The content of the invention
The technical problems to be solved by the invention are a kind of construction method of arc steel box-girder of offer, it is intended to solve existing skill
The problem of being unfavorable for constructing because arc steel box-girder volume weight is larger in art, and easily cause traffic congestion.
In order to solve the above technical problems, the present invention is achieved in that a kind of construction method of arc steel box-girder, including with
Lower step:
Required to set the first connecting cross beam and the second connecting cross beam according to construction site;
Whole arc steel box-girder is split according to the position that first connecting cross beam and the second connecting cross beam match
Into first paragraph, second segment and the 3rd section, the first paragraph, second segment and the 3rd section are divided into two segments, and each segment
Individually produce making;
Two segments of the first paragraph are respectively welded to be fixed on first connecting cross beam and connected away from described second
Connect the side of crossbeam;
Two segments of the second segment are respectively welded be fixed on first connecting cross beam and the second connecting cross beam it
Between, and ensure that the second segment matches with the linear of first paragraph;
Described 3rd section of two segments are respectively welded to be fixed on second connecting cross beam and connected away from described first
The side of crossbeam is connect, and ensures that described 3rd section matches with the linear of the second segment.
Further, it is further comprising the steps of:Some I-shapeds are welded between two segments of the first paragraph steel box-girder
Steel.
Further, it is further comprising the steps of:Some I-shapeds are welded between two segments of the second segment steel box-girder
Steel.
Further, it is further comprising the steps of:Some I-shapeds are welded between two segments of the 3rd section of steel box-girder
Steel.
Further, it is further comprising the steps of:
Need to set eight hangers, each four hangers in two ends on the segment lifted for the first time in each section of steel box-girder;
Four hangers, each two hangers in two ends are set on the segment that second of needs of each section of steel box-girder are lifted.
Compared with prior art, beneficial effect is the present invention:A kind of construction method of arc steel box-girder of the present invention, its
First connecting cross beam and the second connecting cross beam are set at the place for needing to construct by elder generation, then by whole arc steel box-girder point
Into three sections, and the construction method that is welded and fixed respectively with first connecting cross beam and the second connecting cross beam completes arc-shaped steel case
The installation of beam.Because arc steel box-girder is segmented welding and all in accordance with demand processing is fabricated separately in each steel box girder segment, therefore, spelling
Welding equipment connects more convenient, and hoisting process is co-operated without too many crane, can reduce the input of man power and material's cost.Together
When, the steel box girder segment volume after being split due to arc steel box-girder is relatively small, then in work progress, the site area phase of occupancy
To smaller, therefore traffic congestion is not resulted in.
Embodiment
In order to make the purpose , technical scheme and advantage of the present invention be clearer, it is right below in conjunction with drawings and Examples
The present invention is further elaborated.It should be appreciated that the specific embodiments described herein are merely illustrative of the present invention, and
It is not used in the restriction present invention.
As shown in Figures 1 to 7, it is a kind of construction method of arc steel box-girder provided in an embodiment of the present invention, Specific construction
When, comprise the following steps:
S1, requires to set the first connecting cross beam 10 and the second connecting cross beam 20 according to construction site.Reference picture 1, first in institute
The lower section for stating the first connecting cross beam 10 and the second connecting cross beam 20 sets support post (not shown), is then connected described first
The connecting cross beam 20 of crossbeam 10 and second is separately fixed on corresponding support post.
S2, by whole arc steel box-girder according to the position matched with the connecting cross beam 20 of the first connecting cross beam 10 and second
Put and be divided into first paragraph 1, second segment 2 and the 3rd section 3.Reference picture 2, the first paragraph 1, second segment 2 and the 3rd section 3 are divided into two
Individual segment, and each segment individually produces making, so that it is excessive to avoid steel box girder segment volume and weight, is easy to the later stage
Splicing assembling.
S3, the segment 11 and segment 12 of the first paragraph 1 are respectively welded and are fixed on first connecting cross beam 10 far
From the side of second connecting cross beam 20.In reference picture 3, Specific construction engineering, 160T truck cranes are first passed through by the segment
Then 11 liftings are weldingly fixed on first connecting cross beam 10 to specified station.Subsequently, by the truck crane by institute
It is welded and fixed after stating the lifting of segment 12 to the position matched with the segment 11.
S4, reference picture 4 welds some I-steel 13 between the segment 11 and segment 12 of the first paragraph steel box-girder 1.It is logical
Cross the relative position that some I-steel 13 fix the segment 11 and segment 12, it is ensured that the first paragraph steel box-girder 1 will not
Topple.
S5, the segment 21 and segment 22 of the second segment 2 are respectively welded and are fixed on first connecting cross beam 10 and
Between two connecting cross beams 20, reference picture 5, by the way of 160T truck cranes and 80T truck crane double-machine lifting cranes, by the segment 21
Lift to specified station, and solder joint so that the segment 21 matches with the linear of segment 12.Then will be described small then,
Section 22 is lifted to specified station, and solder joint, the segment 22 is matched with the linear of segment 11.
S6, reference picture 6 welds some I-steel 23 between the segment 21 and segment 22 of the second segment steel box-girder 2.It is logical
Cross the relative position that some I-steel 23 fix the segment 21 and segment 22, it is ensured that the second segment steel box-girder 2 will not
Topple.
S7, described 3rd section 3 of segment 31 and segment 32 are respectively welded and are fixed on second connecting cross beam 20 far
From the side of first connecting cross beam 20, reference picture 7, will by the way of 160T truck cranes and 80T truck crane double-machine lifting cranes
The segment 31 is lifted to specified station, and solder joint so that the segment 31 matches with the linear of segment 22.Then,
The segment 32 is lifted to specified station, and solder joint again, the segment 32 is matched with the linear of segment 21.
S8, reference picture 8 welds some I-steel 33 between the segment 31 and segment 32 of the 3rd section of steel box-girder 3.It is logical
Cross the relative position that some I-steel 33 fix the segment 31 and segment 32, it is ensured that the second segment steel box-girder 3 will not
Topple.
In embodiments of the present invention, it is necessary to be completed in the assembly of each segment when lifting the segment 11, segment 21 and segment 31
Dividing plate afterwards sets totally eight hangers, each four of two ends with web junction;Lift the segment 12, segment 22 and segment 32
When, it is necessary to which dividing plate and web junction after the completion of the splicing of each segment set totally four hangers, each two of two ends.Before lifting,
Need the welding quality of inspection hanger, it is ensured that full penetration., during construction due to the danger that may be present of toppling of curved arc section
A upper lifting components for curved arc section are asked to be lifted again after completing the welding of abutment joint with installation component.Meanwhile, it is tight before construction
Lattice set enclosing, water code and men working warning banner board according to traffic dispersion.
In summary, the construction method of a kind of arc steel box-girder provided in an embodiment of the present invention, it is needing to apply by elder generation
First connecting cross beam 10 and the second connecting cross beam 20 are set at the place of work, whole arc steel box-girder is then divided into three sections, and
The construction method that is welded and fixed respectively with the connecting cross beam 20 of the first connecting cross beam 10 and second completes arc steel box-girder
Install.It is therefore, assembled to weld because arc steel box-girder is segmented welding and all in accordance with demand processing is fabricated separately in each steel box girder segment
Connect more convenient, hoisting process is co-operated without too many crane, can reduce the input of man power and material's cost.Meanwhile,
Steel box girder segment volume after being split due to arc steel box-girder is relatively small, then in work progress, the site area of occupancy is relative
It is smaller, therefore do not result in traffic congestion.
The foregoing is merely illustrative of the preferred embodiments of the present invention, is not intended to limit the invention, all essences in the present invention
Any modifications, equivalent substitutions and improvements made within refreshing and principle etc., should be included in the scope of the protection.