CN107037307A - A kind of secondary through-flow method of power plant main system c-type - Google Patents

A kind of secondary through-flow method of power plant main system c-type Download PDF

Info

Publication number
CN107037307A
CN107037307A CN201710203946.1A CN201710203946A CN107037307A CN 107037307 A CN107037307 A CN 107037307A CN 201710203946 A CN201710203946 A CN 201710203946A CN 107037307 A CN107037307 A CN 107037307A
Authority
CN
China
Prior art keywords
relay
current
protection tester
flow
main system
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201710203946.1A
Other languages
Chinese (zh)
Other versions
CN107037307B (en
Inventor
张钢
周亚群
寇水潮
邵云鹏
何信林
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Xian Thermal Power Research Institute Co Ltd
Original Assignee
Xian Thermal Power Research Institute Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Xian Thermal Power Research Institute Co Ltd filed Critical Xian Thermal Power Research Institute Co Ltd
Priority to CN201710203946.1A priority Critical patent/CN107037307B/en
Publication of CN107037307A publication Critical patent/CN107037307A/en
Application granted granted Critical
Publication of CN107037307B publication Critical patent/CN107037307B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • GPHYSICS
    • G01MEASURING; TESTING
    • G01RMEASURING ELECTRIC VARIABLES; MEASURING MAGNETIC VARIABLES
    • G01R31/00Arrangements for testing electric properties; Arrangements for locating electric faults; Arrangements for electrical testing characterised by what is being tested not provided for elsewhere
    • G01R31/50Testing of electric apparatus, lines, cables or components for short-circuits, continuity, leakage current or incorrect line connections
    • GPHYSICS
    • G01MEASURING; TESTING
    • G01RMEASURING ELECTRIC VARIABLES; MEASURING MAGNETIC VARIABLES
    • G01R19/00Arrangements for measuring currents or voltages or for indicating presence or sign thereof
    • G01R19/0092Arrangements for measuring currents or voltages or for indicating presence or sign thereof measuring current only
    • GPHYSICS
    • G01MEASURING; TESTING
    • G01RMEASURING ELECTRIC VARIABLES; MEASURING MAGNETIC VARIABLES
    • G01R25/00Arrangements for measuring phase angle between a voltage and a current or between voltages or currents

Abstract

The invention belongs to electric adjustment and electrical test technical field, and in particular to a kind of secondary through-flow method of power plant electricity main system c-type.This method chooses benchmark CT when secondary through-flow by G-T protective cabinet current channel, by benchmark CT external terminals and subject CT external terminal short circuits in the corresponding body terminal casees of benchmark CT, forms c-type loop.0.1 times of rated current and rated current are exported by relay-protection tester respectively in the corresponding G-T protective cabinet current channel external terminals of benchmark CT; amplitude, phase and the secondary burden of detection subject CT secondary circuit, verify the integrality and accuracy of its secondary circuit.The present invention uses the secondary through-flow method of c-type, without carrying out secondary through-flow test in CT roots, save secondary throughput time, it is easy to operate, it is practical, test efficiency is high, can fast and accurately check CT secondary circuit existing defects, it is adaptable to the secondary through-flow test field of small-sized, medium-sized, Generator Set.

Description

A kind of secondary through-flow method of power plant main system c-type
Technical field:
The invention belongs to electric adjustment and electrical test technical field, and in particular to a kind of power plant main system c-type is secondary Through-flow method.
Background technology:
Current Chinese Economy Development speed is fast, and living standards of the people are increasingly improved, and the fast development of power industry is wherein Serve key effect.At the beginning of 13 plan, electricity needs is growing day by day, and power system installed capacity constantly rises, Unit is built to be continuously increased.
During new power plant construction electric adjustment, it need to ensure that all CT wiring are correct, no open circuit phenomenon, all PT wiring are just Really, no short circuit phenomenon.Power plant electricity main system is high due to voltage class, and equipment operational reliability requires high, and CT configurations are more, and two The features such as minor loop wiring is complicated, it is necessary to check CT second loop return wirings and carry out through-flow test before electric a whole set of startup, The instrument capacity that is put to the test is limited, and is carried out once through-flow difficulty height, is generally only carried out secondary through-flow test, it is ensured that be electrically a whole set of to start It is smoothed out.Method that traditional secondary is through-flow, generally carries out through-flow test, due to primary electrical system CT bodies in CT body terminals case Terminal box is more dispersed, the shortcomings of in situ test power supply wiring is difficult, there is big working strength, throughput time length, experiment facility Property difference the problems such as.
The content of the invention:
The purpose of the present invention is that there is provided a kind of power plant electricity master for deficiency present in the through-flow method of traditional secondary Method that secondary system is through-flow, the accuracy for verifying main system CT secondary circuits, it is ensured that CT secondary circuits without open circuit phenomenon, together Method that Shi Caiyong c-types are through-flow, primary electrical system bis- through-flow tests of all CT, nothing can be just completed in G-T protective cabinet dosage Working strength need to be reduced in each only dosage of CT body terminals packing list, the working time is saved, be that unit the whole series startup is smoothed out carrying For effective guarantee.
To reach above-mentioned purpose, the present invention adopts the following technical scheme that to realize:
A kind of secondary through-flow method of power plant electricity main system c-type, comprises the following steps:
1) the secondary through-flow preliminary preparation of power plant electricity main system c-type is carried out, preparation enters step after terminating 2);
2) relay-protection tester power supply is opened, regulation relay-protection tester exports 0.1 times of rated current, into step 3);
3) measure and record CT secondary side actual currents when relay-protection tester exports 0.1 times of rated current, into step It is rapid 4);
4) amplitude and phase of CT secondary side currents measurement amplitude and phase and relay-protection tester output current are judged It is whether consistent, if the determination result is YES, it was demonstrated that this group of CT secondary circuit is completely reliable, carry out step 6);Otherwise judged result is Into step 5);
5) relay-protection tester is closed, searches and eliminates return to step 2 after the CT secondary circuit defects);
6) regulation relay-protection tester output rated current, into step 7);
7) CT secondary side actual currents when measuring and recording relay-protection tester output rated current, into step 8);
8) amplitude and phase of CT secondary side currents measurement amplitude and phase and relay-protection tester output current are judged It is whether consistent, if the determination result is YES, demonstrate again that the CT secondary circuits are completely reliable, into step 10);Judged result is no Then enter step 9);
9) relay-protection tester is closed, searches and eliminates return to step 6 after the CT secondary circuit defects);
10) in the case where CT secondary side currents are rated current, measure and record bis- burdens of CT, into step 11);
11) judge the burden of CT bis- times whether three-phase equilibrium, if the determination result is YES, into step 13), judged result is no Then enter step 12);
12) relay-protection tester is closed, searches and eliminates return to step 10 after the CT secondary circuit defects);
13) remaining each group bis- through-flow tests of CT are carried out successively, until off-test.
The present invention, which is further improved, to be, the step 1) the secondary through-flow test early-stage preparations of power plant main system c-type Work, detailed process is as follows:
101) loop check is carried out to power plant main system each group CT secondary circuits, from CT roots to CT body terminal casees, Again to each disk cabinet device, it is ensured that each group CT secondary circuit accuracys, and without open circuit phenomenon;
102) power plant main system each CT body terminals tank current is disconnected in flakes, when preventing CT bis- times through-flow, CT secondary sides Electric current senses CT primary sides, draws upper each disk cabinet device current channel electric current in flakes, and it is in flakes and electric to fasten current channel electric current External terminal in stream;
103) G-T protective cabinet current channel includes main system electric current everywhere, and relay-protection tester current channel is connect To G-T protective cabinet circulation road external terminal, the G-T protective cabinet current channel electric current is disconnected in flakes, in G-T protective cabinet By step 101 in CT body terminals case where the current channel corresponding current) CT is considered as benchmark CT, in CT body terminal casees By step 101) benchmark CT external terminals and another group of step 102) CT external terminal short circuits, form c-type current loop;
104) by with step 101) benchmark CT short circuits step 102) CT be considered as subject CT, the step 102 for measuring and recording) CT secondary circuits are the secondary circuit for being tested CT.
Of the invention further improve be, step 3), step 7) include following flow:
First, measured by clamp ammeter and record subject CT current amplitude and phase sequence in body terminal case;
Then, measured between electronics and record subject CT secondary circuits to each disk cabinet current channel amplitude and phase sequence.
The present invention, which is further improved, to be, the step 4) in, relay-protection tester exports 0.1 times of rated current When, subject CT secondary loop currents amplitude and phase are contrasted with relay-protection tester output current, if inconsistent, are stopped immediately Relay-protection tester, checks and eliminates CT secondary circuit defects, proceed after through-flow test, passed examination, according to step 6) regulation relay-protection tester output rated current, check subject CT secondary circuits current amplitude and phase, if still with Relay-protection tester output current is inconsistent, then the CT secondary circuits still have defect, after after defect expressivity, can be again Carry out after rated current through-flow test, passed examination, according to step 10) in the case where CT secondary side currents are rated current, Measure and record bis- burdens of CT, if secondary burden value three-phase equilibrium, bis- through-flow tests of this group of CT terminate, and carry out next group CT through-flow tests, if uneven, secondary circuit defect still has, after defect to be canceled, proceeds rated current situation Under it is secondary burden measurement experiment.
Compared with prior art, the present invention has advantages below:
1st, the present invention utilizes the through-flow method of c-type so that through-flow test can complete electric master in G-T protective cabinet dosage System bis- through-flow tests of all CT, without in each only dosage of CT body terminals packing list, reducing working strength, when saving work Between, improve test efficiency, it is ensured that CT secondary circuit accuracys.
2nd, the present invention first by relay-protection tester export 0.1 times of rated current, check CT secondary circuits amplitude and Phase, the very first time finds and eliminates CT circuit defects.
3rd, the present invention exports 0.1 times of rated current in relay-protection tester respectively and relay-protection tester output is specified Under current conditions, the correctness of CT secondary circuits, and CT bis- times when relay-protection tester exports rated current are judged twice In the case of loop measurement is correct, bis- burdens of CT are checked, prevent CT secondary circuits from there is wiring and not enough fastening, terminal loosens etc. Problem.
4th, the present invention is practical, it is adaptable to different power plant electrical main systems, is easy to promote the use of in Commissioning field, it is ensured that Unit complete start-up test is smoothed out.
In summary, the present invention can save secondary throughput time, easy to operate, practical, and test efficiency is high, can Fast and accurately check CT secondary circuit existing defects, it is adaptable to the secondary through-flow test of small-sized, medium-sized, Generator Set Field.
Brief description of the drawings:
Fig. 1 is c-type through-flow test flow chart of the present invention.
Fig. 2 is primary electrical system wiring diagram of the present invention.
Fig. 3 is the secondary through-flow exemplary plot of c-type.
In figure:1- relay-protection testers, (generator neutral point CT electric currents lead to 2- G-T protective A cabinet terminal blocks figure Road), 3- generator CT body terminal casees, 101,102,103,104 be generator neutral point CT, and 105,106,107,108 be hair Motor generator terminal CT,;201st, high-pressure side cannula C T is become based on 202,203,204 be neutral point of main transformer zero sequence CT, and 205,206 be main transformer Neutral point clearance zero sequence protection CT, 301,302,303,304,305,306,307,308 be booster stations main transformer interval CT, 401,402, 403rd, 404,405 be factory height become high-pressure side CT, 406,407 be A branches zero sequence CT, 408,409 be B branches zero sequence CT, 501, 502nd, 503,504 be 6kV A forked working inlet wires CT, and 601,602,603,604 be 6kV B forked working inlet wires CT, 701, 702nd, 703 be excitation-transformation variable high-pressure side CT, and 704,705,706 be excitation low pressure side CT.
Embodiment:
Below by accompanying drawing, technical scheme is described in further detail.
As shown in Figure 1, Figure 2 and Figure 3, a kind of secondary through-flow method of power plant electricity main system c-type of the present invention, bag Include following steps:
1) the secondary through-flow test preliminary preparation of c-type is carried out, treats to enter step 2 after the completion of all preliminary preparations);
2) relay-protection tester power supply is opened, regulation relay-protection tester exports 0.1 times of rated current, and enters step It is rapid 3);
3) measure and record CT secondary side actual currents when relay-protection tester exports 0.1 times of rated current, with laggard Enter step 4);
4) judge CT secondary side currents measurement amplitude and phase is with relay-protection tester output current amplitude and phase It is no consistent, if the determination result is YES, into step 6);If judged result is no, into step 5);
5) relay-protection tester is closed, searches and eliminates return to step 2 after the CT secondary circuit defects);
6) regulation relay-protection tester output rated current, into step 7);
7) CT secondary side actual currents when measuring and recording relay-protection tester output rated current, subsequently enter step 8);
8) judge CT secondary side currents measurement amplitude and phase is with relay-protection tester output current amplitude and phase It is no consistent, if the determination result is YES, into step 10);If judged result is no, into step 9);
9) relay-protection tester is closed, searches and eliminates return to step 6 after the CT secondary circuit defects);
10) in the case where CT secondary side currents are rated current, measure and record bis- burdens of CT, subsequently enter step 11);
11) judge the burden of CT bis- times whether three-phase equilibrium, if the determination result is YES, into step 13);If judged result is It is no, then into step 12);
12) relay-protection tester is closed, searches and eliminates return to step 10 after the CT secondary circuit defects);
13) remaining each group bis- through-flow tests of CT are carried out successively, until off-test.
In this example, the step 1) the secondary through-flow test preliminary preparation of power plant electricity main system, its specific stream Journey is as follows:
101) loop check is carried out to power plant main system each group CT secondary circuits, from CT roots to CT body terminal casees, Again to each disk cabinet device, it is ensured that each group CT secondary circuit accuracys, and without open circuit phenomenon;
102) power plant main system each CT body terminals tank current is disconnected in flakes, when preventing CT bis- times through-flow, CT secondary sides Electric current senses CT primary sides, draws upper each disk cabinet device current channel electric current in flakes, and it is in flakes and electric to fasten current channel electric current External terminal in stream;
103) G-T protective cabinet current channel includes main system electric current everywhere, and relay-protection tester current channel is connect To G-T protective A cabinet generator generator terminal CT current channel external terminals, disconnect G-T protective A cabinet generator generator terminal CT electric currents and lead to Road electric current in flakes, will be connected to that group of CT of G-T protective A cabinets and be considered as 1LH in benchmark CT, i.e. figure in generator CT body terminal casees, By 1LH external terminals and 2LH external terminal short circuits in generator CT body terminal casees, then 2LH is subject CT.
In the present embodiment, the step 3), step 7) include following flow:
301) measured by clamp ammeter and record 2LH current amplitude and phase sequence in body terminal case;
302) measured between electronics and record 2LH secondary circuits to the amplitude and phase sequence for protecting B cabinet electric currents.
In the present embodiment, above-mentioned steps 4) in, when relay-protection tester exports 0.1 times of rated current, subject CT bis- times Loop current amplitude and phase are contrasted with relay-protection tester output current, it should difference less, if current amplitude difference compared with Big or current phase mistake, then stop relay-protection tester, check and eliminate CT secondary circuit defects, can continue immediately Carry out after through-flow test, passed examination, according to step 6) regulation relay-protection tester output rated current, check subject CT bis- The current amplitude and phase of minor loop, if current amplitude is still larger with relay-protection tester output current, the CT bis- times Loop still has defect, after after defect expressivity, can carry out again after rated current through-flow test, passed examination, according to step It is rapid 10) in the case where CT secondary side currents are rated current, measure and record the burden of CT bis- times, if secondary burden value three is flat Weighing apparatus, then bis- through-flow tests of this group of CT terminate, and carry out next group of CT through-flow test, if uneven, secondary circuit defect is still In the presence of after defect to be canceled, secondary burden measurement is tested in the case of proceeding rated current.
In this example, when carrying out the secondary through-flow test of power plant electricity main system, 2LH bis- times in engine block terminal box After through-flow test terminates, relay-protection tester is closed, 1LH and 2LH external terminal shorting stubs in engine block terminal box are removed, Short circuit 1LH and 3LH external terminal, and 3LH is considered as subject CT, carry out bis- through-flow tests of 3LH.By the method, in transformer unit Protection cabinet in by certain current channel correspondence CT is considered as benchmark CT, in benchmark CT body terminal casees, short circuit subject CT external terminals and Benchmark CT external terminals, are added by relay-protection tester in G-T protective cabinet benchmark CT corresponding current passage external terminals Amount, carries out each bis- through-flow tests of CT of generator primary electrical system successively.
It is described above, only it is presently preferred embodiments of the present invention, not the present invention is imposed any restrictions, it is every according to the present invention Any simple modification, change and equivalent structure change that technical spirit is made to above example, still fall within skill of the present invention In the protection domain of art scheme.

Claims (4)

1. a kind of secondary through-flow method of power plant electricity main system c-type, it is characterised in that comprise the following steps:
1) the secondary through-flow preliminary preparation of power plant electricity main system c-type is carried out, preparation enters step 2 after terminating);
2) relay-protection tester power supply is opened, regulation relay-protection tester exports 0.1 times of rated current, into step 3);
3) measure and record CT secondary side actual currents when relay-protection tester exports 0.1 times of rated current, into step 4);
4) judge CT secondary side currents measurement amplitude and phase and relay-protection tester output current amplitude and phase whether Unanimously, if the determination result is YES, it was demonstrated that this group of CT secondary circuit is completely reliable, step 6 is carried out);Judged result is otherwise to enter Step 5);
5) relay-protection tester is closed, searches and eliminates return to step 2 after the CT secondary circuit defects);
6) regulation relay-protection tester output rated current, into step 7);
7) CT secondary side actual currents when measuring and recording relay-protection tester output rated current, into step 8);
8) judge CT secondary side currents measurement amplitude and phase and relay-protection tester output current amplitude and phase whether Unanimously, if the determination result is YES, demonstrate again that the CT secondary circuits are completely reliable, into step 10);Judged result is otherwise to enter Enter step 9);
9) relay-protection tester is closed, searches and eliminates return to step 6 after the CT secondary circuit defects);
10) in the case where CT secondary side currents are rated current, measure and record bis- burdens of CT, into step 11);
11) judge the burden of CT bis- times whether three-phase equilibrium, if the determination result is YES, into step 13), otherwise judged result is enters Enter step 12);
12) relay-protection tester is closed, searches and eliminates return to step 10 after the CT secondary circuit defects);
13) remaining each group bis- through-flow tests of CT are carried out successively, until off-test.
2. a kind of secondary through-flow method of power plant electricity main system c-type according to claims 1, it is characterised in that institute State step 1) the secondary through-flow test preliminary preparation of power plant main system c-type, detailed process is as follows:
101) loop check is carried out to power plant main system each group CT secondary circuits, from CT roots to CT body terminal casees, then extremely Each disk cabinet device, it is ensured that each group CT secondary circuit accuracys, and without open circuit phenomenon;
102) power plant main system each CT body terminals tank current is disconnected in flakes, when preventing CT bis- times through-flow, CT secondary side currents CT primary sides are sensed, upper each disk cabinet device current channel electric current are drawn in flakes, and fasten current channel electric current in flakes and in electric current External terminal;
103) G-T protective cabinet current channel includes main system electric current everywhere, and relay-protection tester current channel is connected into hair Change group protects cabinet circulation road external terminal, the G-T protective cabinet current channel electric current is disconnected in flakes, in the G-T protective cabinet electricity By step 101 in CT body terminals case where circulation road corresponding current) CT is considered as benchmark CT, and will step in CT body terminal casees Rapid 101) benchmark CT external terminals and another group of step 102) CT external terminal short circuits, form c-type current loop;
104) by with step 101) benchmark CT short circuits step 102) CT be considered as subject CT, the step 102 for measuring and recording) CT bis- Minor loop is the secondary circuit for being tested CT.
3. a kind of secondary through-flow method of power plant main system c-type according to claims 1, it is characterised in that step 3), Step 7) include following flow:
First, measured by clamp ammeter and record subject CT current amplitude and phase sequence in body terminal case;
Then, measured between electronics and record subject CT secondary circuits to each disk cabinet current channel amplitude and phase sequence.
4. a kind of secondary through-flow method of power plant main system c-type according to claims 1, it is characterised in that the step It is rapid 4) in, when relay-protection tester exports 0.1 times of rated current, subject CT secondary loop currents amplitude and phase and relay are protected The contrast of tester output current is protected, if inconsistent, stops relay-protection tester immediately, checks and eliminates CT secondary circuits and lack Fall into, proceed after through-flow test, passed examination, according to step 6) regulation relay-protection tester output rated current, check It is tested the current amplitude and phase of CT secondary circuits, if still inconsistent with relay-protection tester output current, the CT bis- Minor loop still has defect, after after defect expressivity, can carry out again after rated current through-flow test, passed examination, according to Step 10) in the case where CT secondary side currents are rated current, measure and record bis- burdens of CT, if secondary burden value three-phase Balance, then bis- through-flow tests of this group of CT terminate, and carry out next group of CT through-flow test, if uneven, secondary circuit defect is still So exist, after defect to be canceled, proceed secondary burden measurement experiment in the case of rated current.
CN201710203946.1A 2017-03-30 2017-03-30 A kind of secondary through-flow method of power plant main system c-type Active CN107037307B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710203946.1A CN107037307B (en) 2017-03-30 2017-03-30 A kind of secondary through-flow method of power plant main system c-type

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710203946.1A CN107037307B (en) 2017-03-30 2017-03-30 A kind of secondary through-flow method of power plant main system c-type

Publications (2)

Publication Number Publication Date
CN107037307A true CN107037307A (en) 2017-08-11
CN107037307B CN107037307B (en) 2019-06-04

Family

ID=59533465

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710203946.1A Active CN107037307B (en) 2017-03-30 2017-03-30 A kind of secondary through-flow method of power plant main system c-type

Country Status (1)

Country Link
CN (1) CN107037307B (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111413657A (en) * 2020-04-13 2020-07-14 西安热工研究院有限公司 CT body secondary circuit calibration method
CN111707981A (en) * 2020-07-10 2020-09-25 西安热工研究院有限公司 CT indirect secondary through-flow method for generator set
CN112986856A (en) * 2021-03-26 2021-06-18 西安热工研究院有限公司 Method for checking integrity of three-phase current secondary circuit of power plant
CN113589214A (en) * 2021-08-05 2021-11-02 中国大唐集团科学技术研究院有限公司西北电力试验研究院 CT secondary through-flow method for power plant

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
EP1217707A1 (en) * 2000-12-20 2002-06-26 Schneider Electric Industries SA Device for termination of primary current in a current transformer having saturation compensation means
CN101867225A (en) * 2010-05-31 2010-10-20 江苏省电力公司南通供电公司 Debugging method for integrated automation of transformer substation and integration of relaying protection system
CN202975222U (en) * 2012-11-28 2013-06-05 沧州供电公司 Integrated tester for secondary circuit of current transformer
CN105022017A (en) * 2015-07-22 2015-11-04 国家电网公司 Portable CT circuit flow test instrument
CN205080251U (en) * 2015-10-14 2016-03-09 大唐碧口水力发电厂 Through -flow calibration system of current transformer secondary circuit

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
EP1217707A1 (en) * 2000-12-20 2002-06-26 Schneider Electric Industries SA Device for termination of primary current in a current transformer having saturation compensation means
CN101867225A (en) * 2010-05-31 2010-10-20 江苏省电力公司南通供电公司 Debugging method for integrated automation of transformer substation and integration of relaying protection system
CN202975222U (en) * 2012-11-28 2013-06-05 沧州供电公司 Integrated tester for secondary circuit of current transformer
CN105022017A (en) * 2015-07-22 2015-11-04 国家电网公司 Portable CT circuit flow test instrument
CN205080251U (en) * 2015-10-14 2016-03-09 大唐碧口水力发电厂 Through -flow calibration system of current transformer secondary circuit

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111413657A (en) * 2020-04-13 2020-07-14 西安热工研究院有限公司 CT body secondary circuit calibration method
CN111707981A (en) * 2020-07-10 2020-09-25 西安热工研究院有限公司 CT indirect secondary through-flow method for generator set
CN112986856A (en) * 2021-03-26 2021-06-18 西安热工研究院有限公司 Method for checking integrity of three-phase current secondary circuit of power plant
CN113589214A (en) * 2021-08-05 2021-11-02 中国大唐集团科学技术研究院有限公司西北电力试验研究院 CT secondary through-flow method for power plant
CN113589214B (en) * 2021-08-05 2024-02-20 中国大唐集团科学技术研究院有限公司西北电力试验研究院 CT (computed tomography) secondary through-flow method for power plant

Also Published As

Publication number Publication date
CN107037307B (en) 2019-06-04

Similar Documents

Publication Publication Date Title
CN107037307A (en) A kind of secondary through-flow method of power plant main system c-type
CN101706535B (en) Device and method for testing dielectric loss of high voltage transformer
CN103257286B (en) A kind of charging electric vehicle facility automatic test approach and system
CN103438797B (en) Deformation of transformer winding online test method and system
CN104793148B (en) Distributed generator islanding detection method based on grid entry point characteristic harmonics voltage measurement
CN102721898A (en) On-line measurement method and on-line measurement system for deformation of transformer winding
CN106526479B (en) Power shovel electrical malfunction diagnostic method based on mains by harmonics feature
CN102023249A (en) Method for performing preventive test without detaching high-voltage lead of 220-kV zinc oxide arrestor
CN102565618A (en) Method for detecting zero-sequence voltage circuit of transformer substation
CN204044268U (en) A kind of city rail current transformer general low-voltage Auto-Test System
CN104251978B (en) Straight-flow system exchanges the test device that crosstalk and voltage pulsation influence on relay
CN108562860A (en) Electric energy meter two-way accessory power supply power consumption Auto-Test System and test method
CN204740329U (en) High -low pressure AC motor testing system
CN105866592B (en) Dynamic passive compensation response wave shape acquisition system and acquisition method
CN205679693U (en) A kind of alternating-current charging pile calibrating installation
CN103076529B (en) CT secondary circuit intelligent detecting method
CN205749774U (en) Air bag conservator vacuum extractor and transformer oil paper insulation test system
CN106443537A (en) Calibration method for online capacitive equipment insulation parameter monitoring device and calibration equipment
CN104049161A (en) Testing connecting structure and testing method for substation field lightning arrester without demounting primary high-voltage lead
CN103743994B (en) Low-voltage load test method and device
CN103954869B (en) Cable power frequency parameter testing device based on PXI system
CN107037389A (en) A kind of PT leads to pressure method
CN207965041U (en) Electric wire ac voltage withstanding automatic test equipment
CN102628915B (en) Electrical submersible pump on-line insulation detection device
CN205861818U (en) A kind of N600 one point earth test device

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant