CN107083993A - The Embedment and installation structure and installation method of Safety Monitoring Instruments in the long tunnel of high water head - Google Patents

The Embedment and installation structure and installation method of Safety Monitoring Instruments in the long tunnel of high water head Download PDF

Info

Publication number
CN107083993A
CN107083993A CN201611146690.7A CN201611146690A CN107083993A CN 107083993 A CN107083993 A CN 107083993A CN 201611146690 A CN201611146690 A CN 201611146690A CN 107083993 A CN107083993 A CN 107083993A
Authority
CN
China
Prior art keywords
tunnel
embedment
monitoring
instrument
wooden case
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201611146690.7A
Other languages
Chinese (zh)
Other versions
CN107083993B (en
Inventor
周克明
李聂贵
周柏兵
钱亚俊
李家群
李震
王嵩
储华平
范光亚
吴健琨
杨建喜
孙国强
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
JIANGSU NANSHUI TECHNOLOGY Co Ltd
Nanjing Water Conservancy and Hydrology Automatization Institute Ministry of Water Resources
Original Assignee
JIANGSU NANSHUI TECHNOLOGY Co Ltd
Nanjing Water Conservancy and Hydrology Automatization Institute Ministry of Water Resources
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by JIANGSU NANSHUI TECHNOLOGY Co Ltd, Nanjing Water Conservancy and Hydrology Automatization Institute Ministry of Water Resources filed Critical JIANGSU NANSHUI TECHNOLOGY Co Ltd
Priority to CN201611146690.7A priority Critical patent/CN107083993B/en
Publication of CN107083993A publication Critical patent/CN107083993A/en
Application granted granted Critical
Publication of CN107083993B publication Critical patent/CN107083993B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21FSAFETY DEVICES, TRANSPORT, FILLING-UP, RESCUE, VENTILATION, OR DRAINING IN OR OF MINES OR TUNNELS
    • E21F17/00Methods or devices for use in mines or tunnels, not covered elsewhere
    • E21F17/18Special adaptations of signalling or alarm devices
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/04Lining with building materials
    • E21D11/10Lining with building materials with concrete cast in situ; Shuttering also lost shutterings, e.g. made of blocks, of metal plates or other equipment adapted therefor
    • E21D11/102Removable shuttering; Bearing or supporting devices therefor

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Architecture (AREA)
  • Structural Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Geology (AREA)
  • Civil Engineering (AREA)
  • Lining And Supports For Tunnels (AREA)
  • Geophysics And Detection Of Objects (AREA)

Abstract

The invention discloses the Embedment and installation structure of Safety Monitoring Instruments in a kind of long tunnel of high water head and its specific installation method, wherein Embedment and installation structure includes some tunnel monitoring section Embedment and installation units, tunnel monitoring section Embedment and installation unit includes interim protection wooden case and some FBG monitoring instruments, each FBG monitoring instrument is respectively connected with cable, interim protection wooden case is trapezoidal, its top has openable cover plate, side has the adaptable inclined-plane in long canal side in tunnel, opening is provided with casing, the cable that each FBG monitoring instrument is picked out is introduced in interim protection wooden case by the opening, cable is used to connect temporary cable or main transmission cable.The present invention program effectively can draw stern fast by monitoring for protection instrument, improve the integrality of instrument embedding serviceability rate and monitoring materials, and the wavelength measured value of the fiber grating instrument of same monitoring section is not repeated as far as possible, improves system wavelength-division multiplex efficiency.

Description

The Embedment and installation structure and installation method of Safety Monitoring Instruments in the long tunnel of high water head
Technical field
The invention belongs to Geotechnical Monitoring technical field, and in particular to Safety Monitoring Instruments in the long tunnel of high water head Embedment and installation structure and its installation method.
Background technology
Safety Monitoring Instruments must be installed in Geotechnical Engineering to be monitored the links at scene, so as to different in appearance Early warning is carried out when often to take correspondence means in time.Safety Monitoring Instruments are used as reinforcing rib meter, strain gauge, osmometer etc. The electric-type sensor such as differential resistance type, type vibration wire.In recent years, as the implementation of defeated water diversion project and fiber grating are passed over long distances Sense and the development of demodulation techniques, based on optical fiber Bragg raster(Fiber Bragg Grating, abbreviation FBG)Sensor is drawing Progressively it is applied in Hydraulic Projects, this is due to that there is fiber grating instrument long distance signal transmission, flexible networking, anti-electromagnetism to do Disturb, the advantage such as insulating requirements are low.
The difficult point that monitoring instrument one is directly subordinate in construction is installed in constructing tunnel, because tunnel distance length, space is small, apply Work is also more extensive, and this results in constructing tunnel and wants big for the installation of Safety Monitoring Instruments, the relative Other Engineering of protection difficulty, It can not even install at all, even if being installed in place sometimes, but in tunnel casting process, also easily monitoring instrument be caused to damage. Moreover, the data in tunnel lining casting process can not be gathered completely.
The content of the invention
To solve the above problems, the invention discloses the Embedment and installation knot of Safety Monitoring Instruments in a kind of long tunnel of high water head Structure and its specific installation method, can realize and the fast and stable of Safety Monitoring Instruments is installed among long tunnel.
In order to achieve the above object, the present invention provides following technical scheme:
The Embedment and installation method of Safety Monitoring Instruments, comprises the following steps in the long tunnel of high water head:
Step one, excavate after the completion of clear base, start assembling reinforcement, preceding installation form platform synchronous in this storehouse is completed in reinforcing bar colligation Track road, is completed while formwork jumbo is assembled in adjacent storehouse concrete position, circumferentially square on same tunnel monitoring section reinforcing bar To multiple FBG monitoring instruments are installed, the readily removable interim protection wooden case removed is fixed on tunnel floor reinforcing bar, it is the multiple The stern fast that FBG monitoring instrument is picked out is introduced from interim protection wooden case opening in interim protection wooden case;
Step 2, monitoring instrument stern fast enters after interim protection wooden case, and these stern fasts are together in series one by one, wooden case opening is protected Space between place and cable is sealed using expanded foam, it is to avoid concrete mortar enters;
Step 3, is connected after each FBG monitoring instrument is concatenated with guiding to the temporary cable of lower storehouse concrete, using portable Formula fiber Bragg grating (FBG) demodulator tests whether whole monitoring instrument wavelength of energy normal acquisition connection, if any overlapping wavelengths, then adjusts Tandem, until normal measurement;
Step 4, track of the formwork jumbo along tunnel axial direction moves into concreting position, after work in every is complete, template Chassis deploys, and closes after-pouring concrete with wooden model in other special-shaped parts, enters to put in storage face after-pouring concrete in formwork jumbo When, data acquisition frequency measurement on request;
Step 5, concrete is completed after initial set, removes formwork jumbo, pre-buried protection wooden case is dug out, and connects the extraction of instrument Stern fast is directly in the inverted arch position of monitoring section gathered data one by one;
After the completion of step 6, lining construction, remove interim protection wooden case and be drawn off, optical cable welding protecting box is arranged on and faced When the space that is left in lining cutting of protection wooden case, main cable will be fused to after FBG monitoring instrument serial or parallel connection, debugged After the completion of last whole concrete backfill.
Further, the wavelength measured value of the fiber grating instrument in same group of same monitoring section is not repeated.
Further, FBG monitoring instrument sets at least one grating, when setting 2 and above grating, every 2 light The nm of buffering area 0.5 is set between grid.
Further, serial number is less than 5 sensors or 10 wavelength in the step 2.
The Embedment and installation structure of Safety Monitoring Instruments in the long tunnel of high water head, including some tunnel monitoring section Embedment and installations Unit, the tunnel monitoring section Embedment and installation unit includes interim protection wooden case and some to be embedded in same tunnel monitoring disconnected FBG monitoring instrument on the circumference of face, each FBG monitoring instrument is respectively connected with stern fast, and each fiber grating instrument is each other Serial or parallel connection, the interim protection wooden case is trapezoidal, and its top has openable cover plate, and side has Chang Qu sides in tunnel Opening is provided with the adaptable inclined-plane in face, casing, the cable that each FBG monitoring instrument is picked out is drawn by the opening Enter to interim protection wooden case, the cable is used to connect temporary cable or main transmission cable.
Further, it is arranged with protection pipe outside the cable.
Further, the protection pipe is managed for PE.
Further, the interim protection wooden case is embedded in tunnel floor platform, and its apical side height is less than or equal to flat Countertop height.
Further, the opening is arranged on protecting box bottom surface.
Further, each FBG monitoring instrument is connected by flange and is used in same tunnel section Embedment and installation unit Carry out construction time observation.
Compared with prior art, the invention has the advantages that and beneficial effect:
1. effective monitoring for protection instrument draws stern fast, instrument embedding serviceability rate is improved, while can collect after lining cutting is poured to mould Pallet car removes the Monitoring Data in this period, improves the integrality of monitoring materials, accurately obtains a reference value, greatly improves Thereafter the accuracy of data monitoring.
2. the wavelength measured value of the fiber grating instrument of same monitoring section is not repeated as far as possible, system wavelength-division multiplex efficiency is improved.
Brief description of the drawings
Fig. 1 is tunnel schematic perspective view of the present invention.
Fig. 2 is tunnel monitoring section schematic diagram.
Fig. 3 is interim protection wood box construction schematic diagram.
Fig. 4 is tunnel section schematic diagram under formwork jumbo deployed condition.
Fig. 5 is that fiber-optic grating sensor is connected Wavelength distribution schematic diagram, in figure:①:Strain wavelength zone;②:Buffering area; ③:Temperature wavelength zone;④:Buffering area.
Reference numerals list:
1- tunnels, 2- temporary cables, 3- monitoring sections, 4- protects wooden case, 401- openings, 402- inclined-planes, 403- cover plates, 5- temporarily Fiber grating instrument, 6- stern fasts, 7- formwork jumbos, the support of 8- formwork jumbos, 9- concrete linings, 10- portable fiber-optic gratings (FBG) demodulator, the long canals of 11-.
Embodiment
The technical scheme provided below with reference to specific embodiment the present invention is described in detail, it should be understood that following specific Embodiment is only illustrative of the invention and is not intended to limit the scope of the invention.
The Embedment and installation method of Safety Monitoring Instruments, comprises the following steps in the long tunnel of high water head that the present invention is provided:
Step one, excavate after the completion of clear base, starting assembling reinforcement is used to pour tunnel 1, before reinforcing bar colligation is completed in this storehouse Synchronous installation form trolley track, is completed while formwork jumbo 7 is assembled in adjacent storehouse concrete position, in same tunnel monitoring section Along the circumferential direction tied up on 3 reinforcing bars and PE pipes are arranged outside multiple FBG monitoring instruments 5, the stern fast 6 that these instruments are picked out(Also may be used Using other there is the material of some strength to replace PE)As protection, PE pipe plastic band colligations without galvanized wire, it is to avoid mixed Galvanized wire cuts off protection pipe when solidifying soil vibrates and instrument draws stern fast, it is ensured that stern fast is injury-free.Tunnel monitoring section 3 is most of to be Sector, tunnel floor is to be used to set main transmission light in the long canal 11 for being provided with the whole tunnel of insertion in the middle part of platform, platform, long canal Cable, Chang Qu sections are up big and down small trapezoidal.Interim protection wooden case 4 is tied up on tunnel floor reinforcing bar.Interim protection wooden case is cut Face is trapezoidal, the wide 30cm in top, the wide 40cm in bottom, is highly 25cm, length is 100cm.It is provided with the top of interim protection wooden case Openable cover plate 403, bottom is provided with opening 401, and opening size is 20 × 30cm.Above-mentioned multiple FBG monitoring instruments 5 stern fasts 6 picked out detour rear haulage to section bottom along the fan-shaped reinforcing bar of section(As shown in Figure 2), and introduce interim from opening Protect in wooden case.Interim protection wooden case is wooden, easily removes and takes out after the completion of tunnel section is poured.Interim guarantor after fixation The apical side height of guard timber case should be equal to or slightly less than the apical side height for the concrete platform that tunnel floor will be molded, and conveniently dig out Interim protection wooden case.It should be noted that present invention meaning tunnel monitoring section axially has certain length along tunnel, it is usually 1 to 2m.
The FBG sensor array of series connection include multiple sensing gratings, (FBG) demodulator by reflected light wavelength " addressing " each Grating, therefore the grating wavelength wavelength that should have uniqueness, i.e. sensor of series connection will avoid overlapping in whole range, order Require that the wavelength measured value of the fiber grating instrument in same monitoring section in same group is not repeated during goods, improve system wavelength-division and answer Use efficiency.Typically 2 gratings are set in fiber grating strain meter or reinforcing rib meter(Strain, each 1 of temperature grating), strain, temperature Spend grating in the range of transducer range wavelength change amplitude between 1~3 nm.It is of course also possible to only set one as needed The individual or greater number of grating of setting.To improve reliability of the (FBG) demodulator according to wave length addressing, suggestion sets slow between every 2 gratings Rush the nm of area 0.5, it is to avoid overlapping wavelengths when adjacent grating changes in the range of transducer range, Wavelength distribution is general such as Fig. 5 It is shown.
Step 2, monitoring instrument stern fast enters after interim protection wooden case, opens cover plate 403, these monitoring instruments should be divided into The stern fast of monitoring instrument carries out series connection so as to each monitoring instrument of connecting with flange one by one in some groups, same group, general series connection The wavelength measured value that quantity is less than the fiber grating instrument in 5 sensors or 10 wavelength, same group is not repeated.After each group series connection Monitoring instrument stern fast drawn from wooden case gap or wooden case perforate outside wooden case, cover cover plate and fixed, wooden case is protected temporarily Space between casing gap and its opening, perforate and stern fast is sealed using expanded foam, it is to avoid concrete mortar enters.
Step 3, connects temporary cable 2 by the stern fast after each FBG monitoring instrument packet concatenation, temporary cable is drawn To outside this storehouse concrete, temporary cable is connected with portable fiber-optic grating demodulation instrument 10, as shown in figure 1, so in concrete Data acquisition can be normally carried out during lining construction.Can be tested whether using portable fiber-optic grating demodulation instrument can normal acquisition Whole monitoring instrument wavelength of connection, if any overlapping wavelengths, then adjust tandem, until normal measurement.
After above-mentioned steps, the Embedment and installation structure installation of Safety Monitoring Instruments in the long tunnel of high water head. As shown in Figure 1 and Figure 2, the structure includes some tunnel monitoring section Embedment and installation units, and each section Embedment and installation unit includes Interim protection wooden case 4 and multiple FBG monitoring instruments 5 being embedded on same tunnel monitoring section circumference, each optical fiber light Grid monitoring instrument 5 is respectively connected with cable, and each FBG monitoring instrument 5 is one another in series or in parallel.As shown in figure 3, interim protection Wooden case 4 is trapezoidal, and top is provided with openable cover plate 403, and its side has the adaptable inclined-plane in long canal side 11 in tunnel 402, opening 401 is provided with casing(Opening is preferred with being arranged on bottom, but can also change the specific of opening setting as needed Position), the cable that each FBG monitoring instrument is picked out is introduced in interim protection wooden case by the opening, each fiber grating The cable that monitoring instrument is picked out is used to connect temporary cable or main transmission cable.
Step 4, track of the formwork jumbo along tunnel axial direction moves into concreting position, after work in every is complete, Formwork jumbo deploys, and forms a complete sector as shown in Figure 4.In other special-shaped parts after-pouring coagulation is closed with wooden model Soil.When formwork jumbo enters to put in storage face after-pouring concrete, the data acquisition frequency that should be on request utilizes fiber Bragg grating (FBG) demodulator Measure.After the completion of pouring, interim protection wooden case and FBG monitoring instrument in section Embedment and installation unit all by In Transducers Embedded in Concrete.
The step of above-mentioned casting concrete, is as follows:
Using steel pipe pumping mode, concrete is sent into from the active window of formwork jumbo.Concrete is using horizontal slice, symmetrical Pumping, which is put in storage, to be poured.Concrete blinding chassis vibrates to be vibrated using attached vibrator, and charging window periphery poker vibrator shakes Smash auxiliary.Concrete pumping flexible pipe injects coagulation from the charging window (gradually being moved up from most bottom one-level window) of formwork jumbo Soil.Storehouse interior thin layer tiling, the symmetrical blanking of two side walls, unilateral continuously poured in one is highly no more than 1m, prevents template from integrally becoming Shape, conscientiously closes a position, and prevents aggregate separated, it is ensured that continuous placing, it is to avoid cold seam occur.
Preferably, concrete vibrating uses the concrete vibrating mode that artificial vibrating spear and vibration board are combined, bottom the 2nd Using manually vibrating below layer window, vibrated with upper bit using 8 vibration boards being evenly arranged.So concreting It is more uniformly distributed.
Step 5,2-3 days typically after concreting, concrete completes initial set, and formwork jumbo is removed, by pre-buried guarantor Guard timber case is dug out, and the extraction stern fast for exposing instrument can be directly in the inverted arch position of monitoring section gathered data one by one.
Step 6, after the completion of concrete lining 9 is constructed, FBG monitoring instrument needs to be fused to master after serial or parallel connection Optical cable, can now remove interim protection wooden case and be drawn off, and optical cable welding protecting box is arranged on into interim protection wooden case exists Cable in the space left in lining cutting, original interim protection wooden case is inserted in optical cable welding protecting box, and as needed to each Cable carries out serial or parallel connection, last whole concrete backfill after the completion of debugging.
Technological means disclosed in the present invention program is not limited only to the technological means disclosed in above-mentioned embodiment, in addition to Constituted technical scheme is combined by above technical characteristic.It should be pointed out that for those skilled in the art For, under the premise without departing from the principles of the invention, some improvements and modifications can also be made, these improvements and modifications are also considered as Protection scope of the present invention.

Claims (10)

1. the Embedment and installation method of Safety Monitoring Instruments in the long tunnel of high water head, it is characterised in that comprise the following steps:
Step one, excavate after the completion of clear base, start assembling reinforcement, preceding installation form platform synchronous in this storehouse is completed in reinforcing bar colligation Track road, is completed while formwork jumbo is assembled in adjacent storehouse concrete position, circumferentially square on same tunnel monitoring section reinforcing bar To multiple FBG monitoring instruments are installed, the readily removable interim protection wooden case removed is fixed on tunnel floor reinforcing bar, it is the multiple The stern fast that FBG monitoring instrument is picked out is introduced from interim protection wooden case opening in interim protection wooden case;
Step 2, monitoring instrument stern fast enters after interim protection wooden case, and the packet of these stern fasts is together in series, wooden case opening is protected Space between place and cable is sealed using expanded foam, it is to avoid concrete mortar enters;
Step 3, packet is connected after each FBG monitoring instrument is concatenated with guiding to the temporary cable of lower storehouse concrete, is used Portable fiber-optic grating demodulation instrument test whether can normal acquisition connection whole monitoring instrument wavelength, if any overlapping wavelengths, then Tandem is adjusted, until normal measurement;
Step 4, track of the formwork jumbo along tunnel axial direction moves into concreting position, after work in every is complete, template Chassis deploys, and closes after-pouring concrete with wooden model in other special-shaped parts, enters to put in storage face after-pouring concrete in formwork jumbo When, data acquisition frequency measurement on request;
Step 5, concrete is completed after initial set, removes formwork jumbo, pre-buried protection wooden case is dug out, and connects the extraction of instrument Stern fast is directly in the inverted arch position of monitoring section gathered data one by one;
After the completion of step 6, lining construction, remove interim protection wooden case and be drawn off, optical cable welding protecting box is arranged on and faced When the space that is left in lining cutting of protection wooden case, main cable will be fused to after FBG monitoring instrument serial or parallel connection, debugged After the completion of last whole concrete backfill.
2. the Embedment and installation method of Safety Monitoring Instruments in the long tunnel of high water head according to claim 1, it is characterised in that: The wavelength measured value of fiber grating instrument in same group of same monitoring section is not repeated.
3. the Embedment and installation method of Safety Monitoring Instruments in the long tunnel of high water head according to claim 1 or 2, its feature exists In:At least one grating is set in FBG monitoring instrument, when setting 2 and above grating, buffering area is set between every 2 gratings 0.5 nm。
4. the Embedment and installation method of Safety Monitoring Instruments in the long tunnel of high water head according to claim 1, it is characterised in that: Serial number is less than 5 sensors or 10 wavelength in the step 2.
5. the Embedment and installation structure of Safety Monitoring Instruments in the long tunnel of high water head, it is characterised in that:It is disconnected including the monitoring of some tunnels Face Embedment and installation unit, the tunnel monitoring section Embedment and installation unit include interim protection wooden case and it is some be embedded in it is same FBG monitoring instrument on tunnel monitoring section circumference, each FBG monitoring instrument is respectively connected with stern fast, each optical fiber light Grid instrument is one another in series or in parallel, and the interim protection wooden case is trapezoidal, and its top has openable cover plate, and side has tunnel Opening is provided with the adaptable inclined-plane in long canal side, casing in hole, the cable that each FBG monitoring instrument is picked out passes through The opening is introduced in interim protection wooden case, and the cable is used to connect temporary cable or main transmission cable.
6. the Embedment and installation structure of Safety Monitoring Instruments in the long tunnel of high water head according to claim 5, it is characterised in that: Protection pipe is arranged with outside the cable.
7. the Embedment and installation structure of Safety Monitoring Instruments in the long tunnel of high water head according to claim 6, it is characterised in that: The protection pipe is managed for PE.
8. the Embedment and installation structure of Safety Monitoring Instruments in the long tunnel of high water head according to claim 5, it is characterised in that: The interim protection wooden case is embedded in tunnel floor platform, and its apical side height is less than or equal to platform apical side height.
9. the Embedment and installation structure of Safety Monitoring Instruments in the long tunnel of high water head according to claim 5, it is characterised in that: The opening is arranged on protecting box bottom surface.
10. the Embedment and installation structure of Safety Monitoring Instruments in the long tunnel of high water head according to claim 5, its feature exists In:Each FBG monitoring instrument is connected for carrying out construction time sight by flange in same tunnel section Embedment and installation unit Survey.
CN201611146690.7A 2016-12-13 2016-12-13 The Embedment and installation structure and installation method of Safety Monitoring Instruments in the long tunnel of high water head Active CN107083993B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201611146690.7A CN107083993B (en) 2016-12-13 2016-12-13 The Embedment and installation structure and installation method of Safety Monitoring Instruments in the long tunnel of high water head

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201611146690.7A CN107083993B (en) 2016-12-13 2016-12-13 The Embedment and installation structure and installation method of Safety Monitoring Instruments in the long tunnel of high water head

Publications (2)

Publication Number Publication Date
CN107083993A true CN107083993A (en) 2017-08-22
CN107083993B CN107083993B (en) 2019-06-28

Family

ID=59614040

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201611146690.7A Active CN107083993B (en) 2016-12-13 2016-12-13 The Embedment and installation structure and installation method of Safety Monitoring Instruments in the long tunnel of high water head

Country Status (1)

Country Link
CN (1) CN107083993B (en)

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107421671A (en) * 2017-09-08 2017-12-01 浙江省水利水电勘测设计院 A kind of pressure gauge placing device for gentle slope inclined shaft
CN107460861A (en) * 2017-08-29 2017-12-12 云南农业大学 A kind of tubulose monitoring instrument prosthetic appliance
CN109269568A (en) * 2018-10-29 2019-01-25 上海英斯泊物联网有限公司 A kind of structural healthy monitoring system and its application method
CN110485388A (en) * 2019-05-30 2019-11-22 水利部南京水利水文自动化研究所 Hydraulic tunnel dynamic water-pressure monitoring of structures and method based on kinetic head correction
CN110595377A (en) * 2019-09-25 2019-12-20 武汉理工大学 Spatial three-dimensional system for monitoring lining deformation of underground cavern for long time
CN111024778A (en) * 2018-10-10 2020-04-17 中铁一局集团有限公司 Tunnel secondary lining preventive cavity detection system and operation control method thereof

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS5952094A (en) * 1982-09-14 1984-03-26 株式会社竹中工務店 Method of measuring and controlling upper section of spray concrete covering work and excavating forward ground propertyin tunnel construction by method of natomu construction
CN2890345Y (en) * 2006-01-25 2007-04-18 吴江 Pre-warning device capable of real-time monitoring
CN201202496Y (en) * 2008-06-05 2009-03-04 中铁西南科学研究院有限公司 On-line monitoring early warning apparatus of tunnel water burst mud projecting burst geologic hazard
CN204436476U (en) * 2015-02-16 2015-07-01 大连海事大学 Based on the Tunnel Landslide automated watch-keeping facility of structure reaction
CN104965477A (en) * 2015-01-29 2015-10-07 中铁建大桥工程局集团第一工程有限公司 Tunnel automatic monitoring system and method
CN206338092U (en) * 2016-12-13 2017-07-18 水利部南京水利水文自动化研究所 The Embedment and installation structure of Safety Monitoring Instruments in the long tunnel of high water head

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS5952094A (en) * 1982-09-14 1984-03-26 株式会社竹中工務店 Method of measuring and controlling upper section of spray concrete covering work and excavating forward ground propertyin tunnel construction by method of natomu construction
CN2890345Y (en) * 2006-01-25 2007-04-18 吴江 Pre-warning device capable of real-time monitoring
CN201202496Y (en) * 2008-06-05 2009-03-04 中铁西南科学研究院有限公司 On-line monitoring early warning apparatus of tunnel water burst mud projecting burst geologic hazard
CN104965477A (en) * 2015-01-29 2015-10-07 中铁建大桥工程局集团第一工程有限公司 Tunnel automatic monitoring system and method
CN204436476U (en) * 2015-02-16 2015-07-01 大连海事大学 Based on the Tunnel Landslide automated watch-keeping facility of structure reaction
CN206338092U (en) * 2016-12-13 2017-07-18 水利部南京水利水文自动化研究所 The Embedment and installation structure of Safety Monitoring Instruments in the long tunnel of high water head

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107460861A (en) * 2017-08-29 2017-12-12 云南农业大学 A kind of tubulose monitoring instrument prosthetic appliance
CN107460861B (en) * 2017-08-29 2023-03-31 云南农业大学 Tubular monitoring instrument repair equipment
CN107421671A (en) * 2017-09-08 2017-12-01 浙江省水利水电勘测设计院 A kind of pressure gauge placing device for gentle slope inclined shaft
CN111024778A (en) * 2018-10-10 2020-04-17 中铁一局集团有限公司 Tunnel secondary lining preventive cavity detection system and operation control method thereof
CN109269568A (en) * 2018-10-29 2019-01-25 上海英斯泊物联网有限公司 A kind of structural healthy monitoring system and its application method
CN110485388A (en) * 2019-05-30 2019-11-22 水利部南京水利水文自动化研究所 Hydraulic tunnel dynamic water-pressure monitoring of structures and method based on kinetic head correction
CN110595377A (en) * 2019-09-25 2019-12-20 武汉理工大学 Spatial three-dimensional system for monitoring lining deformation of underground cavern for long time

Also Published As

Publication number Publication date
CN107083993B (en) 2019-06-28

Similar Documents

Publication Publication Date Title
CN107083993A (en) The Embedment and installation structure and installation method of Safety Monitoring Instruments in the long tunnel of high water head
CN102937027B (en) A kind of construction method of edge top arch and bottom arch of concrete pouring tunnel
CN102943565B (en) Construction method of large-sized arc-shaped wall
CN110486023B (en) Tunnel defect treatment method
CN111636898B (en) Shield segment stress testing device in connection channel construction process of shield tunnel
MX2012008457A (en) Method and device for introducing a pipe for optical cables into a solid laying foundation.
KR101608624B1 (en) Method for lifting the height of tower
CN108824220A (en) A kind of cast-in-place support and construction method of the rigid structure of cantilever T-type
CN109505229A (en) Highway high gradient slope stress equilibrium and vibration damping are taken precautions against natural calamities high bridge pier structure and construction method
CN104074199A (en) Underwater bearing platform construction method
KR100878323B1 (en) Monitoring device of cavity in Tunnel lining concrete
CN106759307A (en) Protection device and method that bored concrete pile is irrigated in Karst Cave Formation
CN110905602A (en) Tunnel is torn open and is traded section atress monitoring devices and system
CN108487016A (en) The irregular accurate elevation concrete pavement construction method in test site
CN206338092U (en) The Embedment and installation structure of Safety Monitoring Instruments in the long tunnel of high water head
JP2015098734A (en) Tunnel covering arch concrete placing stop management method
CN102877538A (en) Construction method for fixing HDPE (high-density polypropylene) pipe by embedding iron wires
CN106978809A (en) A kind of construction method of casing off concrete protective reserved steel bar
CN107326942A (en) PHC tube pile structure loading detection devices and installation method
CN106948350B (en) The rapid constructing method of deep basal pit accessory structure
CN207265621U (en) A kind of power cable pipe trench structure
CN105926637B (en) The prestressing force support system and design of a kind of existing subway of protection
CN114825187B (en) 220KV sea cable dike crossing restoration construction method for offshore wind farm foundation construction
CN106368116A (en) Construction method of vibration damping bridge pier
CN103527217B (en) Small-curvature-radius shield tunnel duct piece under dense pile foundation environment and manufacturing method thereof

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant