CN106989410B - A kind of waste heat boiler water-cooling wall installation positioning apparatus and installation method - Google Patents

A kind of waste heat boiler water-cooling wall installation positioning apparatus and installation method Download PDF

Info

Publication number
CN106989410B
CN106989410B CN201710166612.1A CN201710166612A CN106989410B CN 106989410 B CN106989410 B CN 106989410B CN 201710166612 A CN201710166612 A CN 201710166612A CN 106989410 B CN106989410 B CN 106989410B
Authority
CN
China
Prior art keywords
cooling wall
water
waste heat
heat boiler
pedestal
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201710166612.1A
Other languages
Chinese (zh)
Other versions
CN106989410A (en
Inventor
席春生
李文凯
何青义
赵艳明
王涛
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China MCC20 Group Corp Ltd
Shanghai Ershiye Construction Co Ltd
Original Assignee
China MCC20 Group Corp Ltd
Shanghai Ershiye Construction Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China MCC20 Group Corp Ltd, Shanghai Ershiye Construction Co Ltd filed Critical China MCC20 Group Corp Ltd
Priority to CN201710166612.1A priority Critical patent/CN106989410B/en
Publication of CN106989410A publication Critical patent/CN106989410A/en
Application granted granted Critical
Publication of CN106989410B publication Critical patent/CN106989410B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F23COMBUSTION APPARATUS; COMBUSTION PROCESSES
    • F23MCASINGS, LININGS, WALLS OR DOORS SPECIALLY ADAPTED FOR COMBUSTION CHAMBERS, e.g. FIREBRIDGES; DEVICES FOR DEFLECTING AIR, FLAMES OR COMBUSTION PRODUCTS IN COMBUSTION CHAMBERS; SAFETY ARRANGEMENTS SPECIALLY ADAPTED FOR COMBUSTION APPARATUS; DETAILS OF COMBUSTION CHAMBERS, NOT OTHERWISE PROVIDED FOR
    • F23M5/00Casings; Linings; Walls
    • F23M5/08Cooling thereof; Tube walls
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B66HOISTING; LIFTING; HAULING
    • B66DCAPSTANS; WINCHES; TACKLES, e.g. PULLEY BLOCKS; HOISTS
    • B66D1/00Rope, cable, or chain winding mechanisms; Capstans
    • B66D1/28Other constructional details
    • B66D1/30Rope, cable, or chain drums or barrels

Landscapes

  • Engineering & Computer Science (AREA)
  • Mechanical Engineering (AREA)
  • Chemical & Material Sciences (AREA)
  • Combustion & Propulsion (AREA)
  • General Engineering & Computer Science (AREA)
  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

The present invention relates to a kind of waste heat boiler water-cooling wall installation positioning apparatus and installation methods, including idler wheel and pedestal, wherein the pedestal is rectangular frame structure, the pedestal upper end is respectively arranged on the left side and the right side bracket, the idler wheel is mounted on the base by bracket, and method includes: that (a) makes several waste heat boiler water-cooling wall installation positioning apparatus;(b) then the device manufactured in step (a) is fixed on the steel construction of water-cooling wall erection;(c) channel steel cross beam on the outside of water-cooling wall is placed on above idler wheel;(d) after water-cooling wall reaches design position, jack is respectively set in waste heat boiler water-cooling wall installation positioning apparatus two sides, water-cooling wall is jacked up from the both ends of water-cooling wall by jack, then withdraws from waste heat boiler water-cooling wall installation positioning apparatus.The present invention is easy to make, easy to operate, in place using the dress installation of more hook blocks compared to traditional, is improved construction efficiency, while reducing the machine-team number of lifting machine, is reduced Construction Cost.

Description

A kind of waste heat boiler water-cooling wall installation positioning apparatus and installation method
Technical field
The invention belongs to waste heat boiler water-cooling wall mounting technique fields, just more particularly to a kind of installation of waste heat boiler water-cooling wall Position device and installation method.
Background technique
In waste heat boiler water-cooling wall hoisting process, hoist lifting hook is influenced by workshop top, steel construction etc., is difficult one Hook is in place, needs to adjust water-cooling wall position again, and directly dilatory method of adjustment, be easy to cause equipment damage under normal conditions, Also time-consuming, laborious simultaneously, influence construction quality and progress.
Summary of the invention
Technical problem to be solved by the invention is to provide a kind of waste heat boiler water-cooling wall installation positioning apparatus and sides in place Method when solving waste heat boiler water-cooling wall by the present apparatus and installing in place, is limited by mounting condition and is difficult to one and is hooked to position, and effectively The problem of solving inefficiency in water-cooling wall installation process, wasting mechanical one-shift.
The technical solution adopted by the present invention to solve the technical problems is: it is in place to provide a kind of waste heat boiler water-cooling wall installation Device, including idler wheel and pedestal, wherein the pedestal is rectangular frame structure, the pedestal upper end is respectively arranged on the left side and the right side Bracket, the idler wheel are mounted on the base by bracket.
Further technical characteristic of the invention is that the pedestal is the rectangular frame knot being welded to form by four angle steel Structure.
Further technical characteristic of the invention is that the bracket includes bracket diagonal brace and vertical support, the vertical branch It is intermediate in support setting chassis side, the bracket diagonal brace setting support two sides, both ends vertically respectively with vertical support and pedestal Connection.
Further technical characteristic of the invention is that with pedestal by being welded to connect, the bracket is oblique for the vertical support Support passes through welded connecting with vertical support and pedestal respectively.
Further technical characteristic of the invention is that the idler wheel is connect with bracket by pin shaft, and idler wheel can be around pin Axis rotation.
A kind of waste heat boiler water-cooling wall installation installation method, including following steps:
(a) several above-mentioned waste heat boiler water-cooling walls are made, positioning apparatus is installed;
(b) then the device manufactured in step (a) is fixed on the steel construction of water-cooling wall erection;
(c) water-cooling wall is sling by Lifting implements, the channel steel cross beam on the outside of water-cooling wall is placed on above idler wheel, in water cooling The adjustment direction of wall and the back side hang chain block, pull water-cooling wall is mobile on idler wheel to set until reaching by chain block Count position;
(d) after water-cooling wall reaches design position, thousand are respectively set in waste heat boiler water-cooling wall installation positioning apparatus two sides Jin top, is jacked up water-cooling wall from the both ends of water-cooling wall by jack, then removes waste heat boiler water-cooling wall installation positioning apparatus Out;
(e) roller under the channel steel on the outside of water-cooling wall is installed in place, finally jack is slowly put down, water-cooling wall is put On roller;
(f) after water-cooling wall is in place, water-cooling wall is fixed.
Further technical characteristic of the invention is, in the step (b), determines waste heat boiler water according to the width of water-cooling wall The number of cold wall installation positioning apparatus.
Beneficial effect
The present invention has the following advantages that and good effect:
1, the present invention is easy to make, easy for installation, with strong points, easy to operate, is pacified compared to traditional filled using more hook blocks Dress is in place, improves construction efficiency, while reducing the machine-team number of lifting machine, reduces Construction Cost;
2, compared to directly pulling, equipment safety is effectively protected, the labor intensity of worker is also reduced;
3, the present apparatus and method can be reduced engineering cost, improve construction efficiency, ensure that construction quality, convenient for pushing away Extensively.
Detailed description of the invention
Fig. 1 is schematic structural view of the invention.
Fig. 2 is the present invention and chain block water-cooling wall schematic diagram in place.
Fig. 3 is water-cooling wall side view in place.
Fig. 4 is to remove schematic diagram of the present invention using jack.
Specific embodiment
Present invention will be further explained below with reference to specific examples.It should be understood that these embodiments are merely to illustrate the present invention Rather than it limits the scope of the invention.In addition, it should also be understood that, after reading the content taught by the present invention, those skilled in the art Member can make various changes or modifications the present invention, and such equivalent forms equally fall within the application the appended claims and limited Range.
Embodiment 1
As shown in Figure 1, a kind of waste heat boiler water-cooling wall installs positioning apparatus, including idler wheel 1 and pedestal 4, wherein the bottom Seat 4 is rectangular frame structure, and 4 upper end of pedestal is respectively arranged on the left side and the right side bracket 5, and the idler wheel 1 is pacified by bracket 5 On pedestal 4.
The pedestal 4 is the rectangular frame structure being welded to form by four angle steel.
The bracket 5 includes bracket diagonal brace 2 and vertical support 3, intermediate, institute in vertical 3 setting 4 side of pedestal of support The setting of bracket diagonal brace 2 is stated connect with vertical support 3 and pedestal 4 respectively at 3 two sides of support, both ends vertically, the vertical support 3 and For pedestal 4 by being welded to connect, the bracket diagonal brace 2 passes through welded connecting with vertical support 3 and pedestal 4 respectively.
The idler wheel 1 is connect with bracket 5 by pin shaft, and idler wheel 1 can be rotated around pin shaft.
As shown in Figures 1 to 4, a kind of waste heat boiler water-cooling wall installs installation method, including following steps:
(a) several above-mentioned waste heat boiler water-cooling walls are made, positioning apparatus is installed;
(b) then the device manufactured in step (a) is fixed on the steel construction 6 of water-cooling wall erection, according to water-cooling wall Width determines the number of waste heat boiler water-cooling wall installation positioning apparatus;
(c) water-cooling wall 10 is sling by Lifting implements, 7 crossbeam of channel steel in 10 outside of water-cooling wall is placed on above idler wheel, Chain block 8 is hung at the adjustment direction of water-cooling wall and the back side, pulls water-cooling wall mobile straight on idler wheel by chain block 8 To arrival design position;
(d) after water-cooling wall reaches design position, thousand are respectively set in waste heat boiler water-cooling wall installation positioning apparatus two sides Jin top 9, is jacked up water-cooling wall 10 from the both ends of water-cooling wall 10 by jack 9, is then installed waste heat boiler water-cooling wall in place Device is withdrawn from;
(e) roller under the channel steel 7 in 10 outside of water-cooling wall is installed in place, is finally slowly put down jack, by water cooling Wall 10 is placed on above roller;
(f) after water-cooling wall 10 is in place, water-cooling wall 10 is fixed.
Auxiliary roller devices in place and method in the present invention can make water-cooling wall smoothly in place, first be fixed on device On corresponding steel construction, then the channel steel cross beam of water-cooling wall is placed on above idler wheel, is adjusted by chain block in place, to solve Certainly under restricted clearance, water-cooling wall lifts the big problem of hook difficulty in place.

Claims (6)

1. a kind of waste heat boiler water-cooling wall installs installation method, it is characterised in that: the following steps are included:
(a) several waste heat boiler water-cooling walls are made and positioning apparatus is installed, including idler wheel (1) and pedestal (4), the pedestal (4) are Rectangular frame structure, pedestal (4) upper end are respectively arranged on the left side and the right side bracket (5), and the idler wheel (1) passes through bracket (5) It is mounted on pedestal (4);
(b) then the device manufactured in step (a) is fixed on the steel construction (6) of water-cooling wall erection;
(c) water-cooling wall (10) is sling by Lifting implements, channel steel (7) crossbeam on the outside of water-cooling wall (10) is placed on idler wheel Face hangs chain block (8) in the adjustment direction of water-cooling wall and the back side, pulls water-cooling wall in idler wheel by chain block (8) Upper movement is until reach design position;
(d) after water-cooling wall reaches design position, jack is respectively set in waste heat boiler water-cooling wall installation positioning apparatus two sides (9), water-cooling wall (10) are jacked up from the both ends of water-cooling wall (10) by jack (9), then waste heat boiler water-cooling wall is installed Positioning apparatus is withdrawn from;
(e) roller under the channel steel (7) on the outside of water-cooling wall (10) is installed in place, is finally slowly put down jack, by water cooling Wall (10) is placed on above roller;
(f) after water-cooling wall (10) is in place, water-cooling wall (10) are fixed.
2. a kind of waste heat boiler water-cooling wall according to claim 1 installs installation method, it is characterised in that: the step (b) in, the number of waste heat boiler water-cooling wall installation positioning apparatus is determined according to the width of water-cooling wall.
3. a kind of waste heat boiler water-cooling wall according to claim 1 installs installation method, it is characterised in that: the pedestal (4) the rectangular frame structure to be welded to form by four angle steel.
4. a kind of waste heat boiler water-cooling wall according to claim 1 installs installation method, it is characterised in that: the bracket It (5) include bracket diagonal brace (2) and vertical support (3), intermediate, the bracket in described vertical support (3) setting pedestal (4) side Diagonal brace (2) setting is connect with vertical support (3) and pedestal (4) respectively at support (3) two sides, both ends vertically.
5. a kind of waste heat boiler water-cooling wall according to claim 4 installs installation method, it is characterised in that: the vertical branch (3) and pedestal (4) are supportted by being welded to connect, the bracket diagonal brace (2) and vertical support (3) and pedestal (4) pass through welding respectively Connection.
6. a kind of waste heat boiler water-cooling wall according to claim 1 installs installation method, it is characterised in that: the idler wheel (1) it is connect with bracket (5) by pin shaft, and idler wheel (1) can be rotated around pin shaft.
CN201710166612.1A 2017-03-20 2017-03-20 A kind of waste heat boiler water-cooling wall installation positioning apparatus and installation method Active CN106989410B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710166612.1A CN106989410B (en) 2017-03-20 2017-03-20 A kind of waste heat boiler water-cooling wall installation positioning apparatus and installation method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710166612.1A CN106989410B (en) 2017-03-20 2017-03-20 A kind of waste heat boiler water-cooling wall installation positioning apparatus and installation method

Publications (2)

Publication Number Publication Date
CN106989410A CN106989410A (en) 2017-07-28
CN106989410B true CN106989410B (en) 2019-03-19

Family

ID=59412086

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710166612.1A Active CN106989410B (en) 2017-03-20 2017-03-20 A kind of waste heat boiler water-cooling wall installation positioning apparatus and installation method

Country Status (1)

Country Link
CN (1) CN106989410B (en)

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
RU2317939C1 (en) * 2006-09-06 2008-02-27 Закрытое акционерное общество "Научно-исследовательский и конструкторский институт центробежных и роторных компрессоров им. В.Б. Шнеппа" Device for equipment positioning
CN103383104A (en) * 2013-07-03 2013-11-06 天津二十冶建设有限公司 Hoisting installation method for quickly mounting economizer and super heater
CN203336186U (en) * 2013-04-03 2013-12-11 中国一冶集团有限公司 Sliding supporting device
CN203638529U (en) * 2014-01-03 2014-06-11 山东齐鲁石化建设有限公司 Overall replacing and using tool for horizontal coolers
CN203845782U (en) * 2014-05-26 2014-09-24 中海石油深海开发有限公司 Device for dragging marine oil module in place
CN106322347A (en) * 2016-08-22 2017-01-11 上海二十冶建设有限公司 Construction method for enabling water-cooling walls of refuse incineration power generation waste heat boiler to integrally penetrate from top

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
RU2317939C1 (en) * 2006-09-06 2008-02-27 Закрытое акционерное общество "Научно-исследовательский и конструкторский институт центробежных и роторных компрессоров им. В.Б. Шнеппа" Device for equipment positioning
CN203336186U (en) * 2013-04-03 2013-12-11 中国一冶集团有限公司 Sliding supporting device
CN103383104A (en) * 2013-07-03 2013-11-06 天津二十冶建设有限公司 Hoisting installation method for quickly mounting economizer and super heater
CN203638529U (en) * 2014-01-03 2014-06-11 山东齐鲁石化建设有限公司 Overall replacing and using tool for horizontal coolers
CN203845782U (en) * 2014-05-26 2014-09-24 中海石油深海开发有限公司 Device for dragging marine oil module in place
CN106322347A (en) * 2016-08-22 2017-01-11 上海二十冶建设有限公司 Construction method for enabling water-cooling walls of refuse incineration power generation waste heat boiler to integrally penetrate from top

Also Published As

Publication number Publication date
CN106989410A (en) 2017-07-28

Similar Documents

Publication Publication Date Title
CN207090809U (en) A kind of in-plant handling device of no suspension centre equipment or part
CN109081247A (en) A kind of hanging method of vestibule large-span steel girder
CN104989111B (en) Steel construction high level construction method for hanging
CN203359755U (en) Assembly and lifting integrated device for anode plate
CN203255914U (en) Unit-typed curtain wall lifting device
CN106989410B (en) A kind of waste heat boiler water-cooling wall installation positioning apparatus and installation method
CN212599995U (en) Welding installation equipment for hot-melt welded pipe
CN104030176B (en) The equalizer bar of hoisting platform truss and hanging method thereof
CN206521755U (en) A kind of dismounting device of building foundation pit prestressing force shaped steel combination inner bracing member
CN110273039A (en) A kind of blast furnace bustle pipe hoisting structure and its installation method
CN202575637U (en) Lifting device for overhauling annealing furnaces
CN206108705U (en) Gallows of frame isolated footing
CN101723240B (en) Special fixture for hoisting rectangular section steel column and hoisting method by using same
CN209906232U (en) Building template lifting device and cross-floor transportation system comprising same
CN107190991A (en) The special-shaped curtain wall vertical lifting system of glass plate
CN202643859U (en) Aluminum guide rod moving lifting trolley
CN110976558A (en) Movable type straightening auxiliary tool for transformer substation channel steel and channel steel straightening method
CN107700854B (en) Steel plate wall sliding installation device and installation method for super high-rise core tube
CN209940350U (en) Part overhead hoist of usefulness is repaired to agricultural machinery
CN218958457U (en) Tubular busbar hoisting bracket special for wind power stepped concrete tower
CN220186028U (en) Pipeline lifting and temporary supporting device
CN205257821U (en) Movable hoisting equipment
CN205077876U (en) Machine and stressing jack linkage are worn to restraint by prestress wire
CN215593688U (en) Bridge pipeline mounting platform
CN210457272U (en) Simple hoisting safety elevator

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant