CN107130618B - 护坡支挡结构施工方法 - Google Patents
护坡支挡结构施工方法 Download PDFInfo
- Publication number
- CN107130618B CN107130618B CN201710536683.6A CN201710536683A CN107130618B CN 107130618 B CN107130618 B CN 107130618B CN 201710536683 A CN201710536683 A CN 201710536683A CN 107130618 B CN107130618 B CN 107130618B
- Authority
- CN
- China
- Prior art keywords
- bank protection
- breast boards
- soil body
- soil
- strut
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D17/00—Excavations; Bordering of excavations; Making embankments
- E02D17/20—Securing of slopes or inclines
Landscapes
- Engineering & Computer Science (AREA)
- Mining & Mineral Resources (AREA)
- Life Sciences & Earth Sciences (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Paleontology (AREA)
- Civil Engineering (AREA)
- General Engineering & Computer Science (AREA)
- Structural Engineering (AREA)
- Pit Excavations, Shoring, Fill Or Stabilisation Of Slopes (AREA)
Abstract
本发明公开了一种护坡支挡结构施工方法,其特征是施工步骤包括:(1)施工护坡柱,护坡柱插入土体;(2)将钢板插入土体作为临时施工支撑;(3)浇筑挡土板、肋梁和护坡板混凝土;浇筑压顶梁混凝土,使挡土板、肋梁和护坡板以及护坡柱形成整体;(4)对1/3护坡高度以上土体进行卸除,卸土后铺设土工布,然后安装土锚板;(5)撑杆穿过挡土板和护坡板的预埋孔顶住土锚板;(6)拆除钢板临时施工支撑,钢板与挡土板之间空隙采用砂填塞;(7)采用千斤顶对撑杆进行预应力顶推;(8)在挡土板和右侧土体之间填充填料。
Description
技术领域
本发明涉及一种支挡施工方法,特别涉及一种护坡支挡施工方法。
背景技术
护坡支挡结构是防止土体塌方或变形失稳的一种构造物,是岩土工程重要的研究课题之一。重力式支挡结构是最古老的挡墙结构,具有就地取材,施工简便等显著的优点,但是随着工程建设规模越来越大,重力式挡墙己不能适应工程条件复杂地区对支挡结构的需要,主要是由于重力式挡墙成本比较高,而且在施工过程中由于开挖较多会引起地基失稳,如何节约工程造价、保证工程安全是工程人员面临的课题。
发明内容
本发明是提供一种护坡支挡施工方法,解决护坡支挡结构不安全和成本高的问题。
本发明在1/3护坡高度处进行卸土,通过预应力顶推右侧护坡土体使右侧护坡土体处于平衡状态,采用格构式结构整体形成挡土结构,格构式结构中护坡柱将主动土压力有效地传递到深层土体。下部朝向土体部位的护坡板采用折线形式,使该区域土体在受荷移动过程中形成土拱,上部土体采用撑杆顶推土锚板使土体维持稳定。
护坡柱伸入基底标高以下2-2.5米,护坡柱设置间距为4-6m,护坡柱截面为正方形,正方形长度为200-250mm,护坡柱外侧设置护坡板,护坡板厚度为60-80mm,护坡板为平板,朝土面设置挡土板,挡土板为折板,折板角度为150-160度,折板右侧形成不同单元的三角形土,三角土体在外推力作用下会出现一定变形,形成水平方向的卸荷拱,卸荷拱内土体产生的水平推力由折线板承受。挡土板留设泄水孔,泄水孔布置间距为每平方1个,泄水孔直径为6-8mm,挡土板与护坡柱之间设置肋梁,肋梁高度为150-250mm,最下排肋梁离基底标高高度为400-500mm,相邻排肋梁竖向间距为600-800mm。护坡柱、护坡板、肋梁、挡土板形成格构式结构,格构式结构顶部设置压顶梁,压顶梁高度为400-600mm,护坡上部1/3总高度位置将土方挖空,土方挖空宽度为0.6-0.8m,右侧土体开挖成斜坡,斜坡与水平线的夹角为70-80度,斜坡表面铺设土工布,土工布上面设置土锚板,土锚板形状为三角形,土锚板为厚度12-18mm的钢筋混凝土板,土锚板带有三根锚筋,锚筋直径为14-16mm,锚筋长度为400-600mm,锚筋伸入右侧土体。撑杆右端顶住土锚板,撑杆左端施加预应力后用锚栓固定在护坡板上,撑杆采用直径为28mm或32mm的钢筋,相邻撑杆距离为0.7-0.9m。土方挖空部位填充填料,填料采用砂碎石,砂碎石粒径不大于80mm,砂碎石通过0.07mm筛孔的土粒应小于15%,或者虽然多于15%但通过0.015mm筛孔的土粒应小于10%。
施工步骤包括:
(1)施工护坡柱,护坡柱插入土体;
(2)将钢板插入土体作为临时施工支撑,钢板右侧用角钢进行支顶,开挖土方留出工作面;
(3)安装挡土板、肋梁和护坡板模板,将挡土板、肋梁和护坡板钢筋架放入模板内,浇筑挡土板、肋梁和护坡板混凝土;然后安装压顶梁模板,将压顶梁钢筋架放入模板内,浇筑压顶梁混凝土,使挡土板、肋梁和护坡板以及护坡柱形成整体;
(4)对1/3护坡高度以上土体进行卸除,卸土后铺设土工布,然后安装土锚板;
(5)撑杆穿过挡土板和护坡板的预埋孔顶住土锚板;
(6)拆除钢板临时施工支撑,钢板与挡土板之间空隙采用砂填塞;
(7)采用千斤顶对撑杆进行预应力顶推;根据千斤顶的压缩值来控制预应力顶推压力,如果撑杆采用直径为28mm的钢筋,千斤顶的压缩值确定为5mm,如果撑杆采用直径为32mm的钢筋,千斤顶的压缩值确定为4mm,撑杆进行预应力顶推后可以有效地应对右侧土体的主动土压力;
为了避免撑杆受腐蚀,在撑杆预应力顶推后刷一层防腐沥青油膏,刷完后用工业纱布包裹,包裹后再刷一层沥青油膏。
(8)在挡土板和右侧土体之间填充填料,填料采用分层回填夯实,每层铺设厚度500mm,铺摊后随之耙平。
本发明安全性能好,工程造价低。
附图说明
图1为护坡支挡结构立面示意图,图2为支挡结构平面示意图,图3为土锚板平面示意图,图4为土锚板立面示意图。
各附图中:1、护坡柱,2、护坡板,3、肋梁,4、挡土板,5、撑杆,6、锚栓,7、土锚板,8、土工布,9、压顶梁,10、填料。
具体实施方式
实施例中护坡柱1伸入基底标高以下2米,护坡柱1设置间距为5m,护坡柱1截面为正方形,正方形长度为250mm,护坡柱1外侧设置护坡板2,护坡板2厚度为80mm,护坡板2为平板,朝土面设置挡土板4,挡土板4为折板,折板角度为160度。挡土板4留设泄水孔,泄水孔布置间距为每平方1个,泄水孔直径为7mm,挡土板4与护坡柱1之间设置肋梁3,肋梁3高度为200mm,最下排肋梁3离基底标高高度为450mm,相邻排肋梁3竖向间距为700mm。护坡柱1、护坡板2、肋梁3、挡土板4形成格构式结构,格构式结构顶部设置压顶梁9,压顶梁9高度为400mm,护坡上部1/3总高度位置将土方挖空,土方挖空宽度为0.7m,右侧土体开挖成斜坡,斜坡与水平线的夹角为75度,斜坡表面铺设土工布8,土工布8上面设置土锚板7,土锚板7形状为三角形,土锚板7为厚度16mm的钢筋混凝土板,土锚板7带有三根锚筋,锚筋直径为14mm,锚筋长度为500mm,锚筋伸入右侧土体。撑杆5右端顶住土锚板7,撑杆5左端施加预应力后用锚栓6固定在护坡板2上,撑杆5采用直径为28mm或32mm的钢筋,相邻撑杆5距离为0.8m。土方挖空部位填充填料10,填料10采用砂碎石,砂碎石粒径不大于80mm,砂碎石通过0.07mm筛孔的土粒应小于15%。
施工步骤包括:
(1)施工护坡柱1,护坡柱1插入土体;
(2)将钢板插入土体作为临时施工支撑,钢板右侧用角钢进行支顶,开挖土方留出工作面;
(3)安装挡土板4、肋梁3和护坡板2模板,将挡土板4、肋梁3和护坡板2钢筋架放入模板内,浇筑挡土板4、肋梁3和护坡板2混凝土;然后安装压顶梁9模板,将压顶梁9钢筋架放入模板内,浇筑压顶梁9混凝土,使挡土板4、肋梁3和护坡板2以及护坡柱1形成整体;
(4)对1/3护坡高度以上土体进行卸除,卸土后铺设土工布8,然后安装土锚板7;
(5)撑杆5穿过挡土板4和护坡板2的预埋孔顶住土锚板7;
(6)拆除钢板临时施工支撑,钢板与挡土板4之间空隙采用砂填塞;
(7)采用千斤顶对撑杆5进行预应力顶推;根据千斤顶的压缩值来控制预应力顶推压力,撑杆5采用直径为28mm的钢筋,千斤顶的压缩值确定为5mm;
为了避免撑杆5受腐蚀,在撑杆5预应力顶推后刷一层防腐沥青油膏,刷完后用工业纱布包裹,包裹后再刷一层沥青油膏。
(8)在挡土板4和右侧土体之间填充填料10,填料10采用分层回填夯实,每层铺设厚度500mm,铺摊后随之耙平。
Claims (4)
1.一种护坡支挡结构施工方法,其特征是在设定高度处进行卸土,通过预应力顶推右侧护坡土体使右侧护坡土体处于平衡状态,采用格构式结构整体形成挡土结构,格构式结构中护坡柱将主动土压力有效地传递到深层土体;下部朝向土体部位的护坡板采用折线形式,使该区域土体在受荷移动过程中形成土拱,上部土体采用撑杆顶推土锚板使土体维持稳定;
护坡柱伸入基底标高以下2-2.5米,护坡柱设置间距为4-6m,护坡柱截面为正方形,正方形长度为200-250mm,护坡柱外侧设置护坡板,护坡板厚度为60-80mm,护坡板为平板,朝土面设置挡土板,挡土板为折板,折板角度为150-160度;挡土板留设泄水孔,泄水孔布置间距为每平方1个,泄水孔直径为6-8mm,挡土板与护坡柱之间设置肋梁,肋梁高度为150-250mm,最下排肋梁离基底标高高度为400-500mm,相邻排肋梁竖向间距为600-800mm;护坡柱、护坡板、肋梁、挡土板形成格构式结构,格构式结构顶部设置压顶梁,压顶梁高度为400-600mm,土方从护坡顶部往下开挖,开挖深度为1/3护坡总高度,土方挖空宽度为0.6-0.8m,右侧土体开挖成斜坡,斜坡与水平线的夹角为70-80度,斜坡表面铺设土工布,土工布上面设置土锚板,土锚板形状为三角形,土锚板为厚度12-18mm的钢筋混凝土板,土锚板带有三根锚筋,锚筋直径为14-16mm,锚筋长度为400-600mm,锚筋伸入右侧土体;撑杆右端顶住土锚板,撑杆左端施加预应力后用锚栓固定在护坡板上,撑杆采用直径为28mm或32mm的钢筋,相邻撑杆距离为0.7-0.9m;土方挖空部位填充填料,填料采用砂碎石;
施工步骤包括:
(1)施工护坡柱,护坡柱插入土体;
(2)将钢板插入土体作为临时施工支撑,钢板右侧用角钢进行支顶,开挖土方留出工作面;
(3)安装挡土板、肋梁和护坡板模板,将挡土板、肋梁和护坡板钢筋架放入模板内,浇筑挡土板、肋梁和护坡板混凝土;然后安装压顶梁模板,将压顶梁钢筋架放入模板内,浇筑压顶梁混凝土,使挡土板、肋梁和护坡板以及护坡柱形成整体;
(4)对1/3护坡高度以上土体进行卸除,卸土后铺设土工布,然后安装土锚板;
(5)撑杆穿过挡土板和护坡板的预埋孔顶住土锚板;
(6)拆除钢板临时施工支撑,钢板与挡土板之间空隙采用砂填塞;
(7)采用千斤顶对撑杆进行预应力顶推;
(8)在挡土板和右侧土体之间填充填料,填料采用分层回填夯实,每层铺设厚度500mm,铺摊后随之耙平。
2.根据权利要求1所述的护坡支挡结构施工方法,其特征是砂碎石粒径不大于80mm,砂碎石通过0.07mm筛孔的土粒小于15%,或者虽然多于15%但通过0.015mm筛孔的土粒小于10%。
3.根据权利要求1所述的护坡支挡结构施工方法,其特征是根据千斤顶的压缩值来控制预应力顶推压力,如果撑杆采用直径为28mm的钢筋,千斤顶的压缩值确定为5mm,如果撑杆采用直径为32mm的钢筋,千斤顶的压缩值确定为4mm。
4.根据权利要求1所述的护坡支挡结构施工方法,其特征是在撑杆预应力顶推后刷一层防腐沥青油膏,刷完后用工业纱布包裹,包裹后再刷一层沥青油膏。
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201710536683.6A CN107130618B (zh) | 2016-04-12 | 2016-04-12 | 护坡支挡结构施工方法 |
Applications Claiming Priority (2)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201610288325.3A CN105839650B (zh) | 2016-04-12 | 2016-04-12 | 护坡支挡结构 |
CN201710536683.6A CN107130618B (zh) | 2016-04-12 | 2016-04-12 | 护坡支挡结构施工方法 |
Related Parent Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201610288325.3A Division CN105839650B (zh) | 2016-04-12 | 2016-04-12 | 护坡支挡结构 |
Publications (2)
Publication Number | Publication Date |
---|---|
CN107130618A CN107130618A (zh) | 2017-09-05 |
CN107130618B true CN107130618B (zh) | 2018-11-09 |
Family
ID=56590728
Family Applications (2)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201710536683.6A Active CN107130618B (zh) | 2016-04-12 | 2016-04-12 | 护坡支挡结构施工方法 |
CN201610288325.3A Active CN105839650B (zh) | 2016-04-12 | 2016-04-12 | 护坡支挡结构 |
Family Applications After (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201610288325.3A Active CN105839650B (zh) | 2016-04-12 | 2016-04-12 | 护坡支挡结构 |
Country Status (1)
Country | Link |
---|---|
CN (2) | CN107130618B (zh) |
Family Cites Families (9)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH0868054A (ja) * | 1994-08-30 | 1996-03-12 | Kensetsu Kiso Eng Co Ltd | 発泡樹脂ブロックによる水平地盤構築方法 |
JP2001317054A (ja) * | 2000-05-09 | 2001-11-16 | Tokyu Constr Co Ltd | 盛土のり面補強用のl型かごの変形防止水平部材およびそれによる補強盛土工法 |
CN201232188Y (zh) * | 2008-05-29 | 2009-05-06 | 安徽省建设工程勘察设计院 | 扶壁式土钉墙 |
CN201671108U (zh) * | 2010-04-27 | 2010-12-15 | 中国科学院武汉岩土力学研究所 | 一种沿河路肩预应力锚索桩板墙 |
CN102330431A (zh) * | 2011-06-16 | 2012-01-25 | 兰州理工大学 | 格构式框架预应力锚杆柔性支护结构及其施工方法 |
KR101181619B1 (ko) * | 2011-10-06 | 2012-09-13 | 쌍용건설 주식회사 | 어스앵커의 재인장을 통한 대규모 지하구조물 높은 옹벽의 축조 공법 |
CN103726495B (zh) * | 2014-01-10 | 2016-01-13 | 上海建工五建集团有限公司 | 近海深基坑支护结构及其施工方法 |
CN204456180U (zh) * | 2015-02-27 | 2015-07-08 | 重庆大学 | 折板桩挡土墙 |
CN204919573U (zh) * | 2015-08-27 | 2015-12-30 | 山东科技大学 | 一种复合式边坡支护结构 |
-
2016
- 2016-04-12 CN CN201710536683.6A patent/CN107130618B/zh active Active
- 2016-04-12 CN CN201610288325.3A patent/CN105839650B/zh active Active
Also Published As
Publication number | Publication date |
---|---|
CN107130618A (zh) | 2017-09-05 |
CN105839650B (zh) | 2017-11-28 |
CN105839650A (zh) | 2016-08-10 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN106499413B (zh) | 一种浅埋偏压段隧道地层加固施工方法 | |
CN109826667B (zh) | 煤矿地下水库工字型挡水坝 | |
CN111485901B (zh) | 侧跨无充填型狭长浅底溶洞段的隧道修建方法 | |
CN105672240B (zh) | 倾倒破坏型危岩体治理方法 | |
CN105089680B (zh) | 一种沿空留巷轻质高强混凝土砌块墙体及其施工工艺 | |
CN109797769B (zh) | 一种湿陷性黄土地区地下综合管廊地基结构及其施工方法 | |
CN109183809B (zh) | 一种淤泥质黏土深基坑工程复合支护换撑的施工方法 | |
CN107447778A (zh) | 一种在役钢筋混凝土挡土墙的加高加固结构及方法 | |
CN106758561A (zh) | 跨越坎儿井高速铁路路基加固结构 | |
CN205475197U (zh) | 松软土岩溶地基加固结构 | |
CN202323960U (zh) | 一种确保边坡稳定的浅基坑成型施工结构 | |
CN108487234B (zh) | 现浇桩板式站台墙施工的方法 | |
CN111622234B (zh) | 一种斜竖向组合钢管桩承托的卸荷式薄壁箱型挡墙及施工工艺 | |
CN107130618B (zh) | 护坡支挡结构施工方法 | |
CN205742290U (zh) | 一种底板后浇带传力结构 | |
CN104196036A (zh) | 基于老旧地下室外墙结构的基坑支护结构及支护方法 | |
CN103669976A (zh) | 古塔纠偏 | |
CN102912800B (zh) | 一种用于处理后筑式高陡填方边坡的立体组合加固方法 | |
CN204097889U (zh) | 一种补桩与增大台帽组合加固已建桥台结构 | |
CN216275591U (zh) | 一种采用预应力混凝土管桩复合地基防沉降结构 | |
CN105113350A (zh) | 桥墩台路基结构及施工方法 | |
CN205977233U (zh) | 一种隧道锁脚旋喷桩结构 | |
CN205776258U (zh) | 一种深基坑桩锚支护体系 | |
CN105672350B (zh) | 一种挡土墙侧向位移修复施工方法 | |
CN205529734U (zh) | 一种用于填方路基的u形支挡结构 |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
GR01 | Patent grant | ||
GR01 | Patent grant | ||
TR01 | Transfer of patent right |
Effective date of registration: 20201126 Address after: 224000 Dajian neighborhood committee, Haitong Town, Sheyang County, Yancheng City, Jiangsu Province Patentee after: Sheyang Tonghai Village Construction Development Co., Ltd Address before: 325000 Jinchuan Road, Tianhe street, Wenzhou economic and Technological Development Zone, Wenzhou City, Zhejiang Province, No. 4 Patentee before: Ye Changqing |
|
TR01 | Transfer of patent right |