CN107122188A - The method and device of project process bar image generation - Google Patents

The method and device of project process bar image generation Download PDF

Info

Publication number
CN107122188A
CN107122188A CN201710283133.8A CN201710283133A CN107122188A CN 107122188 A CN107122188 A CN 107122188A CN 201710283133 A CN201710283133 A CN 201710283133A CN 107122188 A CN107122188 A CN 107122188A
Authority
CN
China
Prior art keywords
progress bar
milestone
scale
bar
hallmark events
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201710283133.8A
Other languages
Chinese (zh)
Other versions
CN107122188B (en
Inventor
刘朝敏
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Netease Hangzhou Network Co Ltd
Original Assignee
Netease Hangzhou Network Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Netease Hangzhou Network Co Ltd filed Critical Netease Hangzhou Network Co Ltd
Priority to CN201710283133.8A priority Critical patent/CN107122188B/en
Publication of CN107122188A publication Critical patent/CN107122188A/en
Application granted granted Critical
Publication of CN107122188B publication Critical patent/CN107122188B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06FELECTRIC DIGITAL DATA PROCESSING
    • G06F40/00Handling natural language data
    • G06F40/10Text processing
    • G06F40/166Editing, e.g. inserting or deleting
    • G06F40/174Form filling; Merging
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/06Resources, workflows, human or project management; Enterprise or organisation planning; Enterprise or organisation modelling
    • G06Q10/063Operations research, analysis or management
    • G06Q10/0631Resource planning, allocation, distributing or scheduling for enterprises or organisations
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/10Office automation; Time management
    • G06Q10/109Time management, e.g. calendars, reminders, meetings or time accounting

Abstract

The invention discloses a kind of method of project process bar image generation, including:Receive the phase data and mileage landmark data for the project;According to the Start Date and Close Date of each sub-stage event, determine that the scale of the scale distribution and each sub-stage event of the progress bar in the progress bar is interval;It is distributed according to the scale of the mileage landmark data and the progress bar, determines display location of each hallmark events on the progress bar;According to the distribution of the scale of the progress bar, display location of each the interval and described hallmark events of each scale of sub-stage event in the progress bar on the progress bar, the image for generating the progress bar is rendered.The invention also discloses a kind of device of project process bar image generation.Using the embodiment of the present invention, the progress bar image of project can be automatically generated, and ensures the reasonability of generation project progress bar image.

Description

The method and device of project process bar image generation
Technical field
The present invention relates to the method and device of field of computer technology, more particularly to a kind of generation of project process bar image.
Background technology
In the process and management of project, administrative staff need to go the progress of understanding project from macroscopical angle, when Between be a good dimension.Time as development of projects dimension, it will usually be related to three classes progress mark:It is stage, inner Journey upright stone tablet, version.
Stage is would generally span longer time.For game item, DEMO stages, project initiation phase, exploitation rank Section all might have different resource follow-ups, such as personnel, fund.So, the stage can allow administrative staff roughly to understand item Purpose progress, and then adjust corresponding docking stock number.
In project process, administrative staff can formulate different interim milestones.Particularly project enters normal exploitation During the operation phase, it is typically a very long process, and milestone can be as the project stage property task of one, so as to very Administrative staff are helped to confirm that whether reasonable development of projects obtains well, it is also possible to be used as the phasic results of product.
But do not suggest that the project information parameter for input automatically generates the project rationally shown and entered in the prior art The concrete mode of bar is spent, the reasonability of progress bar typesetting can not be automatically adjusted.
The content of the invention
A kind of method and device for project process bar image generation that a wherein embodiment of the invention is proposed, can give birth to automatically Into the progress bar image of project, and ensure the reasonability of generation project progress bar image.
In one aspect, the embodiment of the present invention provides a kind of method of project process bar image generation, including:
Receive the phase data and mileage landmark data for the project;The phase data includes each of the project The Start Date and Close Date of individual sub- stage event and each sub-stage event;The milestone data include described Each hallmark events of project and the target date of each hallmark events;
According to the Start Date and Close Date of each sub-stage event, the scale distribution of the progress bar is determined It is interval with scale of each sub-stage event in the progress bar;
According to the scale of the mileage landmark data and the progress bar be distributed, determine each hallmark events it is described enter The display location spent on bar;
It is distributed according to the scale of the progress bar, scale of each sub-stage event in the progress bar be interval and institute Display location of each hallmark events on the progress bar is stated, the image for generating the progress bar is rendered automatically.
In another aspect, the embodiment of the present invention provides a kind of device of project process bar image generation, including:
Data reception module, for receiving phase data and mileage landmark data for the project;The phase data The Start Date and Close Date of each sub-stage event and each sub-stage event including the project;It is described Milestone data include each hallmark events of the project and the target date of each hallmark events;
Scale division module, for the Start Date and Close Date according to each sub-stage event, determines institute State the scale of the scale distribution and each sub-stage event of progress bar in the progress bar interval;
Mark shows determining module, for being distributed according to the scale of the mileage landmark data and the progress bar, it is determined that often Display location of one hallmark events on the progress bar;And,
Image rendering generation module, for according to the distribution of the scale of the progress bar, each sub-stage event is described Display location of each the interval and described hallmark events of scale in progress bar on the progress bar, renders generation automatically The image of the progress bar.
Implement a wherein embodiment of the invention, have the advantages that:
A kind of method and apparatus for project process bar image generation that a wherein embodiment of the invention is provided, pass through receiving item Purpose phase data and mileage landmark data, and phase data and mileage landmark data are parsed, obtain the relevant parameter of project Information, generating item purpose progress bar image is rendered according to parameter information, it is achieved thereby that can be automatic according to project data automatically Generating item purpose progress bar image, and sub-stage and milestone typesetting in progress bar are adjusted, to ensure generation project progress bar figure The reasonability of picture, so as to avoid the presentation of information on progress bar from being blocked.
Brief description of the drawings
Fig. 1 is the schematic flow sheet of one embodiment of the method for the project process bar image generation that the present invention is provided;
Fig. 2 is an implementation of the image of the progress bar of the method generation for the project process bar image generation that the present invention is provided The schematic diagram of example;
Fig. 3 is the structural representation of one embodiment of the device for the project process bar image generation that the present invention is provided;
Fig. 4 is one embodiment of the scale division module of the device for the project process bar image generation that the present invention is provided Structural representation;
Fig. 5 is that the calculating and amendment of the scale division module of the device for the project process bar image generation that the present invention is provided are single The structural representation of one embodiment of member;
Fig. 6 is that the mark of the device for the project process bar image generation that the present invention is provided shows an implementation of determining module The structural representation of example;
Fig. 7 is that the mark of the device for the project process bar image generation that the present invention is provided shows the display location of determining module The structural representation of one embodiment of determining unit;
Fig. 8 is an implementation of the image rendering generation module of the device for the project process bar image generation that the present invention is provided The structural representation of example.
Embodiment
Below in conjunction with the accompanying drawing in the embodiment of the present invention, the technical scheme in the embodiment of the present invention is carried out clear, complete Site preparation is described, it is clear that described embodiment is only a part of embodiment of the invention, rather than whole embodiments.It is based on Embodiment in the present invention, it is every other that those of ordinary skill in the art are obtained under the premise of creative work is not made Embodiment, belongs to the scope of protection of the invention.
It is the flow signal of one embodiment of the method for the project process bar image generation that the present invention is provided referring to Fig. 1 Figure;The embodiment of the present invention provides a kind of method of project process bar image generation, including step S1 to S4:
S1, receives the phase data and mileage landmark data of the project;The phase data includes each of the project The Start Date and Close Date of individual sub- stage event and each sub-stage event;The milestone data include described Each hallmark events of project and the target date of each hallmark events.
It has been required for it should be noted that all sub-stage data and mileage landmark data are shown in the image of progress bar The date of determination, so need to carry out basic pretreatment to incoming data to judge, i.e., to the sub-stage data that receive with Mileage landmark data judges that its corresponding date whether there is, meanwhile, the above-mentioned data received can be classified and be entered according to the date Row successively sorts, the convenient operation subsequently screened, calculated to data, improves the efficiency of image generation.
S2, according to the Start Date and Close Date of each sub-stage event, determines the scale of the progress bar The scale of distribution and each sub-stage event in the progress bar is interval.
It should be noted that in actual project management, the date span of sub-stage and sub-stage sometimes can not be complete In full linking, and then it is empty content that can there are sub-stage on progress bar, in order to show this problem to consultant, it is necessary to The interval of the sub-stage of blank is shown on progress bar, thus, the embodiment of the present invention passes through the date to each sub-stage Calculated, show that the scale of each sub-stage event on a progress bar is interval, and then obtain the scale of the sub-stage of blank Interval, then rendering the process of generation image, and the scale interval of the sub-stage of the blank is indicated with special color.
S3, is distributed according to the scale of the mileage landmark data and the progress bar, determines each hallmark events in institute State the display location on progress bar.
It should be noted that display location of each hallmark events on the progress bar, refers to the characteristic events Corresponding display box or the center for showing word.
S4, it is interval according to the distribution of the scale of the progress bar, scale of each sub-stage event in the progress bar With display location of each the described hallmark events on the progress bar, the image for generating the progress bar is rendered automatically.
It should be noted that passing through above-mentioned steps S1 to step S4 image generation process, one kind of the image generated Display mode is as shown in Fig. 2 Fig. 2 illustrates the image for the progress bar for rendering generation, and progress bar is incremented by according to the scale value on days, With mutually different colour code, (Fig. 2 is with different shades for the scale area on the progress bar of different sub-stage events Represent different colors), each hallmark events is shown in the progress bar pullup or pulldown in milestone mode, figure 2 are shown with pulling up mode.After the scale value corresponding date except identifying progress bar, in addition to mark works as the day before yesterday Phase, the time point for allowing the clear and definite progress bar of consultant to be presently in, and understanding are presently in sub-stage and other comparative informations. In addition, carrying out dissection process by the above-mentioned phase data to receiving and mileage landmark data, each sub-stage is adjusted and every The layout position of one hallmark events, it is ensured that the reasonability of the progress bar image of generation.
Further, in order to ensure observability of the project process data on view, for sub-stage Data Date this Individual key point such as is screened, calculated at the operation to sub- phase data, then above-mentioned steps S2 specific implementation process is:
From the Start Date and Close Date of each sub-stage event, extract sequence on the most preceding date and On the last date, obtain the whole story span number of days of the progress bar;
Calculate the width of the progress bar and the ratio of the progress bar whole story span number of days, obtain every day it is described enter Spend the span value of bar;
According to the span value of most preceding date, the last date and the progress bar, the progress bar is determined Scale distribution;Wherein, on the start index of the progress bar date most preceding for described in, the termination scale of the progress bar is institute The last date is stated, the distance between the adjacent scale of the progress bar is the span value of the progress bar;
It is distributed according to the scale of the progress bar, it is determined that the Start Date and Close Date of each sub-stage event Corresponding scale value, obtains scale of each the described sub-stage event in the progress bar interval respectively.
It should be noted that the specific implementation process of above-mentioned steps 2 calculates the scale distributed data of progress bar, and often The scale of one sub- stage event on a progress bar is interval, and there is provided the basic framework data of progress bar, it is ensured that sub-stage is being entered It is clear when being shown on degree bar, that is, ensure that the typesetting of sub-stage data is reasonable.
Further, there be individual arrow one end of progress bar, and arrow head part can take certain number of days, then also need to meter Calculate arrow scale distribution, and due to arrow to be considered scale be distributed, then need calculate arrow account for progress bar day numerical value, And the span value of amendment progress bar, to prevent the too small or excessive display problem in arrow portion after image is generated, thus it is above-mentioned Step S2 specific implementation process also includes, after the span value of the progress bar is obtained, and calculates the arrow and accounts for the progress The day numerical value of bar and the span value for correcting the progress bar, specifically:
After the span value I of the progress bar is obtained, according to the preset length S1 of the arrow and the progress bar across Angle value I, calculates the day numerical value D1 that the arrow accounts for the progress bar,Wherein, floor () is downward Bracket function;
The day numerical value D1 of the progress bar is accounted for according to the arrow, the preset length S1 and the arrow of the arrow is calculated Physical length between deviant F1, F1=S1-D1*I;
Judge whether the deviant F1 of the arrow and the deviant F2 of the progress bar are all higher than deviant threshold value;Its In, F2=S2-D2*I, S2 is the width of the progress bar;D2 is the whole story span number of days of the progress bar;
When the deviant F1 of the arrow is more than the deviant threshold value, or when the deviant F2 of the progress bar is big When the deviant threshold value, according to the deviant of the arrow, the span value for correcting the progress bar is I,
According to the span value I of the revised progress bar, the day numerical value that the arrow accounts for the progress bar is recalculated D1, the deviant F1 of the arrow and the progress bar deviant F2, until the deviant F1 and the progress of the arrow The deviant F2 of bar is respectively less than the deviant threshold value;
When the deviant F1 of the arrow and the deviant F2 of the progress bar are respectively less than the deviant threshold value, institute is exported State arrow and account for the day numerical value D1 of the progress bar and span value I of the progress bar.
It should be noted that by it is above-mentioned calculate the arrow account for the day numerical value D1 of the progress bar and have modified it is described After the span value I of progress bar, it may be determined that arrow is D1*I in the length shared by progress bar.The default length of above-mentioned arrow It is what is pre-set to spend S1 and deviant threshold value, the convenient day numerical value and progress bar adjusted in above-mentioned calculating process shared by arrow Span value.
Further, above-mentioned steps S3 specific implementation process is:
Calculate the word occupy-place length of each hallmark events and multiplying for the mark displaying ratio of the progress bar Product, obtains the milestone width that each described hallmark events are shown in milestone mode in the progress bar;The mark Will displaying ratio is text importing unit length occupied in the image of the progress bar;
The milestone display mode set according to the progress bar and each hallmark events show in the progress bar The milestone width shown, determines display location of each hallmark events on the progress bar.
Specifically, be shown as the target date of hallmark events correspondence on the progress bar in milestone mode The center of the milestone of scale value position and the hallmark events is shown described significant with an axis The target date of the milestone of event and the hallmark events scale value position on the progress bar connecting line.
It should be noted that in order to accomplish that it is suitable that each hallmark events in mileage landmark data are shown in progress covering Should, and each characteristic events with milestone when being shown, because the length of word content can make milestone width also can be Difference, is to need to avoid the screening between multiple milestones when there are multiple milestones in the minor time slice on progress bar secondly Gear problem, thus need to calculate the width of each milestone, and the position determination side for the milestone for passing through following multi-layer Formula solves problem above:
According to the target date of each hallmark events, each described hallmark events are in chronological sequence entered Row sequence;Data to each hallmark events are ranked up according to the date, and the data after sequence are logical to be treated to follow-up Cheng Jinhang simplifies, it is to avoid data corruption.
For the 1st hallmark events, by the 1st hallmark events with milestone display mode include it is described enter Position during the first milestone level of degree article is used as the 1st position of the hallmark events on the progress bar;For 1st hallmark events, without a liter level.As shown in Fig. 2 the first milestone in Fig. 2 can see the 1st hallmark events as Milestone.
For i-th of hallmark events, by i-th of hallmark events with milestone display mode include it is described enter During the position for the first milestone level for spending bar, the position shown according to i-th of hallmark events in the progress bar The position of the milestone of the previous characteristic events shown with milestone width and in current milestone level and milestone are wide Degree, judge the milestones of i-th of hallmark events and the previous hallmark events of its place level milestone whether Have overlapping;I is the natural number more than 1;
If so, then continuing with milestone display mode to include i-th of hallmark events under the progress bar The position of one milestone level judged, until the milestone of i-th of hallmark events and its place level is previous The milestone of individual hallmark events do not have it is overlapping untill, and i-th of hallmark events are shown in current milestone level Position as i-th of hallmark events in the display location of the progress bar.
If it is not, regarding i-th of hallmark events as described i-th mark in the position that current milestone level is shown Sexual behavior part is in the display location of the progress bar.
It should be noted that if the right position of the current corresponding milestone of hallmark events and the milestone are in current layer When the left position of the corresponding milestone of previous hallmark events of level display has overlapping, the milestone of current characteristic events Need to rise a level, if still have overlapping in new level, level is risen again, until there is no overlapping to be in new level Only.As shown in Fig. 2 determining the position of the 3rd milestone, the 3rd journey upright stone tablet is first placed on the first milestone level and shown, when The left side for the corresponding milestone of previous hallmark events (the second milestone) that preceding level is shown and the right side of the 3rd milestone It is overlapping, and then one level of the 3rd milestone rising is shown, and it is not overlapping with the generation of other milestones in this level, because And the display location provided using the 3rd mileage in the position currently shown as it in the process for rendering generation.Thus, by upper State the arrangement to milestone position so that image generation process can directly according to the display location of each hallmark events, Call data to be shown, both solve the problem of milestone is overlapping, the efficiency of image generation can be improved again.
Further, above-mentioned steps S4 specific implementation process is:
It is distributed according to the scale of the progress bar, renders the framework for generating the progress bar;
According to each described sub-stage event in the scale interval of the progress bar and each sub-stage described The requirement that the color shown in progress bar is differed, renders the face for showing that the scale of each sub-stage is interval in the progress bar Color and the interval corresponding sub-stage event content of scale;
According to each described hallmark events in the display location of the progress bar, according to display location from top to bottom and Mode from right to left, is one by one rendered hallmark events in the progress bar in milestone mode, completes the progress bar Image generation.
It should be noted that the order of the image rendering generation of above-mentioned progress bar can be, framework, the Mei Yizi of progress bar Sign, the month time scale mark of stage, milestone, current date on a progress bar.And for each hallmark events Using milestone mode render order on a progress bar as:By display location priority up and down order, successively with top to bottm and from The right mode to a left side carries out inverted order and rendered.Wherein, mode from top to bottom, which is rendered, can hide the connection that may intersect well Line, this connecting line is the connecting line that milestone is connected in correspondence date calibration value, as shown in Fig. 2 the connection of the 3rd milestone Line can be hidden under the second milestone;Mode from right to left, the index of degression type compares, and can lift process performance, can To improve the speed of image rendering generation.
The method of project process bar image provided in an embodiment of the present invention generation, by receiving item purpose phase data and inner Journey landmark data, and phase data and mileage landmark data are parsed, the relevant parameter information of project is obtained, according to parameter information Automatically generating item purpose progress bar image is rendered, it is achieved thereby that the progress bar figure of project can be automatically generated according to project data Picture, and sub-stage and milestone typesetting in progress bar are adjusted, to ensure the reasonability of generation project progress bar image, so as to avoid Presentation of information on progress bar is blocked.
It is the structural representation of one embodiment of the device for the project process bar image generation that the present invention is provided referring to Fig. 3 Figure;The embodiment of the present invention also provides a kind of device of project process bar image generation, can implement the side of above-described embodiment offer Whole flows of method, are specifically included:
Data reception module 10, phase data and mileage landmark data for receiving the project;The phase data bag Include each sub-stage event of the project and the Start Date and Close Date of each sub-stage event;In described Journey landmark data includes each hallmark events of the project and the target date of each hallmark events;
Scale division module 20, for the Start Date and Close Date according to each sub-stage event, it is determined that The scale of the scale distribution of the progress bar and each sub-stage event in the progress bar is interval;
Mark shows determining module 30, for being distributed according to the scale of the mileage landmark data and the progress bar, it is determined that Display location of each hallmark events on the progress bar;And,
Image rendering generation module 40, for according to the distribution of the scale of the progress bar, each sub-stage event is in institute Display location of each the interval and described hallmark events of scale on the progress bar in progress bar is stated, life is rendered automatically Into the image of the progress bar.
Further, as shown in figure 4, the scale of the device for the project process bar image generation that Fig. 4, which is the present invention, to be provided is drawn The structural representation of one embodiment of sub-module;The scale division module 20, is specifically included:
Span number of days acquiring unit 21, for from the Start Date and Close Date of each sub-stage event, Sequence is extracted on most preceding date and last date, the whole story span number of days of the progress bar is obtained;
Span value computing unit 22, for calculating the width of the progress bar and the ratio of the progress bar whole story span number of days Value, obtains span value of the every day in the progress bar;
Scale distribution unit 23, for according to most preceding date, the last date and the progress bar across Angle value, determines the scale distribution of the progress bar;Wherein, the start index of the progress bar date most preceding for described in, described The scale that terminates of progress bar is the last date, and the distance between the adjacent scale of the progress bar is the progress bar Span value;
Scale interval determination unit 24, for being distributed according to the scale of the progress bar, it is determined that each described sub-stage The Start Date of event and Close Date distinguish corresponding scale value, obtain each described sub-stage event in the progress bar In scale it is interval.
Referring to Fig. 5, be the device for the project process bar image generation that the present invention is provided scale division module calculating with The structural representation of one embodiment of amending unit;
Further, the scale distribution also scale including arrow of the progress bar is distributed, then the scale division module Also include calculating is used for after the span value of the progress bar is obtained with amending unit 25, the calculating with amending unit 25, meter Calculate the arrow to account for the day numerical value of the progress bar and correct the span value of the progress bar, specifically include:
Arrow number of days computation subunit 251, for after the span value I of the progress bar is obtained, according to the arrow Preset length S1 and the progress bar span value I, calculate the day numerical value D1 that the arrow accounts for the progress bar,Wherein, floor () is downward bracket function;
Arrow calculations of offset subelement 252, the day numerical value D1 for accounting for the progress bar according to the arrow calculates described Deviant F1, F1=S1-D1*I between the preset length S1 of arrow and the physical length of the arrow;
Deviant judgment sub-unit 253, for judging the deviant F1 of the arrow and the deviant F2 of the progress bar Whether deviant threshold value is all higher than;Wherein, F2=S2-D2*I, S2 are the width of the progress bar;D2 is the beginning of the progress bar Last span number of days;
Span value revise subelemen 254, for when the arrow deviant F1 be more than the deviant threshold value when, or When the deviant F2 of the progress bar is more than the deviant threshold value, according to the deviant of the arrow, the progress is corrected The span value of bar is I,
Subelement 255 is recalculated, for the span value I according to the revised progress bar, the arrow is recalculated Head accounts for the day numerical value D1, the deviant F1 of the arrow and the progress bar of the progress bar deviant F2, until the arrow The deviant F1 of head and the deviant F2 of the progress bar are respectively less than the deviant threshold value;
Numerical value export subelement 256, for when the deviant F1 of the arrow and the deviant F2 of the progress bar it is small In the deviant threshold value, export the arrow and account for the day numerical value D1 of the progress bar and span value I of the progress bar.
It is that the mark of the device for the project process bar image generation that the present invention is provided shows the one of determining module referring to Fig. 6 The structural representation of individual embodiment;
Further, the mark shows determining module 30, specifically includes:
Milestone width calculation unit 31, for calculate the word occupy-place length of each hallmark events with it is described The product of the mark displaying ratio of progress bar, obtains each described hallmark events and is shown in the progress in milestone mode Milestone width in bar;The mark displaying ratio is text importing list occupied in the image of the progress bar Bit length;
Display location determining unit 32, for the milestone display mode set according to the progress bar and each mark The milestone width that sexual behavior part is shown in the progress bar, determines display of each hallmark events on the progress bar Position.
It is that the mark of the device for the project process bar image generation that the present invention is provided shows the aobvious of determining module referring to Fig. 7 Show the structural representation of one embodiment of position determination unit;
Further, the display location determining unit 32, is specifically included:
Sort subelement 321, for the target date according to each hallmark events, to each described mark Sexual behavior part is in chronological sequence ranked up;
Determination subelement 322 is put in first place, for for the 1st hallmark events, by the 1st hallmark events with inner Position when journey upright stone tablet display mode is shown in the first milestone level of the progress bar exists as the 1st hallmark events Position on the progress bar;
Judgment sub-unit 323 is put in non-first place, for for i-th of hallmark events, by i-th of hallmark events with When milestone display mode is shown in the position of the first milestone level of the progress bar, according to described i-th mark sexual behavior Position that part is shown in the progress bar and milestone width and the previous characteristic events shown in current milestone level Milestone position and milestone width, judge the previous of the milestones of i-th of hallmark events and level where it It is overlapping whether the milestone of individual hallmark events has;I is the natural number more than 1;
Second place determination subelement 324, for level where the milestone when i-th of hallmark events and its The milestone of previous hallmark events is when having overlapping, then to continue i-th of hallmark events with milestone display side The position that formula is shown in next milestone level of the progress bar is judged, until in i-th of hallmark events Journey upright stone tablet with its where level previous hallmark events milestone do not have it is overlapping untill, and will described i-th mark sexual behavior The position that part is shown in current milestone level is as i-th of hallmark events in the display location of the progress bar.
Second place determination subelement 325, for level where the milestone when i-th of hallmark events and its When the milestone of previous hallmark events does not have overlapping, i-th of hallmark events are shown in current milestone level Position as i-th of hallmark events in the display location of the progress bar.
It is the one of the image rendering generation module of the device for the project process bar image generation that the present invention is provided referring to Fig. 8 The structural representation of individual embodiment;
Further, described image renders generation module and specifically included:
Framework rendering unit 41, for being distributed according to the scale of the progress bar, renders the framework for generating the progress bar;
Stage rendering unit 42, for according to each described sub-stage event the scale of the progress bar it is interval and The requirement that the color that each sub-stage is shown in the progress bar is differed, renders and each son is shown in the progress bar The interval color of the scale in stage and the interval corresponding sub-stage event content of scale;
Milestone rendering unit 43, for each described hallmark events of basis in the display location of the progress bar, According to display location mode from top to bottom and from right to left, one by one by hallmark events with milestone mode render it is described enter Spend in bar, complete the image generation of the progress bar.
Yet further, the milestone display mode is:The target date of hallmark events is on the progress bar The center of the milestone of scale value position and the hallmark events is shown described significant with an axis The target date of the milestone of event and the hallmark events scale value position on the progress bar connecting line.
The device of project process bar image provided in an embodiment of the present invention generation, by receiving item purpose phase data and inner Journey landmark data, and phase data and mileage landmark data are parsed, the relevant parameter information of project is obtained, according to parameter information Automatically generating item purpose progress bar image is rendered, it is achieved thereby that the progress bar figure of project can be automatically generated according to project data Picture, and sub-stage and milestone typesetting in progress bar are adjusted, to ensure the reasonability of generation project progress bar image, so as to avoid Presentation of information on progress bar is blocked.
One of ordinary skill in the art will appreciate that realize all or part of flow in above-described embodiment method, being can be with The hardware of correlation is instructed to complete by computer program, described program can be stored in a computer read/write memory medium In, the program is upon execution, it may include such as the flow of the embodiment of above-mentioned each method.Wherein, described storage medium can be magnetic Dish, CD, read-only memory (Read-OnlyMemory, ROM) or random access memory (RandomAccess Memory, RAM) etc..
Described above is the preferred embodiment of the present invention, it is noted that for those skilled in the art For, under the premise without departing from the principles of the invention, some improvements and modifications can also be made, these improvements and modifications are also considered as Protection scope of the present invention.

Claims (14)

1. a kind of method of project process bar image generation, it is characterised in that including:
Receive the phase data and mileage landmark data of the project;The phase data includes each sub-stage of the project The Start Date and Close Date of event and each sub-stage event;The milestone data include the every of the project The target date of one hallmark events and each hallmark events;
According to the Start Date and Close Date of each sub-stage event, determine that the scale of the progress bar is distributed and every Scale of one sub- stage event in the progress bar is interval;
It is distributed according to the scale of the mileage landmark data and the progress bar, determines each hallmark events in the progress bar On display location;
It is interval and described every according to the distribution of the scale of the progress bar, each scale of sub-stage event in the progress bar Display location of one hallmark events on the progress bar, renders the image for generating the progress bar automatically.
2. the method for project process bar image as claimed in claim 1 generation, it is characterised in that described in the basis each The Start Date and Close Date of sub-stage event, determine that the scale of the progress bar is distributed with each sub-stage event in institute The scale stated in progress bar is interval, is specially:
From the Start Date and Close Date of each sub-stage event, sequence is extracted on most preceding date and last Date, obtain the whole story span number of days of the progress bar;
The width of the progress bar and the ratio of the progress bar whole story span number of days are calculated, every day is obtained in the progress bar Span value;
According to the span value of most preceding date, the last date and the progress bar, the quarter of the progress bar is determined Degree distribution;Wherein, the start index of the progress bar is most preceding date, the termination scale of the progress bar for it is described most Date afterwards, the distance between the adjacent scale of the progress bar is the span value of the progress bar;
It is distributed according to the scale of the progress bar, it is determined that the Start Date of each sub-stage event and Close Date difference Corresponding scale value, obtains scale of each the described sub-stage event in the progress bar interval.
3. the method for project process bar image generation as claimed in claim 2, it is characterised in that the scale of the progress bar point The cloth also scale including arrow is distributed, then the method for the project process bar image generation also includes, and is obtaining the progress bar Span value after, calculate the arrow and account for the day numerical value of the progress bar and correct the span value of the progress bar, be specially:
After the span value I of the progress bar is obtained, according to the preset length S1 of the arrow and the progress bar span value I, calculates the day numerical value D1 that the arrow accounts for the progress bar,Wherein, floor () is to round letter downwards Number;
The day numerical value D1 of the progress bar is accounted for according to the arrow, the preset length S1 of the arrow and the reality of the arrow is calculated Deviant F1, F1=S1-D1*I between the length of border;
Judge whether the deviant F1 of the arrow and the deviant F2 of the progress bar are all higher than deviant threshold value;Wherein, F2 =S2-D2*I, S2 are the width of the progress bar;D2 is the whole story span number of days of the progress bar;
When the deviant F1 of the arrow is more than the deviant threshold value, or when the deviant F2 of the progress bar is more than institute When stating deviant threshold value, according to the deviant of the arrow, the span value for correcting the progress bar is I,
According to the span value I of the revised progress bar, recalculate the arrow and account for the day numerical value D1 of the progress bar, institute State the deviant F1 of arrow and the deviant F2 of the progress bar, until the arrow deviant F1 and the progress bar it is inclined Shifting value F2 is respectively less than the deviant threshold value;
When the deviant F1 of the arrow and the deviant F2 of the progress bar are respectively less than the deviant threshold value, the arrow is exported Head accounts for the day numerical value D1 of the progress bar and span value I of the progress bar.
4. the method for project process bar image generation as claimed in claim 1, it is characterised in that described according to the milestone The scale value of data and the progress bar, determines display location of each hallmark events on the progress bar, is specially:
The product of the word occupy-place length of each hallmark events and the mark displaying ratio of the progress bar is calculated, is obtained Obtain the milestone width that each described hallmark events are shown in milestone mode in the progress bar;The mark display Ratio is text importing unit length occupied in the image of the progress bar;
What the milestone display mode and each hallmark events set according to the progress bar was shown in the progress bar Milestone width, determines display location of each hallmark events on the progress bar.
5. the method for project process bar image generation as claimed in claim 4, it is characterised in that described according to the progress bar The milestone width that the milestone display mode and each hallmark events of setting are shown in the progress bar, is determined each Display location of the individual hallmark events on the progress bar, be specially:
According to the target date of each hallmark events, each described hallmark events are in chronological sequence arranged Sequence;
For the 1st hallmark events, the 1st hallmark events are included in the progress bar with milestone display mode The first milestone level when position be used as the 1st position of the hallmark events on the progress bar;
For i-th of hallmark events, i-th of hallmark events are included in the progress bar with milestone display mode The first milestone level position when, the position that is shown according to i-th of hallmark events in the progress bar and inner The position and milestone width of journey upright stone tablet width and the milestone of the previous characteristic events shown in current milestone level, sentence Whether the milestone of disconnected i-th of hallmark events and the milestone of the previous hallmark events of level where it have weight It is folded;I is the natural number more than 1;
If so, then continue by i-th of hallmark events with milestone display mode include the progress bar it is next in The position of journey upright stone tablet level is judged, until the milestone of i-th of hallmark events and the previous mark of level where it The milestone of will sexual behavior part do not have it is overlapping untill, and the position that i-th of hallmark events are shown in current milestone level Put as i-th of hallmark events in the display location of the progress bar.
If it is not, regarding i-th of hallmark events as described i-th mark sexual behavior in the position that current milestone level is shown Part is in the display location of the progress bar.
6. the method for project process bar image generation as claimed in claim 1, it is characterised in that described according to the progress bar Scale distribution, each sub-stage event in each interval and described hallmark events of the scale of the progress bar described Display location on progress bar, renders the image for generating the progress bar automatically, is specially:
It is distributed according to the scale of the progress bar, renders the framework for generating the progress bar;
According to each described sub-stage event in the scale interval of the progress bar and each sub-stage in the progress The requirement that the color shown in bar is differed, render shown in the progress bar color that the scale of each sub-stage is interval and The interval corresponding sub-stage event content of scale;
According to each described hallmark events in the display location of the progress bar, according to display location from top to bottom and from the right side To left mode, hallmark events are rendered in the progress bar in milestone mode one by one, the figure of the progress bar is completed As generation.
7. the method for the project process bar image generation as described in claim 5 or 6, it is characterised in that the milestone is shown Mode is:Scale value position and the hallmark events of the target date correspondence of hallmark events on the progress bar Milestone center with an axis, and the milestone and the hallmark events of the display hallmark events Target date the scale value position on the progress bar connecting line.
8. a kind of device of project process bar image generation, it is characterised in that including:
Data reception module, phase data and mileage landmark data for receiving the project;The phase data includes described Each sub-stage event of project and the Start Date and Close Date of each sub-stage event;The milestone number According to each hallmark events including the project and the target date of each hallmark events;
Scale division module, for the Start Date and Close Date according to each sub-stage event, it is determined that it is described enter Spend the scale of the scale distribution and each sub-stage event of bar in the progress bar interval;
Mark shows determining module, for being distributed according to the scale of the mileage landmark data and the progress bar, determines each Display location of the hallmark events on the progress bar;And,
Image rendering generation module, for according to the distribution of the scale of the progress bar, each sub-stage event is in the progress Display location of each the interval and described hallmark events of scale in bar on the progress bar, renders generation described automatically The image of progress bar.
9. the device of project process bar image generation as claimed in claim 8, it is characterised in that the scale division module, Specifically include:
Span number of days acquiring unit, for from the Start Date and Close Date of each sub-stage event, extracting Sequence obtains the whole story span number of days of the progress bar on most preceding date and last date;
Span value computing unit, for calculating the width of the progress bar and the ratio of the progress bar whole story span number of days, is obtained Obtain span value of the every day in the progress bar;
Scale distribution unit, for the span value on most preceding date, the last date and the progress bar according to, really The scale distribution of the fixed progress bar;Wherein, the start index of the progress bar date most preceding for described in, the progress bar Termination scale is the last date, and the distance between the adjacent scale of the progress bar is the span value of the progress bar;
Scale interval determination unit, for being distributed according to the scale of the progress bar, it is determined that each sub-stage event Start Date and Close Date distinguish corresponding scale value, obtain each the described quarter of sub-stage event in the progress bar Degree is interval.
10. the device of project process bar image generation as claimed in claim 9, it is characterised in that the scale of the progress bar The distribution also scale including arrow is distributed, then the scale division module also includes calculating and amending unit, and the calculating is with repairing Positive unit is used for after the span value of the progress bar is obtained, and calculates day numerical value and amendment institute that the arrow accounts for the progress bar The span value of progress bar is stated, is specifically included:
Arrow number of days computation subunit, for after the span value I of the progress bar is obtained, according to the preset length of the arrow S1 and the progress bar span value I, calculate the day numerical value D1 that the arrow accounts for the progress bar,Its In, floor () is downward bracket function;
Arrow calculations of offset subelement, the day numerical value D1 for accounting for the progress bar according to the arrow calculates the arrow Deviant F1, F1=S1-D1*I between the physical length of preset length S1 and the arrow;
Deviant judgment sub-unit, for judge the arrow deviant F1 and the progress bar deviant F2 it is whether big In deviant threshold value;Wherein, F2=S2-D2*I, S2 are the width of the progress bar;D2 is the whole story span day of the progress bar Number;
Span value revise subelemen, for when the deviant F1 of the arrow is more than the deviant threshold value, or when described When the deviant F2 of progress bar is more than the deviant threshold value, according to the deviant of the arrow, correct the progress bar across Angle value is I,
Subelement is recalculated, for the span value I according to the revised progress bar, the arrow is recalculated and accounts for described Day numerical value D1, the deviant F1 of the arrow and the deviant F2 of the progress bar of progress bar, until the skew of the arrow The deviant F2 of value F1 and the progress bar is respectively less than the deviant threshold value;
Numerical value export subelement, for when the deviant F1 of the arrow and deviant F2 of the progress bar be respectively less than it is described partially Shifting value threshold value, exports the arrow and accounts for the day numerical value D1 of the progress bar and span value I of the progress bar.
11. the device of project process bar image generation as claimed in claim 8, it is characterised in that the mark display is determined Module, is specifically included:
Milestone width calculation unit, word occupy-place length and the progress bar for calculating each hallmark events Mark displaying ratio product, obtain each described hallmark events and be shown in milestone mode in the progress bar Milestone width;The mark displaying ratio is that text importing unit occupied in the image of the progress bar is long Degree;
Display location determining unit, for the milestone display mode set according to the progress bar and each hallmark events The milestone width shown in the progress bar, determines display location of each hallmark events on the progress bar.
12. the device of project process bar image generation as claimed in claim 11, it is characterised in that the display location is determined Unit, is specifically included:
Sort subelement, for the target date according to each hallmark events, to each described hallmark events In chronological sequence it is ranked up;
Determination subelement is put in first place, for for the 1st hallmark events, the 1st hallmark events to be shown with milestone The position when mode of showing is shown in the first milestone level of the progress bar as the 1st hallmark events it is described enter The position spent on bar;
Judgment sub-unit is put in non-first place, for for i-th of hallmark events, by i-th of hallmark events with milestone When display mode is shown in the position of the first milestone level of the progress bar, according to i-th of hallmark events in institute State the mileage of the position shown in progress bar and milestone width and the previous characteristic events shown in current milestone level The position of upright stone tablet and milestone width, judge the milestone and the previous mark of level where it of i-th of hallmark events It is overlapping whether the milestone of sexual behavior part has;I is the natural number more than 1;
Second place determination subelement, for the milestone when i-th of hallmark events with its where level it is previous The milestone of hallmark events is when having overlapping, then to continue to show i-th of hallmark events with milestone display mode Judged in the position of next milestone level of the progress bar, until i-th of hallmark events milestone with The milestone of the previous hallmark events of level where it does not have it is overlapping untill, and will i-th of hallmark events ought The position that preceding milestone level is shown is as i-th of hallmark events in the display location of the progress bar.
Second place determination subelement, for the milestone when i-th of hallmark events with its where level it is previous When the milestone of hallmark events does not have overlapping, the position that i-th of hallmark events are shown in current milestone level As i-th of hallmark events in the display location of the progress bar.
13. the device of project process bar image generation as claimed in claim 8, it is characterised in that described image renders generation Module is specifically included:
Framework rendering unit, for being distributed according to the scale of the progress bar, renders the framework for generating the progress bar;
Stage rendering unit, for according to each described sub-stage event the scale of the progress bar it is interval and each The requirement that the color that sub-stage is shown in the progress bar is differed, renders and each sub-stage is shown in the progress bar The interval color of scale and the interval corresponding sub-stage event content of scale;
Milestone rendering unit, for, in the display location of the progress bar, foundation to be aobvious according to each described hallmark events Show the mode of position from top to bottom and from right to left, one by one render hallmark events in the progress bar in milestone mode In, complete the image generation of the progress bar.
14. the device of the project process bar image generation as described in claim 12 or 13, it is characterised in that the milestone shows The mode of showing is:Scale value position and the mark sexual behavior of the target date correspondence of hallmark events on the progress bar The center of the milestone of part is with an axis, and the milestone and the hallmark events of the display hallmark events Target date scale value position on the progress bar connecting line.
CN201710283133.8A 2017-04-26 2017-04-26 Method and device for generating project progress bar image Active CN107122188B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710283133.8A CN107122188B (en) 2017-04-26 2017-04-26 Method and device for generating project progress bar image

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710283133.8A CN107122188B (en) 2017-04-26 2017-04-26 Method and device for generating project progress bar image

Publications (2)

Publication Number Publication Date
CN107122188A true CN107122188A (en) 2017-09-01
CN107122188B CN107122188B (en) 2021-05-11

Family

ID=59726053

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710283133.8A Active CN107122188B (en) 2017-04-26 2017-04-26 Method and device for generating project progress bar image

Country Status (1)

Country Link
CN (1) CN107122188B (en)

Cited By (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107680149A (en) * 2017-10-09 2018-02-09 广州四三九九信息科技有限公司 Project tendency drawing drawing method, device and server
CN108595678A (en) * 2018-05-02 2018-09-28 网易(杭州)网络有限公司 Task data processing method and processing device, electronic equipment, storage medium
CN108921493A (en) * 2018-05-31 2018-11-30 沈文策 A kind of information display method and device based on display interface
CN109343778A (en) * 2018-09-25 2019-02-15 北京金山安全软件有限公司 Display method and device and electronic equipment
WO2019105222A1 (en) * 2017-11-28 2019-06-06 深圳市大疆创新科技有限公司 Generation device, generation system, image capturing system, moving body, and generation method
CN109901894A (en) * 2017-12-07 2019-06-18 腾讯科技(深圳)有限公司 A kind of progress bar image generating method, device and storage medium
CN112149020A (en) * 2020-09-17 2020-12-29 成都知道创宇信息技术有限公司 Progress bar display method and device, electronic equipment and storage medium
CN113780860A (en) * 2021-09-17 2021-12-10 上海易立德信息技术股份有限公司 Progress display method and system for milestone and storage medium
CN114020266A (en) * 2021-10-28 2022-02-08 四川启睿克科技有限公司 Method for realizing sectional type progress bar assembly based on VUE

Citations (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101630252A (en) * 2009-07-07 2010-01-20 中国科学院软件研究所 Method for controlling software project progress based on process stimulating technology
CN103136636A (en) * 2013-03-15 2013-06-05 中广核工程有限公司 Nuclear power project progress measuring method and system
US20130227350A1 (en) * 2012-02-23 2013-08-29 Cadence Design Systems, Inc. Recording and playback of trace and video log data for programs
CN103699953A (en) * 2013-11-06 2014-04-02 北京驭时德隆科技有限公司 Project management system, and data processing method and device thereof
CN104573991A (en) * 2015-01-28 2015-04-29 携程计算机技术(上海)有限公司 Project process management system
CN106408271A (en) * 2016-10-10 2017-02-15 上海博辕信息技术服务有限公司 Method and device for monitoring project
CN106408172A (en) * 2016-08-31 2017-02-15 广东达安项目管理股份有限公司 Project management system
CN106529788A (en) * 2016-10-25 2017-03-22 乐视控股(北京)有限公司 Project plan chart generation method and device
CN106529904A (en) * 2016-10-25 2017-03-22 乐视控股(北京)有限公司 Branching view generating method and branching view generating device

Patent Citations (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101630252A (en) * 2009-07-07 2010-01-20 中国科学院软件研究所 Method for controlling software project progress based on process stimulating technology
US20130227350A1 (en) * 2012-02-23 2013-08-29 Cadence Design Systems, Inc. Recording and playback of trace and video log data for programs
CN103136636A (en) * 2013-03-15 2013-06-05 中广核工程有限公司 Nuclear power project progress measuring method and system
CN103699953A (en) * 2013-11-06 2014-04-02 北京驭时德隆科技有限公司 Project management system, and data processing method and device thereof
CN104573991A (en) * 2015-01-28 2015-04-29 携程计算机技术(上海)有限公司 Project process management system
CN106408172A (en) * 2016-08-31 2017-02-15 广东达安项目管理股份有限公司 Project management system
CN106408271A (en) * 2016-10-10 2017-02-15 上海博辕信息技术服务有限公司 Method and device for monitoring project
CN106529788A (en) * 2016-10-25 2017-03-22 乐视控股(北京)有限公司 Project plan chart generation method and device
CN106529904A (en) * 2016-10-25 2017-03-22 乐视控股(北京)有限公司 Branching view generating method and branching view generating device

Non-Patent Citations (2)

* Cited by examiner, † Cited by third party
Title
LI SHUHUA ET AL.: "《project process bar image》", 《2011 INTERNATIONAL CONFERENCE ON CONSUMER ELECTRONICS, COMMUNICATIONS AND NETWORKS (CECNET)》 *
王学营: "《海洋工程项目进度计划管理技术研究》", 《中国优秀硕士学位论文全文数据库(电子期刊)信息科技辑》 *

Cited By (14)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107680149A (en) * 2017-10-09 2018-02-09 广州四三九九信息科技有限公司 Project tendency drawing drawing method, device and server
US11340772B2 (en) 2017-11-28 2022-05-24 SZ DJI Technology Co., Ltd. Generation device, generation system, image capturing system, moving body, and generation method
WO2019105222A1 (en) * 2017-11-28 2019-06-06 深圳市大疆创新科技有限公司 Generation device, generation system, image capturing system, moving body, and generation method
CN109901894A (en) * 2017-12-07 2019-06-18 腾讯科技(深圳)有限公司 A kind of progress bar image generating method, device and storage medium
CN109901894B (en) * 2017-12-07 2021-06-08 腾讯科技(深圳)有限公司 Progress bar image generation method and device and storage medium
CN108595678A (en) * 2018-05-02 2018-09-28 网易(杭州)网络有限公司 Task data processing method and processing device, electronic equipment, storage medium
CN108921493A (en) * 2018-05-31 2018-11-30 沈文策 A kind of information display method and device based on display interface
CN109343778A (en) * 2018-09-25 2019-02-15 北京金山安全软件有限公司 Display method and device and electronic equipment
CN112149020A (en) * 2020-09-17 2020-12-29 成都知道创宇信息技术有限公司 Progress bar display method and device, electronic equipment and storage medium
CN112149020B (en) * 2020-09-17 2023-04-28 成都知道创宇信息技术有限公司 Progress bar display method and device, electronic equipment and storage medium
CN113780860A (en) * 2021-09-17 2021-12-10 上海易立德信息技术股份有限公司 Progress display method and system for milestone and storage medium
CN113780860B (en) * 2021-09-17 2022-11-29 上海易立德信息技术股份有限公司 Progress display method, system and storage medium for milestone
CN114020266A (en) * 2021-10-28 2022-02-08 四川启睿克科技有限公司 Method for realizing sectional type progress bar assembly based on VUE
CN114020266B (en) * 2021-10-28 2024-04-12 四川启睿克科技有限公司 Method for realizing sectional progress bar assembly based on VUE

Also Published As

Publication number Publication date
CN107122188B (en) 2021-05-11

Similar Documents

Publication Publication Date Title
CN107122188A (en) The method and device of project process bar image generation
US11036930B2 (en) Methods, systems and computer program products for facilitating visualization of interrelationships in a spreadsheet
US6738761B1 (en) Information processing system capable of indicating tendency to change
US7424668B2 (en) Pre-formulated spreadsheet cell groups
US8965799B2 (en) Reading, organizing and manipulating accounting data
US6018617A (en) Test generating and formatting system
CN102591848A (en) Selection of foreground characteristics based on background
US20090006939A1 (en) Task-specific spreadsheet worksheets
US20140344291A9 (en) Tabular Data Sorting and Display
JPS59137987A (en) Graphic pattern overlapping method
US8700983B2 (en) Method of generating a graphical resume
CN104346405B (en) A kind of method and device of the Extracting Information from webpage
US11929049B2 (en) Output content generation apparatus, output content generation method and program
KR101966177B1 (en) Method and system for processing multi-dimentional spread sheet document
EP0120977A1 (en) Card image data processing system
CN106126031A (en) The method of a kind of word input and terminal
JPS62241066A (en) Program execution control for processing form of data processor
CN108228115B (en) A kind of browser shows the Method of printing and device of the page
CN113221509B (en) Automatic generation method, device and equipment of slide and storage medium
JP7226136B2 (en) Information processing device and program
CN109254807A (en) The method of two-page separation function is realized in a kind of ios system
KR102032084B1 (en) Method and system for processing multi-dimentional spread sheet document
Walkenbach et al. Excel 2000
Bryer et al. Package ‘multilevelPSA’
Katz et al. Excel 2010 Made Simple

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant