CN107044288A - Prefabricated support lining structure and construction method for large-deformation tunnel in soft rock - Google Patents
Prefabricated support lining structure and construction method for large-deformation tunnel in soft rock Download PDFInfo
- Publication number
- CN107044288A CN107044288A CN201710361617.XA CN201710361617A CN107044288A CN 107044288 A CN107044288 A CN 107044288A CN 201710361617 A CN201710361617 A CN 201710361617A CN 107044288 A CN107044288 A CN 107044288A
- Authority
- CN
- China
- Prior art keywords
- prefabricated
- preliminary bracing
- tunnel
- prefabricated pipe
- deformation
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
- 238000010276 construction Methods 0.000 title claims abstract description 30
- 239000011435 rock Substances 0.000 title claims abstract description 22
- 239000004567 concrete Substances 0.000 claims abstract description 14
- 238000009412 basement excavation Methods 0.000 claims abstract description 5
- 238000007363 ring formation reaction Methods 0.000 claims abstract description 3
- 239000011083 cement mortar Substances 0.000 claims description 7
- XLYOFNOQVPJJNP-UHFFFAOYSA-N water Substances O XLYOFNOQVPJJNP-UHFFFAOYSA-N 0.000 claims description 6
- 238000005266 casting Methods 0.000 claims description 5
- 238000002347 injection Methods 0.000 claims description 3
- 239000007924 injection Substances 0.000 claims description 3
- 239000000203 mixture Substances 0.000 claims description 2
- 238000009417 prefabrication Methods 0.000 claims description 2
- 230000011218 segmentation Effects 0.000 claims description 2
- 239000011378 shotcrete Substances 0.000 abstract description 5
- 230000007812 deficiency Effects 0.000 abstract description 3
- 238000010923 batch production Methods 0.000 abstract description 2
- 238000005452 bending Methods 0.000 abstract description 2
- 239000011150 reinforced concrete Substances 0.000 abstract description 2
- 229910000831 Steel Inorganic materials 0.000 abstract 2
- 239000007921 spray Substances 0.000 abstract 2
- 239000010959 steel Substances 0.000 abstract 2
- 238000005336 cracking Methods 0.000 abstract 1
- 239000000243 solution Substances 0.000 description 2
- 239000004568 cement Substances 0.000 description 1
- 238000006243 chemical reaction Methods 0.000 description 1
- 230000015271 coagulation Effects 0.000 description 1
- 238000005345 coagulation Methods 0.000 description 1
- 238000010586 diagram Methods 0.000 description 1
- 230000000694 effects Effects 0.000 description 1
- 238000005516 engineering process Methods 0.000 description 1
- 239000002002 slurry Substances 0.000 description 1
Classifications
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH OR ROCK DRILLING; MINING
- E21D—SHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
- E21D11/00—Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
- E21D11/006—Lining anchored in the rock
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH OR ROCK DRILLING; MINING
- E21D—SHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
- E21D11/00—Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
- E21D11/003—Linings or provisions thereon, specially adapted for traffic tunnels, e.g. with built-in cleaning devices
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH OR ROCK DRILLING; MINING
- E21D—SHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
- E21D11/00—Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
- E21D11/04—Lining with building materials
- E21D11/08—Lining with building materials with preformed concrete slabs
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH OR ROCK DRILLING; MINING
- E21D—SHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
- E21D11/00—Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
- E21D11/04—Lining with building materials
- E21D11/10—Lining with building materials with concrete cast in situ; Shuttering also lost shutterings, e.g. made of blocks, of metal plates or other equipment adapted therefor
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH OR ROCK DRILLING; MINING
- E21D—SHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
- E21D11/00—Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
- E21D11/04—Lining with building materials
- E21D11/10—Lining with building materials with concrete cast in situ; Shuttering also lost shutterings, e.g. made of blocks, of metal plates or other equipment adapted therefor
- E21D11/105—Transport or application of concrete specially adapted for the lining of tunnels or galleries ; Backfilling the space between main building element and the surrounding rock, e.g. with concrete
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH OR ROCK DRILLING; MINING
- E21D—SHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
- E21D11/00—Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
- E21D11/38—Waterproofing; Heat insulating; Soundproofing; Electric insulating
Landscapes
- Engineering & Computer Science (AREA)
- Mining & Mineral Resources (AREA)
- Structural Engineering (AREA)
- Architecture (AREA)
- Civil Engineering (AREA)
- Life Sciences & Earth Sciences (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Geochemistry & Mineralogy (AREA)
- Geology (AREA)
- Lining And Supports For Tunnels (AREA)
Abstract
The present invention relates to a kind of prefabricated support lining structure and construction method for large-deformation tunnel in soft rock.The excavation pre-stress on large deformation stratum is big, deformation velocity is fast, spray anchor shaped steel supporting construction maximum efficiency from performing to playing needs certain time, before supporting construction reaches design strength the problems such as local first generation gunite concrete cracking peeling, steelframe bending, distortion and unstability.The present invention replaces traditional spray anchor shaped steel supporting construction using prefabricated reinforced concrete segment formula supporting construction, builds armored concrete secondary lining by the preliminary bracing of prefabricated pipe chip and mould and constitutes;Prefabricated pipe chip preliminary bracing structure by the prefabricated unit section of jurisdiction of some batch production in tunnel using pipe sheet assembling machinery it is assembled, unit section of jurisdiction is bolted cyclization.Prefabricated pipe chip preliminary bracing structure of the present invention can realize immediate support after tunnel excavation, and load-carrying properties are given full play to as early as possible, and effectively reduction is further exacerbated by the risk of deformation because early stage support rigidity deficiency causes.
Description
Technical field
The present invention relates to traffic engineering technical field, and in particular to a kind of prefabricated supporting for large-deformation tunnel in soft rock is served as a contrast
Build structure and construction method.
Background technology
Large-deformation tunnel in soft rock, due to stress direction, the attitude of rocks, stratigraphic structure, the soft or hard inequality in rock stratum, underground water etc.
The comprehensive function of various factors, often shows as deflection greatly, the deformation duration is long, supporting construction stress is complicated in construction,
It will bear to act on from different directions, different size of pressure from surrounding rock, traditional combined bolting and shotcrete structure is from performing to giving full play to
Its maximum efficiency generally requires the regular hour, before gunite concrete gives full play to efficiency supporting construction integral rigidity compared with
It is weak, it is impossible to enough rigidity is provided in time and supporting construction is tended to occur in soft rock large deformation, construction is not up to design to resist
Before intensity, it is local first occur gunite concrete crack and flake off, steelframe bending, distortion and the problems such as unstability, and then cause
Supporting construction loses bearing capacity in advance.Therefore, develop that to be capable of the supporting construction of fast onset its load-carrying properties be the big change of soft rock
In shape tunnel the problem of a urgent need to resolve.
The content of the invention
It is an object of the invention to provide a kind of prefabricated support lining structure and construction method for large-deformation tunnel in soft rock,
Reduce to greatest extent because supporting construction is further exacerbated by the risk of deformation not in time, caused by early stage support rigidity is not enough.
The technical solution adopted in the present invention is:
Prefabricated support lining structure for large-deformation tunnel in soft rock, it is characterised in that:
Prefabricated support lining structure is built armored concrete secondary liner structure by prefabricated pipe chip preliminary bracing structure and mould and constituted;
Prefabricated pipe chip preliminary bracing structure is assemblied to form by the unit section of jurisdiction of some prefabrications, unit section of jurisdiction it is horizontally-spliced into
Ring, each ring is longitudinal spliced into pipe along tunnel axis direction.
The unit section of jurisdiction of prefabricated pipe chip preliminary bracing structure assembling construction in tunnel, is interconnected into by bolt
Ring.
Space internal pressure water filling cement mortar between prefabricated pipe chip preliminary bracing structure and stratum body, makes prefabricated pipe chip
Preliminary bracing structure is in close contact with stratum body.
Mould builds armored concrete secondary liner structure and is segmented one-piece casting along tunnel axis direction.
Prefabricated pipe chip preliminary bracing structure interior surface lays waterproof layer.
Construction method for the prefabricated support lining structure of large-deformation tunnel in soft rock, it is characterised in that:
Comprise the following steps:
Step one:Stratum body is excavated along tunnel contour, after the completion for the treatment of that stratum body is excavated, section of jurisdiction is used in its inner surface immediately
Assembling machine assembly prefabricated pipe chip preliminary bracing structure;
Step 2:After prefabricated pipe chip preliminary bracing structure assembly is finished, by stratum body inner surface and prefabricated pipe chip
Space internal pressure water filling cement mortar between preliminary bracing structural outer surface, it is ensured that stratum body and prefabricated pipe chip preliminary bracing knot
Structure is closely connected;
Step 3:After pressure injection cement mortar is finished, waterproof layer is laid in prefabricated pipe chip preliminary bracing structure interior surface;
Step 5:After waterproof layer laying is finished, the secondary lining of armored concrete is built in waterproof layer inner surface segmentation one-piece casting mould
Build structure.
The present invention has advantages below:
The present invention is used in high ground stress soft rock stress large deformation tunnel, by prefabricated pipe chip preliminary bracing structure, cast in place reinforced bar coagulation
Native secondary liner structure and its waterproof layer composition between the two, prefabricated preliminary bracing structure can realize that batch production is prefabricated, scene
Assembly, do mechanization operation degree is high, and prefabricated piecemeal can be adjusted according to structure stress and construction, be passed through between prefabricated section
Bolt connection, can be achieved quick-assembling, and realization is quickly performed, and the effect that supporting construction undertakes stratum load be played as early as possible, in tunnel
Road can realize immediate support after excavating, and supporting construction bearing capacity is given full play to as early as possible, and effectively reduction is because of early stage support rigidity
Deficiency causes the risk for being further exacerbated by deformation.
Brief description of the drawings
Fig. 1 is structure transverse face of the present invention figure;
Fig. 2 is section of structure of the present invention;
Fig. 3 is prefabricated pipe chip preliminary bracing structure piecemeal schematic diagram of the present invention.
In figure, 1-stratum body, 2-prefabricated pipe chip preliminary bracing structure, 3- locking anchor tubes, 4-waterproof layer, 5-mould
Build armored concrete secondary liner structure.
Embodiment
With reference to embodiment, the present invention will be described in detail.
A kind of prefabricated support lining structure for large-deformation tunnel in soft rock of the present invention, by prefabricated pipe chip initial stage
Supporting construction 2 and mould are built armored concrete secondary liner structure 5 and constituted.Prefabricated pipe chip preliminary bracing structure 2 is by some factories
Prefabricated unit section of jurisdiction is assemblied to form, and the horizontally-spliced cyclization in unit section of jurisdiction, each ring is longitudinal spliced into pipe along tunnel axis direction.
The unit section of jurisdiction of prefabricated pipe chip preliminary bracing structure 2 assembling construction in tunnel, is interconnected into by bolt
Ring.Space internal pressure water filling cement mortar between prefabricated pipe chip preliminary bracing structure 2 and stratum body 1, at the beginning of making prefabricated pipe chip
Phase supporting construction 2 is in close contact with stratum body 1.Mould is built armored concrete secondary liner structure 5 and is segmented along tunnel axis direction
One-piece casting.The inner surface of prefabricated pipe chip preliminary bracing structure 2 lays waterproof layer 4.
Work progress is:
Along tunnel contour after the excavation of stratum body 1, immediately in inner surface assembling construction prefabricated pipe chip preliminary bracing structure 2;
Prefabricated pipe chip preliminary bracing structure 2 is assembled using pipe sheet assembling machinery, is connected by screw bolts between the unit of section of jurisdiction;It is being assembled into
The laying waterproof layer 4 of prefabricated pipe chip preliminary bracing structure 2 of ring;Finally reinforced concrete is built in the inner side subsection setup mould of waterproof layer 4
Native secondary liner structure 5.
In order that stratum body 1 and prefabricated pipe chip preliminary bracing structure 2 are closely connected, assembly can be by pressure injection cement after finishing
Space between the inner surface of slurry placement stratum body 1 and the outer surface of prefabricated pipe chip preliminary bracing structure 2.The present invention is in tunnel
After excavation, prefabricated pipe chip preliminary bracing structure 2 can realize quick-assembling, and immediate support gives full play to supporting construction as early as possible
Bearing capacity, effectively reduction are further exacerbated by the risk of deformation because early stage support rigidity deficiency causes.Reach quick immediate support
Purpose, effectively solve large-deformation tunnel in soft rock construction in the gunite concrete because of caused by preliminary bracing early stage insufficient rigidity open
Split, the problems such as steelframe is distorted.
Present disclosure is not limited to cited by embodiment, and those of ordinary skill in the art are by reading description of the invention
And any equivalent conversion taken technical solution of the present invention, it is that claim of the invention is covered.
Claims (6)
1. the prefabricated support lining structure for large-deformation tunnel in soft rock, it is characterised in that:
Prefabricated support lining structure is by prefabricated pipe chip preliminary bracing structure(2)Armored concrete secondary liner structure is built with mould
(5)Composition;
Prefabricated pipe chip preliminary bracing structure(2)It is assemblied to form by the unit section of jurisdiction of some prefabrications, unit section of jurisdiction is laterally spelled
Ring is connected into, each ring is longitudinal spliced into pipe along tunnel axis direction.
2. the prefabricated support lining structure according to claim 1 for large-deformation tunnel in soft rock, it is characterised in that:
Prefabricated pipe chip preliminary bracing structure(2)Unit section of jurisdiction in tunnel assembling construction, pass through bolt interconnect cyclization.
3. the prefabricated support lining structure according to claim 1 for large-deformation tunnel in soft rock, it is characterised in that:
Prefabricated pipe chip preliminary bracing structure(2)With stratum body(1)Between space internal pressure water filling cement mortar, make prefabricated pipe section
Formula preliminary bracing structure(2)With stratum body(1)It is in close contact.
4. the prefabricated support lining structure according to claim 1 for large-deformation tunnel in soft rock, it is characterised in that:
Mould builds armored concrete secondary liner structure(5)One-piece casting is segmented along tunnel axis direction.
5. the prefabricated support lining structure according to claim 1 for large-deformation tunnel in soft rock, it is characterised in that:
Prefabricated pipe chip preliminary bracing structure(2)Inner surface lays waterproof layer(4).
6. the construction method of the prefabricated support lining structure for large-deformation tunnel in soft rock, it is characterised in that:
Comprise the following steps:
Step one:Stratum body is excavated along tunnel contour(1), treat stratum body(1)After the completion of excavation, adopted immediately in its inner surface
With the assembled prefabricated pipe chip preliminary bracing structure of duct piece assembling machine(2);
Step 2:Prefabricated pipe chip preliminary bracing structure(2)After assembly is finished, by stratum body(1)Inner surface with it is prefabricated
Pipe type preliminary bracing structure(2)Space internal pressure water filling cement mortar between outer surface, it is ensured that stratum body(1)And prefabricated pipe section
Formula preliminary bracing structure(2)It is closely connected;
Step 3:After pressure injection cement mortar is finished, in prefabricated pipe chip preliminary bracing structure(2)Inner surface lays waterproof layer(4);
Step 5:Treat waterproof layer(4)After laying is finished, armored concrete is built in waterproof layer inner surface segmentation one-piece casting mould secondary
Liner structure(5).
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201710361617.XA CN107044288A (en) | 2017-05-22 | 2017-05-22 | Prefabricated support lining structure and construction method for large-deformation tunnel in soft rock |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201710361617.XA CN107044288A (en) | 2017-05-22 | 2017-05-22 | Prefabricated support lining structure and construction method for large-deformation tunnel in soft rock |
Publications (1)
Publication Number | Publication Date |
---|---|
CN107044288A true CN107044288A (en) | 2017-08-15 |
Family
ID=59546161
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201710361617.XA Pending CN107044288A (en) | 2017-05-22 | 2017-05-22 | Prefabricated support lining structure and construction method for large-deformation tunnel in soft rock |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN107044288A (en) |
Cited By (9)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN107630708A (en) * | 2017-11-06 | 2018-01-26 | 山东建筑大学 | A kind of prefabricated assembled composite support system based on shaped steel |
CN108119164A (en) * | 2017-11-06 | 2018-06-05 | 山东建筑大学 | A kind of prefabricated assembled composite supporting construction |
CN108843342A (en) * | 2018-08-15 | 2018-11-20 | 中铁第勘察设计院集团有限公司 | Realize the assembled preliminary bracing structure of tunnel quick closure |
CN109162728A (en) * | 2017-09-25 | 2019-01-08 | 许生安 | A kind of tunnel structure of high-strength anti-seismic |
CN109899092A (en) * | 2017-12-08 | 2019-06-18 | 中铁二局集团有限公司 | A kind of soft rock extrusion pressing type large deformation tunnel arch lock solid structure and method |
CN110056371A (en) * | 2019-05-28 | 2019-07-26 | 长安大学 | A kind of tunnel morning strong supporting system and its installation method |
CN110529154A (en) * | 2019-09-16 | 2019-12-03 | 中铁十一局集团有限公司 | Prefabricated assembled space grid structure and its construction method for tunnel support |
CN110700211A (en) * | 2019-11-09 | 2020-01-17 | 黄河勘测规划设计研究院有限公司 | Assembly type steel segment template construction method suitable for rapid lining of horseshoe-shaped tunnel |
CN111075477A (en) * | 2020-01-17 | 2020-04-28 | 中铁工程装备集团有限公司 | Semi-rigid supporting structure system of large-section soft rock tunnel and construction method of semi-rigid supporting structure system |
Citations (11)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH0821196A (en) * | 1994-07-07 | 1996-01-23 | Masahiro Yoshida | Structure of floor system for segment type tunnel, and construction of segment type tunnel with precast floor system |
JPH0835398A (en) * | 1994-07-22 | 1996-02-06 | Three Bond Co Ltd | Secondary lining work structure for shield tunnel and its construction method |
JPH08246799A (en) * | 1992-01-30 | 1996-09-24 | Maeda Corp | Reinforcing method of primary lining segment |
JP2000064793A (en) * | 1998-08-25 | 2000-02-29 | Tekken Constr Co Ltd | Lining structure of tunnel and its lining method |
JP2009203623A (en) * | 2008-02-26 | 2009-09-10 | Tokyu Construction Co Ltd | Joint structure and connecting method for steel segment |
EP2495394A1 (en) * | 2011-03-02 | 2012-09-05 | Silvino Pompeu Santos | Tunnel with exterior tube and reinforced interior tube |
CN202900285U (en) * | 2012-11-08 | 2013-04-24 | 金陵科技学院 | Damping shield tunnel structure |
CN204646270U (en) * | 2015-01-23 | 2015-09-16 | 北京东方雨虹防水工程有限公司 | Shield method waterproof construction system |
CN205206838U (en) * | 2015-12-17 | 2016-05-04 | 长安大学 | Collapsible loess tunnel supporting construction |
CN105781575A (en) * | 2016-03-11 | 2016-07-20 | 济南轨道交通集团有限公司 | Water-rich stratum pipe piece combination structure and construction method thereof |
CN206801578U (en) * | 2017-05-22 | 2017-12-26 | 中铁第一勘察设计院集团有限公司 | A kind of prefabricated support lining structure for large-deformation tunnel in soft rock |
-
2017
- 2017-05-22 CN CN201710361617.XA patent/CN107044288A/en active Pending
Patent Citations (11)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH08246799A (en) * | 1992-01-30 | 1996-09-24 | Maeda Corp | Reinforcing method of primary lining segment |
JPH0821196A (en) * | 1994-07-07 | 1996-01-23 | Masahiro Yoshida | Structure of floor system for segment type tunnel, and construction of segment type tunnel with precast floor system |
JPH0835398A (en) * | 1994-07-22 | 1996-02-06 | Three Bond Co Ltd | Secondary lining work structure for shield tunnel and its construction method |
JP2000064793A (en) * | 1998-08-25 | 2000-02-29 | Tekken Constr Co Ltd | Lining structure of tunnel and its lining method |
JP2009203623A (en) * | 2008-02-26 | 2009-09-10 | Tokyu Construction Co Ltd | Joint structure and connecting method for steel segment |
EP2495394A1 (en) * | 2011-03-02 | 2012-09-05 | Silvino Pompeu Santos | Tunnel with exterior tube and reinforced interior tube |
CN202900285U (en) * | 2012-11-08 | 2013-04-24 | 金陵科技学院 | Damping shield tunnel structure |
CN204646270U (en) * | 2015-01-23 | 2015-09-16 | 北京东方雨虹防水工程有限公司 | Shield method waterproof construction system |
CN205206838U (en) * | 2015-12-17 | 2016-05-04 | 长安大学 | Collapsible loess tunnel supporting construction |
CN105781575A (en) * | 2016-03-11 | 2016-07-20 | 济南轨道交通集团有限公司 | Water-rich stratum pipe piece combination structure and construction method thereof |
CN206801578U (en) * | 2017-05-22 | 2017-12-26 | 中铁第一勘察设计院集团有限公司 | A kind of prefabricated support lining structure for large-deformation tunnel in soft rock |
Cited By (11)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN109162728A (en) * | 2017-09-25 | 2019-01-08 | 许生安 | A kind of tunnel structure of high-strength anti-seismic |
CN109162728B (en) * | 2017-09-25 | 2020-01-10 | 济宁市鸿翔公路勘察设计研究院有限公司 | High-strength anti-seismic tunnel structure |
CN107630708A (en) * | 2017-11-06 | 2018-01-26 | 山东建筑大学 | A kind of prefabricated assembled composite support system based on shaped steel |
CN108119164A (en) * | 2017-11-06 | 2018-06-05 | 山东建筑大学 | A kind of prefabricated assembled composite supporting construction |
CN108119164B (en) * | 2017-11-06 | 2024-01-19 | 山东建筑大学 | Prefabricated assembled composite support structure |
CN109899092A (en) * | 2017-12-08 | 2019-06-18 | 中铁二局集团有限公司 | A kind of soft rock extrusion pressing type large deformation tunnel arch lock solid structure and method |
CN108843342A (en) * | 2018-08-15 | 2018-11-20 | 中铁第勘察设计院集团有限公司 | Realize the assembled preliminary bracing structure of tunnel quick closure |
CN110056371A (en) * | 2019-05-28 | 2019-07-26 | 长安大学 | A kind of tunnel morning strong supporting system and its installation method |
CN110529154A (en) * | 2019-09-16 | 2019-12-03 | 中铁十一局集团有限公司 | Prefabricated assembled space grid structure and its construction method for tunnel support |
CN110700211A (en) * | 2019-11-09 | 2020-01-17 | 黄河勘测规划设计研究院有限公司 | Assembly type steel segment template construction method suitable for rapid lining of horseshoe-shaped tunnel |
CN111075477A (en) * | 2020-01-17 | 2020-04-28 | 中铁工程装备集团有限公司 | Semi-rigid supporting structure system of large-section soft rock tunnel and construction method of semi-rigid supporting structure system |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN107044288A (en) | Prefabricated support lining structure and construction method for large-deformation tunnel in soft rock | |
CN101666232B (en) | Construction method for six-part excavation of super-large section tunnel | |
CN204984441U (en) | It backfills novel section of jurisdiction of quality behind one's back to change single shield TBM section of jurisdiction | |
CN107725068A (en) | A kind of assembled supporting construction and its construction method based on outside steel arch-shelf and inner side concrete slab | |
CN102322027A (en) | A kind of method that adopts the Mine Method expansion to dig shield tunnel construction subway station | |
CN104533446A (en) | Construction method and structure of two-layer preliminary support for preventing geological disaster of large-section weak surrounding rock tunnel | |
CN101864959A (en) | Method for tunneling construction of main structure of underground station | |
CN105909268B (en) | Prestressing combination formula well tunnel modular structure construction method and modular structure | |
CN106869969A (en) | A kind of excavation supporting construction method of soft rock large section tunnel | |
CN110259485B (en) | Loess tunnel support system and installation method thereof | |
CN106014456A (en) | Double-layer lining special quasi-circular sectional mining method tunnel structure and construction method thereof | |
CN102287207B (en) | Assembling jacking method in relation to serious collapse of small-section tunnel | |
CN103628885A (en) | Tunnel exit cover-excavation construction method of Ultra-shadow buried tunnel | |
CN106930777A (en) | The construction method of the lining of Bored Section of Metro main track assembled two | |
CN108843342A (en) | Realize the assembled preliminary bracing structure of tunnel quick closure | |
CN103670446B (en) | Circular diversion tunnel 2/3 circle concrete-liner construction method | |
CN109736850B (en) | Roadway shell and arch combined strong bearing structure and construction method thereof | |
CN104831733A (en) | Arch bridge abutment tunnel type large-angle inclined pile construction method | |
CN107401161A (en) | High ferro shield tunnel construction method is worn under pipe-roof method and MJS method joint reinforcements | |
CN207033463U (en) | Mine shield handing-over tunnel folded type joint design in the middle part of marine site | |
CN107806349A (en) | A kind of steel FRP complex waves card tunnel secondary liner structure and its apply method | |
CN111305869A (en) | Prefabricated lining structure of arch wall and construction method | |
CN113775356A (en) | Shield constructs underground butt joint section secondary lining structure | |
CN108915714A (en) | The double TBM installation methods in one hole | |
CN105065032B (en) | Suitable for the large cross-section tunnel support system construction method of steep dip stratified rock masses |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
RJ01 | Rejection of invention patent application after publication |
Application publication date: 20170815 |
|
RJ01 | Rejection of invention patent application after publication |