagulation earth steps platform and ground connect Cha Chu uniformly poured with Ground matches identical without stone cement mortar;
S3, laying built-in fitting:Horizontal prestressed pipe and vertical prestressing pipe are laid on coagulation earth steps platform;
S4, building wall:To be built below the center line of wall height using sealed concrete solid building block, more than the center line of wall height Using steam pressure sand aerated concrete block, and connector is preset with steam pressure sand aerated concrete block, pipeline is installed reserved And building wall and door and window, lintel, post, build gap between top by laying bricks or stones and coordinate and build;
S5, wall reinforcement:Strong position, which is shunk, in wall is equipped with seizing wire or the fiberglass gridding cloth of resistance to alkali lye;
S6, floorslab concrete construction;Floorslab concrete is divided into four sections and poured by flowing water section, and vibration board vibrates movement When, the edge that flat board covers jolt ramming part is not less than 100mm;
S7, construction joint indwelling and processing:
The indwelling of construction joint:Every layer of top plate is divided by four flowing water sections and is retained in the range of span centre 1/3, is stayed in per story shear wall At top plate lower surface above 5mm;
Treatment of construction joints:Concrete strength at construction joint is not less than 1.2Mpa, and it is 50 that a layer thickness is first uniformly poured before pouring ~100mm and subtract stone cement mortar with concrete composition identical;
S8, wall and floor are reinforced:Carbon cloth is equipped between the connector and floor that metope is reserved;
S9, external wall plastering.
2. construction wall construction method according to claim 1, it is characterised in that:The coagulation earth steps platform is poured using layering Build and vibrate, every layer pours thickness for 30cm, casting concrete Kan Tai is is carried out continuously, and interval time is no more than concrete final set Time, when pouring concrete at door-window opening, the symmetrical blanking in both sides, and vibrating spear is 15~20cm apart from hole side.
3. construction wall construction method according to claim 2, it is characterised in that:When coagulation earth steps platform vibrates, vibrate Depth is not less than 50mm in rod insertion lower-layer concrete, and the displacement of vibrating spear is not more than 350mm, vibrates and is presented floating with envelope Slurry and not in degree of being settled into, and post on vibrating spear the adhesive tape for mark, coagulation earth steps platform is poured finish after, by it is suitable for reading, Built-in fitting at construction joint is cleared up and is cleaned out landing ash.
4. construction wall construction method according to claim 1, it is characterised in that:Block is taken using dislocation during building wall, Sealed concrete solid building block, which is taken, builds length is more than sealed concrete solid building block length 1/3rd, and mortar joint is smooth vertical and horizontal to be set, level Seam, perps saturation degree are all higher than being equal to 80%.
5. construction wall construction method according to claim 4, it is characterised in that:Horizontal mortar joint degree and perps width are 3-4mm。
6. construction wall construction method according to claim 1, it is characterised in that:Building wall and door and window, lintel, Post, top is built by laying bricks or stones when building, after cavity is built by laying bricks or stones and should at least be spaced 14 days completely, then is mended and build jam-packed.
7. construction wall construction method according to claim 1, it is characterised in that:Sealed concrete solid building block builds height by laying bricks or stones daily Degree is less than 1.5m, and is beared down on one when stopping building on the skin brick of highest one with 1 skin float block, is taken away again when continuing to build by laying bricks or stones within the 2nd day.
8. construction wall construction method according to claim 1, it is characterised in that:In building wall in external wall plastering layer Between be equipped with thickness for 20mm, 1:2 cement mortar and the interior vertical damp-proof layer for mixing the waterproofing agent of cement weight 5%.
9. construction wall construction method according to claim 1, it is characterised in that:Spread between coagulation earth steps platform and ground It is 20mm, 1 provided with thickness:2 cement mortar and the interior horizontal damp-proof course for mixing the waterproofing agent of cement weight 5%.
10. construction wall construction method according to claim 1, it is characterised in that:It is described without stone cement mortar thickness For 50mm.
CN201710501063.9A 2017-06-27 2017-06-27 Construction wall construction method Active CN107165306B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710501063.9A CN107165306B (en) 2017-06-27 2017-06-27 Construction wall construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710501063.9A CN107165306B (en) 2017-06-27 2017-06-27 Construction wall construction method

Publications (2)

Publication Number Publication Date
CN107165306A true CN107165306A (en) 2017-09-15
CN107165306B CN107165306B (en) 2019-04-30

Family

ID=59826875

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710501063.9A Active CN107165306B (en) 2017-06-27 2017-06-27 Construction wall construction method

Country Status (1)

Country Link
CN (1) CN107165306B (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109680824A (en) * 2018-12-26 2019-04-26 谢世琴 A kind of building filling wall integrated construction technique
CN111677146A (en) * 2020-06-19 2020-09-18 中建富林集团有限公司 Construction process of masonry wall

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20100170187A1 (en) * 2004-03-24 2010-07-08 Oryzatech, Inc. Culm block and method for forming the same
CN103266767A (en) * 2013-05-27 2013-08-28 中国航天建设集团有限公司 Construction method for preventing and treating cracks between concrete structure and filler wall
CN103821253A (en) * 2014-02-28 2014-05-28 浙江海天建设集团有限公司 Constructing technique for aerated concrete block filler wall
CN103821252A (en) * 2014-02-28 2014-05-28 浙江海天建设集团有限公司 Process for constructing aerated concrete building block infilled wall through membrane maintenance technology
CN106836551A (en) * 2017-01-02 2017-06-13 浙江泛华工程监理有限公司 Infill Wall with Aerated Concrete Block construction method

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20100170187A1 (en) * 2004-03-24 2010-07-08 Oryzatech, Inc. Culm block and method for forming the same
CN103266767A (en) * 2013-05-27 2013-08-28 中国航天建设集团有限公司 Construction method for preventing and treating cracks between concrete structure and filler wall
CN103821253A (en) * 2014-02-28 2014-05-28 浙江海天建设集团有限公司 Constructing technique for aerated concrete block filler wall
CN103821252A (en) * 2014-02-28 2014-05-28 浙江海天建设集团有限公司 Process for constructing aerated concrete building block infilled wall through membrane maintenance technology
CN106836551A (en) * 2017-01-02 2017-06-13 浙江泛华工程监理有限公司 Infill Wall with Aerated Concrete Block construction method

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
陈文明: "某钢筋混凝土工程质量控制实例", 《内蒙古煤炭经济》 *

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109680824A (en) * 2018-12-26 2019-04-26 谢世琴 A kind of building filling wall integrated construction technique
CN111677146A (en) * 2020-06-19 2020-09-18 中建富林集团有限公司 Construction process of masonry wall

Also Published As

Publication number Publication date
CN107165306B (en) 2019-04-30

Similar Documents

Publication Publication Date Title
CN102116061B (en) Masonry construction method for filling wall core pillar, core girder and building blocks into framework structure
CN103821364B (en) The construction method of reinforced concrete water pond
CN103410332B (en) A kind of concrete hollow block reinforcement wall construction technology
CN106192907B (en) Add the construction method of 150m~300m grade high concrete panel rock-fill dams of cement sand and gravel structure sheaf
CN102392549B (en) Construction working method for seamless prestressed-concrete self-waterproof clean water reservoir
CN106836551A (en) Infill Wall with Aerated Concrete Block construction method
CN102776897B (en) Wash apron anti-settling anti-cracking construction method and structure
CN106801517A (en) A kind of schoolhouse surface consolidation of Prefabricated porous plate brick mixed structure strengthens method
CN201224933Y (en) Frame beam preventing water seepage and crack and wall stuffing structure
CN106499070A (en) The construction method of connecting sewing between assembled architecture component and component
CN110792200A (en) Masonry construction method without post-picking and pipe wrapping structure thereof
CN205576955U (en) Raft foundation's reinforced structure is displaced into to strip footing
CN106978907A (en) A kind of construction method of tall and big curved wall secondary structure
CN107165306B (en) Construction wall construction method
CN108130992A (en) Rubble plate, styrofoam and porous brick compound thermal-insulating decorative external wall construction engineering method
CN105201101A (en) Light aggregate concrete small hollow block building masonry construction method
CN113374295A (en) Old steel-wood structure roof truss dismantling and rebuilding construction method
CN109898698A (en) A kind of construction method of pseudo-classic architecture silk seam wall
CN104631658B (en) The construction method and sun-dried mud brick of a kind of adobe wall suitable for highly seismic region of providing fortification against earthquakes
CN109113068A (en) A kind of inverse construction joint structure for building construction of deep basal pit
CN103469828A (en) Construction method of hydrophobic structure of post-cast strip of bottom plate of basement
CN104763158B (en) Tenon joint type light-weight aggregate chained block construction method
CN109057066A (en) A kind of flexible connection anti-seismic structure and construction method
CN206844389U (en) Building blocks wall structure
CN102767284B (en) Semi-prefabricating construction process for concrete thin-wall lower return eave

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant