CN107067081A - Substation secondary maintenance safety measure generation method based on many object models - Google Patents
Substation secondary maintenance safety measure generation method based on many object models Download PDFInfo
- Publication number
- CN107067081A CN107067081A CN201610856132.3A CN201610856132A CN107067081A CN 107067081 A CN107067081 A CN 107067081A CN 201610856132 A CN201610856132 A CN 201610856132A CN 107067081 A CN107067081 A CN 107067081A
- Authority
- CN
- China
- Prior art keywords
- safety measure
- objective
- implementation
- maintenance safety
- secondary maintenance
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
- 238000012423 maintenance Methods 0.000 title claims abstract description 93
- 238000000034 method Methods 0.000 title claims abstract description 34
- 230000006978 adaptation Effects 0.000 claims abstract description 23
- 230000004224 protection Effects 0.000 claims description 33
- 238000013461 design Methods 0.000 claims description 29
- 239000013307 optical fiber Substances 0.000 claims description 10
- 230000008569 process Effects 0.000 claims description 10
- 230000003287 optical effect Effects 0.000 claims description 8
- 239000000284 extract Substances 0.000 claims description 5
- 230000005611 electricity Effects 0.000 claims description 3
- 238000002156 mixing Methods 0.000 claims description 3
- 230000011664 signaling Effects 0.000 claims description 3
- 230000009471 action Effects 0.000 claims description 2
- 238000007792 addition Methods 0.000 abstract description 2
- 238000012217 deletion Methods 0.000 abstract description 2
- 230000037430 deletion Effects 0.000 abstract description 2
- 230000001737 promoting effect Effects 0.000 abstract description 2
- 238000007689 inspection Methods 0.000 description 6
- 238000000605 extraction Methods 0.000 description 3
- 239000000835 fiber Substances 0.000 description 3
- 230000008859 change Effects 0.000 description 2
- 230000007547 defect Effects 0.000 description 2
- 238000010586 diagram Methods 0.000 description 2
- 230000008030 elimination Effects 0.000 description 2
- 238000003379 elimination reaction Methods 0.000 description 2
- 238000002955 isolation Methods 0.000 description 2
- 239000000203 mixture Substances 0.000 description 2
- 238000012545 processing Methods 0.000 description 2
- 230000001681 protective effect Effects 0.000 description 2
- 238000011160 research Methods 0.000 description 2
- 230000009466 transformation Effects 0.000 description 2
- 238000012795 verification Methods 0.000 description 2
- 241000272814 Anser sp. Species 0.000 description 1
- 241000406668 Loxodonta cyclotis Species 0.000 description 1
- 238000013459 approach Methods 0.000 description 1
- 230000009286 beneficial effect Effects 0.000 description 1
- 238000006243 chemical reaction Methods 0.000 description 1
- 238000004891 communication Methods 0.000 description 1
- 238000007418 data mining Methods 0.000 description 1
- 238000005516 engineering process Methods 0.000 description 1
- 238000009472 formulation Methods 0.000 description 1
- 230000008531 maintenance mechanism Effects 0.000 description 1
- 238000012986 modification Methods 0.000 description 1
- 230000004048 modification Effects 0.000 description 1
- 230000008521 reorganization Effects 0.000 description 1
- 230000008439 repair process Effects 0.000 description 1
- 238000009666 routine test Methods 0.000 description 1
- 238000005204 segregation Methods 0.000 description 1
- 238000010561 standard procedure Methods 0.000 description 1
- 239000000126 substance Substances 0.000 description 1
- 239000013589 supplement Substances 0.000 description 1
- 238000012360 testing method Methods 0.000 description 1
- 238000009941 weaving Methods 0.000 description 1
Classifications
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06Q—INFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
- G06Q10/00—Administration; Management
- G06Q10/20—Administration of product repair or maintenance
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06Q—INFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
- G06Q50/00—Information and communication technology [ICT] specially adapted for implementation of business processes of specific business sectors, e.g. utilities or tourism
- G06Q50/06—Energy or water supply
Landscapes
- Business, Economics & Management (AREA)
- Engineering & Computer Science (AREA)
- Human Resources & Organizations (AREA)
- Economics (AREA)
- Physics & Mathematics (AREA)
- Theoretical Computer Science (AREA)
- Health & Medical Sciences (AREA)
- Marketing (AREA)
- Strategic Management (AREA)
- Tourism & Hospitality (AREA)
- General Physics & Mathematics (AREA)
- General Business, Economics & Management (AREA)
- Entrepreneurship & Innovation (AREA)
- Quality & Reliability (AREA)
- Operations Research (AREA)
- Public Health (AREA)
- Water Supply & Treatment (AREA)
- General Health & Medical Sciences (AREA)
- Primary Health Care (AREA)
- Supply And Distribution Of Alternating Current (AREA)
- Management, Administration, Business Operations System, And Electronic Commerce (AREA)
Abstract
The invention discloses a kind of substation secondary maintenance safety measure generation method based on many object models, by typical secondary maintenance safety Measures Standard, secondary maintenance safety measure adaptation data storehouse is set up;Based on SCD file to pending transformer station progress objective for implementation, the modelling of operation object;Objective for implementation example and operation object example defined in SCD file are embodied as according to secondary maintenance safety measure adaptation data storehouse and objective for implementation, operation object;According to actual conditions in station, the secondary maintenance safety measure of additions and deletions graphically aided in, adjust secondary maintenance safety measure execution sequence, generate finally can practical application secondary maintenance safety measure.This invention ensures that secondary maintenance safety measure establishment efficiency and integrality, the ability of raising efficiency with SCD file standardization and integrality lifting has been reserved in substation data object model module, has possessed exploitativeness and promotional value.
Description
Technical field
The present invention relates to a kind of substation secondary maintenance safety measure generation method based on many object models.
Background technology
Secondary maintenance safety measure put into operation as reply transformer station after defect elimination, maintenance, upgrading and the scene such as reorganization and expansion work
The technical guarantee of work, to ensure the equipment of intelligent substation first and second safety and power network stable operation it is significant.Pressure
Plate and loop are the primary operational objects in secondary maintenance safety measure, and are using fiber optic communication and IEC61850 information modelings
Secondary system of intelligent substation in, it is seen that " hardwire " become " optical fiber ", " real terminal " becomes " empty terminal ", " hard
Pressing plate " becomes " soft pressing plate ", and introduces the concept of " maintenance pressing plate ", more crucially all kinds of " soft pressing plates " and " maintenance pressure
Influence of the plate " to interoperation relation between device is also complicated more than normal station, and these new changes are to being engaged in intelligent substation two
The establishment of secondary maintenance safety measure, the staff performed bring very big difficulty.
For above situation, scientific research institution and relevant unit are according to the technical characterstic of intelligent substation in industry, and research is simultaneously
Form the related code of a series of secondary safety measure, specification.
Prior art have arranged for the secondary peace of existing intelligent station maintenance have that security is low, being easily caused protection, locking etc. by mistake is asked
Topic, it is proposed that using open in flakes, solution cored wire mode separate the secondary electrical circuit in place;Digital channel is disconnected using soft pressing plate is first moved back
The first line of defence is set;Optical fiber is pulled out after utilization and forms obvious breakpoint (or throwing maintenance pressing plate enables intelligent station maintenance mechanism) setting head
The secondary peace of 220kV intelligent stations point interval interruption maintenance in the second defence line arranged of inspection (or regular inspection) secondary peace arranges new approaches.
《A kind of process layer debugging plan compared based on secondary circuit file and safety measure generation method》, the method lead to
The difference of secondary circuit in analysis different editions configuration file is crossed, testing equipment and the interface of operational outfit is divided, effectively referred to
Lead the debugging of reconstruction and extension project electrical secondary system and the formulation of safety measure.
Guo Wang companies formulate and issued in succession《State Grid Corporation of China's electric power safety working regulation (power transformation part)》、《Intelligence
Can substation relay protection and power grid security automatics work on the spot security personnel's regulation》.But Regulations are that some are general
Principle or technical requirements.At the scene, it is necessary to which secondary maintainer combines maintenance scene and specific transformer station in real work
The secondary safety measure ticket of design drawing hand woven.Because live secondary maintainer's technical merit is uneven and intelligent power transformation
Stand being continuously increased of O&M maintenance workload, complete hand weaving, checked the accuracy and efficiency of secondary safety measure ticket
Real work needs can not be met, or even cause some security incidents, so how to ensure intelligent substation secondary maintenance peace
It is to be badly in need of solving the problems, such as in intelligent substation maintenance work to arrange the integrality and correctness of ticket.
The content of the invention
The present invention is in order to solve the above problems, it is proposed that a kind of substation secondary maintenance safety based on many object models is arranged
Generation method is applied, the present invention combines the parsing of all types of objects in SCD file, be adapted to general rule semanteme, automation generation
Go out the safety measure sequence that upkeep operation should be carried out.
To achieve these goals, the present invention is adopted the following technical scheme that:
A kind of substation secondary maintenance safety measure generation method based on many object models, comprises the following steps:
(1) by typical secondary maintenance safety Measures Standard, secondary maintenance safety measure adaptation data storehouse is set up;
(2) based on SCD file to pending transformer station progress objective for implementation, the modelling of operation object;
(3) it is embodied as according to secondary maintenance safety measure adaptation data storehouse and objective for implementation, operation object in SCD file
The objective for implementation example and operation object example of definition, are matched using desc fuzzy match mode;
(4) according to actual conditions in station, secondary maintenance safety measure execution sequence is adjusted, generating finally can practical application
Secondary maintenance safety measure.
In the step (1), secondary maintenance safety measure adaptation data storehouse is set up, by the various secondary inspections of typical case in code
Repair safety measure and change into the set that can be recognized, data basis is provided for adaptation.
In the step (1), specifically include and define Substation Design scheme, maintenance model and objective for implementation and operation pair
As.
In the step (1), define Substation Design scheme need consider voltage class, main wiring mode, relaying configuration,
Sampled form, whether using combining unit and whether use intelligent terminal.
In the step (1), maintenance model will consider maintenance type and primary equipment power failure range, specifically include whole station and stop
Electricity, voltage class have a power failure, interval has a power failure or do not had a power failure.
In the step (1), the set of the objective for implementation includes power failure range of mark, equipment to be checked, maintenance class
Type, space from start type, starting type of device, purpose interval type and/or destination device type.
In the step (1), the set of the operation object, including objective for implementation, space from start type, starting device class
Type, operation object, purpose interval type and/or destination device type.
In the step (2), parsing SCD file and Substation Design optical cable inventory instantiate all kinds of objective for implementation, have
Body process includes:
(2-1) determine transformer substation voltage grade, design, relaying configuration, sampled form, whether use combining unit with
And whether use intelligent terminal;
(2-2) extracts all kinds of secondary device types and affiliated interval defined in SCD file;
(2-3) parses SCD file, determines the correspondence between any two equipment, similar empty signal is merged
One group of empty signal is formed, defining one group of empty signal group turns into an objective for implementation.
In the step (2), being related to does not have the object handles mode of modeling as follows in SCD:
(2-a) is with reference to the manual additional configurations modeling of design drawing, including modeling transformer Ontology and and combining unit
Between electric current, voltage use loop objective for implementation;
(2-b) is with reference to the manual additional configurations modeling of design drawing, including modeling breaker body object and and intelligent terminal
Between blending lock, the objective for implementation of position signalling;
(2-c) sets up a protection device object in each route protection offside, and combines transformer station's actual design feelings
Objective for implementation between condition configuration finishing device.
In the step (2), the specific method of operation object instantiation is the pressure in extraction SCD file and optical cable inventory
Plate, maintenance pressing plate, and set up the incidence relation of pressing plate and objective for implementation.
In the step (3), it is determined that under maintenance scene, the typical secondary maintenance safety measure number of the formalization based on determination
According to storehouse, each objective for implementation of modeled transformer station and operation object are matched one by one.
In the step (3), detailed process includes:
(3-1) clear and definite blackout condition and overhaul of the equipments type;
(3-2) according to equipment to be checked, according to the design attribute of the affiliated transformer station of equipment to be checked, automatic of maintenance model
Allot the typical secondary maintenance safety measure that should be referred to;
(3-3) is according to each objective for implementation in typical secondary maintenance safety action data storehouse and instantiated transformer station's number
Intelligent Matching is carried out according to object;
Operation object and matched transformer station's implementation pair that (3-4) is associated the instance objects of definition based on keyword
Pressing plate, optical fiber as association are matched.
Beneficial effects of the present invention are:
(1) present invention passes through the typical case of formalization on the basis of being actually needed of secondary maintenance safety measure is fully studied
Safety measure semanteme realizes oneself of intelligent substation safety measure with substation data Object Semanteme adaptation method in SCD file
Dynamic generation, adds low volume data configuration work to SCD file data mining, it is ensured that secondary maintenance safety measure works out efficiency and complete
Whole property;
(2) reserved in substation data object model module with SCD file standardization and integrality lifting
The ability of raising efficiency, possesses exploitativeness and promotional value, it will greatly improve overhaul efficiency, improves the safe operation of power network
Level.
Brief description of the drawings
Fig. 1 is the workflow diagram of the present invention;
Fig. 2 is the intelligent Matching process flow diagram flow chart of the present invention.
Embodiment:
The invention will be further described with embodiment below in conjunction with the accompanying drawings.
The description of safety measure, which is generally, " extracts on XX line protective devices, connects the straight daylighting of XX circuit combining units
The semanteme such as fibre ", " XX pressing plates are exited in XX protections ".By furtheing investigate visible, the typical peace of abstractness to exemplary secure measure
Content arrange to be described it is determined that in voltage class, the transformer station for determining the mode of connection, existing to a certain certain types of device
When carrying out certain service work under specific primary equipment running situation, if Awaiting Overhaul equipment and had between operational outfit mutually
Operative relationship is it is necessary to considering with the contact between certain safety measure isolation, to ensure the safety in operational outfit, typical ticket
It is middle that this contact is defined as objective for implementation.And the specific execution of objective for implementation is, it is necessary to pass through one or more specific operations
Object is completed.In intelligent substation, operation object can be divided into three classes:
1) certain function pressing plate of protection device is exited;
2) the soft pressing plate communicated between extractor or hard pressing plate (or loop is in flakes);
3) optical fiber communicated between device is pulled out.
So safety measure is exactly the sequential combination of above-mentioned isolation contact object, table 1 illustrates the related reality of device A to be checked
Apply the relation of object and operation object.
The peace of table 1 arranges object to illustrate
Function pressing plate, soft pressing plate in objective for implementation, operation object all have standard method description in SCD, can be with
Easily pass through microcomputer modelling;Although in addition, optical fiber, maintenance pressing plate, the secondary operation object such as in flakes be not in SCD file
Description, but it is all physics, the check of visible, convenient scene at the scene.
Therefore, exemplary secure measure can carry out formalized description, form computer and may be appreciated semantic rules, then
Maintainer can combine transformer substation voltage grade, the mode of connection, equipment class to be checked when actually working out specific safety measure
The key elements such as type, primary equipment running situation, service work type are instantiated, and the present invention proposes semantic based on SCD file
The substation secondary maintenance safety measure generation method based on many object models of adaptation, i.e., with reference to all types of right in SCD file
The parsing of elephant, is adapted to general rule semanteme, and the safety measure sequence that upkeep operation should be carried out is generated to authorized personnel's automation
Row.
Based on resolving ideas, technical scheme is generally divided into four parts, as shown in Figure 1.
1) typical secondary maintenance safety measure formalization, i.e.,:Various typical secondary maintenance safety measures in code are turned
The semantic rules that chemical conversion computer can be recognized, basis is provided for semanteme adaptation;
2) substation data objectification, i.e., based on SCD file or optical cable inventory, drawing etc. by the implementation pair of specific transformer station
As, operation object is modeled, this is the data basis of semantic adaptation;
3) semantic rules being adapted to the semanteme of transformer station specific object, i.e., by the general implementation pair in general semantic rules
As the objective for implementation example and operation object example that are embodied as with operation object defined in SCD file.
4) peace arranges the editor of ticket to adjust and check, and entrance is provided to staff, can be according to actual conditions, figure in station
Change the secondary maintenance safety measure of additions and deletions of auxiliary, adjust secondary maintenance safety measure execution sequence, generation finally can practical application
Secondary maintenance safety measure.The check of integrality and succession is provided simultaneously, so as to finally ensure secondary maintenance safety measure
It is overall reliable.
The secondary maintenance safety measure formalization of typical case
The form of the secondary safety measure of typical case is divided into three partial contents,
Substation Design schema definition
The design of transformer station mainly considers the key element of following dimension:Voltage class, main wiring mode, relaying configuration,
Sampled form (electronic mutual inductor or routine transformer), whether using combining unit, whether use intelligent terminal.
Maintenance model is defined
Maintenance model will consider primary equipment power failure range, and (whole station has a power failure, voltage class has a power failure, interval has a power failure, do not stopped
Electricity), maintenance type (first inspection, routine test, defect elimination are upgraded).
Peace arranges objective for implementation and operation object to formalize
In operating standard, in the transformer station of every kind of design, each device type (busbar protective device, line
Line protection device, main transformer protection, combining unit, intelligent terminal, prepared auto restart etc.) it is determined that maintenance model under the safety to be carried out
Measure has all carried out detailed regulation, is accomplished by combining operating standard here to the objective for implementation and operation object in safety measure
Be identified and model it one by one, objectification.
(1) objective for implementation form is turned to:
[power failure range] [equipment to be checked] [maintenance type] { [space from start type] [starting type of device] to [mesh
Interval type] [destination device type] of [objective for implementation semantic]
Objective for implementation semanteme is the logical semantics of objective for implementation, is the keyword of semantic adaptation, following table be route protection with
The semantic example of the objective for implementation of bus protection.
Table 2, which is pacified, arranges the semanteme of objective for implementation
(2) operation object form is turned to:
[objective for implementation] { [space from start type] [starting type of device] [operation object] or [purpose interval type]
[destination device type] [operation object] }
Substation data object model
The main process of substation data object model is parsing SCD file and Substation Design optical cable inventory, by respectively
Class object is instantiated.
Substation Design scheme type is determined
Determine that (electronic mutual inductor is conventional mutual for transformer substation voltage grade, design, relaying configuration, sampled form
Sensor), whether using combining unit, whether use intelligent terminal.
Interval and device instantiation
IED Naming conventions during based on current domestic each integrator configuration SCD, are extracted all kinds of two defined in SCD file
Secondary device type and affiliated interval.Such as PM represents bus protection, PL and represents route protection.
Objective for implementation is instantiated
Parse and there is correspondence between SCD file, any two device, including GOOSE transmitting-receivings and SV transmitting-receivings, all define
To there is objective for implementation between device, then similar empty signal being merged to form one group of empty signal, defining one group of empty letter
Number composition is objective for implementation, and packet refers to following table according to the matching keyword in semantic:
Pacify the semantic rules for arranging objective for implementation to extract
Being related to does not have the object handles mode of modeling as follows in SCD:
1. electric current, voltage transformer:With reference to the manual additional configurations modeling of design drawing, including modeling transformer Ontology
And electric current, the voltage between combining unit use loop objective for implementation;
2. breaker:With reference to the modeling of design drawing manual additional configurations, including modeling breaker body object and with intelligence
The objective for implementation such as blending lock, position signalling between terminal;
3. route protection offside protection device:Default treatment, a protection device is set up in each route protection offside
Object, and combine the objective for implementation between transformer station's actual design situation configuration finishing device, such as this side electric current, switch position
Put, far jump.
Operation object is instantiated
Extract SCD file and pressing plate in optical cable inventory, maintenance pressing plate, and set up associating for pressing plate and objective for implementation
System.According in No. 1396 texts to empty terminal and the semanteme of soft pressing plate, the search rule of the empty loop of definition and soft pressing plate.For using
General semantics are (such as:Logical node is GGIO, and DO is SPCS) the empty loop that defines and soft pressing plate, using desc fuzzy matching side
Formula defines search rule, the modeling for completing to associate between pressing plate and objective for implementation by search rule, in indivedual SCD files
Pressing plate name is lack of standardization, the situation for causing modeling to fail, and supports human configuration adjustment.
With the instantiation of objective for implementation, the instantiation of operation object there is also the object handles situation for not having modeling in SCD,
Processing mode is as follows:
Optical fiber circuit and fiber port, can be by importing the supplement modeling of optical cable inventory, including route protection and offside protection
Between optical fibre channel;
Loop between electric current, voltage transformer and combining unit is in flakes:With reference to the manual additional configurations modeling of design drawing;
Rule is adapted to the semanteme of object
Determined under maintenance scene as shown in Fig. 2 rule is adapted to the semanteme of object, the typical case of the formalization based on determination
Secondary maintenance safety measure semantic rules, matches each objective for implementation of modeled transformer station and operation object one by one
Process.
Select some equipment to be checked of some transformer station, maintenance model, i.e., a clear and definite blackout condition and equipment are set
Overhaul type.
According to equipment to be checked, according to the design attribute of the affiliated transformer station of equipment to be checked (including voltage class, main electrical scheme
Mode etc.), maintenance model Auto-matching go out the typical secondary maintenance safety measure semantic rules that should be referred to.
The semantic adaptation of objective for implementation is carried out based on semantic rules, adaptation method is according to each objective for implementation in semantic rules
Logical semantics carry out intelligent Matching with instantiated substation data object.For example, during typical case's peace is arranged:" [circuit
Protection] to [start failure protection] of [bus protection] " matching is " [protection of PL2201 Mount Tais golden circuit] to [PM2202II# buses guarantor
Shield] [start failure protection].
The semantic adaptation of operation object is carried out based on semantic rules, i.e., by the instance objects association defined in semantic rules
Pressing plate, the optical fiber that operation object is associated with matched transformer station's objective for implementation are matched, and matching is carried out based on keyword.
For example, the operation object that objective for implementation is associated in semantic rules is " connection [circuit combining unit] in extraction [route protection]
[straight daylighting is fine] " matching is " connection [ML2201 circuits combining unit] in extraction [protection of PL2201 Mount Tais golden circuit]
[AOB1688-005 optical fiber] ".
In adaptation procedure, transformer station's number can not be matched as there is objective for implementation or operation object defined in semantic rules
Prompting is provided according to the situation of object.
Peace arranges ticket editor to adjust and check
Complete after semantic adaptation, automatically generating work to the safety measure of the service work has completed, and staff can
Each safety measure is adjusted and edited with the situation according to adaptation, especially the semantic rules not matched will be subject to
Processing, can provide integrity check and timing check by manually adding in New Measure, editing process.
Whether integrity check is complete based on the safety measure after substation data object modelization verification final adjustment
Consider all objective for implementation.
Operator precedence level dynamic adaptation of the timing verification based on objective for implementation, the rule of adaptation is carried from operating standard
Take.When timing mistake occurs in secondary maintenance safety measure, prompting is provided.
Application case
The present invention have chosen the double set configurations of 220kV double bus schemes mode, protection device, using traditional transformer+merging
One transformer station's case of the design of unit+intelligent terminal, with heads of the route protection PL2203 under the blackout condition of interval
Exemplified by inspection, illustrate to pacify and arrange the implementation process of establishment.
1) typical secondary maintenance safety measure formalization
" route protection head inspections (maintenance of A4 classes) work only considers in line segregation primary equipment power-off condition regulation in code
It is lower to carry out, take double set " route protection+combining unit+intelligent terminal " stoppage in transit maintenance models ".Specific maintenance safety measure shape
It is as shown in table 3 that formula, which turns to semantic rules,.
The peace of table 3 arranges semantic rules example
2) safety measure after semantic adaptation
Safety measure after the adaptation of table 4
Although above-mentioned the embodiment of the present invention is described with reference to accompanying drawing, not to present invention protection model
The limitation enclosed, one of ordinary skill in the art should be understood that on the basis of technical scheme those skilled in the art are not
Need to pay various modifications or deform still within protection scope of the present invention that creative work can make.
Claims (10)
1. a kind of substation secondary maintenance safety measure generation method based on many object models, it is characterized in that:Including following step
Suddenly:
(1) by typical secondary maintenance safety Measures Standard, secondary maintenance safety measure adaptation data storehouse is set up;
(2) based on SCD file to pending transformer station progress objective for implementation, the modelling of operation object;
(3) it is embodied as according to secondary maintenance safety measure adaptation data storehouse and objective for implementation, operation object defined in SCD file
Objective for implementation example and operation object example, matched using desc fuzzy match mode;
(4) according to actual conditions in station, adjust secondary maintenance safety measure execution sequence, generate finally can practical application it is secondary
Maintenance safety measure.
2. a kind of substation secondary maintenance safety measure generation method based on many object models as claimed in claim 1, its
It is characterized in:
In the step (1), specifically include and define Substation Design scheme, maintenance model and objective for implementation and operation object:It is fixed
Whether adopted Substation Design scheme needs to consider voltage class, main wiring mode, relaying configuration, sampled form, single using merging
Member and whether use intelligent terminal.
3. a kind of substation secondary maintenance safety measure generation method based on many object models as claimed in claim 2, its
It is characterized in:In the step (1), maintenance model will consider maintenance type and primary equipment power failure range, specifically include whole station and stop
Electricity, voltage class have a power failure, interval has a power failure or do not had a power failure.
4. a kind of substation secondary maintenance safety measure generation method based on many object models as claimed in claim 1, its
It is characterized in:In the step (1), the set of the objective for implementation includes power failure range of mark, equipment to be checked, maintenance class
Type, space from start type, starting type of device, purpose interval type and/or destination device type;
In the step (1), the set of the operation object, including objective for implementation, space from start type, starting type of device,
Operation object, purpose interval type and/or destination device type.
5. a kind of substation secondary maintenance safety measure generation method based on many object models as claimed in claim 1, its
It is characterized in:In the step (2), parsing SCD file and Substation Design optical cable inventory instantiate all kinds of objective for implementation, have
Body process includes:
(2-1) determine transformer substation voltage grade, design, relaying configuration, sampled form, whether using combining unit and being
No use intelligent terminal;
(2-2) extracts all kinds of secondary device types and affiliated interval defined in SCD file;
(2-3) parses SCD file, determines the correspondence between any two equipment, similar empty signal is merged to be formed
One group of empty signal, defining one group of empty signal group turns into an objective for implementation.
6. a kind of substation secondary maintenance safety measure generation method based on many object models as claimed in claim 1, its
It is characterized in:In the step (2), being related to does not have the object handles mode of modeling as follows in SCD:
(2-a) is with reference to the modeling of design drawing manual additional configurations, including modeling transformer Ontology and between combining unit
Electric current, voltage use loop objective for implementation;
(2-b) is with reference to the modeling of design drawing manual additional configurations, including modeling breaker body object and between intelligent terminal
Blending lock, the objective for implementation of position signalling;
(2-c) sets up a protection device object in each route protection offside, and combination transformer station actual design situation is matched somebody with somebody
Put the objective for implementation between finishing device.
7. a kind of substation secondary maintenance safety measure generation method based on many object models as claimed in claim 1, its
It is characterized in:In the step (2), the specific method of operation object instantiation for extract SCD file and pressing plate in optical cable inventory,
Pressing plate is overhauled, and sets up the incidence relation of pressing plate and objective for implementation.
8. a kind of substation secondary maintenance safety measure generation method based on many object models as claimed in claim 1, its
It is characterized in:In the step (2), empty loop and soft pressing plate for definition are defined using desc fuzzy match mode and searched
Rule, the modeling for completing to associate between pressing plate and objective for implementation by search rule.
9. a kind of substation secondary maintenance safety measure generation method based on many object models as claimed in claim 1, its
It is characterized in:In the step (3), it is determined that under maintenance scene, the typical secondary maintenance safety measure number of the formalization based on determination
According to storehouse, each objective for implementation of modeled transformer station and operation object are matched one by one.
10. a kind of substation secondary maintenance safety measure generation method based on many object models as claimed in claim 1, its
It is characterized in:In the step (3), detailed process includes:
(3-1) clear and definite blackout condition and overhaul of the equipments type;
(3-2), according to equipment to be checked, according to the design attribute of the affiliated transformer station of equipment to be checked, maintenance model Auto-matching goes out
The typical secondary maintenance safety measure that should be referred to;
(3-3) is according to each objective for implementation in typical secondary maintenance safety action data storehouse and instantiated substation data pair
As carrying out intelligent Matching;
(3-4) is closed based on the operation object that keyword associates the instance objects of definition with matched transformer station's objective for implementation
Pressing plate, the optical fiber of connection are matched.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201610856132.3A CN107067081A (en) | 2016-09-27 | 2016-09-27 | Substation secondary maintenance safety measure generation method based on many object models |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201610856132.3A CN107067081A (en) | 2016-09-27 | 2016-09-27 | Substation secondary maintenance safety measure generation method based on many object models |
Publications (1)
Publication Number | Publication Date |
---|---|
CN107067081A true CN107067081A (en) | 2017-08-18 |
Family
ID=59616796
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201610856132.3A Pending CN107067081A (en) | 2016-09-27 | 2016-09-27 | Substation secondary maintenance safety measure generation method based on many object models |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN107067081A (en) |
Cited By (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN107944668A (en) * | 2017-11-06 | 2018-04-20 | 广东电网有限责任公司肇庆供电局 | A kind of protection signal intelligent modeling method based on interval division |
CN108054720A (en) * | 2017-12-12 | 2018-05-18 | 南京国电南自电网自动化有限公司 | Towards the relay protection device of intelligent substation modeling method of physical device object |
CN108197401A (en) * | 2018-01-15 | 2018-06-22 | 上海交通大学 | The intelligent substation peace that logic-based calculates, which is arranged, operates check method |
CN108492660A (en) * | 2018-04-02 | 2018-09-04 | 国网青海省电力公司 | Substation's peace arranges analogy method, device and system |
CN108923529A (en) * | 2018-05-14 | 2018-11-30 | 许继集团有限公司 | A kind of intelligent substation secondary peace arranges diagnostic method and system |
CN108931972A (en) * | 2018-06-25 | 2018-12-04 | 国电南瑞科技股份有限公司 | A kind of substation secondary device condition intelligent diagnostic method based on model-driven |
Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN105005941A (en) * | 2015-07-09 | 2015-10-28 | 国网新疆电力公司 | Service rule based examining method for virtual secondary circuit between intelligent station devices |
CN105045991A (en) * | 2015-07-09 | 2015-11-11 | 山东容弗新信息科技有限公司 | Auditing method for intelligent apparatus configuration scheme and virtual terminals of intelligent substation |
CN105095571A (en) * | 2015-07-09 | 2015-11-25 | 中国能源建设集团山西省电力勘测设计院有限公司 | Method for checking configuration solution of intelligent transformer substation intelligent apparatus based on business rule |
CN105184660A (en) * | 2015-07-09 | 2015-12-23 | 山东容弗新信息科技有限公司 | Virtual secondary circuit examination method between intelligent station intelligent device configuration scheme and device |
CN105914892A (en) * | 2016-06-16 | 2016-08-31 | 国网福建省电力有限公司 | Secondary maintenance safety measure ticket system and realization method thereof |
-
2016
- 2016-09-27 CN CN201610856132.3A patent/CN107067081A/en active Pending
Patent Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN105005941A (en) * | 2015-07-09 | 2015-10-28 | 国网新疆电力公司 | Service rule based examining method for virtual secondary circuit between intelligent station devices |
CN105045991A (en) * | 2015-07-09 | 2015-11-11 | 山东容弗新信息科技有限公司 | Auditing method for intelligent apparatus configuration scheme and virtual terminals of intelligent substation |
CN105095571A (en) * | 2015-07-09 | 2015-11-25 | 中国能源建设集团山西省电力勘测设计院有限公司 | Method for checking configuration solution of intelligent transformer substation intelligent apparatus based on business rule |
CN105184660A (en) * | 2015-07-09 | 2015-12-23 | 山东容弗新信息科技有限公司 | Virtual secondary circuit examination method between intelligent station intelligent device configuration scheme and device |
CN105914892A (en) * | 2016-06-16 | 2016-08-31 | 国网福建省电力有限公司 | Secondary maintenance safety measure ticket system and realization method thereof |
Cited By (9)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN107944668A (en) * | 2017-11-06 | 2018-04-20 | 广东电网有限责任公司肇庆供电局 | A kind of protection signal intelligent modeling method based on interval division |
CN108054720A (en) * | 2017-12-12 | 2018-05-18 | 南京国电南自电网自动化有限公司 | Towards the relay protection device of intelligent substation modeling method of physical device object |
CN108054720B (en) * | 2017-12-12 | 2020-02-21 | 南京国电南自电网自动化有限公司 | Modeling method of intelligent substation relay protection device for physical equipment object |
CN108197401A (en) * | 2018-01-15 | 2018-06-22 | 上海交通大学 | The intelligent substation peace that logic-based calculates, which is arranged, operates check method |
CN108197401B (en) * | 2018-01-15 | 2021-06-22 | 上海交通大学 | Intelligent substation safety measure operation checking method based on logic calculation |
CN108492660A (en) * | 2018-04-02 | 2018-09-04 | 国网青海省电力公司 | Substation's peace arranges analogy method, device and system |
CN108923529A (en) * | 2018-05-14 | 2018-11-30 | 许继集团有限公司 | A kind of intelligent substation secondary peace arranges diagnostic method and system |
CN108923529B (en) * | 2018-05-14 | 2020-10-27 | 许继集团有限公司 | Intelligent substation secondary safety measure diagnosis method and system |
CN108931972A (en) * | 2018-06-25 | 2018-12-04 | 国电南瑞科技股份有限公司 | A kind of substation secondary device condition intelligent diagnostic method based on model-driven |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN107067081A (en) | Substation secondary maintenance safety measure generation method based on many object models | |
CN106021596B (en) | A kind of analysis method of electric network fault rush of current topological diagram | |
CN108549650B (en) | Intelligent substation anti-misoperation lockout logic rule source end configuration method and system | |
CN102508059B (en) | Topology error-preventing checking method based on intelligent identification of state of equipment | |
CN106159759B (en) | A kind of method for automatically generating secondary system of intelligent substation maintenance safety measure | |
CN110674282B (en) | Expert knowledge rule base-based one-key sequential control operation order intelligent simulation method | |
CN102591223B (en) | Intelligentized diagnostic system of substation-operation operation tickets | |
CN104915750A (en) | Intelligent operation ticket management method and system for achieving integration with an EMS and an OMS | |
CN103996099B (en) | Method for conducting intelligent evaluation on student operation in training system | |
CN107045706A (en) | Intelligent substation secondary safety measure operation order automatic generation method | |
CN107871176A (en) | The safety-optimized method and system of secondary device applied to IEC61850 information modelings | |
CN104360835B (en) | A kind of sequence operation ticket automatic generation method based on topological mode | |
CN102495850A (en) | Method for splicing multi-stage multi-region interconnected power grid relay protection model | |
CN103414169A (en) | Relay protection and error prevention system based on power grid dispatching automation system and working method | |
CN102638027B (en) | Switch refusing action fault simulation method for online safety and stability evaluation of electric power system | |
CN107153946A (en) | Intelligent station is secondary to pacify automatic generation method and the system of arranging | |
CN104331777A (en) | Error-preventing management system for county level power grid dispatching operation | |
CN107275963B (en) | A kind of intelligent substation secondary maintenance safety measure automatic generation method | |
CN108304947A (en) | The safety-optimized method and system of secondary device based on SCD file object model | |
CN107133883A (en) | Based on the intelligent substation safety measure automatic generation method and device that safety measure is semantic | |
CN110704700A (en) | One-key sequential control equipment state intelligent simulation method based on expert knowledge rule base | |
CN107871030A (en) | Substation secondary maintenance safety measure generation method based on SCD file object model | |
CN107871168A (en) | Intelligent substation secondary maintenance safety measure generation method | |
CN107292524A (en) | Intelligent substation secondary safety measure automatic generation method and device | |
CN107872022A (en) | For the substation secondary maintenance safety measure matching process of fiber optic communication |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination |