CN107143064A - One kind interval steel pipe and combined concrete shear wall system - Google Patents

One kind interval steel pipe and combined concrete shear wall system Download PDF

Info

Publication number
CN107143064A
CN107143064A CN201710567206.6A CN201710567206A CN107143064A CN 107143064 A CN107143064 A CN 107143064A CN 201710567206 A CN201710567206 A CN 201710567206A CN 107143064 A CN107143064 A CN 107143064A
Authority
CN
China
Prior art keywords
steel pipe
shear wall
interval
wall system
lacing
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201710567206.6A
Other languages
Chinese (zh)
Inventor
陈明
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
SHANGHAI OPEN STEEL JOIST CO Ltd
Original Assignee
SHANGHAI OPEN STEEL JOIST CO Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by SHANGHAI OPEN STEEL JOIST CO Ltd filed Critical SHANGHAI OPEN STEEL JOIST CO Ltd
Priority to CN201710567206.6A priority Critical patent/CN107143064A/en
Publication of CN107143064A publication Critical patent/CN107143064A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B2/00Walls, e.g. partitions, for buildings; Wall construction with regard to insulation; Connections specially adapted to walls
    • E04B2/56Load-bearing walls of framework or pillarwork; Walls incorporating load-bearing elongated members
    • E04B2/58Load-bearing walls of framework or pillarwork; Walls incorporating load-bearing elongated members with elongated members of metal
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B2/00Walls, e.g. partitions, for buildings; Wall construction with regard to insulation; Connections specially adapted to walls
    • E04B2/56Load-bearing walls of framework or pillarwork; Walls incorporating load-bearing elongated members
    • E04B2/58Load-bearing walls of framework or pillarwork; Walls incorporating load-bearing elongated members with elongated members of metal
    • E04B2/60Load-bearing walls of framework or pillarwork; Walls incorporating load-bearing elongated members with elongated members of metal characterised by special cross-section of the elongated members

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Physics & Mathematics (AREA)
  • Electromagnetism (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Forms Removed On Construction Sites Or Auxiliary Members Thereof (AREA)

Abstract

The invention provides one kind interval steel pipe and combined concrete shear wall system, including the shear wall skeleton being made up of the steel pipe and the batten plate of lateral arrangement being vertically equally spaced, template is respectively arranged with along the both sides in shear wall skeleton extension direction;Wherein, batten plate is located between steel pipe and along the height bearing of trend spaced set of steel pipe;Wherein, the inner chamber of steel pipe is cast with grouting material.By the combination of steel pipe and batten plate, steel pipe arranged for interval is formed, is used between steel pipe and casting concrete is reproduced after template, form shear wall;Rectangular steel pipe arranged for interval so that floor beam, plate can be penetrated continuously at the position without steel pipe so that more preferably, building globality is stronger for flooring horizontal force.

Description

One kind interval steel pipe and combined concrete shear wall system
Technical field
It is specially a kind of interval steel pipe and combined concrete shear wall the present invention relates to building, civil engineering technical field System.
Background technology
At present, China proposes higher Compulsory Feature to house assembling.Although continuous steel pipe beam shear wall is Progressively popularization and application at home, but the steel using amount of steel pipe bundle is bigger than normal, such as 4 millimeter thicknesss of slab more as primary structure member redundancy Continuous steel pipe beam shear wall can reach 84 kilograms/square meter per square meter steel using amount.Although continuous steel pipe bundle shear wall scheme is built Building percentage of usable dwelling area has 5% or so increase, but comprehensive cost has more compared to the complete cast-in-place reinforced concrete shear wall of tradition and often put down 300 yuan to 500 yuan of rice.
In addition, continuous steel pipe bundle shear wall, has cut off floor arrangement of reinforcement, floor bar, which has arrived wall, to be disconnected, or Scene is welded with steel plate wall, reduces the continuity of floor.
The content of the invention
It is an object of the invention to provide one kind interval steel pipe and combined concrete shear wall system, principle is simple, makes Convenient, cost is low, easy construction, while making the modulus between batten plate and template mutually unify, further improves the assembling of wall And standardization.
To achieve the above object, interval steel pipe proposed by the present invention and combined concrete shear wall system, including by vertical The shear wall skeleton that the steel pipe and the batten plate of lateral arrangement being equally spaced are constituted, along the both sides point in shear wall skeleton extension direction Template is not provided with it;
Wherein, the batten plate is located between steel pipe and along the height bearing of trend spaced set of steel pipe;
Wherein, the inner chamber of the steel pipe is cast with grouting material.
Further, in the interval steel pipe with combined concrete shear wall system, being set in steel pipe top and bottom Have on continuous top connecting plate and bottom connecting plate, and top connecting plate and bottom connecting plate respectively with steel pipe opposite position It is provided with grout hole.
Further, in the interval steel pipe and combined concrete shear wall system, the batten plate includes be arrangeding in parallel Lacing I, lacing II, and between lacing I, lacing II be provided with reservation member.
Further, in the interval steel pipe and combined concrete shear wall system, the reservation member is hollow circuit cylinder The reserved column piece of type.
Further, in the interval steel pipe with being provided with interior in combined concrete shear wall system, in the reserved column piece Screw thread, and in being respectively equipped with bolt access aperture on the corresponding lacing I of reserved column piece bearing of trend, lacing II, the bolt is accessed The corresponding template in hole be provided with through hole, in bolt access aperture, through hole be provided with fastening bolt.
Further, in the interval steel pipe and combined concrete shear wall system, in the reserved column piece extension side Pick out reserved screw rod on to corresponding lacing I, lacing II respectively, the corresponding template of the reserved screw rod is provided with through hole, described Reserved screw rod accesses the through hole and is connected with a nut.
Further, in the interval steel pipe and combined concrete shear wall system, the steel pipe is hollow long strip type Rod member, the steel tube section is enclosed type section.
Further, in the interval steel pipe and combined concrete shear wall system, the enclosed type rectangular cross-section, Square is circular.
Further, in the interval steel pipe and combined concrete shear wall system, the template is aluminum alloy pattern plate, punching block Plate, plank sheathing or precast concrete form.
Compared with prior art, the beneficial effects of the invention are as follows:
1. by the continuous arranged for interval of steel pipe, steel pipe belongs to market conventional products, without steel construction processing factory additional customized, Fished pipe need to only be bought and carry out secondary operation.
2. setting up batten plate between steel pipe, metope is set to form entirety.Steel pipe spacing can be determined according to design so that wall size Flexibility greatly increase.
3. two free ends of steel pipe are respectively provided with connecting plate, and open up grout hole at position corresponding with steel pipe, it is easy to coagulation Soil is poured, while being also convenient for the wall connecting of levels.
4. steel pipe arranged for interval so that floor beam, plate can be penetrated continuously at the position without steel pipe, make flooring horizontal force more Good, the globality of building is stronger.
5. the template between steel pipe on wall, by the reservation member on batten plate, is joined directly together with template.Pass through cleverly chi Very little design so that the spacing of these reservation members meets the requirement of modulus, further improves wall assembling and standardization.
Brief description of the drawings
Fig. 1 is interval steel pipe and combined concrete shear wall system structure diagram in one embodiment of the invention;
Fig. 2 is joint steel pipe batten plate structural representation in one embodiment of the invention;
Fig. 3 is Fig. 2 top view;
Fig. 4 is model sheetinstallat structural representation in one embodiment of the invention.
Embodiment
The interval steel pipe of the present invention is carried out with combined concrete shear wall system below in conjunction with schematic diagram more detailed Description, which show the preferred embodiments of the present invention, it should be appreciated that those skilled in the art can change described here Invention, and still realize the advantageous effects of the present invention.Therefore, description below is appreciated that for those skilled in the art's It is widely known, and it is not intended as limitation of the present invention.
It is an object of the invention to provide a kind of new building shear walls design, manufacture and construction method --- an inter-species Every steel pipe and combined concrete shear wall system.The combined shear wall system of the present invention is a kind of beyond tradition steel pipe bundle shearing Wall, it is adaptable to the structure stress wall in assembling building, by the combination of steel pipe and batten plate, forms steel pipe arranged for interval, Used between steel pipe and casting concrete is reproduced after template, form shear wall;Rectangular steel pipe arranged for interval so that floor beam, plate exist Position without steel pipe can be penetrated continuously so that more preferably, building globality is stronger for flooring horizontal force.
Specifically, as shown in Figures 1 to 4, interval steel pipe proposed by the present invention and combined concrete shear wall system, including Steel pipe 1, batten plate 2, template 3, grout hole 5 etc..Wherein, steel pipe 1 is hollow long strip type rod member, and the section of steel pipe 1 is enclosed type section Face, such as rectangle, square or circular, it is therefore preferable to rectangular or square.Template 3 can use aluminum alloy pattern plate, steel form, plank sheathing Or precast concrete form, the template 3, which has, also serves as insulation, the effect of decoration.
As shown in figure 1, being the shear wall bone being made up of vertical spaced apart steel pipe 1 and the batten plate 2 being arranged laterally at a spacing Frame 100, template 3 is respectively arranged with along the both sides in the extension direction of shear wall skeleton 100.
Wherein, the interior intracavitary of steel pipe 1 is cast with grouting material, the spacing of steel pipe 1 can according to design it needs to be determined that so that wall chi Very little flexibility is greatly increased.Such as steel pipe width 200mm, and steel pipe clear spacing 300mm, you can 500mm is made a list Member, two units are exactly 1 meter, are not only convenient for design, and consider very reasonable from loading angle.Most of all, between steel pipe 1 Every arrangement so that floor beam, plate can be penetrated continuously at the position without steel pipe, make flooring horizontal force more preferably, the globality of building It is stronger.
Wherein, batten plate 2 is located between steel pipe 1 and along the height bearing of trend spaced set of steel pipe 1, and the spacing is generally 300~600mm, batten plate 2 is used to connect two adjacent steel pipes 1, so that metope forms entirety, is set on batten plate 2 There is reservation member 4.Directly template 3 can be arranged on shear wall skeleton 100 by the reservation member 4 of batten plate 2.Reservation member 4 is mixed Solidifying soil is stayed in wall after pouring, and can be used as connection when next step construction heat-insulating and decorative wall panels.By cleverly Size design so that the spacing of these reservation members 4 meets the requirement of modulus, further improves wall assembling and standardization.
Above-mentioned batten plate 2 includes lacing I21, the lacing II22 be arrangeding in parallel, and between lacing I21, lacing II22 Reservation member 4.The reservation member 4 is generally the reserved column piece of hollow cylinder shape.
For the ease of installation of the template 3 on shear wall skeleton 100, the structure of reserved column piece 4 can use following two Form:
Reserved column structure one:Internal thread is provided with reserved column piece 4, and in the corresponding lacing of the reserved bearing of trend of column piece 4 Bolt access aperture is respectively equipped with I21, lacing II22.Through hole is provided with the corresponding template 3 of bolt access aperture, in bolt access Fastening bolt 8 is provided with hole, through hole.Template 3 is arranged on shear wall skeleton 100 (as shown in Figure 4) by fastening bolt 8.
Reserved column structure two:Picked out respectively on the corresponding lacing I21 of the reserved bearing of trend of column piece 4, lacing II22 reserved Screw rod (not shown), is provided with through hole in the corresponding template of reserved screw rod, the through hole in the reserved screw rod access template 3, so Template 3 is arranged on shear wall skeleton 100 by a nut afterwards.
The top of steel pipe 1 and bottom are provided with continuous top connecting plate 6 and bottom connecting plate 7, and the He of top connecting plate 6 Grout hole 5 is provided with the opposite position of steel pipe 1 respectively on bottom connecting plate 7, is easy to pouring for the grouting materials such as concrete, simultaneously The wall of levels can also be easy to be connected.The opening of general grout hole 5 and the section of steel pipe 1 match.
In addition, the template 3 on the outside of shear wall skeleton can be installed before wall lifting on ground, in shear wall skeleton Side template 3 can successively be installed again after wall lifting, have more turnovers thereby using the template on the inside of shear wall skeleton Number of times, it is further cost-effective.
To sum up, in interval steel pipe and combined concrete shear wall system provided in an embodiment of the present invention, by steel pipe with The combination of batten plate, forms steel pipe arranged for interval, is used between steel pipe and casting concrete is reproduced after template, form shear wall;Square Shape steel pipe arranged for interval so that floor beam, plate can be penetrated continuously at the position without steel pipe so that flooring horizontal force more preferably, is built Build globality stronger.
The preferred embodiments of the present invention are above are only, any restriction effect is not played to the present invention.Belonging to any Those skilled in the art, in the range of technical scheme is not departed from, to the invention discloses technical scheme and Technology contents make the variation such as any type of equivalent substitution or modification, belong to the content without departing from technical scheme, still Belong within protection scope of the present invention.

Claims (9)

1. one kind interval steel pipe and combined concrete shear wall system, it is characterised in that including the steel by being vertically equally spaced The shear wall skeleton that pipe and the batten plate of lateral arrangement are constituted, template is respectively arranged with along the both sides in shear wall skeleton extension direction;
Wherein, the batten plate is located between steel pipe and along the height bearing of trend spaced set of steel pipe;
Wherein, the inner chamber of the steel pipe is cast with grouting material.
2. interval steel pipe according to claim 1 and combined concrete shear wall system, it is characterised in that in steel pipe top And bottom be provided with continuous top connecting plate and bottom connecting plate, and top connecting plate and bottom connecting plate respectively with steel pipe Opposite position is provided with grout hole.
3. interval steel pipe according to claim 1 and combined concrete shear wall system, it is characterised in that the batten plate bag The lacing I be arrangeding in parallel, lacing II are included, and provided with reservation member between lacing I, lacing II.
4. interval steel pipe according to claim 3 and combined concrete shear wall system, it is characterised in that the reservation member For the reserved column piece of hollow cylinder shape.
5. interval steel pipe according to claim 4 and combined concrete shear wall system, it is characterised in that the reserved post It is provided with internal thread in part, and in being respectively equipped with bolt access aperture, institute on the corresponding lacing I of reserved column piece bearing of trend, lacing II The corresponding template of bolt access aperture is stated provided with through hole, in being provided with fastening bolt in bolt access aperture, through hole.
6. interval steel pipe according to claim 4 and combined concrete shear wall system, it is characterised in that in described reserved Pick out reserved screw rod on the corresponding lacing I of column piece bearing of trend, lacing II respectively, the corresponding template of the reserved screw rod is provided with Through hole, the reserved screw rod accesses the through hole and is connected with a nut.
7. interval steel pipe and combined concrete shear wall system according to claim 1, it is characterised in that the steel pipe is Hollow long strip type rod member, the steel tube section is enclosed type section.
8. interval steel pipe according to claim 7 and combined concrete shear wall system, it is characterised in that the enclosed type Rectangular cross-section, square or circle.
9. interval steel pipe and combined concrete shear wall system according to claim 1, it is characterised in that the template is Aluminum alloy pattern plate, steel form, plank sheathing or precast concrete form.
CN201710567206.6A 2017-07-12 2017-07-12 One kind interval steel pipe and combined concrete shear wall system Pending CN107143064A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710567206.6A CN107143064A (en) 2017-07-12 2017-07-12 One kind interval steel pipe and combined concrete shear wall system

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710567206.6A CN107143064A (en) 2017-07-12 2017-07-12 One kind interval steel pipe and combined concrete shear wall system

Publications (1)

Publication Number Publication Date
CN107143064A true CN107143064A (en) 2017-09-08

Family

ID=59776096

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710567206.6A Pending CN107143064A (en) 2017-07-12 2017-07-12 One kind interval steel pipe and combined concrete shear wall system

Country Status (1)

Country Link
CN (1) CN107143064A (en)

Cited By (12)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107761998A (en) * 2017-10-19 2018-03-06 上海欧本钢结构有限公司 The heat preservation decoration integrative shear wall assembly system that steel joist is fixed with outer armor
CN108252405A (en) * 2018-03-30 2018-07-06 郑勤民 A kind of prefabricated steel reinforced concrete cavity shear wall assembled architecture and its method of construction
CN108678247A (en) * 2018-05-16 2018-10-19 江南大学 A kind of prefabricated assembled light floor and its manufacturing method
CN110195482A (en) * 2019-06-06 2019-09-03 上海欧本钢结构有限公司 A kind of combined type shear wall formwork and shear wall construction process
CN110485597A (en) * 2019-06-06 2019-11-22 上海欧本钢结构有限公司 A kind of construction process of shear wall assembly template and shear wall
CN110924557A (en) * 2019-11-22 2020-03-27 苏州科技大学 Aluminum alloy framework building structure wall capable of being assembled and connected and preparation method thereof
CN111051625A (en) * 2019-03-13 2020-04-21 鞠楠 Energy-conserving combination wall of assembled lightweight steel construction
CN112282122A (en) * 2020-10-16 2021-01-29 合力建设有限公司 Steel construction composite wall of house
CN112282121A (en) * 2020-11-20 2021-01-29 浙江汉林建筑设计有限公司 Prefabricated built-in corrugated steel plate reinforced concrete combined shear wall and construction process
CN114232846A (en) * 2021-12-28 2022-03-25 中建八局天津建设工程有限公司 Combined formwork structure of concrete wall and construction method thereof
CN114658140A (en) * 2022-04-14 2022-06-24 北京工业大学 Built-in lattice column type double-steel-plate shear wall and mounting method thereof
CN114856036A (en) * 2022-05-28 2022-08-05 南通装配式建筑与智能结构研究院 Recycled concrete ribbed diaphragm shell concrete shear wall

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2003027462A (en) * 2001-07-16 2003-01-29 Sumitomo Constr Co Ltd Construction method of underground continuous wall, and construction method of underground structure
CN103615072A (en) * 2013-11-25 2014-03-05 广西大学 Steel-encased concrete steel column with built-in spiral stirrup
CN104818784A (en) * 2015-05-13 2015-08-05 中国建筑技术集团有限公司 Thin-wall steel pipe concrete frame-light steel light concrete combined shear wall and construction method thereof
CN205134946U (en) * 2015-09-23 2016-04-06 中建三局第三建设工程有限责任公司 Fixed structure of outer wall wall post template
CN205242701U (en) * 2015-10-28 2016-05-18 中国建筑东北设计研究院有限公司 Lattice formula shaped steel concrete shear force wall by batten plate connection
CN206971471U (en) * 2017-07-12 2018-02-06 上海欧本钢结构有限公司 One kind interval steel pipe and combined concrete shear wall system

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2003027462A (en) * 2001-07-16 2003-01-29 Sumitomo Constr Co Ltd Construction method of underground continuous wall, and construction method of underground structure
CN103615072A (en) * 2013-11-25 2014-03-05 广西大学 Steel-encased concrete steel column with built-in spiral stirrup
CN104818784A (en) * 2015-05-13 2015-08-05 中国建筑技术集团有限公司 Thin-wall steel pipe concrete frame-light steel light concrete combined shear wall and construction method thereof
CN205134946U (en) * 2015-09-23 2016-04-06 中建三局第三建设工程有限责任公司 Fixed structure of outer wall wall post template
CN205242701U (en) * 2015-10-28 2016-05-18 中国建筑东北设计研究院有限公司 Lattice formula shaped steel concrete shear force wall by batten plate connection
CN206971471U (en) * 2017-07-12 2018-02-06 上海欧本钢结构有限公司 One kind interval steel pipe and combined concrete shear wall system

Cited By (15)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107761998A (en) * 2017-10-19 2018-03-06 上海欧本钢结构有限公司 The heat preservation decoration integrative shear wall assembly system that steel joist is fixed with outer armor
CN108252405A (en) * 2018-03-30 2018-07-06 郑勤民 A kind of prefabricated steel reinforced concrete cavity shear wall assembled architecture and its method of construction
CN108252405B (en) * 2018-03-30 2024-02-20 郑勤民 Prefabricated steel-concrete cavity shear wall assembled building and construction method thereof
CN108678247A (en) * 2018-05-16 2018-10-19 江南大学 A kind of prefabricated assembled light floor and its manufacturing method
CN111051625B (en) * 2019-03-13 2021-03-23 鞠楠 Energy-conserving combination wall of assembled lightweight steel construction
CN111051625A (en) * 2019-03-13 2020-04-21 鞠楠 Energy-conserving combination wall of assembled lightweight steel construction
CN110485597A (en) * 2019-06-06 2019-11-22 上海欧本钢结构有限公司 A kind of construction process of shear wall assembly template and shear wall
CN110195482A (en) * 2019-06-06 2019-09-03 上海欧本钢结构有限公司 A kind of combined type shear wall formwork and shear wall construction process
CN110924557A (en) * 2019-11-22 2020-03-27 苏州科技大学 Aluminum alloy framework building structure wall capable of being assembled and connected and preparation method thereof
CN112282122A (en) * 2020-10-16 2021-01-29 合力建设有限公司 Steel construction composite wall of house
CN112282121A (en) * 2020-11-20 2021-01-29 浙江汉林建筑设计有限公司 Prefabricated built-in corrugated steel plate reinforced concrete combined shear wall and construction process
CN114232846A (en) * 2021-12-28 2022-03-25 中建八局天津建设工程有限公司 Combined formwork structure of concrete wall and construction method thereof
CN114658140A (en) * 2022-04-14 2022-06-24 北京工业大学 Built-in lattice column type double-steel-plate shear wall and mounting method thereof
CN114856036A (en) * 2022-05-28 2022-08-05 南通装配式建筑与智能结构研究院 Recycled concrete ribbed diaphragm shell concrete shear wall
CN114856036B (en) * 2022-05-28 2024-02-06 南通装配式建筑与智能结构研究院 Recycled concrete ribbed membrane shell concrete shear wall

Similar Documents

Publication Publication Date Title
CN107143064A (en) One kind interval steel pipe and combined concrete shear wall system
CN206971471U (en) One kind interval steel pipe and combined concrete shear wall system
CN206957041U (en) Piecemeal assembling type outer wall plate and its connecting structure
CN107227822A (en) Building post and its construction technology that a kind of steel pipe is combined with batten plate
CN205954995U (en) Coincide wallboard structure with inside and outside double -deck heat preservation is insulated against heat
CN104179250B (en) Light-board house system and construction method thereof
CN206016309U (en) A kind of overall assembled building system
CN105863111A (en) Embedded prefabricated concrete shear wall anti-bending steel frame structure
CN106381923A (en) Multilayer architectural structure adopting prefabricated panel and construction method thereof
CN104878836B (en) A kind of prefabricated house and its construction method
CN107700667A (en) A kind of precast floor slab and girder steel lower flange connecting node
CN108265828A (en) Assembly concrete-filled steel tube beam column goes along with sb. to guard him integrated system
CN106760036A (en) A kind of prefabricated steel combined concrete shear wall
CN104790555B (en) Light steel keel and lightweight concrete prefabricated combining wall and construction method thereof
CN108867880A (en) A kind of assembled steel Reinforced Concrete Buildings
CN104818784B (en) Thin-wall steel pipe concrete frame-light steel light concrete combined shear wall and construction method thereof
CN107299718A (en) The precast floor slab and its mounting process of light weight energy-conserving and environment-protective
CN108412036B (en) Assembled H profile steel column-isolated footing-concrete collar tie beam cross connecting node
CN207003719U (en) A kind of prefabricated steel faced wall with steel bar girder
CN102418382A (en) Profile steel space lattice assembly integrated box-type structure for small high-rise energy-saving residential building
CN203080733U (en) External built-mold and internal masonry building structure system
CN109680868A (en) Complete prefabricated ribbed plate exterior wall single storey industry workshop
CN201649291U (en) Box house
CN106638956A (en) Concrete wallboard and ribbed slab dry type connection node
CN107605101A (en) A kind of heat-preserving load-bearing one steel concrete combined special-shaped column and its construction method

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20170908

RJ01 Rejection of invention patent application after publication