CN107143354A - Subway station side wall self-propelled integrated hydraulic formwork jumbo construction method - Google Patents

Subway station side wall self-propelled integrated hydraulic formwork jumbo construction method Download PDF

Info

Publication number
CN107143354A
CN107143354A CN201710432763.7A CN201710432763A CN107143354A CN 107143354 A CN107143354 A CN 107143354A CN 201710432763 A CN201710432763 A CN 201710432763A CN 107143354 A CN107143354 A CN 107143354A
Authority
CN
China
Prior art keywords
formwork jumbo
template
side wall
formwork
construction
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201710432763.7A
Other languages
Chinese (zh)
Inventor
苏春生
林羽
梁朋刚
何十美
汤振亚
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Dianchi College of Yunnan University
Fifth Engineering Co Ltd of China Railway Construction Bridge Engineering Bureau Group Co Ltd
Original Assignee
Dianchi College of Yunnan University
Fifth Engineering Co Ltd of China Railway Construction Bridge Engineering Bureau Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Dianchi College of Yunnan University, Fifth Engineering Co Ltd of China Railway Construction Bridge Engineering Bureau Group Co Ltd filed Critical Dianchi College of Yunnan University
Priority to CN201710432763.7A priority Critical patent/CN107143354A/en
Publication of CN107143354A publication Critical patent/CN107143354A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/04Lining with building materials
    • E21D11/10Lining with building materials with concrete cast in situ; Shuttering also lost shutterings, e.g. made of blocks, of metal plates or other equipment adapted therefor
    • E21D11/102Removable shuttering; Bearing or supporting devices therefor

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Structural Engineering (AREA)
  • Mining & Mineral Resources (AREA)
  • Civil Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Geology (AREA)
  • Lining And Supports For Tunnels (AREA)

Abstract

The invention discloses subway station side wall self-propelled integrated hydraulic formwork jumbo construction method, following construction procedure is specifically included:Preparation of construction;Installation of embedded parts;Formwork jumbo track laying;Formwork jumbo is assembled;Template Location;Chassis is reinforced;Side wall concrete is poured;Template is stripped;Spud carriage shifting;Template is cleared up.Compared with prior art, the present invention is compared with conventional art, and technique is simple, easy to use, it is adaptable to relatively large station straightway continuous productive process;The present invention use bulk steel form, reinforcement measure in place after, Stability Analysis of Structures, non-explosive mould, run mould, it is safe, overall construction quality be easy to ensure;Energy-conserving and environment-protective of the present invention, construction speed are fast, efficiency high, using do mechanization operation, labour's less investment, are lost small, repeat utilization rate high.

Description

Subway station side wall self-propelled integrated hydraulic formwork jumbo construction method
Technical field
It is subway station side wall self-propelled integrated hydraulic specifically the present invention relates to subway engineering technical field of construction Formwork jumbo construction method.
Background technology
Using steel pipe frame country's subway engineering falsework at present more(Or bowl buckle frame)The form of+plank sheathing;Steel pipe frame Set up a large amount of manpowers of needs, material usage is also than larger, and peace tears that the cycle is longer open, and need during setting up the details of control compared with Many, setting up quality should not ensure, there is larger security risk on quality and personnel;Thus use conventional art, safety, The need for quality, cost, management, human input everyway are difficult in adapt to market.
The content of the invention
It is an object of the invention to provide subway station side wall self-propelled integrated hydraulic formwork jumbo construction method, the present invention Compared with conventional art, technique is simple, easy to use, it is adaptable to relatively large station straightway continuous productive process;Energy-saving ring of the present invention Protect, construction speed is fast, efficiency high, using do mechanization operation, small, repeatable utilization rate height is lost in labour's less investment.
The present invention is achieved through the following technical solutions:Subway station side wall self-propelled integrated hydraulic formwork jumbo construction party Method, specifically includes following construction procedure:
Step S1:Preparation of construction;
Step S2:Installation of embedded parts;
Step S3:Formwork jumbo track laying;Specifically refer to, first the accurate location of measurement and positioning formwork jumbo track;It is to be measured After the completion of amount, formwork jumbo track installation is carried out;
Step S4:Formwork jumbo is assembled;The formwork jumbo includes template main part, the connection wire rod being connected with template main part and liquid Press jack and circuit and oil pipe on template main part;The template main part includes chassis, installed in chassis bottom Running gear, the upper skeleton installed in chassis upper, the template main beam for connecting upper skeleton and template and for propping up That supports shores brace;
Step S5:Template Location;Specifically include following construction procedure:
Step S51:The brace of shoring of formwork jumbo bottom is reinforced;
Step S52:Template bottom control snap the line is clung on concrete surface;
Step S53:The horizontal anchor bar of formboard fastening bottom;
Step S54:Accurate adjustment is carried out to template;
Step S55:Install and the connection wire rod between formboard fastening and formwork jumbo;
Step S56:The girt at brace and base angle is shored in secondary fastening;
Step S57:Template position is checked, each component tightness is checked, Template Location, formwork erection is completed;
Step S6:Formwork jumbo is reinforced;
Step S7:Side wall concrete is poured;
Step S8:Template is stripped;
Step S9:Formwork jumbo is shifted;Specifically include following construction procedure:
Step S91:Traveling steel rail is installed on the circuit planned to implement, after the completion of previous storehouse wall form removal, brace reinforcing is shored in dismounting Measure, using jackscrew device by formwork jumbo integral raising;
Step S92:Formwork jumbo walking is set to arrive specified location by motor driving;The motor is attached with running gear;
Step S93:Using jacking apparatus reduction formwork jumbo height, formwork jumbo supporting leg is driven to be located on rail;
Step S94:Formwork jumbo afterbody sets counterweight;
Step S95:It is should determine that before formwork jumbo walking around formwork jumbo without other staff and barrier;
Step S96:Formwork jumbo movable motor is preferably point operation control;
Step S10:Template is cleared up, and completes this work surface construction;Chassis runs to subsequent work face;Template is cleared up and brushes the demoulding Agent, repeats the construction procedures such as Template Location, until all construction is completed working face.
Operation principle:Pin-connected panel type steel skeleton is connected using flange;Hydraulic pressure with single action and linkage dual-use function is installed Jack, Fully-mechanized formwork erection and the form removal of bulk steel form are realized by jack;Pre-buried anti-floating anchorage device, support earth anchor And girt, formwork jumbo is fixed by built-in fitting, support leading screw and anti-floating pull bar, multiple stress ensures to reinforce The stabilization of system;Early buy flat panel form pallet bottom and roller, track and electric car running gear are installed, realize the fast of formwork jumbo Speed is mobile, quick peace is torn open, realizes the streamlined mechanical work of subway station wall.
Further, in order to preferably realize the present invention, the step S4 is specifically referred to:Using getting on, get off, first stand The order of rear pattern plate carries out formwork jumbo assembling;Rigging chassis lower running system and chassis, then install bone first Frame, then installation form girder, last installation form, formwork jumbo main part install connection wire rod and hydraulic jack after being completed Top, finally installs circuit and oil pipe.
Further, in order to preferably realize the present invention, the step S6 specifically includes following construction procedure:
Step S61:Formwork jumbo is located in orbit;
Step S62:Brace lower end will be shored to support on mounted counterforce device;
Step S63:After template is in place, installation form bottom level pull bar fastening bolt carries out template debugging;
Step S64:After template debugging is finished, formboard fastening bottom level pull bar and brace is shored successively;
Step S65:Anti-floating system is installed, formwork jumbo is completed and reinforces.
Further, in order to preferably realize the present invention, the step S7 is specifically referred to:
Step S71:Check mold plate verticality, formwork jumbo reinforcement measure;Determine that chassis is reinforced and template silk before concreting Bar is all tightened, it is to avoid stress is inadequate.
Step S72:Side wall concrete placement layer by layer.
Further, in order to preferably realize the present invention, the step S72, which specifically refers to pour every time, to be highly not more than Speed of perfusion is not more than 1.0m/h in 50cm, short transverse;When structural stratification is segmented, concrete single pours height and is no more than 5m;The height of drop that concrete departs from don't be after pipe is not more than 2m;Formwork jumbo leading portion and rear end concrete difference in height are not more than 60cm。
Further, in order to preferably realize the present invention, the step S8 specifically includes following construction procedure:
Step S81:Remove plug mould;
Step S82:Release girt bolt;
Step S83:Release or form removal and formwork jumbo between connection wire rod one end;It is mixed that operation template jack departs from side form Solidifying soil surface.
Further, in order to preferably realize the present invention, the step S83 is specifically referred to:Can not be disposably strong during the demoulding The row demoulding, it is necessary to point be stripped several times, and must point both sides intersect the demoulding twice.It is effective avoid because active force is excessive and to template Or concrete surface is damaged.
Further, in order to preferably realize the present invention, the step S9 is specifically referred to:Row is installed on the circuit planned to implement Rail is walked, after the completion of previous storehouse wall form removal, brace reinforcement measure is shored in dismounting, is integrally lifted formwork jumbo with jackscrew device It is high;Formwork jumbo walking is set to arrive specified location by motor driving;The motor is attached with running gear;Dropped with jacking apparatus Low formwork jumbo height, is that formwork jumbo supporting leg is located on rail;When formwork jumbo is shifted, set and match somebody with somebody in formwork jumbo afterbody Weight;Determined before formwork jumbo walking around formwork jumbo without other staff and barrier;Formwork jumbo movable motor is used Point operation control.
Further, in order to preferably realize the present invention, in work progress, Site quality control measure and safety are carried out Control measure.
The present invention compared with prior art, with advantages below and beneficial effect:
(1)The present invention is compared with conventional art, and technique is simple, easy to use, it is adaptable to relatively large station straightway continuous productive process;
(2)The present invention use bulk steel form, reinforcement measure in place after, Stability Analysis of Structures, non-explosive mould, run mould, it is safe, always Body construction quality is easy to ensure;
(3)Energy-conserving and environment-protective of the present invention, construction speed are fast, efficiency high, using do mechanization operation, labour's less investment, be lost it is small, can High recycling rate.
Brief description of the drawings
Fig. 1 is construction process figure of the invention.
Embodiment
Embodiments of the invention are described below in detail, the example of the embodiment is shown in the drawings, wherein from beginning to end Same or similar label represents same or similar element or the element with same or like function.Below with reference to attached The embodiment of figure description is exemplary, it is intended to for explaining the present invention, and be not considered as limiting the invention.
In the description of the invention, it is to be understood that term " " center ", " longitudinal direction ", " transverse direction ", " length ", " width ", " thickness ", " on ", " under ", "front", "rear", "left", "right", " vertical ", " level ", " top ", " bottom " " interior ", " outer ", " up time The orientation or position relationship of the instruction such as pin ", " counterclockwise " are, based on orientation shown in the drawings or position relationship, to be for only for ease of The description present invention and simplified description, rather than indicate or imply that the device or element of meaning must have specific orientation, Yi Te Fixed azimuth configuration and operation, therefore be not considered as limiting the invention.
In the present invention, unless otherwise clearly defined and limited, term " installation ", " connected ", " connection ", " fixation " etc. Term should be interpreted broadly, for example, it may be being fixedly connected or being detachably connected, or be integrally connected;It can be machine Tool is connected or electrically connected;Can be joined directly together, can also be indirectly connected to by intermediary, can be two members Connection inside part.For the ordinary skill in the art, above-mentioned term can be understood in this hair as the case may be Concrete meaning in bright.
The present invention is described in further detail with reference to embodiment, but the implementation of the present invention is not limited to this.
Embodiment 1:
The present embodiment does further optimization on the basis of above-described embodiment, as shown in figure 1, subway station side wall self-propelled is overall Hydraulic template trolley construction method, specifically includes following construction procedure:
Step S1:Preparation of construction;
Step S2:Installation of embedded parts;
Step S3:Formwork jumbo track laying;Specifically refer to, first the accurate location of measurement and positioning formwork jumbo track;It is to be measured After the completion of amount, formwork jumbo track installation is carried out;
Step S4:Formwork jumbo is assembled;The formwork jumbo includes template main part, the connection wire rod being connected with template main part and liquid Press jack and circuit and oil pipe on template main part;The template main part includes chassis, installed in chassis bottom Running gear, the upper skeleton installed in chassis upper, the template main beam for connecting upper skeleton and template and for propping up That supports shores brace;
Step S5:Template Location;Specifically include following construction procedure:
Step S51:The brace of shoring of formwork jumbo bottom is reinforced;
Step S52:Template bottom control snap the line is clung on concrete surface;
Step S53:The horizontal anchor bar of formboard fastening bottom;
Step S54:Accurate adjustment is carried out to template;
Step S55:Install and the connection wire rod between formboard fastening and formwork jumbo;
Step S56:The girt at brace and base angle is shored in secondary fastening;
Step S57:Template position is checked, each component tightness is checked, Template Location, formwork erection is completed;
Step S6:Formwork jumbo is reinforced;
Step S7:Side wall concrete is poured;
Step S8:Template is stripped;
Step S9:Formwork jumbo is shifted;Specifically include following construction procedure:
Step S91:Traveling steel rail is installed on the circuit planned to implement, after the completion of previous storehouse wall form removal, brace reinforcing is shored in dismounting Measure, using jackscrew device by formwork jumbo integral raising.
Step S92:Formwork jumbo walking is set to arrive specified location by motor driving;The motor is connected with running gear Connect;
Step S93:Using jacking apparatus reduction formwork jumbo height, formwork jumbo supporting leg is driven to be located on rail;
Step S94:Formwork jumbo afterbody sets counterweight;
Step S95:It is should determine that before formwork jumbo walking around formwork jumbo without other staff and barrier;
Step S96:Formwork jumbo movable motor is preferably point operation control;
Step S10:Template is cleared up, and completes this work surface construction;Chassis runs to subsequent work face;Template is cleared up and brushes the demoulding Agent, repeats the construction procedures such as Template Location, until all construction is completed working face.
It should be noted that by above-mentioned improvement, pin-connected panel type steel skeleton is connected using flange;Installing has single action and connection The hydraulic jack of dynamic dual-use function, Fully-mechanized formwork erection and the form removal of bulk steel form are realized by jack;Pre-buried anti-floating Anchorage device, support earth anchor and girt, are consolidated by built-in fitting, support leading screw and anti-floating pull bar to formwork jumbo Fixed, multiple stress ensures the stabilization of reinforcement system;Early buy flat panel form pallet bottom and roller, track and electric car Running System are installed System, realizes that quick mobile, the quick peace of formwork jumbo is torn open, realizes the streamlined mechanical work of subway station wall.
The other parts of the present embodiment are same as the previously described embodiments, therefore repeat no more.
Embodiment 2:
The present embodiment does further optimization on the basis of above-described embodiment, as shown in figure 1, subway station side wall self-propelled is overall Hydraulic template trolley construction method, specifically includes following construction procedure:
Step S1:Preparation of construction.
Step S2:Installation of embedded parts.
Step S3:Formwork jumbo track laying.Specifically refer to, first the accurate location of measurement and positioning formwork jumbo track. After the completion of to be measured, formwork jumbo track installation is carried out.
Before the formwork jumbo is installed, bottom plate is cleaned out, the accurate location of measurement and positioning trolley track, handle track Basal plane, attachment rail, track both sides are fixed with rivet.
Step S4:Formwork jumbo is assembled.
The formwork jumbo includes template main part, the connection wire rod and hydraulic jack that are connected with template main part, Yi Jian Circuit and oil pipe on template main part.
The template main part include chassis, the running gear installed in chassis bottom, the upper skeleton installed in chassis upper, For connecting the template main beam and template of upper skeleton and shoring brace for support.
Side wall formwork jumbo is installed and got on, get off, the order assembling of first stand rear pattern plate, first assembling trolley lower running System and chassis, then install upper skeleton, then installation form girder, last installation form, after formwork jumbo main part is completed Connection wire rod and hydraulic jack are installed, circuit and oil pipe are finally installed.
Step S5:Template Location.Specifically refer to:The formwork jumbo being completed is moved, after chassis is moved into place, The brace of shoring of pallet bottom is reinforced first.
Template bottom is compareed into snap the line by the level jack between template and chassis to cling on concrete surface, template Top keeps vertical with bottom substantially.
The horizontal anchor bar of formboard fastening bottom.
Accurate adjustment is carried out to template, it is ensured that template leading portion and micro- end and wall inclination position consistency, template are vertically vertical.Install Connection wire rod between formboard fastening and chassis, make between chassis and template turn into be rigidly connected.
The girt at brace and base angle is shored in secondary fastening, forms rigid system.
Template position is checked, each component tightness is checked.
It is finely adjusted when local problematic, completes template formwork erection.
The new last panel front that is used in used first sprays one layer of thin oil film(Match ratio is new diesel oil:New machine oil=7: 3), after oil film is air-dried, in uniform brushing aqueous demoulding agent, brush should not be mended in time for wiped clean black dirt after rain drop erosion.Often Should the releasing agent of brushing in time after the secondary template demoulding.
5cm sponge strip should be pasted before matched moulds in new-old concrete joint part, to prevent the foot of a wall spillage.
During model sheetinstallat, die head should set certain lead, typically preferably 5cm.
The step S5 specifically includes following construction procedure:
Step S51:The brace of shoring of formwork jumbo bottom is reinforced.
Step S52:Template bottom control snap the line is clung on concrete surface.
Step S53:The horizontal anchor bar of formboard fastening bottom.
Step S54:Accurate adjustment is carried out to template.
Step S55:Install and the connection wire rod between formboard fastening and formwork jumbo.
Step S56:The girt at brace and base angle is shored in secondary fastening.
Step S57:Template position is checked, each component tightness is checked, Template Location, formwork erection is completed.
Step S6:Formwork jumbo is reinforced.
Step S7:Side wall concrete is poured.
Step S8:Template is stripped.
Step S9:Formwork jumbo is shifted.Specifically include following construction procedure:
Step S91:Traveling steel rail is installed on the circuit planned to implement, after the completion of previous storehouse wall form removal, brace reinforcing is shored in dismounting Measure, using jackscrew device by formwork jumbo integral raising.
Step S92:Formwork jumbo walking is set to arrive specified location by motor driving.The motor is connected with running gear Connect.
Step S93:Using jacking apparatus reduction formwork jumbo height, formwork jumbo supporting leg is driven to be located on rail.
Step S94:Formwork jumbo afterbody sets counterweight.
Step S95:It is should determine that before formwork jumbo walking around formwork jumbo without other staff and barrier.
Step S96:Formwork jumbo movable motor is preferably point operation control.
Step S10:Template is cleared up, and completes this work surface construction;Chassis runs to subsequent work face;Template is cleared up and brushed Releasing agent, repeats the construction procedures such as Template Location, until all construction is completed working face.Chassis be moved to after new position, it is necessary to Template surface is cleared up, the attachments such as concrete slurry are understood, in punching block surface smear form oil, prepares coagulation next time Soil is poured.
The other parts of the present embodiment are same as the previously described embodiments, therefore repeat no more.
Embodiment 3:
The present embodiment does further optimization on the basis of above-described embodiment, as shown in figure 1, the step S6 specifically include it is following Construction procedure:
Step S61:Formwork jumbo is located in orbit;
Step S62:Brace lower end will be shored to support on mounted counterforce device;
Step S63:After template is in place, installation form bottom level pull bar fastening bolt carries out template debugging;
Step S64:After template debugging is finished, formboard fastening bottom level pull bar and brace is shored successively;
Step S65:Anti-floating system is installed, formwork jumbo is completed and reinforces..
It should be noted that by above-mentioned improvement, chassis is run to after specified location, chassis is steadily sat by steel leg Fall in orbit;Brace lower end will be shored to support on mounted counterforce device(Tighten, be difficult stress excessive, it is to avoid Steel pipe is caused to tilt);After template is in place, installation form bottom level pull bar fastening bolt;After template debugging is finished, fasten first Template bottom level pull bar;Then tighten and shore brace;Anti-floating system is installed, chassis is completed and reinforces.
The other parts of the present embodiment are same as the previously described embodiments, therefore repeat no more.
Embodiment 4:
The present embodiment does further optimization, the points for attention that specially formwork jumbo is reinforced on the basis of above-described embodiment:
Casting concrete front template pallet bottom, which shores brace, must support firm.Brace must be tightened fully, and the strong point is pre-buried Part must have enough rigidity and intensity, and all screw mandrels and built-in fitting are made up of by Force system while stress shaped steel etc..
Anti-floating counter-force can be provided using anti-floating pull bar or anti-floating cucurbit etc., anti-floating is trapezoidal there must be enough rigidity and strong Degree, must fully stress, and still with triumphant auspicious modulability in concreting process before casting concrete.
Track stress is put after chassis larger, attachment rail money must clear up track bottom extrusion, it is ensured that base is smooth, without part It is raised or sunken, can make track uniform stressed, track extrusion must have enough intensity and bearing capacity, it is ensured that concrete is poured It is not in broken during building and sedimentation.
The pre-buried girt when pouring bottom plate or middle plate, pull bar answers fixation, can bear the pulling force of one end, pull bar With enough intensity, formwork reinforcement bottom rigidity ensure that.
The other parts of the present embodiment are same as the previously described embodiments, therefore repeat no more.
Embodiment 5:
In work progress, Site quality control measure and safety control measures are carried out.
It should be noted that quality control method is specifically included:
A, console Vehicle Processing precision, all bolts hole are necessary for mechanism hole.
B, chassis welding quality must are fulfilled for welding conditions requirement.
Connecting bolt should be tightened up at least twice after C, chassis assembling, it is ensured that the stability of trolley structure.
D, trolley track need to carry out track basal plane processing before installing, it is ensured that track extrusion has enough strength and stiffness, and Meet the requirement of linearity and perpendicularity.
E, chassis are reinforced and should reinforce and reinforce in order, and all primary structure members must be tightened up before concreting.
Close inspection template flatness is answered in F, chassis reinforcing process, and ensures each shop uniform force.
G, chassis are before use, debugging, experiment hydraulic system, electrical system and running gear, it is ensured that each part can be normal Use.
Safety assurance measures are specifically included:Site safety is managed and side wall template construction Safety Technical Management.Side wall template Construction safety technical management is specifically referred to:
(1), in formwork jumbo walking process it should be noted that the safety of periphery personnel.
(2), it is regular to formwork jumbo maintain, hydraulic system, electrical system and running gear are inspected periodically, it is ensured that The security of equipment.
(3), formwork jumbo walking when use Manual Mode, control the speed of travel.
(4), construction operation when to have abundance light, safety management and workmen will keep a close eye on operation overall process.
(5), want rail safety situation after close inspection, it is ensured that track Shunzi, firmly install.
The other parts of the present embodiment are same as the previously described embodiments, therefore repeat no more.
Embodiment 6:
Hydraulic system, electrical system, running gear and the motor being connected with running gear in the present invention, are existing knot Structure, is commercially bought, and is installed and debugged;Therefore its internal structure is not repeated.
It is described above, be only presently preferred embodiments of the present invention, any formal limitation not done to the present invention, it is every according to According to the present invention technical spirit above example is made any simple modification, equivalent variations, each fall within the present invention protection Within the scope of.

Claims (9)

1. subway station side wall self-propelled integrated hydraulic formwork jumbo construction method, it is characterised in that:Specifically include following construction Step:
Step S1:Preparation of construction;
Step S2:Installation of embedded parts;
Step S3:Formwork jumbo track laying;Specifically refer to, first the accurate location of measurement and positioning formwork jumbo track;It is to be measured After the completion of amount, formwork jumbo track installation is carried out;
Step S4:Formwork jumbo is assembled;The formwork jumbo includes template main part, the connection wire rod being connected with template main part and liquid Press jack and circuit and oil pipe on template main part;The template main part includes chassis, installed in chassis bottom Running gear, the upper skeleton installed in chassis upper, the template main beam for connecting upper skeleton and template and for propping up That supports shores brace;
Step S5:Template Location;Specifically include following construction procedure:
Step S51:The brace of shoring of formwork jumbo bottom is reinforced;
Step S52:Template bottom control snap the line is clung on concrete surface;
Step S53:The horizontal anchor bar of formboard fastening bottom;
Step S54:Accurate adjustment is carried out to template;
Step S55:Install and the connection wire rod between formboard fastening and formwork jumbo;
Step S56:The girt at brace and base angle is shored in secondary fastening;
Step S57:Template position is checked, each component tightness is checked, Template Location, formwork erection is completed;
Step S6:Formwork jumbo is reinforced;
Step S7:Side wall concrete is poured;
Step S8:Template is stripped;
Step S9:Formwork jumbo is shifted;Specifically include following construction procedure:
Step S91:Traveling steel rail is installed on the circuit planned to implement, after the completion of previous storehouse wall form removal, brace reinforcing is shored in dismounting Measure, using jackscrew device by formwork jumbo integral raising;
Step S92:Formwork jumbo walking is set to arrive specified location by motor driving;The motor is attached with running gear;
Step S93:Using jacking apparatus reduction formwork jumbo height, formwork jumbo supporting leg is driven to be located on rail;
Step S94:Formwork jumbo afterbody sets counterweight;
Step S95:It is should determine that before formwork jumbo walking around formwork jumbo without other staff and barrier;
Step S96:Formwork jumbo movable motor is preferably point operation control;
Step S10:Template is cleared up, and completes this work surface construction;Chassis runs to subsequent work face;Template is cleared up and brushes the demoulding Agent, repeats the construction procedures such as Template Location, until all construction is completed working face.
2. subway station side wall self-propelled integrated hydraulic formwork jumbo construction method according to claim 1, it is characterised in that: The step S4 is specifically referred to:Using getting on, get off, the order of first stand rear pattern plate carries out formwork jumbo assembling;Mould is assembled first Pallet car lower running system and chassis, then install upper skeleton, then installation form girder, last installation form, formwork jumbo Main part installs connection wire rod and hydraulic jack after being completed, and finally installs circuit and oil pipe.
3. subway station side wall self-propelled integrated hydraulic formwork jumbo construction method according to claim 1, it is characterised in that: The step S6 specifically includes following construction procedure:
Step S61:Formwork jumbo is located in orbit;
Step S62:Brace lower end will be shored to support on mounted counterforce device;
Step S63:After template is in place, installation form bottom level pull bar fastening bolt carries out template debugging;
Step S64:After template debugging is finished, formboard fastening bottom level pull bar and brace is shored successively;
Step S65:Anti-floating system is installed, formwork jumbo is completed and reinforces.
4. subway station side wall self-propelled integrated hydraulic formwork jumbo construction method according to claim 1, it is characterised in that: The step S7 is specifically referred to:
Step S71:Check mold plate verticality, formwork jumbo reinforcement measure;
Step S72:Side wall concrete placement layer by layer.
5. subway station side wall self-propelled integrated hydraulic formwork jumbo construction method according to claim 3, it is characterised in that: The step S72 specifically refers to pour speed of perfusion in height no more than 50cm, short transverse every time and is not more than 1.0m/h;Structure During layer and section, concrete single pours height and is no more than 5m;The height of drop that concrete departs from don't be after pipe is not more than 2m;Template Chassis leading portion and rear end concrete difference in height are not more than 60cm.
6. subway station side wall self-propelled integrated hydraulic formwork jumbo construction method according to claim 1, it is characterised in that: The step S8 specifically includes following construction procedure:
Step S81:Remove plug mould;
Step S82:Release girt bolt;
Step S83:Release or form removal and formwork jumbo between connection wire rod one end;It is mixed that operation template jack departs from side form Solidifying soil surface.
7. subway station side wall self-propelled integrated hydraulic formwork jumbo construction method according to claim 6, it is characterised in that: The step S83 is specifically referred to:Can not disposable forced demoulding during the demoulding, it is necessary to point be stripped several times, and both sides must be divided twice Intersect the demoulding.
8. subway station side wall self-propelled integrated hydraulic formwork jumbo construction method according to claim 1, it is characterised in that: The step S9 is specifically referred to:Traveling steel rail is installed on the circuit planned to implement, after the completion of previous storehouse wall form removal, dismounting is shored tiltedly Bar reinforcement measure, with jackscrew device by formwork jumbo integral raising;Formwork jumbo walking is set to arrive specified location by motor driving;Institute Motor is stated to be attached with running gear;It is that formwork jumbo supporting leg is located rail with jacking apparatus reduction formwork jumbo height On;When formwork jumbo is shifted, counterweight is set in formwork jumbo afterbody;Determined before formwork jumbo walking around formwork jumbo without other Staff and barrier;Formwork jumbo movable motor uses point operation control.
9. according to any one of the claim 1-8 subway station side wall self-propelled integrated hydraulic formwork jumbo construction methods, its It is characterised by:In work progress, Site quality control measure and safety control measures are carried out.
CN201710432763.7A 2017-06-09 2017-06-09 Subway station side wall self-propelled integrated hydraulic formwork jumbo construction method Pending CN107143354A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710432763.7A CN107143354A (en) 2017-06-09 2017-06-09 Subway station side wall self-propelled integrated hydraulic formwork jumbo construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710432763.7A CN107143354A (en) 2017-06-09 2017-06-09 Subway station side wall self-propelled integrated hydraulic formwork jumbo construction method

Publications (1)

Publication Number Publication Date
CN107143354A true CN107143354A (en) 2017-09-08

Family

ID=59781305

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710432763.7A Pending CN107143354A (en) 2017-06-09 2017-06-09 Subway station side wall self-propelled integrated hydraulic formwork jumbo construction method

Country Status (1)

Country Link
CN (1) CN107143354A (en)

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2009186184A (en) * 2008-02-01 2009-08-20 Enzan Kobo:Kk Centre surveying method
CN103556817A (en) * 2013-11-14 2014-02-05 广州鑫桥建筑劳务有限公司 Side wall concrete construction method employing side wall trolley
CN103967050A (en) * 2014-01-29 2014-08-06 广州机施建设集团有限公司 Construction system of subway station
CN104153389A (en) * 2014-08-11 2014-11-19 中铁建大桥工程局集团第六工程有限公司 Construction method for prefabricated assembly type subway station

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2009186184A (en) * 2008-02-01 2009-08-20 Enzan Kobo:Kk Centre surveying method
CN103556817A (en) * 2013-11-14 2014-02-05 广州鑫桥建筑劳务有限公司 Side wall concrete construction method employing side wall trolley
CN103967050A (en) * 2014-01-29 2014-08-06 广州机施建设集团有限公司 Construction system of subway station
CN104153389A (en) * 2014-08-11 2014-11-19 中铁建大桥工程局集团第六工程有限公司 Construction method for prefabricated assembly type subway station

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
郑东升: "地下车站侧墙模板台车全自动流水化作业技术", 《国防交通工程与技术》 *

Similar Documents

Publication Publication Date Title
CN106677211B (en) Early-dismantling assembly type pipe gallery aluminum mould trolley system for integrally casting wall and top plate and construction method thereof
CN113463522B (en) Auxiliary device and method for bent cap construction
CN109137976A (en) Municipal administration synthesis pipe gallery hydraulic jumbo and its construction method
CN110396937A (en) The asynchronous construction of hollow thin-walled high pier binder pier beam
CN110410109A (en) A kind of construction of hangar tunnel lining cutting arch shifting formwork trolley and construction method
CN106088608B (en) A kind of slding form operation method of metro depot beam slab concrete structure
CN111455852A (en) Assembling method of movable formwork for bridge construction
CN104894954A (en) Overall mounting and constructing method of pier stud reinforcing steel bars of urban bridge
CN108755421A (en) Capping beam construction device and construction method
CN110184948A (en) A kind of Bridge beam construction method
CN112211113A (en) Cast-in-place construction method for large-span diamond-shaped bent cap of high pier
CN113152262A (en) Bridge single-column pier reinforcement construction method
CN110424268A (en) A kind of main bridge hollow pier structure construction technique
CN109869153A (en) The whole of rapid construction vertical shaft lining cutting promotes cantilever form device and construction method
CN104499706B (en) Hoistway formwork platform and construction method thereof
CN213951970U (en) Pier stud template
CN108677722A (en) Hollow High Pier with Thin Wall stub top section construction technology
CN106284989B (en) The sliding form bracing system of double track and complete construction method
CN110792038B (en) Self-propelled mold hanging tool and method for high-altitude cast-in-place of tie rod arch bridge beam
CN210370698U (en) Mould shifting trolley for shed tunnel lining arch construction
CN210061545U (en) Prefabricated T roof beam concrete placement platform truck
CN107143354A (en) Subway station side wall self-propelled integrated hydraulic formwork jumbo construction method
CN115030527B (en) Steel structure installation equipment for portal steel frame factory building
CN110080299A (en) A kind of shallow embedding mountain tunnel open-cut engineering method
CN107090772B (en) Construction method of side span cast-in-place beam bracket of extra-large cable-stayed bridge

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20170908

RJ01 Rejection of invention patent application after publication