CN107152089A - A kind of waterproof construction method on the ground for having a floor heating - Google Patents
A kind of waterproof construction method on the ground for having a floor heating Download PDFInfo
- Publication number
- CN107152089A CN107152089A CN201710449067.7A CN201710449067A CN107152089A CN 107152089 A CN107152089 A CN 107152089A CN 201710449067 A CN201710449067 A CN 201710449067A CN 107152089 A CN107152089 A CN 107152089A
- Authority
- CN
- China
- Prior art keywords
- waterproof
- floor heating
- coat
- ground
- construction method
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04B—GENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
- E04B1/00—Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
- E04B1/62—Insulation or other protection; Elements or use of specified material therefor
- E04B1/66—Sealings
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04F—FINISHING WORK ON BUILDINGS, e.g. STAIRS, FLOORS
- E04F15/00—Flooring
- E04F15/18—Separately-laid insulating layers; Other additional insulating measures; Floating floors
- E04F15/181—Insulating layers integrally formed with the flooring or the flooring elements
Landscapes
- Engineering & Computer Science (AREA)
- Architecture (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Physics & Mathematics (AREA)
- Electromagnetism (AREA)
- Road Paving Structures (AREA)
Abstract
The invention discloses a kind of waterproof construction method on the ground for having a floor heating, comprise the following steps:1) construction quality is carried out to original ground screed-coat to survey and repair;2) dust of original ground screed-coat is cleared up, metope and original ground screed-coat and original ground screed-coat are handled with sewer pipe junction using leak stopping king;3) waterproofing agent is added to look for slope and levelling formation sloping layer to floor drain direction using concrete, with smashing with light and conserve;4) EP waterproof rolls are layered on sloping layer with binding agent, EP waterproof rolls turn to few 100mm on corner and pipe root;5) binding agent is scraped to whole coverings in EP waterproof rolls surface batch, and foster water 48h, which does not leak, to be passed through;6) floor heating pipe takes fluting form to climb over waterproof beam, in the surface concreting of EP waterproof rolls and covering floor heating pipe;7) cross-notching walks EP waterproof rolls progress leak stopping king's closure repairing of tube damage;8) water 24h is supported, does not leak and passes through, the simple cost of constructing operation is low, the good water-proof effect time is long.
Description
Technical field
The invention belongs to indoor waterproof construction technology field, and in particular to a kind of waterproof construction side on the ground for having a floor heating
Method.
Background technology
Traditional heating rooms are radiator or air-conditioning, and toilet heating mode is to install super bath, but effect and are paid no attention to
Think, one is the sensation for having baking when using;Two be super bath high-intensity illumination easily induce melanin increase, make skin darkening or
Dermal melanin cancer is likely to result in, is unfavorable for healthy.And floor heating heating is because the simple ripe, cost of construction is low, save
Space and be widely used because floor heating is conducted heat from bottom to top in the form of radiation by ground, and floor heating remote
Infrared radiation wavelength is 8 microns~12 microns, beneficial to human body, and can also thoroughly remove room especially toilet, shower
The humidity and peculiar smell in the heavier space of the steam such as room and kitchen.The pipeline of ground warm device is to extend into toilet by other rooms to drench
The heavier space of the steam such as bath room, often have under threshold stone into toilet floor heating pipe in actual prior art work progress
Pass by one's way, but because floor heating pipe and surrounding environment difference variation are larger, therefore cement mortar fully wrapped around can not have gap, toilet
Wet area's moisture can be flowed to toilet along floor heating pipe and be caused damage with exterior domain;Existing construction method also is with entering toilet
Heating coil burrow destruction waterproof beam mode pass by one's way, waterproof beam can be destroyed, the hidden danger of seepage is left;Construction method also treats health
Between after the completion of ground warm device lays, poured on floor heating layer and smash pea gravel concreten protective layer, and make the mixed of Isolation Toilet ground
Solidifying soil water bar.But, because concrete water bar is located at the top of floor heating layer, if ground warm device pipeline has percolating water, health
Between can produce horizontal leak, or even spread to outside toilet, cause the percolating water of room large area.
The content of the invention
Object of the present invention is to provide a kind of waterproof construction method on the ground for having a floor heating, constructing operation is simple, into
This is low, the good water-proof effect and time is permanent.
For up to above-mentioned purpose, major technique solution of the invention is to provide a kind of waterproof construction on the ground for having floor heating
Method, comprises the following steps:
1) carry out Construction Quality to original ground screed-coat to survey, do not met in maintenance original ground screed-coat thoroughly
The place of construction quality requirement,
2) dust of original ground screed-coat is cleared up, right angle joint to metope and original ground screed-coat and primitively
Face screed-coat does height and width at least 20mm leak stopping bar with sewer pipe junction using leak stopping king, and the vertical of leak stopping bar cuts
Face is the arcuate shape that outside is less than inner side,
3) waterproofing agent is added to look for slope and levelling formation sloping layer to floor drain direction using pea gravel concreten, with smashing with light and support
Shield, sloping layer and metope right angle joint do same step 2 using leak stopping king) in as leak stopping bar,
4) Central-South formaldehydeless 901 glue spice is added to roll up EP waterproofs as cable laying operation binding agent using No. 325 striaght cements
Material is laid on sloping layer, and EP waterproof rolls turn to few 100mm on corner and root of pipeline nature,
5) criticized once again on EP waterproof rolls surface and scrape step 4) in binding agent to all cover EP waterproof rolls, support water
48h, ne-leakage confirms that examination passes through,
6) floor heating pipe takes fluting form to climb over the waterproof beam of wall bottom with the use of floor heating pipe bend pipe accessory, prevents in EP
The concreting of water coiled material surface and covering floor heating pipe formation ground floor,
7) cross-notching walks the progress leak stopping king closure of EP waterproof rolls and repairing of tube damage,
8) water 24h is supported once again, and ne-leakage confirms that examination passes through.
The situation of construction quality requirement is not met in the original ground screed-coat includes hollowing and cracking.
The original ground screed-coat and the root that sewer pipe junction is sewer pipe.
The sloping layer thickness is 50mm thick, and thinnest part is 20mm thick, and the waterproofing agent is that Zhejiang University seeks the type of scholar's board 2000.
The step 1) in original ground screed-coat be located on original cast-in-situ floor,
The step 3) in downcomer if any displacement, first blocked at downcomer displacement with leak stopping king.
The step 4) in pea gravel concreten intensity be C20.
The step 4) in EP waterproof rolls overlap width >=10mm.
The step 6) in waterproof beam be connected with original cast-in-situ floor.
The beneficial effects of the invention are as follows:Constructing operation is simple, cost is low, and good water-proof effect and time are permanent, are prevented effectively from
Floor heating pipe from threshold stone descended or the burrowed mode of destruction waterproof beam crosses the leak being likely to result in existing construction method.
Brief description of the drawings
The floor heating pipe that Fig. 1 is the present invention takes fluting form to climb over wall bottom with the use of floor heating pipe Special bending pipe fitting
Waterproof beam structural representation,
In figure:Original cast-in-situ floor 1, original ground screed-coat 2, waterproof beam 3, leak stopping bar 4, sloping layer 5, EP waterproof rolls
6th, floor heating pipe 7, floor heating pipe bend pipe accessory 8, ground floor 9, wall 10.
Embodiment
Below in conjunction with the accompanying drawing in the embodiment of the present invention, the technical scheme in the embodiment of the present invention is carried out clear, complete
Site preparation is described, it is clear that described embodiment is only a part of embodiment of the invention, rather than whole embodiments.It is based on
Embodiment in the present invention, the every other embodiment that those of ordinary skill in the art are obtained belongs to what the present invention was protected
Scope.
As shown in figure 1, a kind of described by the present embodiment has the waterproof construction method on the ground of floor heating, including following step
Suddenly:
1) carry out Construction Quality to original ground screed-coat 2 to survey, be not inconsistent in maintenance original ground screed-coat 2 thoroughly
Build the place for building quality requirement jointly,
2) floor-dust of cleaning original ground screed-coat 2, right angle joint to metope and original ground screed-coat 2 and
Original ground screed-coat 2 does height and width at least 20mm leak stopping bar 4, and leak stopping with sewer pipe junction using leak stopping king
The longitudinal section of bar 4 is the arcuate shape that outside is less than inner side,
3) waterproofing agent is added to look for slope and levelling formation sloping layer 5 to floor drain direction using pea gravel concreten, with smashing with light and support
Shield, sloping layer 5 and metope right angle joint do same step 2 using leak stopping king) in as leak stopping bar 4,
4) Central-South formaldehydeless 901 glue spice is added to roll up EP waterproofs as cable laying operation binding agent using No. 325 striaght cements
Material 6 is laid on sloping layer 5, and EP waterproof rolls 6 turn to few 100mm on corner and root of pipeline nature,
5) criticized once again on the surface of EP waterproof rolls 6 and scrape step 4) in binding agent to all covering EP waterproof rolls 6, support water
48h, ne-leakage confirms that examination passes through,
6) floor heating pipe 7 takes fluting form to use cooperatively the waterproof beam 3 that floor heating pipe bend pipe accessory 8 climbs over the bottom of wall 10,
In the surface concreting of EP waterproof rolls 6 and the covering formation ground floor 9 of floor heating pipe 7,
7) cross-notching walks the progress leak stopping king closure of EP waterproof rolls 6 and repairing of tube damage,
8) water 24h is supported once again, and ne-leakage confirms that examination passes through.
The situation of construction quality requirement is not met in the original ground screed-coat 2 includes hollowing and cracking.
The original ground screed-coat 2 and the root that sewer pipe junction is sewer pipe.
The thickness of sloping layer 5 is 50mm thick, and thinnest part is 20mm thick, and the waterproofing agent is that Zhejiang University seeks scholar's board 2000
Type.
The step 1) in original ground screed-coat 2 be located on original cast-in-situ floor 1,
The step 3) in downcomer if any displacement, first blocked at downcomer displacement with leak stopping king.
The step 4) in pea gravel concreten intensity be C20.
The step 4) in EP waterproof rolls 6 overlap width >=10mm.
The step 6) in waterproof beam 3 be connected with original cast-in-situ floor 1.
Constructing operation of the present invention is simple, cost is low, and good water-proof effect and time are permanent, effectively prevent existing construction method
The mode that middle floor heating pipe 7 descended or burrowed to destroy waterproof beam 3 from threshold stone crosses the leak being likely to result in, and can be applied particularly to defend
Between life, shower house, the heavier space of steam such as kitchen and balcony carry out water-proofing treatment.
The present invention is not limited to above-mentioned preferred forms, and anyone can show that other are various under the enlightenment of the present invention
The product of form, however, make any change in its shape or structure, it is every that there is skill identical or similar to the present application
Art scheme, is within the scope of the present invention.
Claims (8)
1. a kind of waterproof construction method on the ground for having a floor heating, it is characterised in that comprise the following steps:
1) carry out Construction Quality to original ground screed-coat (2) to survey, be not inconsistent in maintenance original ground screed-coat (2) thoroughly
Build the place for building quality requirement jointly,
2) original ground screed-coat (2) dust is cleared up, right angle joint to metope and original ground screed-coat (2) and primitively
Face screed-coat (2) does height and width at least 20mm leak stopping bar (4), and leak stopping bar with sewer pipe junction using leak stopping king
(4) longitudinal section is the arcuate shape that outside is less than inner side,
3) waterproofing agent is added to look for slope and levelling formation sloping layer (5) to floor drain direction using pea gravel concreten, with smashing with light and conserve,
Sloping layer (5) and metope right angle joint do same step 2 using leak stopping king) in as leak stopping bar (4),
4) add Central-South formaldehydeless 901 glue spice as cable laying operation binding agent by EP waterproof rolls (6) using No. 325 striaght cements
It is laid on sloping layer (5), EP waterproof rolls (6) turn to few 100mm on corner and root of pipeline nature,
5) criticized once again on EP waterproof rolls (6) surface and scrape step 4) in binding agent to all covering EP waterproof rolls (6), support water
48h, ne-leakage confirms that examination passes through,
6) floor heating pipe (7) takes fluting form to use cooperatively the waterproof beam that floor heating pipe bend pipe accessory (8) climbs over wall (10) bottom
(3), in EP waterproof rolls (6) surface concreting and covering floor heating pipe (7) formation ground floor (9),
7) cross-notching walks EP waterproof rolls (6) the progress leak stopping king closure and repairing of tube damage,
8) water 24h is supported once again, and ne-leakage confirms that examination passes through.
2. the waterproof construction method on the ground according to claim 1 for having a floor heating, it is characterised in that the original ground is looked for
The situation of construction quality requirement is not met in flat bed (2) includes hollowing and cracking.
3. the waterproof construction method on the ground according to claim 1 for having a floor heating, it is characterised in that the original ground is looked for
Flat bed (2) and the root that sewer pipe junction is sewer pipe.
4. the waterproof construction method on the ground according to claim 1 for having a floor heating, it is characterised in that the sloping layer (5) is most
Thick for 50mm at thickness, thinnest part is 20mm thick, and the waterproofing agent is that Zhejiang University seeks the type of scholar's board 2000.
5. the waterproof construction method on the ground according to claim 1 for having a floor heating, it is characterised in that the step 1) in
Original ground screed-coat (2) is located on original cast-in-situ floor (1).
6. the waterproof construction method on the ground according to claim 1 for having a floor heating, it is characterised in that the step 4) in
Pea gravel concreten intensity is C20.
7. the waterproof construction method on the ground according to claim 1 for having a floor heating, it is characterised in that the step 4) in EP
Overlap width >=10mm of waterproof roll (6).
8. the waterproof construction method on the ground according to claim 5 for having a floor heating, it is characterised in that the step 6) in
Waterproof beam (3) is connected with original cast-in-situ floor (1).
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201710449067.7A CN107152089A (en) | 2017-06-14 | 2017-06-14 | A kind of waterproof construction method on the ground for having a floor heating |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201710449067.7A CN107152089A (en) | 2017-06-14 | 2017-06-14 | A kind of waterproof construction method on the ground for having a floor heating |
Publications (1)
Publication Number | Publication Date |
---|---|
CN107152089A true CN107152089A (en) | 2017-09-12 |
Family
ID=59795623
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201710449067.7A Pending CN107152089A (en) | 2017-06-14 | 2017-06-14 | A kind of waterproof construction method on the ground for having a floor heating |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN107152089A (en) |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN108532951A (en) * | 2018-04-20 | 2018-09-14 | 宁波大泽天成云空间设计有限公司 | A kind of waterproof technology installed in floor heating shower house |
CN110409632A (en) * | 2019-07-03 | 2019-11-05 | 广州市艺鸿装饰工程有限公司 | A kind of balcony waterproof technology |
Citations (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN103790264A (en) * | 2014-03-03 | 2014-05-14 | 江苏省苏中建设集团股份有限公司 | Construction method for seepproof screen of low-temperature hot water radiant heating floor toilet |
CN204850903U (en) * | 2015-07-30 | 2015-12-09 | 浙江银建装饰工程有限公司 | Waterproof node structure warms up bathroom |
CN205077752U (en) * | 2015-09-24 | 2016-03-09 | 中国建筑第八工程局有限公司 | Roofing flashing waterproofing membrane of department brick wall protection architecture |
CN205747096U (en) * | 2016-05-11 | 2016-11-30 | 杭州铭成装饰工程有限公司 | There is the separating dry space from moist space district of floor heating pipe |
CN205876046U (en) * | 2016-07-26 | 2017-01-11 | 德才装饰股份有限公司 | Bathroom threshold stone waterproof construction |
CN206220272U (en) * | 2016-09-27 | 2017-06-06 | 尚层装饰(北京)有限公司 | Ground hot water lays heating toilet doorway sealing damp proof insulation construction |
-
2017
- 2017-06-14 CN CN201710449067.7A patent/CN107152089A/en active Pending
Patent Citations (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN103790264A (en) * | 2014-03-03 | 2014-05-14 | 江苏省苏中建设集团股份有限公司 | Construction method for seepproof screen of low-temperature hot water radiant heating floor toilet |
CN204850903U (en) * | 2015-07-30 | 2015-12-09 | 浙江银建装饰工程有限公司 | Waterproof node structure warms up bathroom |
CN205077752U (en) * | 2015-09-24 | 2016-03-09 | 中国建筑第八工程局有限公司 | Roofing flashing waterproofing membrane of department brick wall protection architecture |
CN205747096U (en) * | 2016-05-11 | 2016-11-30 | 杭州铭成装饰工程有限公司 | There is the separating dry space from moist space district of floor heating pipe |
CN205876046U (en) * | 2016-07-26 | 2017-01-11 | 德才装饰股份有限公司 | Bathroom threshold stone waterproof construction |
CN206220272U (en) * | 2016-09-27 | 2017-06-06 | 尚层装饰(北京)有限公司 | Ground hot water lays heating toilet doorway sealing damp proof insulation construction |
Non-Patent Citations (3)
Title |
---|
胡仕伟: "《住宅全装修产品的构成及互联网销售模式》", 31 December 2015, 浙江大学出版社 * |
胡伦坚: "《建筑工程施工工艺手册 中册 装饰工程施工工艺》", 31 August 2007, 机械工业出版社 * |
范秋雨: "《建筑工地实用技术问答》", 30 April 2003, 中国建筑工业出版社 * |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN108532951A (en) * | 2018-04-20 | 2018-09-14 | 宁波大泽天成云空间设计有限公司 | A kind of waterproof technology installed in floor heating shower house |
CN110409632A (en) * | 2019-07-03 | 2019-11-05 | 广州市艺鸿装饰工程有限公司 | A kind of balcony waterproof technology |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN203462722U (en) | Floor water-proof structure of bathroom paved with floor heating equipment | |
CN104358305B (en) | A kind of cyclone, water drainage riser connecting piece of caisson type washroom | |
CN107152089A (en) | A kind of waterproof construction method on the ground for having a floor heating | |
CN102563741B (en) | Method for paving heating carbon fiber composite electro-thermal materials laid under cement screed-coat | |
CN108678029B (en) | Water-rich land area basement water-proof and drainage construction method for river-facing hills | |
CN108867850A (en) | A kind of prefabricated building and its construction method | |
CN103321393B (en) | Plastering on inner walls construction method | |
CN112211372A (en) | Anti-cracking structure of integrated indoor heat-insulation sound-insulation ground and construction method thereof | |
CN104695706B (en) | AAC building block freely loads wall construction | |
CN206220272U (en) | Ground hot water lays heating toilet doorway sealing damp proof insulation construction | |
CN108532951A (en) | A kind of waterproof technology installed in floor heating shower house | |
CN205476118U (en) | Hollow building block parapet | |
CN206529977U (en) | Compound water-proof thermal-insulation is slight high-strength foam concrete roofing | |
CN107869233A (en) | Reduce peculiar smell technique in a kind of wet area ground | |
JP2004344263A (en) | Collapsible sauna room | |
KR101507026B1 (en) | System for preventing and drainning condensation on exterior wall insulating structures | |
TW451019B (en) | Water-proof and damp-proof method for basement side wall | |
CN109138361A (en) | A kind of method of kitchen and bath's waterproof construction and backfill | |
CN107327118A (en) | A kind of house floor heating heat supply kitchen and toilet waterproof construction method | |
CN209040314U (en) | Integrated bathroom water-proof chassis on log cabin | |
CN204282499U (en) | A kind of cyclone, water drainage riser connecting piece of caisson type washroom | |
CN203782897U (en) | Excess water drainage and pressure reduction efforescence prevention structure for stone ground bonding layer construction | |
CN206655331U (en) | A kind of inorganic heat insulation mortar expansion joint for preventing wall from seeping water | |
CN203891153U (en) | Floor drain | |
CN209468871U (en) | A kind of floor heating water collecting and diversifying device seepage-proof structure and the ground heating system including it |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
RJ01 | Rejection of invention patent application after publication | ||
RJ01 | Rejection of invention patent application after publication |
Application publication date: 20170912 |