CN107013231B - 一种用于大孔隙率巨型岩堆松散体中控注浆加固范围的施工方法 - Google Patents
一种用于大孔隙率巨型岩堆松散体中控注浆加固范围的施工方法 Download PDFInfo
- Publication number
- CN107013231B CN107013231B CN201710314948.8A CN201710314948A CN107013231B CN 107013231 B CN107013231 B CN 107013231B CN 201710314948 A CN201710314948 A CN 201710314948A CN 107013231 B CN107013231 B CN 107013231B
- Authority
- CN
- China
- Prior art keywords
- grouting
- grout
- stopping curtain
- grout stopping
- row
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Images
Classifications
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH DRILLING; MINING
- E21D—SHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
- E21D11/00—Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
- E21D11/04—Lining with building materials
- E21D11/10—Lining with building materials with concrete cast in situ; Shuttering also lost shutterings, e.g. made of blocks, of metal plates or other equipment adapted therefor
Abstract
本发明公开了一种用于大孔隙率巨型岩堆松散体中控注浆加固范围的施工方法,测放注浆加固区域四周止浆帷幕注浆孔位置。采用大型跟管钻机跳孔钻进止浆帷幕注浆孔。注入袖阀套壳料。插入注浆芯管,逐排完成止浆帷幕孔注浆后,形成限定注浆加固区域四周范围的止浆帷幕墙。逐排跳孔钻进注浆加固区域注浆孔,当所有注浆钻孔底部3米注浆完成后,形成注浆加固区域底部止浆帷幕墙。底部止浆帷幕墙与四周止浆帷幕墙交叉封闭,最终形成控制注浆加固范围的“U”型止浆帷幕。通过特定注浆加固区域外围形成的“U”止浆帷幕墙,能有效防止采用普通注浆工艺因岩堆松散体中架空结构造成的浆液大量流失,施工速度快,工效高,总的管理成本低。
Description
技术领域
本发明涉及大空隙率巨型岩堆松散体注浆加固施工技术领域,具体涉及一种用于大孔隙率巨型岩堆松散体中控注浆加固范围的“U”型止浆帷幕的施工方法。
背景技术
大前石岭隧道进口岩堆的规模极大,岩堆范围包括了隧道进口从山脚到山顶的几乎整个山体,岩堆为上部薄下部厚的楔形依附在山体之上,自然坡度26°~38°,岩堆厚度为26.3~48.4米,岩堆体垂直厚度最深达50多米,岩堆体下部依山体延伸到河中。岩堆主要由大小不一的块石及少量沙石组成,结构松散,基本无粘接,岩质为石英砂岩,块石一般为0.2-0.8米,最大可达到1.5,个别达到2米以上,呈松散架空状态,岩堆的空隙率达45%-50%。
大前石岭隧道进口从大空隙率巨型岩堆松散体中部穿过,隧道顶部岩堆最大厚度50米,隧道底部离岩堆底基岩深度达32米以上,隧道开挖因受岩堆结构松散等不良地质情况和渗水的影响,极易形成局部坍塌引起整个山体上的岩堆滑移,造成安全事故,对隧道施工和铁路运营安全也极为不利。为了解决大孔隙率岩堆松散体没有粘接力,开挖极易局部坍塌、整体滑移,铁路运营易扰动等问题,在隧道顶部上7米、底部下5米、隧道中线两侧各13.5米的岩堆松散体的范围内进行局部注浆加固,但由于岩堆呈石块松散架空状态,采用一般的注浆方法,注浆范围极难控制,浆液极易沿岩堆中块石的架空空隙扩散到下面的河流中,造成浆液流失和环境污染。如何在大空隙率巨型岩堆松散体中把注浆加固范围控制在某个特定区域,并且使注浆量和注浆加固质量得到有效控制是施工的一大难题。
发明内容
本发明的目的就在于解决上述大孔隙率岩堆松散体内局部特定区域注浆加固中存在的注浆范围、注浆量和注浆加固质量不易控制的难题,从而提供一种用于大孔隙率巨型岩堆松散体中控制注浆加固范围在某一特定区域的“U”型止浆帷幕的施工方法。该方法仅需使用跟管钻孔和袖阀管注浆的相关设备,施工工艺简单、安全、经济、实用、灵活。
本发明的技术方案是:一种用于大孔隙率巨型岩堆松散体中控注浆加固范围的施工方法,其特征在于:依照下列步骤进行:
①测放注浆加固区域四周止浆帷幕注浆孔位置。②按照先外排、再内排、然后中排的顺序,采用大型跟管钻机跳孔钻进止浆帷幕注浆孔。③成孔后安放袖阀注浆管,抽拔钻孔跟管,注入袖阀套壳料。④当套壳料达到注浆强度后,插入注浆芯管,按钻孔顺序,采用袖阀管分层注浆工艺,逐层注入膨胀率为2倍的速凝膨胀浆液(耐特加固Ⅱ号)。逐排完成止浆帷幕孔注浆后,形成限定注浆加固区域四周范围的止浆帷幕墙。⑤逐排跳孔钻进注浆加固区域注浆孔,成孔后按③、④的步骤进行底部3米止浆帷幕墙注浆施工,当所有注浆钻孔底部3米注浆完成后,形成注浆加固区域底部止浆帷幕墙。⑥底部止浆帷幕墙与四周止浆帷幕墙交叉封闭,最终形成控制注浆加固范围的“U”型止浆帷幕。⑦然后在靠近“U”型止浆帷幕内侧3米范围内,按④、⑤的方法和步骤,采用水泥水玻璃双液浆进行止浆帷幕内“U”型止浆帷幕加强层注浆施工,对外层“U”型止浆帷幕止浆效果进行加强。
通过上述步骤形成控制特定区域注浆加固范围的“U”型止浆帷幕,解决了大空隙率巨型岩堆松散体特定注浆区域范围不易控制和浆液极易大量流失的难题。
本发明具有如下的优点和积极效果:
①对机械设备配置要求低,只需要利用正常的跟管钻进机和袖阀管分层注浆所需的设备,即可完成大空隙率巨型岩堆松散体中控制局部特定区域定向定位注浆加固范围的“U”型止浆帷幕墙施工。
②采用跟管钻机可解决大孔隙率巨型岩堆松散体深孔钻进易卡钻的难题,加快钻孔速度,提高钻孔效率。
③“U”型止浆帷幕选用速凝膨胀浆液,达到快速封闭岩堆松散体架空块石间的架空空隙,能减少浆液大量流失,防止河流污染。
④采用袖阀管分层注浆工艺,注浆位置和注浆量易控制,可实现一孔注多种浆液和多次反复注浆,提高U型止浆帷幕的止浆效果。
⑤经济性好,“U”型止浆帷幕内止浆加强层采用水泥水玻璃双液浆,进一步填充了外部“U”型止浆帷幕可能存在的空洞,增强了“U”型止浆帷幕的效果,减少了浆液大量流失,施工速度快,工效高,总成本低。
附图说明
图1是大孔隙率巨型岩堆“U”型止浆帷幕施工平面示意图。
图2是大孔隙率巨型岩堆“U”型止浆帷幕施工纵断面示意图。
图3是大孔隙率巨型岩堆“U”型止浆帷幕施工横断面示意图。
图4是大孔隙率巨型岩堆袖阀注浆工艺示意图。
具体实施方式
①在岩堆注浆加固区域进行分段平整形成多级钻孔注浆平台,然后测放注浆加固区域四周最外围止浆帷幕注浆三排止浆墙钻孔(1)位置。②按照先外排、再内排、然后中排的顺序,采用大型跟管钻机跳孔钻进止浆帷幕止浆墙钻孔(1)。③成孔后安放袖阀注浆管(5),抽拔钻孔跟管,注入袖阀套壳料(6),在设计注浆范围顶面以上1米范围内采用速凝水泥砂浆封堵。④当套壳料达到注浆强度后,插入注浆芯管(7),按钻孔顺序,采用袖阀管分层注浆工艺,逐层注入膨胀率为2倍的速凝膨胀浆液(耐特加固Ⅱ号)。注浆依照先外排、再内排、最后中排的顺序,逐排完成外围三排止浆帷幕孔注浆,形成限定注浆加固区域范围的四周止浆帷幕墙(2)。⑤在四周止浆帷幕墙(2)内注浆加固区域逐排跳孔钻进注浆钻孔(3),成孔后按③、④的步骤进行注浆加固区域注浆钻孔(3)底部3米止浆帷幕墙注浆施工,注浆采用先底层、再上层、后中间层的顺序,当所有注浆钻孔(3)底部3米注浆完成后,形成注浆加固区域底部止浆帷幕墙(4)。⑥底部止浆帷幕墙(4)与四周止浆帷幕墙(2)交叉封闭,最终形成控制注浆加固范围的“U”型止浆帷幕。⑦然后在靠近“U”型止浆帷幕内侧3米范围内,按④、⑤的方法和步骤,采用水泥水玻璃双液浆进行止浆帷幕内“U”型止浆帷幕加强层注浆施工,对外层“U”型止浆帷幕止浆效果进行加强。
通过上述步骤实现超大空隙率巨型岩堆松散体中特定区域控制注浆加固范围的“U”型止浆帷幕施工。
Claims (1)
1.一种用于大孔隙率巨型岩堆松散体中控注浆加固范围的施工方法,其特征在于:该方法依照下列步骤进行:
①测放注浆加固区域四周止浆帷幕注浆孔位置;②按照先外排、再内排、然后中排的顺序,采用大型跟管钻机跳孔钻进止浆帷幕注浆孔;③成孔后安放袖阀注浆管,抽拔钻孔跟管,注入袖阀套壳料;④当套壳料达到注浆强度后,插入注浆芯管,按钻孔顺序,采用袖阀管分层注浆工艺,逐层注入膨胀率为2倍的速凝膨胀浆液;逐排完成止浆帷幕孔注浆后,形成限定注浆加固区域四周范围的止浆帷幕墙;⑤逐排跳孔钻进注浆加固区域注浆孔,成孔后按③、④的步骤进行底部3米止浆帷幕墙注浆施工,当所有注浆钻孔底部3米注浆完成后,形成注浆加固区域底部止浆帷幕墙;⑥底部止浆帷幕墙与四周止浆帷幕墙交叉封闭,最终形成控制注浆加固范围的“U”型止浆帷幕;⑦然后在靠近“U”型止浆帷幕内侧3米范围内,按④、⑤的方法和步骤,采用水泥水玻璃双液浆进行止浆帷幕内“U”型止浆帷幕加强层注浆施工,对外层“U”型止浆帷幕止浆效果进行加强;
“U”型止浆帷幕外围止浆帷幕墙钻孔注浆依照先外排、再内排、最后中排的顺序;
“U”型止浆帷幕底部止浆帷幕墙钻孔注浆采用先底层、再上层、后中间层的顺序;
“U”型止浆帷幕采用膨胀率为2倍的速凝膨胀浆液,浆液膨胀能快速封闭岩堆松散体架空块石间的架空空隙;
“U”型止浆帷幕内的止浆加强层采用水泥水玻璃双液浆;
“U”型止浆帷幕墙采用袖阀管分层注浆工艺,注浆位置和注浆量易控制。
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201710314948.8A CN107013231B (zh) | 2017-05-07 | 2017-05-07 | 一种用于大孔隙率巨型岩堆松散体中控注浆加固范围的施工方法 |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201710314948.8A CN107013231B (zh) | 2017-05-07 | 2017-05-07 | 一种用于大孔隙率巨型岩堆松散体中控注浆加固范围的施工方法 |
Publications (2)
Publication Number | Publication Date |
---|---|
CN107013231A CN107013231A (zh) | 2017-08-04 |
CN107013231B true CN107013231B (zh) | 2021-05-25 |
Family
ID=59450450
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201710314948.8A Active CN107013231B (zh) | 2017-05-07 | 2017-05-07 | 一种用于大孔隙率巨型岩堆松散体中控注浆加固范围的施工方法 |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN107013231B (zh) |
Families Citing this family (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN113217020B (zh) * | 2021-04-09 | 2022-07-05 | 中铁六局集团有限公司 | 山体袖阀管加固施工方法 |
Citations (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
EP1757771A3 (en) * | 2005-08-23 | 2007-10-24 | Trevi S.p.A. | Method for consolidating and impermeabilizing the ground around a tunnel |
CN101638987A (zh) * | 2009-07-24 | 2010-02-03 | 中铁二十一局集团有限公司 | 用帷幕注浆加止浆墙穿越高压富水断裂带的隧道施工方法 |
CN203499698U (zh) * | 2013-10-24 | 2014-03-26 | 中铁十三局集团第五工程有限公司 | 一种应用于地下工程施工的超前帷幕注浆系统 |
CN104806257A (zh) * | 2015-04-27 | 2015-07-29 | 中国水利水电第七工程局有限公司 | 砂卵石地层盾构施工帽式地面超前加固结构及其方法 |
CN105714764A (zh) * | 2015-12-08 | 2016-06-29 | 中国铁建大桥工程局集团有限公司 | 一种隧道地表深孔袖阀管注浆施工方法 |
CN106013264A (zh) * | 2016-07-08 | 2016-10-12 | 中铁西南科学研究院有限公司 | 一种适用于隧底填充结构隆起开裂的整治方法 |
-
2017
- 2017-05-07 CN CN201710314948.8A patent/CN107013231B/zh active Active
Patent Citations (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
EP1757771A3 (en) * | 2005-08-23 | 2007-10-24 | Trevi S.p.A. | Method for consolidating and impermeabilizing the ground around a tunnel |
CN101638987A (zh) * | 2009-07-24 | 2010-02-03 | 中铁二十一局集团有限公司 | 用帷幕注浆加止浆墙穿越高压富水断裂带的隧道施工方法 |
CN203499698U (zh) * | 2013-10-24 | 2014-03-26 | 中铁十三局集团第五工程有限公司 | 一种应用于地下工程施工的超前帷幕注浆系统 |
CN104806257A (zh) * | 2015-04-27 | 2015-07-29 | 中国水利水电第七工程局有限公司 | 砂卵石地层盾构施工帽式地面超前加固结构及其方法 |
CN105714764A (zh) * | 2015-12-08 | 2016-06-29 | 中国铁建大桥工程局集团有限公司 | 一种隧道地表深孔袖阀管注浆施工方法 |
CN106013264A (zh) * | 2016-07-08 | 2016-10-12 | 中铁西南科学研究院有限公司 | 一种适用于隧底填充结构隆起开裂的整治方法 |
Non-Patent Citations (2)
Title |
---|
箱型帷幕注浆在三明市污水处理厂5#泵站基坑支护中的应用;王高旺;《福建地质》;20051230;第24卷(第4期);第250-253页 * |
隧道软弱围岩大变形段注浆加固施工技术;殷月欣;《设备管理与维修》;20170306(第3期);第76-77页 * |
Also Published As
Publication number | Publication date |
---|---|
CN107013231A (zh) | 2017-08-04 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN110230309B (zh) | 岩溶区桥梁溶洞桩基施工方法 | |
CN106640120B (zh) | 地表定点深孔分层注浆施工方法 | |
CN105041325A (zh) | 一种高压富水特大断层软弱角砾岩隧道的施工方法 | |
CN104806257A (zh) | 砂卵石地层盾构施工帽式地面超前加固结构及其方法 | |
CN105525619B (zh) | 一种富水地层暗挖隧道咬合管幕 | |
CN103362117A (zh) | 注浆段全段注浆的方法 | |
CN111074899A (zh) | 一种用于不同填充类型溶洞的注浆方法 | |
CN110469332B (zh) | 一种穿越泥石流堆积体隧道的超前支护固结方法 | |
CN107503362A (zh) | 一种适用于库岸边坡的复合抗滑桩墙支挡结构及施工方法 | |
CN110284885A (zh) | 盾构检修井施工方法 | |
CN110700842A (zh) | 一种适用于盾构端头富水砂层段的超前注浆加固方法 | |
CN114483109B (zh) | 穿越隧道断层破碎带的帷幕注浆超前大管棚贯通施工方法 | |
CN110700860B (zh) | 一种穿越黄土沟谷的土石分界隧道施工方法 | |
KR101746654B1 (ko) | 광산 대규모 채굴공동 보강을 위한 골재 그라우트 기둥 시공 방법 | |
CN111287769A (zh) | 一种隧道围岩超前注浆加固结构及其施工方法 | |
CN105369799A (zh) | 预制桩地下连续墙混凝土预制桩及施工方法 | |
CN107013231B (zh) | 一种用于大孔隙率巨型岩堆松散体中控注浆加固范围的施工方法 | |
CN109853477A (zh) | 廊道中化动水为静水的集中渗漏封堵结构及方法 | |
CN211973505U (zh) | 一种用于不同填充类型溶洞的注浆系统 | |
CN201406687Y (zh) | 深基坑支护结构 | |
CN209603062U (zh) | 廊道中化动水为静水的集中渗漏封堵结构 | |
CN112145203A (zh) | 全断面前进式分段注浆施工方法及重叠隧道施工工法 | |
CN218934444U (zh) | 冻土地区高压水平旋喷桩隧道加固结构 | |
CN111519647A (zh) | 一种适用于海相软基地基处理及加固的新型基础及施工方法 | |
CN112127899B (zh) | 一种砾岩地层隧洞拱圈固结灌浆的方法 |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
GR01 | Patent grant | ||
GR01 | Patent grant |