CN106988220B - A kind of continous way suspension bridge cat road head-rope crosses tower structure and method - Google Patents

A kind of continous way suspension bridge cat road head-rope crosses tower structure and method Download PDF

Info

Publication number
CN106988220B
CN106988220B CN201710148965.9A CN201710148965A CN106988220B CN 106988220 B CN106988220 B CN 106988220B CN 201710148965 A CN201710148965 A CN 201710148965A CN 106988220 B CN106988220 B CN 106988220B
Authority
CN
China
Prior art keywords
tower
rope
head
arc
channel
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201710148965.9A
Other languages
Chinese (zh)
Other versions
CN106988220A (en
Inventor
刘帅帅
钱育强
周战涛
王志强
孙存良
单晓东
孙开达
杨浩
庞庆
蔡悬
高凤婷
胡茳
李磊
王鹏
张森
王浩
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
THE SIXTH ENGINEERING CO., LTD OF CCCC FOURTH HIGHWAY ENGINEERING CO., LTD.
Original Assignee
Sixth Engineering Co Ltd Of Cccc Fourth Highway Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Sixth Engineering Co Ltd Of Cccc Fourth Highway Engineering Co Ltd filed Critical Sixth Engineering Co Ltd Of Cccc Fourth Highway Engineering Co Ltd
Priority to CN201710148965.9A priority Critical patent/CN106988220B/en
Publication of CN106988220A publication Critical patent/CN106988220A/en
Application granted granted Critical
Publication of CN106988220B publication Critical patent/CN106988220B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D21/00Methods or apparatus specially adapted for erecting or assembling bridges
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D11/00Suspension or cable-stayed bridges
    • E01D11/02Suspension bridges

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Bridges Or Land Bridges (AREA)

Abstract

Tower structure and method are crossed the present invention relates to a kind of continous way suspension bridge cat road head-rope, the corresponding ducts Chuan Ta of head-rope quantity in the roads suspension bridge king-tower tower body Zhong Sheyumao, it is worn above and below tower opening of the channel each, pre-buried junction steel plate, an arc-shaped transition beam is respectively welded above and below tower opening of the channel along wearing, it is each passed through the ducts Chuan Ta per the roads Gen Mao head-rope, after adjustment cat road head-rope is consistent with main cable alignment, head-rope is fixed at tower opening of the channel with rope card in close wear.

Description

A kind of continous way suspension bridge cat road head-rope crosses tower structure and method
Technical field
The invention belongs to suspension bridge construction technical fields, are related to the setting structure of suspension bridge cat road head-rope, more particularly to A kind of structure and construction method for crossing suspension bridge king-tower for continous way cat road head-rope.
Background technology
The head-rope in continous way cat road is drawn from a bank to another bank, and intermediate demand crosses suspension bridge king-tower.Traditional side Formula is to turn cable saddle in tower top setting for cat road head-rope to pass through, and turns cable saddle and is connect with tower top by foundation bolt, but turns cable saddle Volume has seriously tied up the limited space of tower top very much greatly, is unfavorable for engineering construction.And to keep cat road and main rope of suspension bridge line Shape is consistent, after king-tower is crossed in cat road, it is also necessary to its height is reduced, this need the head-rope displacement of king-tower both sides installation cat road, Pull device, and large-scale operation platform, process and complicated, construction cost is high.
Invention content
It is an object of the present invention to which improving current cat road head-rope crosses tower structure and method, the roads Shi Mao head-rope is direct Across tower body, to save tower top space, and head-rope drop-down, displacement process and device are omitted, to save construction cost.
For achieving the above object, the present invention provides a kind of tower structure excessively of continous way suspension bridge cat road head-rope, skill Art scheme is as follows:
A kind of continous way suspension bridge cat road head-rope crosses tower structure, it is characterised in that:Equipped with cat road head-rope quantity The corresponding ducts Chuan Ta for traversing suspension bridge king-tower, the ducts Chuan Ta are the bellowss for the diameter 10cm being embedded in tower body; The ducts Chuan Ta both ends open is located in tower wall and each wears above and below tower opening of the channel in the tower wall of king-tower both sides, Be embedded with junction steel plate, an arc-shaped transition beam set above and below tower opening of the channel respectively along wearing, the arc-shaped transition beam with it is described Junction steel plate welds;Above the arc-shaped transition beam worn above tower opening of the channel and wear under arc-shaped transition beam below tower opening of the channel Side, is respectively equipped with the floor that polylith is resisted against on transition beam, the floor is vertical with arc-shaped transition beam, and is welded on the connection On steel plate;The ducts Chuan Ta are each passed through per the roads Gen Mao head-rope, it is solid on the position worn at tower opening of the channel on head-rope Determine at least three rope card.
For achieving the above object, tower method is crossed the present invention also provides a kind of continous way suspension bridge cat road head-rope, Technical solution is as follows:
(1) in suspension bridge Construction of Pylon, according to cat road design height in the roads tower body pre-buried Pai Yumao head-rope quantity The corresponding ducts Chuan Ta for traversing suspension bridge king-tower, the ducts Chuan Ta both ends open are located in the tower wall of king-tower both sides in tower wall It each wears above and below tower opening of the channel, pre-buried junction steel plate;
(2) edge is worn sets an arc-shaped transition beam respectively above and below tower opening of the channel, by the arc-shaped transition beam and the company Connect steel plate welding;Above the arc-shaped transition beam worn above tower opening of the channel and wear below arc-shaped transition beam below tower opening of the channel, The floor that polylith is resisted against on transition beam is set respectively, and the floor is vertical with arc-shaped transition beam, and is welded on the junction steel plate On;
(3) fag end before head-rope is drawn from a bank tunnel anchorage to the end bay side of the bank king-tower, manually by load-bearing with tower crane Fag end passes through the ducts Chuan Ta before rope, is connect with device is pulled, and after traction to another bank king-tower span centre side, releases and pull the company of device It connects, by fag end before head-rope using being manually inserted through tower duct, then pulls in end bay side and again device and connect, draw to another bank Tunnel anchorage;
(4) after the linear and sag of adjustment cat road head-rope is consistent with main rope of suspension bridge, in the king-tower both sides holes Chuan Ta The roads Chu Jiangmao head-rope rope card in road junction is fixed, and in each gear for wearing and being equipped with a covering at tower opening of the channel and wearing tower opening of the channel Baffle is welded on the arc-shaped transition beam by plate, and baffle is equipped with the arc-shaped slot that can accommodate head-rope, by cat road head-rope It is stuck in the arc-shaped slot on baffle.
The present invention is passed through by the ducts Chuan Ta being located on tower body for cat road head-rope, need not be built cat road in tower top and be held Rope turns cable saddle again, saves tower top space;After head-rope passes through the ducts Chuan Ta, it need not be conjugated, be pulled down in Sarasota both sides I.e. controllable cat road is linear is consistent with main push-towing rope, saves construction material, while being more advantageous to raising into bridge installation accuracy, drops Main push-towing rope tune rope difficulty in low construction can accomplish that cat road controls to minimum journey the added influence of permanent structure in practice of construction Degree.The roads Shi Mao of the present invention line style keeps good, and personnel, which pass through, to be easy, and constructing operation is convenient, has very in 800m or less bridge types Strong practicability.
Description of the drawings
The roads Tu1Shi Mao head-rope passes through the schematic view of facade structure in the ducts Chuan Ta;
The roads Tu2Shi Mao head-rope crosses the planar structure schematic diagram of tower structure;
Fig. 3 is enlarged drawing at A in Fig. 1, shows the detailed construction at the ducts Chuan Ta of the present invention;
Fig. 4 was set-up mode schematic diagram of the tower duct on king-tower side wall;
Fig. 5 is the status diagram worn after tower opening of the channel setting arc-shaped transition beam;
The roads Tu6Shi Jiangmao head-rope passes through the status diagram behind the ducts Chuan Ta.
Specific implementation mode
As shown in Figure 1, Figure 2, Figure 3 shows, the present invention is equipped with the suspension bridge king-tower 2 of traversing corresponding with cat road 1 quantity of head-rope The ducts Chuan Ta 3,3 both ends open of the ducts Chuan Ta are located in tower wall in the both sides tower wall of king-tower and each wear tower opening of the channel Above and below, it is embedded with junction steel plate 4, an arc-shaped transition beam 5, the arc are set above and below tower opening of the channel respectively along wearing Shape transition beam 5 is welded with the junction steel plate 4;The ducts Chuan Ta 3 are each passed through per the roads Gen Mao head-rope 1, are located in head-rope 1 It wears and fixes at least three rope card 6 on the position at tower opening of the channel.
Round steel pipe can be used in arc-shaped transition beam, and transverse weld is being worn above and below tower opening of the channel.For strengthening arc-shaped mistake Bridging beam 5 above the arc-shaped transition beam worn above tower opening of the channel and can be worn below arc-shaped transition beam below tower opening of the channel, respectively If polylith is resisted against the arc floor 7 on transition beam, the arc floor 7 is vertical with arc-shaped transition beam, and is welded on the company It connects on steel plate 4.
It, can be in each gear for wearing and being equipped with a covering at tower opening of the channel and wearing tower opening of the channel for limitation cat road head-rope transverse shifting Plate 8, baffle 8 are welded on the arc-shaped transition beam 5, and baffle 8 is equipped with the arc-shaped slot that can accommodate head-rope, cat road head-rope 1 passes through the ducts Chuan Ta by the arc-shaped slot on baffle.
When crossing tower construction of continous way suspension bridge cat road head-rope is carried out using the above structure, and detailed process is as follows:
(1) suitably high in the tower body of king-tower 2 according to cat road design height as shown in figure 4, in suspension bridge Construction of Pylon The corresponding ducts Chuan Ta 3 for traversing suspension bridge king-tower of the roads pre-buried Pai Yumao head-rope quantity are spent, diameter can be used in the ducts Chuan Ta The bellows of 10cm;The ducts Chuan Ta both ends open is located in tower wall in the tower wall of king-tower both sides and each wears the upper of tower opening of the channel Side and lower section, pre-buried junction steel plate 4 facilitate the installation of later stage opening of the channel transition beam.
(2) as shown in figure 5, before the erection of cat road head-rope, an arc-shaped transition is set respectively above and below the ducts Chuan Ta 3 Beam 5 welds the arc-shaped transition beam 5 with the junction steel plate 4;Arc-shaped transition beam action is to prevent cat road head-rope in mistake It is bent when hole, damages head-rope.The steel pipe and fill concrete of diameter 4.8cm can be used in transition beam, ensures the rigidity of steel pipe.
The top of the arc-shaped transition beam 5 of 3 overthe openings and arc-shaped transition beam 5 below tower opening of the channel is worn in the ducts Chuan Ta Lower section sets the arc floor 7 that polylith is resisted against on transition beam respectively, and arc floor 7 is vertical with arc-shaped transition beam 5, and is welded on On the junction steel plate 4;The radian of arc floor, which is arranged, makes it that can just block arc-shaped transition beam.
(3) as shown in fig. 6, being drawn the preceding fag end of head-rope 1 to the end bay of the bank king-tower 2 from a bank tunnel anchorage with tower crane Fag end before head-rope 1 is manually passed through the ducts Chuan Ta 3 by side.Then head-rope is connect with device is pulled, traction to another bank king-tower Behind span centre side, the connection of device is first released and pulls, by fag end before head-rope using tower duct was manually inserted through, then in end bay side It is connect with device is pulled again, traction to another bank tunnel anchorage.
(4) as shown in Figure 1, Figure 2, Figure 3 shows, linear and the sag and main rope of suspension bridge of adjustment cat road head-rope are consistent Afterwards, it wears the rope card 6 of the roads tower opening of the channel Chu Jiangmao head-rope 1 in king-tower both sides to fix, and is equipped at tower opening of the channel in each wear The baffle 8 of tower opening of the channel is worn in one covering, and baffle 8 is welded on the arc-shaped transition beam, and baffle, which is equipped with, can accommodate head-rope Arc-shaped slot, cat road head-rope is stuck in the arc-shaped slot on baffle.
All cat roads head-rope is sequentially completed using the above method and wears tower erection construction, you can carries out the laying of cat road wire side Construction, it is no longer necessary to head-rope be pulled down, conjugated.

Claims (3)

1. a kind of continous way suspension bridge cat road head-rope crosses tower structure, it is characterised in that:Equipped with cat road head-rope quantity pair That answers traverses the ducts Chuan Ta of suspension bridge king-tower, and the ducts Chuan Ta are the bellowss for the diameter 10cm being embedded in tower body;Institute The ducts Chuan Ta both ends open is stated in the tower wall of king-tower both sides, is located in tower wall and each wears above and below tower opening of the channel, in advance It is embedded with junction steel plate, an arc-shaped transition beam is set above and below tower opening of the channel respectively along wearing, the arc-shaped transition beam and the company Connect steel plate welding;Above the arc-shaped transition beam worn above tower opening of the channel and wear below arc-shaped transition beam below tower opening of the channel, It is respectively equipped with the floor that polylith is resisted against on transition beam, the floor is vertical with arc-shaped transition beam, and is welded on the connection steel On plate;The ducts Chuan Ta are each passed through per the roads Gen Mao head-rope, it is fixed on the position worn at tower opening of the channel on head-rope At least three rope card.
2. continous way suspension bridge cat road according to claim 1 head-rope crosses tower structure, it is characterised in that:It is worn each The baffle that tower opening of the channel is worn in a covering is equipped at tower opening of the channel, the baffle is welded on the arc-shaped transition beam, is set on baffle The arc-shaped slot of head-rope can be accommodated by having, and cat road head-rope passes through the ducts Chuan Ta by the arc-shaped slot on baffle.
3. a kind of continous way suspension bridge cat road head-rope crosses tower method, which is characterized in that include the following steps:
(1) it in suspension bridge Construction of Pylon, is corresponded in the roads tower body pre-buried Pai Yumao head-rope quantity according to cat road design height The ducts Chuan Ta for traversing suspension bridge king-tower, the ducts Chuan Ta both ends open is located at each in tower wall in the tower wall of king-tower both sides It wears above and below tower opening of the channel, pre-buried junction steel plate;
(2) edge is worn sets an arc-shaped transition beam respectively above and below tower opening of the channel, by the arc-shaped transition beam and the connection steel Plate welds;It above the arc-shaped transition beam worn above tower opening of the channel and wears below arc-shaped transition beam below tower opening of the channel, respectively If polylith is resisted against the floor on transition beam, the floor is vertical with arc-shaped transition beam, and is welded on the junction steel plate;
(3) fag end before head-rope is drawn from a bank tunnel anchorage to the end bay side of the bank king-tower with tower crane, it manually will be before head-rope Fag end passes through the ducts Chuan Ta, is connect with device is pulled, and after traction to another bank king-tower span centre side, releases and pull the connection of device, will Fag end was using being manually inserted through tower duct before head-rope, then pulls in end bay side and again device and connect, draws to another bank tunnel Anchor;
(4) after the linear and sag of adjustment cat road head-rope is consistent with main rope of suspension bridge, tower opening of the channel is worn in king-tower both sides The roads Chu Jiangmao head-rope rope card is fixed, and in each baffle for wearing and being equipped with a covering at tower opening of the channel and wearing tower opening of the channel, will Baffle is welded on the arc-shaped transition beam, and baffle is equipped with the arc-shaped slot that can accommodate head-rope, and cat road head-rope is stuck in In arc-shaped slot on baffle.
CN201710148965.9A 2017-03-13 2017-03-13 A kind of continous way suspension bridge cat road head-rope crosses tower structure and method Active CN106988220B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710148965.9A CN106988220B (en) 2017-03-13 2017-03-13 A kind of continous way suspension bridge cat road head-rope crosses tower structure and method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710148965.9A CN106988220B (en) 2017-03-13 2017-03-13 A kind of continous way suspension bridge cat road head-rope crosses tower structure and method

Publications (2)

Publication Number Publication Date
CN106988220A CN106988220A (en) 2017-07-28
CN106988220B true CN106988220B (en) 2018-10-30

Family

ID=59413146

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710148965.9A Active CN106988220B (en) 2017-03-13 2017-03-13 A kind of continous way suspension bridge cat road head-rope crosses tower structure and method

Country Status (1)

Country Link
CN (1) CN106988220B (en)

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109371838B (en) * 2018-10-15 2023-09-15 中交二航局第二工程有限公司 Integral catwalk deflection steel frame

Family Cites Families (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2720339B2 (en) * 1990-12-28 1998-03-04 株式会社竹中工務店 Cable laying method
WO2005121456A1 (en) * 2004-06-09 2005-12-22 Incorporated Administrative Agency Public Works Research Institute Cable stayed suspension bridge making combined use of one-box and two-box girders
CN201047059Y (en) * 2007-05-15 2008-04-16 四川天元机械工程有限责任公司 Suspension structure of rope-suspension bridge and rope clip thereof
CN202881852U (en) * 2012-08-02 2013-04-17 巨力索具股份有限公司 Suspension bridge cable installation system
CN105401524B (en) * 2015-10-23 2017-07-04 中交第二公路工程局有限公司 A kind of suspension bridge continous way cat road track cable crosses tower top constructional device
CN206667061U (en) * 2017-03-13 2017-11-24 中交第四公路工程局有限公司 A kind of continous way suspension bridge cat road head-rope crosses tower structure

Also Published As

Publication number Publication date
CN106988220A (en) 2017-07-28

Similar Documents

Publication Publication Date Title
LU102302B1 (en) Steel reinforcement cage for use in ventilation shaft diaphragm wall, and usage method
CN102979041B (en) Soft overhead reinforcing jacking method for construction of span box bridge of jacking block of underpass turnout group of railway
CN106592441A (en) Mounting method of stayed cable of cable-stayed bridge
CN106522112B (en) Cable-stayed bridge end bay beam section construction system and its method
CN110700237A (en) Construction method of diaphragm wall for preventing concrete from flowing around
CN107816170A (en) A kind of great diameter and long steel reinforcement cage and its construction method
CN108086354A (en) A kind of prefabricated assembled pipe gallery spliced with cast-in-place hidden girder and its construction method
CN108643056A (en) Complex curve steel box-girder pushing tow drag construction method
CN108166525A (en) A kind of half prefabricated assembled pipe gallery spliced with cast-in-place hidden girder and its construction method
CN107255188A (en) A kind of lifting pipeline method suitable at pipe gallery intersection node
CN109457708A (en) The construction method of temporary support in a kind of deep foundation ditch concrete structure construction procedure
CN109680619A (en) A kind of steel truss beam sling Arch Bridge Construction method big suitable for environmental restrictions
CN110206366A (en) A kind of arch large-span prestressed steel structure and its construction method
CN106988220B (en) A kind of continous way suspension bridge cat road head-rope crosses tower structure and method
CN108951642B (en) Reinforced structure capable of preventing foundation pit from rising and crossing existing tunnel and construction method
CN108166395B (en) A kind of construction method for building beam bridge across Business Line
CN106284989B (en) The sliding form bracing system of double track and complete construction method
CN104032676B (en) A kind of horizontal drawing cable bridge steel wire rope self-anchored type bridge abutment structure
CN206667061U (en) A kind of continous way suspension bridge cat road head-rope crosses tower structure
CN210174677U (en) Hard crossing for changing electrified railway into moving
CN108797760A (en) The construction method of rail yard drainage pipeline temporary support structure
CN108086168A (en) Ride cable-styled erection crane
CN206874293U (en) Subway tunnel soft oil support device
CN109024306A (en) Mountain terrain place Gao Dun rides pier formula door frame bridge lifting construction method
CN104372746A (en) Prefabricated post-tensioning-method simply-supported T-girder concrete injection formwork support and mounting process thereof of railway bridge

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
TA01 Transfer of patent application right
TA01 Transfer of patent application right

Effective date of registration: 20180410

Address after: 301700 Tianjin city Wuqing District Fuyuan Road on the north side of business headquarters building 10 layer B11

Applicant after: THE SIXTH ENGINEERING CO., LTD OF CCCC FOURTH HIGHWAY ENGINEERING CO., LTD.

Address before: 100022 Chaoyang District, Jianguo Road, No. 91, golden center, block A, floor 27, Beijing

Applicant before: CCCC Fourth Highway Engineering Co., Ltd.

Applicant before: THE SIXTH ENGINEERING CO., LTD OF CCCC FOURTH HIGHWAY ENGINEERING CO., LTD.

GR01 Patent grant
GR01 Patent grant