CN107059867A - A kind of Driven Piles stop hammering control method into shape - Google Patents
A kind of Driven Piles stop hammering control method into shape Download PDFInfo
- Publication number
- CN107059867A CN107059867A CN201710216053.0A CN201710216053A CN107059867A CN 107059867 A CN107059867 A CN 107059867A CN 201710216053 A CN201710216053 A CN 201710216053A CN 107059867 A CN107059867 A CN 107059867A
- Authority
- CN
- China
- Prior art keywords
- stake
- driven piles
- control method
- shape
- scale
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D7/00—Methods or apparatus for placing sheet pile bulkheads, piles, mouldpipes, or other moulds
- E02D7/02—Placing by driving
- E02D7/06—Power-driven drivers
- E02D7/08—Drop drivers with free-falling hammer
Abstract
In Driven Piles of the present invention stop hammer control method, in the upper end periphery iso-surface patch graticule of stake, the nonadjustable signal on the ground by stake, the height H1 of graticule before every gust of beginning time hammering is recorded during pile monkey Driven Piles, record the height H2 of graticule before every gust of end time hammering, judge whether the deflection of every gust of stake meets the requirements, pile monkey stops Driven Piles when continuous some gusts deflection meets the requirements, and otherwise pile monkey continues Driven Piles.A deflection, measurement process, which can more be accurately measured, need not stop hammer and measurement distance of the gauger in safety.
Description
Technical field
The present invention relates to building field, particularly a kind of Driven Piles stop hammering control method into shape.
Background technology
It is to reach supporting course certain depth as design requirement using pile top that hammering pile driving construction middle-end, which holds stake,.What is generally controlled stops hammer
In standard, it is desirable to which last three gusts of hammerings deflection control is no more than 5 centimetres (every gust 10 is hit) at every gust.In rock stratum, (stake supports power
Layer) distribution in erratic curve area, it is virtually impossible to survey the rock stratum absolute altitude of report to control the embedded depth of stake from ground, therefore
Also the reference for stopping hammer standard can not be used as according to stake embedded depth.
Be present more drawback in current various methods, controlled only with experience and pure range estimation, or stop hammer after hammering 10 times
Measure stake deflection.The former can cause a penetration control deviation excessive, as stake is not up to design supporting course, later stage superstructure
There is differential settlement risk;Hammering is excessive, not only lengthens the engineering time, further increases the risk burst after stake top excessively hammering.
The latter discontinuously hammers influence construction speed, and continuous hammering measurement then can influence workman dangerous in bottom operation.
The content of the invention
Present invention aims at providing a kind of Driven Piles to stop hammering control method into shape, can more accurately measure a deflection,
Measurement process need not stop hammer and gauger is in the measurement distance of safety.
Stop hammering control method into shape in order to achieve the above-mentioned advantages, the present invention provides a kind of Driven Piles, methods described includes:A, in the upper of stake
Hold periphery iso-surface patch graticule;B, the nonadjustable signal on the ground by stake, the diameter parallel of scale is in the axis of stake, and scale is along axis
Direction is disposed with multiple scale marks by the first setting spacing;C, use pile monkey Driven Piles;D, the note during pile monkey Driven Piles
The height H1 of graticule before the beginning time hammering of every gust of record, records the height H2 of graticule before every gust of end time hammering;E, calculating are every
The deflection of battle array stake, deflection is height H2 and height H1 difference;F, judge whether the deflection of every gust of stake meets the requirements, when
Pile monkey stops Driven Piles when continuous some gusts deflection meets the requirements, and otherwise pile monkey continues Driven Piles.
In one embodiment that Driven Piles of the present invention stop hammer control method, axis of the graticule perpendicular to the stake.
In one embodiment that Driven Piles of the present invention stop hammer control method, it is downward that the scale lower end is fixed with several
The scale is fixed on the inserted link of extension, the ground that the inserted link is used to insert by the stake.
In one embodiment that Driven Piles of the present invention stop hammer control method, the upper end periphery iso-surface patch graticule in stake
Including:Multiple graticules are drawn along the stake axis direction along the second setting spacing.
In one embodiment that Driven Piles of the present invention stop hammer control method, the scale mark is perpendicular to the scale
The line segment of axis.
In the one embodiment for stopping to hammer into shape control method in Driven Piles of the present invention, described first sets spacing as 5cm, and described the
Two set spacing as 50cm.
In one embodiment that Driven Piles of the present invention stop hammer control method, the step B is before the step A.
In one embodiment that Driven Piles of the present invention stop hammer control method, the graticule is drawn by chalk and formed.
In one embodiment that Driven Piles of the present invention stop hammer control method, the stake is piling bar.
In one embodiment that Driven Piles of the present invention stop hammer control method, the stake is concrete precast pile.
In Driven Piles of the present invention stop hammer control method, in the upper end periphery iso-surface patch graticule of stake, on the ground by stake
Nonadjustable signal, records the height H1 of graticule before every gust of beginning time hammering during pile monkey Driven Piles, records every gust of end
The height H2 of graticule before secondary hammering, judges whether the deflection of every gust of stake meets the requirements, when continuous some gusts deflection is accorded with
Pile monkey stops Driven Piles when conjunction is required, otherwise pile monkey continues Driven Piles.A deflection, measurement process can more be accurately measured
Hammer need not be stopped and gauger is in the measurement distance of safety.
Brief description of the drawings
The Driven Piles that Fig. 1 show first embodiment of the invention stop hammering the principle of the pile monkey Driven Piles process of control method into shape
Figure.
Fig. 2 show the structural representation of Fig. 1 scale.
The Driven Piles that Fig. 3 show second embodiment of the invention stop hammering the principle of the pile monkey Driven Piles process of control method into shape
Figure.
Fig. 4 show the structural representation of Fig. 3 scale.
Embodiment
Further to illustrate the present invention to reach the technological means and effect that predetermined goal of the invention is taken, below in conjunction with
Accompanying drawing and preferred embodiment, to proposing embodiment, structure, feature and its effect according to the present invention, are described in detail as after.
The Driven Piles that Fig. 1 show first embodiment of the invention stop hammering the principle of the pile monkey Driven Piles process of control method into shape
Figure.Fig. 2 show the structural representation of Fig. 1 scale.Fig. 1,2 are referred to, the Driven Piles of first embodiment of the invention stop hammer control
Method processed, including:
A, in the upper end outer peripheral face of stake 1 along the axis direction of stake 2 along the second setting spacing draw multiple graticules 10;Stake 1 is steel
Stake, stake 1 is Vertical Pile (stake axis is perpendicular to horizontal plane), and the upper end of stake 1 has a pile cover 3, graticule 10 perpendicular to stake 1 axis, the
Two set spacing as 50cm, and graticule 10 is drawn by chalk and formed.
B, the nonadjustable signal 2 on the ground 5 on the side of stake 1, the diameter parallel of scale 2 is in the axis of stake 1, and scale 2 is along axis side
Multiple scale marks 21,22 are disposed with to by the first setting spacing, the main body of scale 2 is a long narrow steel plate;The main body of scale 2
There is scale mark 21,22 to include alternate long graduation mark 21, short graduation mark 22 on two sides, and long graduation mark 21 is red, short scale
Line 22 is yellow, and first between long graduation mark 21 and short graduation mark 22 sets spacing as 5cm, and the lower end of scale 2 is welded with three
The inserted link 20 extended downwardly, inserted link 20 is bar dowel, and inserted link 20 is flared out arrangement in branch type.Inserted link 20 is used to insert stake 1
The other nonadjustable signal 2 of ground 5.Scale mark 21,22 is the line segment perpendicular to the axis of scale 2.
C, use the Driven Piles 1 of pile monkey 4;
D, the height H1 for recording during the Driven Piles 1 of pile monkey 4 graticule 10 before every gust of beginning time hammering, record every gust
Terminate the height H2 of graticule 10 before time hammering;
E, the deflection for calculating every gust of stake 1, deflection are height H2 and height H1 difference;
F, judge whether the deflection of every gust of stake 1 meets the requirements, the stake when continuous some gusts deflection meets the requirements
Hammer 4 stops Driven Piles 1, and otherwise pile monkey 4 continues Driven Piles 1.
Further the state of burying after observation pile monkey is hit, after stake is driven into soil amount per hammer close to quality requirement, is carried out
Step D, the height H1 for recording during the Driven Piles 1 of pile monkey 4 graticule 10 before every gust of beginning time hammering, record every gust of end
The height H2 of graticule 10 before secondary hammering.
In one embodiment of the present of invention, soil amount is driven into per hammer after in stake, then perform step A, in stake 1
Upper end outer peripheral face is solid along the second setting multiple graticules 10 of spacing drafting and step B, on the ground 5 on the side of stake 1 along the axis direction of stake 2
Drift slide 2.
The Driven Piles that Fig. 3 show second embodiment of the invention stop hammering the principle of the pile monkey Driven Piles process of control method into shape
Figure.Fig. 4 show the structural representation of Fig. 3 scale.Refer in Fig. 3,4, the present embodiment, stake 1 is concrete precast pile, stake
1 is taper pile.
Step B, the nonadjustable signal 2 on the ground 5 on the side of stake 1 in the present embodiment, in step A, the upper end outer peripheral face edge in stake 1
2 axis directions of stake are drawn along the second setting spacing before multiple graticules 10.
Scale mark 23 is alternate rectangle coating, and the color of each scale mark 23 preferably is different.
Inserted link 20 is the rod-like structure of taper, and the quantity of inserted link 20 is one.
In Driven Piles of the present invention stop hammer control method, in the upper end periphery iso-surface patch graticule of stake, on the ground by stake
Nonadjustable signal, records the height H1 of graticule before every gust of beginning time hammering during pile monkey Driven Piles, records every gust of end
The height H2 of graticule before secondary hammering, judges whether the deflection of every gust of stake meets the requirements, when continuous some gusts deflection is accorded with
Pile monkey stops Driven Piles when conjunction is required, otherwise pile monkey continues Driven Piles.Gauger can see in safe distance in measurement process
The deflection of stake is examined, a deflection, measurement process can more be accurately measured not with the relative position of graticule and scale mark
Need to stop hammer and gauger is in the measurement distance of safety.
In addition the application has further the advantage that compared with prior art:
1st, operate fairly simple, conveniently, safely;
2nd, hammer need not middle be stopped, it is ensured that the continuity as far as possible of hammering, because Driven Piles are whenever intermediate hold one
Hammered again after the section time, it is compacted because soil layer has gradually bounced back, the injection difficulty phase of both strike-ons after continuous and interruption
Difference is more, and strike-on is more difficult to be squeezed into.
3rd, this method is relatively more directly perceived and safe, and opposite end holds type Driven Piles and stops hammer standard control accuracy height, can more accurately control
Stake processed reaches the depth of design supporting course, does not owe to beat, and does not also surpass and beats.Reduce later stage superstructure differential settlement and crack in pile crown
Risk.
More than, only it is presently preferred embodiments of the present invention, any formal limitation not is made to the present invention, although this
Invention is disclosed above with preferred embodiment, but is not limited to the present invention, any those skilled in the art,
Do not depart from the range of technical solution of the present invention, when the technology contents using the disclosure above make a little change or are modified to equivalent
The equivalent embodiment of change, as long as being that, without departing from technical solution of the present invention content, the technical spirit according to the present invention is real to more than
Any simple modification, equivalent variations and modification that example made are applied, in the range of still falling within technical solution of the present invention.
Claims (10)
1. a kind of Driven Piles stop hammering control method into shape, it is characterised in that methods described includes:A, the upper end periphery iso-surface patch mark in stake
Line;B, the nonadjustable signal on the ground by stake, the diameter parallel of scale is in the axis of stake, and scale is in the axial direction by the first setting
Spacing is disposed with multiple scale marks;C, use pile monkey Driven Piles;D, the beginning time for recording during pile monkey Driven Piles every gust
The height H1 of graticule before hammering, records the height H2 of graticule before every gust of end time hammering;E, the deflection for calculating every gust of stake, under
The difference that heavy amount is height H2 and height H1;F, judge whether the deflection of every gust of stake meets the requirements, under continuous some gusts
Pile monkey stops Driven Piles when heavy amount meets the requirements, and otherwise pile monkey continues Driven Piles.
2. Driven Piles according to claim 1 stop hammering control method into shape, it is characterised in that the graticule is perpendicular to the stake
Axis.
3. Driven Piles according to claim 1 stop hammering control method into shape, it is characterised in that the scale lower end is fixed with some
The scale is fixed on the individual inserted link extended downwardly, the ground that the inserted link is used to insert by the stake.
4. Driven Piles according to claim 1 stop hammering control method into shape, it is characterised in that the upper end outer peripheral face in stake is painted
Graticule processed includes:Multiple graticules are drawn along the stake axis direction along the second setting spacing.
5. Driven Piles according to claim 1 stop hammering control method into shape, it is characterised in that the scale mark is perpendicular to institute
State the line segment of scale axis.
6. Driven Piles according to claim 1 stop hammering control method into shape, it is characterised in that described first sets spacing as 5cm,
Described second sets spacing as 50cm.
7. Driven Piles according to claim 1 stop hammer into shape control method, it is characterised in that the step B the step A it
Before.
8. Driven Piles according to claim 1 stop hammer into shape control method, it is characterised in that the graticule by chalk draw and
Into.
9. Driven Piles according to claim 1 stop hammering control method into shape, it is characterised in that the stake is piling bar.
10. Driven Piles according to claim 1 stop hammering control method into shape, it is characterised in that the stake is concrete precast pile.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201710216053.0A CN107059867B (en) | 2017-04-05 | 2017-04-05 | A kind of Driven Piles stop hammering control method into shape |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201710216053.0A CN107059867B (en) | 2017-04-05 | 2017-04-05 | A kind of Driven Piles stop hammering control method into shape |
Publications (2)
Publication Number | Publication Date |
---|---|
CN107059867A true CN107059867A (en) | 2017-08-18 |
CN107059867B CN107059867B (en) | 2019-11-12 |
Family
ID=59603284
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201710216053.0A Active CN107059867B (en) | 2017-04-05 | 2017-04-05 | A kind of Driven Piles stop hammering control method into shape |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN107059867B (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN115559303A (en) * | 2022-11-21 | 2023-01-03 | 三亚宏岩岩土工程有限公司 | Replacement structure of open circular tube steel pile for ocean platform |
Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN102051891A (en) * | 2011-01-27 | 2011-05-11 | 王红卫 | Device and method for observing relative settlement of huge building foundation |
CN203613541U (en) * | 2013-11-15 | 2014-05-28 | 中交天航港湾建设工程有限公司 | Driving device for vertical pipe sinking in shallow sea reclamation area |
JP2015190222A (en) * | 2014-03-28 | 2015-11-02 | パイルフォーラム株式会社 | Piled raft foundation structure for use in small-scale structure |
CN205314086U (en) * | 2015-12-23 | 2016-06-15 | 东风设计研究院有限公司 | Long tubular pile structure of effective record stake |
-
2017
- 2017-04-05 CN CN201710216053.0A patent/CN107059867B/en active Active
Patent Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN102051891A (en) * | 2011-01-27 | 2011-05-11 | 王红卫 | Device and method for observing relative settlement of huge building foundation |
CN203613541U (en) * | 2013-11-15 | 2014-05-28 | 中交天航港湾建设工程有限公司 | Driving device for vertical pipe sinking in shallow sea reclamation area |
JP2015190222A (en) * | 2014-03-28 | 2015-11-02 | パイルフォーラム株式会社 | Piled raft foundation structure for use in small-scale structure |
CN205314086U (en) * | 2015-12-23 | 2016-06-15 | 东风设计研究院有限公司 | Long tubular pile structure of effective record stake |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN115559303A (en) * | 2022-11-21 | 2023-01-03 | 三亚宏岩岩土工程有限公司 | Replacement structure of open circular tube steel pile for ocean platform |
Also Published As
Publication number | Publication date |
---|---|
CN107059867B (en) | 2019-11-12 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN103558044B (en) | The indoor model test device that shield tunnel mortar depositing construction affects neighboring piles | |
CN206191060U (en) | Gas pipeline push pipe construction structures | |
CN103913145A (en) | Crack opening two-direction deformation monitoring structure and measurement method | |
CN201627180U (en) | Reinforced structure of large fault of dam foundation of gravity dam | |
CN109281688B (en) | Tunnel advanced pipe shed accurate positioning system and construction method | |
JP2012082676A (en) | Displacement controlling method | |
CN107059867B (en) | A kind of Driven Piles stop hammering control method into shape | |
CN203256733U (en) | Device for detecting pile top concrete elevation of cast-in-place pile | |
CN106284366B (en) | External pulling type Larsen steel sheet pile reinforcement means | |
CN110872839B (en) | Construction method of conical pile tip tubular pile capable of post-grouting | |
CN207113887U (en) | Dismountable pit displacement monitoring device | |
CN110159308A (en) | A kind of tunnel long pipe shed localization method | |
CN104074209A (en) | Deep plate loading test device | |
CN106760872A (en) | A kind of segment girder precast measurement formula of consolidating superelevation observation tower | |
CN208039242U (en) | The pile anchoring of novel building engineering ground | |
CN106403996A (en) | Production method of forced centering observation mark stake for precision engineering measurement | |
CN106871882A (en) | Borehole pile verticality and flatness laser guidance device and its construction method | |
CN108982249A (en) | Prevent the lever direct shear apparatus and its test method of upper and lower shear box relative tilt | |
CN210151532U (en) | Side pile positioning device for roadbed and pavement engineering construction | |
CN109972635A (en) | Side slope pastes high roadbed quality in slope and controls construction method | |
CN106245689B (en) | A kind of monitoring method of mixing material support stake axle power | |
CN204849855U (en) | Clump of piles field test's model device | |
CN107355258A (en) | Shallow tunnel advance core restrains system for monitoring displacement and method in advance | |
CN109853581B (en) | Mechanism for improving verticality qualification rate of open-cut tunnel foundation pit steel latticed column and using method thereof | |
CN205314086U (en) | Long tubular pile structure of effective record stake |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
GR01 | Patent grant | ||
GR01 | Patent grant |