CN107090953A - A kind of punching drain measure method before waterproofing and thermal insulation of roofing construction - Google Patents

A kind of punching drain measure method before waterproofing and thermal insulation of roofing construction Download PDF

Info

Publication number
CN107090953A
CN107090953A CN201710441724.3A CN201710441724A CN107090953A CN 107090953 A CN107090953 A CN 107090953A CN 201710441724 A CN201710441724 A CN 201710441724A CN 107090953 A CN107090953 A CN 107090953A
Authority
CN
China
Prior art keywords
roof
drainage
layer
drainpipe
construction
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201710441724.3A
Other languages
Chinese (zh)
Inventor
周骏宇
季韬
余学晖
余美佑
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
FUJIAN MINHUA WATERPROOF MATERIAL ENGINEERING Co Ltd
Original Assignee
FUJIAN MINHUA WATERPROOF MATERIAL ENGINEERING Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by FUJIAN MINHUA WATERPROOF MATERIAL ENGINEERING Co Ltd filed Critical FUJIAN MINHUA WATERPROOF MATERIAL ENGINEERING Co Ltd
Priority to CN201710441724.3A priority Critical patent/CN107090953A/en
Publication of CN107090953A publication Critical patent/CN107090953A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04DROOF COVERINGS; SKY-LIGHTS; GUTTERS; ROOF-WORKING TOOLS
    • E04D13/00Special arrangements or devices in connection with roof coverings; Protection against birds; Roof drainage ; Sky-lights
    • E04D13/04Roof drainage; Drainage fittings in flat roofs, balconies or the like

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Building Environments (AREA)

Abstract

The present invention provides a kind of punching drain measure method before waterproofing and thermal insulation of roofing construction, comprises the following steps:1st, the debris of roof construction layer is cleaned;2nd, water is sprinkled with roof construction layer, the roof ponding bosom on roof construction layer is found out;3rd, a drainage hole is made a call in roof ponding bosom;4th, drainage thread is penetrated in drainage hole and carries out water conservancy diversion, the outer surface of drainage thread is fitted in the inwall of drainage hole, and drainage thread upper end is fixed on roof construction layer, and lower end is stretched into the bucket in roof construction layer lower chambers;Or drainpipe is docked in the water outlet of drainage hole, the lower port of drainpipe is stretched into the bucket in roof construction layer lower chambers;5th, roof ponding flows in the presence of gravity and diffusion along the inwall of drainage hole, is flowed to by drainage thread or drainpipe in bucket;6th, after the construction that heat-insulation layer and waterproof layer are completed on roof construction layer, drainage thread or drainpipe are removed, drainage hole is blocked.The present invention is easy to drain roof ponding.

Description

A kind of punching drain measure method before waterproofing and thermal insulation of roofing construction
Technical field
The present invention relates to the punching water conservancy diversion row before technical field of building construction, more particularly to a kind of construction of waterproofing and thermal insulation of roofing Water method.
Background technology
The roofing area of modern building is larger, in rainy season, if waterproof roll have little time it is complete before rainwater arrives If full construction terminates, rainwater will accumulate in foam concrete slowly seepage flow to roof construction layer.Over time, Roof construction layer meeting occurrence of large-area infiltration destruction, waterproof layer is also due to drum destruction has occurred for the gasification of ponding.
The content of the invention
The technical problem to be solved in the present invention, is to provide the punching drain measure side before a kind of waterproofing and thermal insulation of roofing construction Method, is easy to drain roof ponding.
What the present invention was realized in:
A kind of punching drain measure method before waterproofing and thermal insulation of roofing construction, comprises the following steps:
Step 1, base treatment:Before heat-insulation layer and construction of waterproof layer, the debris of roof construction layer is cleaned;
Step 2, look for low-lying place:Water is sprinkled with roof construction layer, is found out according to the depth profile of water on roof construction layer The roof ponding bosom of different zones on roof construction layer;
Step 3, punching processing:A drainage hole, two adjacent rows are made a call to the roof ponding bosom of different zones is each The distance between water through hole is no less than 2m;
Step 4, water conservancy diversion processing:Drainage thread is penetrated in drainage hole and carries out water conservancy diversion, the outer surface laminating of the drainage thread In the inwall of drainage hole, the drainage thread upper end is fixed on roof construction layer, and lower end is stretched into roof construction layer lower chambers Bucket in;Or drainpipe is docked in the water outlet of the drainage hole, the lower port of the drainpipe stretches into roofing knot In bucket in structure layer lower chambers;
Step 5, ponding are collected:Roof ponding flows in the presence of gravity and diffusion along the inwall of drainage hole, leads to Cross drainage thread or drainpipe is flowed in bucket;
Step 6, closure processing:The construction of heat-insulation layer and waterproof layer is sequentially completed on roof construction layer, after construction terminates, Confirm that the drainage thread or drainpipe remove the drainage thread or drainpipe after no longer dripping, and block drainage hole.
Further, the drainage thread is drainage cotton thread.
Further, the drainpipe is water drainage plastics pipe.
The invention has the advantages that:
The drainage technology of the present invention is simple, finds the low-lying place of roofing by the method for watering, threading is punched in lowest part, into This is relatively low, but preferable to the protecting effect of roof construction layer and waterproof layer, can accelerate foam concrete foam after rainy season construction Inside concrete ponding quickly discharges roofing;It can avoid because foam concrete ponding causes roof construction layer large area in roofing Infiltration destruction;It can avoid making waterproof layer play drum destruction because heat-insulation layer reclaimed water gasifies at high temperature.
Brief description of the drawings
The present invention is further illustrated in conjunction with the embodiments with reference to the accompanying drawings.
Fig. 1 is the execution flow chart for punching drain measure method before a kind of waterproofing and thermal insulation of roofing construction of the invention.
Fig. 2 shows for the structure of embodiment one in the punching drain measure method before a kind of waterproofing and thermal insulation of roofing construction of the invention It is intended to.
Fig. 3 shows for the structure of embodiment two in the punching drain measure method before a kind of waterproofing and thermal insulation of roofing construction of the invention It is intended to.
Label declaration in figure:
1- roof construction layers, 11- drainage holes, 2- drainage threads, 2'- drainpipes, 3- buckets, 4- heat-insulation layers, 5- waterproof layers.
Embodiment
To cause the present invention to become apparent, now with a preferred embodiment, and accompanying drawing is coordinated to be described in detail below.
Embodiment one:
As depicted in figs. 1 and 2, the punching drain measure method before a kind of waterproofing and thermal insulation of roofing of the invention construction, including Following steps:
Step 1, base treatment:Before heat-insulation layer 4 and waterproof layer 5 are constructed, the debris of roof construction layer 1 is cleaned;
Step 2, look for low-lying place:Water (about 5mm-30mm is thick) is sprinkled with roof construction layer 1, according on roof construction layer 1 The depth profile of water finds out the roof ponding bosom of different zones on roof construction layer 1;
Step 3, punching processing:A drainage hole 11, adjacent two are made a call to the roof ponding bosom of different zones is each The distance between drainage hole is no less than 2m;
Step 4, water conservancy diversion processing:Drainage thread 2 is penetrated in drainage hole 11 and carries out water conservancy diversion, the outer surface of the drainage thread 2 The inwall of drainage hole 11 is fitted in, the drainage thread 2 is consistent with the diameter of the drainage hole 11;The upper end of drainage thread 2 (reserved about 2cm length) is fixed on roof construction layer 1, and lower end is stretched into the bucket 3 in the lower chambers of roof construction layer 1;
Step 5, ponding are collected:Roof ponding flows in the presence of gravity and diffusion along the inwall of drainage hole 11, Flowed to by drainage thread 2 in bucket 3;
Step 6, closure processing:The construction of heat-insulation layer and waterproof layer is sequentially completed on roofing, after construction terminates, institute is confirmed State and the drainage thread 2 is removed after drainage thread 2 no longer drips, and block drainage hole 11.
The drainage thread 2 is drainage cotton thread, and the material of cotton thread is cotton fiber material, and relatively slimmer and more graceful, good water absorption is easy to The collection of roof ponding.
After raining, rainwater will accumulate in foam concrete slowly seepage flow to roof construction layer 1, the roof construction layer The roof ponding of 1 upper surface can flow toward the low-lying place of roof construction layer 1, then along the inwall stream of the drainage hole 11 Under, on the inwall that the drainage hole 11 is close to due to the drainage thread 2, roof ponding will take advantage of a situation absorption in the drainage On line 2, in the presence of gravity and diffusion, roof ponding can be located at the lower chambers of roof construction layer 1 along the drainage thread 2 flow direction In the interior bucket 3, roof ponding can be thus collected into the bucket 3 in time, facilitate draining.
Embodiment two:
As shown in figures 1 and 3, the punching drain measure method before a kind of waterproofing and thermal insulation of roofing of the invention construction, including Following steps:
Step 1, base treatment:Before heat-insulation layer 4 and waterproof layer 5 are constructed, the debris of roof construction layer 1 is cleaned;
Step 2, look for low-lying place:Water (about 5mm-30mm is thick) is sprinkled with roof construction layer 1, according on roof construction layer 1 The depth profile of water finds out the roof ponding bosom of different zones on roof construction layer 1;
Step 3, punching processing:A drainage hole 11, adjacent two are made a call to the roof ponding bosom of different zones is each The distance between drainage hole is no less than 8m;
Step 4, water conservancy diversion processing:Under water outlet docking the drainpipe 2', the drainpipe 2' of the drainage hole Port is stretched into the bucket 3 in the lower chambers of roof construction layer 1;
Step 5, ponding are collected:Roof ponding flows in the presence of gravity and diffusion along the inwall of drainage hole 11, Flowed to by drainpipe 2' in bucket 3;
Step 6, closure processing:The construction of heat-insulation layer and waterproof layer is sequentially completed on roofing, after construction terminates, institute is confirmed State and the drainpipe 2' is removed after drainpipe 2' no longer drips, and block drainage hole 11.
The drainpipe 2' is water drainage plastics pipe, the upper port of the drainpipe 2' and the delivery port of the drainage hole 11 Docking, the upper end of the drainpipe 2' is inserted in the bottom of the drainage hole 11, and the external diameter of the drainpipe 2' with The internal diameter of the delivery port of the drainage hole 11 is consistent, it is ensured that after inwall of the roof ponding along the drainage hole 11 is flowed down, It can flow into the drainpipe 2', the lower port of the drainpipe 2' is inserted in the bucket 3.
After raining, rainwater will accumulate in foam concrete slowly seepage flow to roof construction layer 1, the roof construction layer The roof ponding of 1 upper surface can flow toward the low-lying place of roof construction layer 1, then along the inwall stream of the drainage hole 11 Under, in the presence of gravity and diffusion, roof ponding can enter the drainpipe 2' along the inwall of the drainage hole 11, then Flowed to via the drainpipe 2' in the bucket 3 being located in the lower chambers of roof construction layer 1, thus can be in time by roofing Ponding is collected into the bucket 3, facilitates draining.
Embodiment one and the maximum difference of embodiment two are the difference of both diversion modes, and embodiment one is by leading Stream cotton thread guides to roof ponding in bucket 3, and embodiment two is to be guided to roof ponding in bucket 3 by drainpipe 2'.
Advantages of the present invention is as follows:
During construction, roof construction layer 1, heat-insulation layer 4 and waterproof layer 5 are disposed with from top to bottom, when the roof structure Layer 1 has been constructed completions, and the heat-insulation layer 4 or the waterproof layer 5 be when constructing also, and in the case of rainy, rainwater is just assembled Product is accomplished by carrying out draining to roof ponding this when in the upper surface and heat-insulation layer 4 of the roof construction layer 1.
The present invention is before the heat-insulation layer 4 and the waterproof layer 5 are constructed, at the low-lying place of the roof construction layer 1 Drainage hole 11 is opened up, roof ponding is guided in the drainage hole 11, then will by the drainage thread 2 or the drainpipe 2' Roof ponding is drained into the bucket 3, when the heat-insulation layer 4 and the waterproof layer 5 are all constructed after finishing, removes drainage thread 2 Or drainpipe 2', drainage hole 11 is blocked.
The drainage technology of the present invention is simple, finds the low-lying place of roofing by the method for watering, threading is punched in lowest part, into This is relatively low, but preferable to the protecting effect of roof construction layer 1 and waterproof layer 5, and this drainage pattern can accelerate foam concrete to exist Ponding quickly discharges roofing inside foam concrete after rainy season construction;It can avoid because foam concrete ponding causes room in roofing The infiltration destruction of the large area of face structure sheaf 1;It can avoid because 4 water gasify make the drum destruction of waterproof layer 5 at high temperature in heat-insulation layer.
Although the foregoing describing the embodiment of the present invention, those familiar with the art should manage Solution, the specific embodiment described by us is merely exemplary, rather than for the restriction to the scope of the present invention, is familiar with this The equivalent modification and change that the technical staff in field is made in the spirit according to the present invention, should all cover the present invention's In scope of the claimed protection.

Claims (3)

1. a kind of punching drain measure method before waterproofing and thermal insulation of roofing construction, it is characterised in that:Comprise the following steps:
Step 1, base treatment:Before heat-insulation layer and construction of waterproof layer, the debris of roof construction layer is cleaned;
Step 2, look for low-lying place:Water is sprinkled with roof construction layer, roofing is found out according to the depth profile of water on roof construction layer The roof ponding bosom of different zones on structure sheaf;
Step 3, punching processing:A drainage hole is made a call to the roof ponding bosom of different zones is each, and two adjacent drainings are led to The distance between hole is no less than 2m;
Step 4, water conservancy diversion processing:Drainage thread is penetrated in drainage hole and carries out water conservancy diversion, the outer surface of the drainage thread is fitted in row The inwall of water through hole, the drainage thread upper end is fixed on roof construction layer, the water that lower end is stretched into roof construction layer lower chambers In bucket;Or drainpipe is docked in the water outlet of the drainage hole, the lower port of the drainpipe stretches into roof construction layer In bucket in lower chambers;
Step 5, ponding are collected:Roof ponding flows in the presence of gravity and diffusion along the inwall of drainage hole, by drawing Streamline or drainpipe are flowed in bucket;
Step 6, closure processing:The construction of heat-insulation layer and waterproof layer is sequentially completed on roof construction layer, after construction terminates, is confirmed The drainage thread or drainpipe remove the drainage thread or drainpipe after no longer dripping, and block drainage hole.
2. the punching drain measure method before a kind of waterproofing and thermal insulation of roofing construction according to claim 1, it is characterised in that: The drainage thread is drainage cotton thread.
3. the punching drain measure method before a kind of waterproofing and thermal insulation of roofing construction according to claim 1, it is characterised in that: The drainpipe is water drainage plastics pipe.
CN201710441724.3A 2017-06-13 2017-06-13 A kind of punching drain measure method before waterproofing and thermal insulation of roofing construction Pending CN107090953A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710441724.3A CN107090953A (en) 2017-06-13 2017-06-13 A kind of punching drain measure method before waterproofing and thermal insulation of roofing construction

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710441724.3A CN107090953A (en) 2017-06-13 2017-06-13 A kind of punching drain measure method before waterproofing and thermal insulation of roofing construction

Publications (1)

Publication Number Publication Date
CN107090953A true CN107090953A (en) 2017-08-25

Family

ID=59640057

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710441724.3A Pending CN107090953A (en) 2017-06-13 2017-06-13 A kind of punching drain measure method before waterproofing and thermal insulation of roofing construction

Country Status (1)

Country Link
CN (1) CN107090953A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107882156A (en) * 2017-12-10 2018-04-06 成都隶盈科技有限公司 The construction method that a kind of basement guarded drainage combines

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1117305A (en) * 1993-12-01 1996-02-21 格布瑞特技术股份公司 Roof-water run-in
CN202227940U (en) * 2011-07-18 2012-05-23 佳木斯大学 Collector for collecting water accumulated on indoor windowsill
CN103938807A (en) * 2014-05-07 2014-07-23 邹尚云 Green, ecological and environment-friendly roof and construction method of green, ecological and environment-friendly roof
CN204850272U (en) * 2015-07-24 2015-12-09 职慧云 Building roof eaves mouth drainage structures
KR101644042B1 (en) * 2015-04-23 2016-07-29 강영심 Waterproofing method for the rooftop

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1117305A (en) * 1993-12-01 1996-02-21 格布瑞特技术股份公司 Roof-water run-in
CN202227940U (en) * 2011-07-18 2012-05-23 佳木斯大学 Collector for collecting water accumulated on indoor windowsill
CN103938807A (en) * 2014-05-07 2014-07-23 邹尚云 Green, ecological and environment-friendly roof and construction method of green, ecological and environment-friendly roof
KR101644042B1 (en) * 2015-04-23 2016-07-29 강영심 Waterproofing method for the rooftop
CN204850272U (en) * 2015-07-24 2015-12-09 职慧云 Building roof eaves mouth drainage structures

Non-Patent Citations (2)

* Cited by examiner, † Cited by third party
Title
无语翘楚: "《百度知道》", 28 October 2015 *
杨永起等: "《建筑防水施工技术》", 31 October 2015, 北京:中国建材工业出版社 *

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107882156A (en) * 2017-12-10 2018-04-06 成都隶盈科技有限公司 The construction method that a kind of basement guarded drainage combines

Similar Documents

Publication Publication Date Title
CN204326390U (en) Shed deckhead drainage system
CN207829026U (en) A kind of basement waterproofing structure
CN103266724B (en) Drainage structure of planted roof
CN207927433U (en) A kind of gardens water ecology circulatory system
CN206707132U (en) A kind of ecological grassplot that reutilization system is collected with siphon drainage
CN203583797U (en) Invisible drainage connecting device in decorative heat-preserving layer of roof
CN106884508A (en) A kind of ecological grassplot that reutilization system is collected with siphon drainage
CN205369740U (en) Zero slope protection siphon drainage collecting system of pds
CN206467914U (en) The discharge structure of planted roof
CN206128314U (en) Waterproof system of building masonry wall
CN201245930Y (en) Support point type plastic sandwich plate planting roof drainage structure
CN107090953A (en) A kind of punching drain measure method before waterproofing and thermal insulation of roofing construction
CN108086444A (en) A kind of gardens water storage device
CN110306736A (en) A kind of reinforced concrete roof waterproof construction
CN205421741U (en) Prevent drainage system with layer
CN206256341U (en) City ponding collection system
CN210421325U (en) Prevent soil erosion and water loss's greenbelt
CN107100671A (en) A kind of pressure surface shape of tunnel rich water country rock, which drops down, draws drainage mechanism in adfluxion
CN207032698U (en) A kind of punching drain measure structure before waterproofing and thermal insulation of roofing construction
CN207331931U (en) A kind of water seepage prevention floor drain
CN206801577U (en) A kind of waterproof/drainage structure of mountain tunnel vault and mid-board
CN203188498U (en) Planted roof drainage structure
CN207110272U (en) A kind of glass sunlight house platform waterproof construction
CN208309760U (en) Drain structure and floor heating ground structure
CN107882156A (en) The construction method that a kind of basement guarded drainage combines

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
CB02 Change of applicant information
CB02 Change of applicant information

Address after: 350000 the 2 floor, 202 room, 416 section of the regulatory building of Fuzhou bonded port processing trade zone, Fuzhou, Fujian.

Applicant after: Fujian min Hua Building Materials Science and Technology Development Co., Ltd.

Address before: 350000 the 2 floor, 202 room, 416 section of the regulatory building of Fuzhou bonded port processing trade zone, Fuzhou, Fujian.

Applicant before: FUJIAN MINHUA WATERPROOF MATERIAL ENGINEERING CO., LTD.

RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20170825