CN106968176A - A kind of embedding batholith foundation construction of bridge deepwater - Google Patents

A kind of embedding batholith foundation construction of bridge deepwater Download PDF

Info

Publication number
CN106968176A
CN106968176A CN201710183021.5A CN201710183021A CN106968176A CN 106968176 A CN106968176 A CN 106968176A CN 201710183021 A CN201710183021 A CN 201710183021A CN 106968176 A CN106968176 A CN 106968176A
Authority
CN
China
Prior art keywords
cofferdam
construction
platform
batholith
embedding
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201710183021.5A
Other languages
Chinese (zh)
Inventor
朱海军
叶亦盛
石九州
任毅
刘强
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Ccteb Infrastructure Construction Co Ltd
China Construction Third Engineering Bureau Co Ltd
Original Assignee
Ccteb Infrastructure Construction Co Ltd
China Construction Third Engineering Bureau Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Ccteb Infrastructure Construction Co Ltd, China Construction Third Engineering Bureau Co Ltd filed Critical Ccteb Infrastructure Construction Co Ltd
Priority to CN201710183021.5A priority Critical patent/CN106968176A/en
Publication of CN106968176A publication Critical patent/CN106968176A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D21/00Methods or apparatus specially adapted for erecting or assembling bridges
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D19/00Keeping dry foundation sites or other areas in the ground
    • E02D19/02Restraining of open water
    • E02D19/04Restraining of open water by coffer-dams, e.g. made of sheet piles
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D27/00Foundations as substructures

Abstract

The invention discloses a kind of embedding batholith foundation construction of bridge deepwater, it is related to bridge foundation construction technical field;The present invention is according to riverbed rock stratum situation and specific environmental requirement, by setting cofferdam locating slot, make cofferdam stable on the thin riverbed of coating, and it is effectively anchored in riverbed by casting concrete in groove, cofferdam had both been met cofferdam and cross big vast requirement, cofferdam effective sealing purpose requirement in the case of not back cover is met again, simplifies the deepwater foundation construction technique under specific environmental requirement;After being drawn water in cofferdam, dry operating environment is formed, it is easy to operate, effectively shorten the construction period, save bottom concrete, by the use of cofferdam inner support as drilling platform, reduce construction cost.

Description

A kind of embedding batholith foundation construction of bridge deepwater
Technical field
The present invention relates to bridge foundation construction technical field, specially a kind of embedding batholith foundation construction of bridge deepwater.
Background technology
At present, it is general using the basic pile foundation of first construction bridges on the water in the construction of bridge foundation, utilize pile foundation steel pile casting Double-Wall Steel Boxed Cofferdam is transferred, bearing platform construction is then carried out, such a arrangement and method for construction water-stagnating effect is poor, efficiency of construction is low, construction environment Difference, construction cost is high.
The content of the invention
The purpose of the present invention is that provides a kind of bridge deepwater embedding batholith foundation construction to solve the above problems.
The present invention is achieved through the following technical solutions above-mentioned purpose, a kind of embedding batholith foundation construction of bridge deepwater, bag Include following construction procedure:
S1, first cleaning rock surface coating, set up groove milling platform, install rotary drilling rig on washing trough platform, are accurately positioned, and carry out Cofferdam locating slot construction, is excavated to 1m below middle weathered rock formation top surface by riverbed rock stratum, after the completion of locating slot construction, utilizes diving Member to situation in groove touch and visits and clear up;
S2, washing trough Platform pipe column weld platform for lining bracket, set up the bottomless cofferdam platform for lining of double-walled steel jacket box, according to Water level conditions, determine the assembled height in cofferdam;
S3, installation cofferdam lowering system, cofferdam is changed to lowering system from platform for lining, transferred to cofferdam locating slot bottom, According to cofferdam state, cofferdam posture is finely tuned using lowering system;
S4, cofferdam borehole wall concrete is poured to scar, concrete is reached after intensity, release the company between cofferdam and lowering system Connect, high cofferdam is connect by design requirement;
Drawn water in S5, cofferdam to riverbed scar, cutting basement rock in the basement rock in the range of mechanical treatment cushion cap, cofferdam using rock mass digs Except to cushion cap bottom 30cm, and in cofferdam corner, sump is set;
S6, by the use of cofferdam inner support as guiding, be accurately positioned steel pile casting, steel pile casting dropped down onto into scar top layer, pour 30cm pads Layer concrete, its lower end is fixed on scar;
S7, in steel pile casting and inner support correspondence position, weld bracket, for drilled pile construction, impact drill be installed on inner support Machine, drilled pile construction then carries out cushion cap reinforcing bar colligation, carries out bearing platform construction.
It is preferred that, in the S1, with reference to formation geology at bridge location and guarantor's particular/special requirement, using rotary drilling rig in cofferdam scope It is interior progress locating slot construction, clamping slot depth need to below middle weathered rock top surface 1m.
In the S2, Double-wall sin-gle-image radiography is anti-fog durability cofferdam, and bottom is inside and outside along nothing in the range of short transverse 2m Panel.
In the S3, by sinking of cofferdam to bottom land, borehole wall concrete is poured to certain altitude, and cofferdam is met sealing will Ask.
In the S6, before casting concrete bed course, sump is set in cofferdam corner, rock cranny is extracted out from cofferdam inside Infiltration.
In the S6, cofferdam inner support both transferred guider as steel pile casting, and was used as Drilling Platform for Bored Pile Construction.
The beneficial effects of the invention are as follows:The present invention is enclosed according to riverbed rock stratum situation and specific environmental requirement by setting Weir locating slot, makes cofferdam is stable it is effectively anchored in riverbed on the thin riverbed of coating, and by casting concrete in groove, Cofferdam had both been met cofferdam and cross big vast requirement, cofferdam effective sealing purpose requirement in the case of not back cover is met again, spy is simplified Determine the deepwater foundation construction technique under environmental requirement;After being drawn water in cofferdam, dry operating environment is formed, it is easy to operate, effectively shorten Construction period, bottom concrete is saved, by the use of cofferdam inner support as drilling platform, reduce construction cost.
Brief description of the drawings
Fig. 1 is construction method schematic diagram of the present invention;
Fig. 2 is Double-Wall Steel Boxed Cofferdam groove milling platform construction figure in the present invention;
In figure:1- steel platforms, 2- rotary drilling rigs
Fig. 3 is Double-Wall Steel Boxed Cofferdam decentralization figure in the present invention;
In figure:3- transfers bracket, 4- Double-Wall Steel Boxed Cofferdams
Fig. 4 is pile foundation construction drawing of the present invention;
In figure:5- steel pile castings, 6- inner supports
Fig. 5 is bottom concrete construction drawing in the present invention;
Fig. 6 is cofferdam top view in the present invention.
Embodiment
Below in conjunction with the accompanying drawing in the embodiment of the present invention, the technical scheme in the embodiment of the present invention is carried out clear, complete Site preparation is described, it is clear that described embodiment is only a part of embodiment of the invention, rather than whole embodiments.It is based on Embodiment in the present invention, it is every other that those of ordinary skill in the art are obtained under the premise of creative work is not made Embodiment, belongs to the scope of protection of the invention.
Embodiment:
Refer to shown in Fig. 1-6, a kind of embedding batholith foundation construction of bridge deepwater, including following construction procedure:
S1, first cleaning rock surface coating, set up groove milling platform, install rotary drilling rig on washing trough platform, are accurately positioned, and carry out Cofferdam locating slot construction, is excavated to 1m below middle weathered rock formation top surface by riverbed rock stratum, after the completion of locating slot construction, utilizes diving Member to situation in groove touch and visits and clear up;Wherein, with reference to formation geology at bridge location and guarantor's particular/special requirement, churning driven is utilized Machine carries out locating slot construction in the range of cofferdam, clamping slot depth need to below middle weathered rock top surface 1m;
S2, washing trough Platform pipe column weld platform for lining bracket, set up the bottomless cofferdam platform for lining of double-walled steel jacket box, according to Water level conditions, determine the assembled height in cofferdam;Wherein Double-wall sin-gle-image radiography is anti-fog durability cofferdam, and bottom is along short transverse 2m In the range of without inside and outside panel;
S3, installation cofferdam lowering system, cofferdam is changed to lowering system from platform for lining, transferred to cofferdam locating slot bottom, According to cofferdam state, cofferdam posture is finely tuned using lowering system;And by sinking of cofferdam to bottom land, borehole wall concrete is poured to one Fixed height, makes cofferdam meet sealing requirement.
S4, cofferdam borehole wall concrete is poured to scar, concrete is reached after intensity, release between cofferdam and lowering system Connection, high cofferdam is connect by design requirement;
Drawn water in S5, cofferdam to riverbed scar, cutting basement rock in the basement rock in the range of mechanical treatment cushion cap, cofferdam using rock mass digs Except to cushion cap bottom 30cm, and in cofferdam corner, sump is set;
S6, by the use of cofferdam inner support as guiding, be accurately positioned steel pile casting, steel pile casting dropped down onto into scar top layer, pour 30cm pads Layer concrete, its lower end is fixed on scar;Wherein before casting concrete bed course, sump is set in cofferdam corner, from enclosing Extract rock cranny infiltration inside weir out;Cofferdam inner support both transferred guider as steel pile casting, and flat as drilled pile construction Platform;
S7, in steel pile casting and inner support correspondence position, weld bracket, for drilled pile construction, impact drill be installed on inner support Machine, drilled pile construction then carries out cushion cap reinforcing bar colligation, carries out bearing platform construction.
It is obvious to a person skilled in the art that the invention is not restricted to the details of above-mentioned one exemplary embodiment, Er Qie In the case of without departing substantially from spirit or essential attributes of the invention, the present invention can be realized in other specific forms.Therefore, no matter From the point of view of which point, embodiment all should be regarded as exemplary, and be nonrestrictive, the scope of the present invention is by appended power Profit is required rather than described above is limited, it is intended that all in the implication and scope of the equivalency of claim by falling Change is included in the present invention.Any reference in claim should not be considered as to the claim involved by limitation.
Moreover, it will be appreciated that although the present specification is described in terms of embodiments, not each embodiment is only wrapped Containing an independent technical scheme, this narrating mode of specification is only that for clarity, those skilled in the art should Using specification as an entirety, the technical solutions in the various embodiments may also be suitably combined, forms those skilled in the art It may be appreciated other embodiment.

Claims (6)

1. a kind of embedding batholith foundation construction of bridge deepwater, it is characterised in that including following construction procedure:
S1, first cleaning rock surface coating, set up groove milling platform, install rotary drilling rig on washing trough platform, are accurately positioned, and carry out Cofferdam locating slot construction, is excavated to 1m below middle weathered rock formation top surface by riverbed rock stratum, after the completion of locating slot construction, utilizes diving Member to situation in groove touch and visits and clear up;
S2, washing trough Platform pipe column weld platform for lining bracket, set up the bottomless cofferdam platform for lining of double-walled steel jacket box, according to Water level conditions, determine the assembled height in cofferdam;
S3, installation cofferdam lowering system, cofferdam is changed to lowering system from platform for lining, transferred to cofferdam locating slot bottom, According to cofferdam state, cofferdam posture is finely tuned using lowering system;
S4, cofferdam borehole wall concrete is poured to scar, concrete is reached after intensity, release the company between cofferdam and lowering system Connect, high cofferdam is connect by design requirement;
Drawn water in S5, cofferdam to riverbed scar, cutting basement rock in the basement rock in the range of mechanical treatment cushion cap, cofferdam using rock mass digs Except to cushion cap bottom 30cm, and in cofferdam corner, sump is set;
S6, by the use of cofferdam inner support as guiding, be accurately positioned steel pile casting, steel pile casting dropped down onto into scar top layer, pour 30cm pads Layer concrete, its lower end is fixed on scar;
S7, in steel pile casting and inner support correspondence position, weld bracket, for drilled pile construction, impact drill be installed on inner support Machine, drilled pile construction then carries out cushion cap reinforcing bar colligation, carries out bearing platform construction.
2. the embedding batholith foundation construction of a kind of bridge deepwater according to claim 1, it is characterised in that:In the S1, knot Formation geology and guarantor's particular/special requirement at bridge location are closed, locating slot construction is carried out in the range of cofferdam using rotary drilling rig, groove depth is positioned Degree need to below middle weathered rock top surface 1m.
3. the embedding batholith foundation construction of a kind of bridge deepwater according to claim 1, it is characterised in that:It is double in the S2 Wall steel boxed cofferdam is anti-fog durability cofferdam, and bottom along in the range of short transverse 2m without inside and outside panel.
4. the embedding batholith foundation construction of a kind of bridge deepwater according to claim 1, it is characterised in that:, will in the S3 Sinking of cofferdam pours borehole wall concrete to certain altitude, cofferdam is met sealing requirement to bottom land.
5. the embedding batholith foundation construction of a kind of bridge deepwater according to claim 1, it is characterised in that:In the S6, pour Build before concrete cushion, sump is set in cofferdam corner, rock cranny infiltration is extracted out from cofferdam inside.
6. the embedding batholith foundation construction of a kind of bridge deepwater according to claim 1, it is characterised in that:In the S6, enclose Weir inner support both transferred guider as steel pile casting, and was used as Drilling Platform for Bored Pile Construction.
CN201710183021.5A 2017-03-24 2017-03-24 A kind of embedding batholith foundation construction of bridge deepwater Pending CN106968176A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710183021.5A CN106968176A (en) 2017-03-24 2017-03-24 A kind of embedding batholith foundation construction of bridge deepwater

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710183021.5A CN106968176A (en) 2017-03-24 2017-03-24 A kind of embedding batholith foundation construction of bridge deepwater

Publications (1)

Publication Number Publication Date
CN106968176A true CN106968176A (en) 2017-07-21

Family

ID=59328987

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710183021.5A Pending CN106968176A (en) 2017-03-24 2017-03-24 A kind of embedding batholith foundation construction of bridge deepwater

Country Status (1)

Country Link
CN (1) CN106968176A (en)

Cited By (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107869144A (en) * 2017-11-17 2018-04-03 中铁二十二局集团第四工程有限公司 A kind of pre- slotting ring seal Double-Wall Steel Boxed Cofferdam deep water foundation comprehensive construction method
CN108179735A (en) * 2018-02-28 2018-06-19 中国葛洲坝集团第五工程有限公司 A kind of boulder bed large-sized deep water foundation construction platform and method
CN108179759A (en) * 2017-12-29 2018-06-19 重庆华力建设有限公司 The underwater drill core slotting of driftway is without bottom sealing method
CN109469084A (en) * 2018-09-21 2019-03-15 中交武汉港湾工程设计研究院有限公司 The embedded construction method of deep water hard rock
CN109469085A (en) * 2018-08-13 2019-03-15 中建三局第三建设工程有限责任公司 A kind of embedding rock cushion cap foundation construction method of deep water
CN109707307A (en) * 2018-12-11 2019-05-03 中铁五局集团贵州工程有限公司 At the construction method of polygon annular groove on a kind of rock stratum under water
CN111119213A (en) * 2019-12-18 2020-05-08 中建三局基础设施建设投资有限公司 Double-wall steel cofferdam with open edge feet and construction method thereof
CN111608173A (en) * 2020-06-04 2020-09-01 石家庄铁道大学 Construction method and device for deep water steep slope bare rock drilled pile
CN112411593A (en) * 2020-11-26 2021-02-26 中国铁建大桥工程局集团有限公司 Construction method of steel sleeve box for rock-socketed bearing platform construction under water level change
CN113585302A (en) * 2021-07-22 2021-11-02 中交第二航务工程局有限公司 Construction method of bottom-sealing-free concrete double-wall steel cofferdam for deep water bare rock geology

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2011006982A (en) * 2009-06-29 2011-01-13 Jfe Steel Corp Wall structure constructed in ground and construction method for the same
CN102011405A (en) * 2010-11-17 2011-04-13 安徽省公路桥梁工程公司 Deepwater cofferdam slot sinking construction method
CN102720140A (en) * 2012-07-12 2012-10-10 中铁二十局集团第一工程有限公司 Large-span prestress concrete continuous beam deepwater pier construction process
CN102864779A (en) * 2012-10-25 2013-01-09 中铁上海工程局有限公司第五分公司 Method for synchronously controlling sinking double-wall steel cofferdam by jack
CN106088120A (en) * 2016-06-16 2016-11-09 中铁上海工程局集团有限公司 Construction method is transferred in a kind of cofferdam

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2011006982A (en) * 2009-06-29 2011-01-13 Jfe Steel Corp Wall structure constructed in ground and construction method for the same
CN102011405A (en) * 2010-11-17 2011-04-13 安徽省公路桥梁工程公司 Deepwater cofferdam slot sinking construction method
CN102720140A (en) * 2012-07-12 2012-10-10 中铁二十局集团第一工程有限公司 Large-span prestress concrete continuous beam deepwater pier construction process
CN102864779A (en) * 2012-10-25 2013-01-09 中铁上海工程局有限公司第五分公司 Method for synchronously controlling sinking double-wall steel cofferdam by jack
CN106088120A (en) * 2016-06-16 2016-11-09 中铁上海工程局集团有限公司 Construction method is transferred in a kind of cofferdam

Cited By (13)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107869144A (en) * 2017-11-17 2018-04-03 中铁二十二局集团第四工程有限公司 A kind of pre- slotting ring seal Double-Wall Steel Boxed Cofferdam deep water foundation comprehensive construction method
CN108179759B (en) * 2017-12-29 2020-06-26 重庆华力建设有限公司 Underwater core drilling and undercutting bottomless method for pilot well
CN108179759A (en) * 2017-12-29 2018-06-19 重庆华力建设有限公司 The underwater drill core slotting of driftway is without bottom sealing method
CN108179735A (en) * 2018-02-28 2018-06-19 中国葛洲坝集团第五工程有限公司 A kind of boulder bed large-sized deep water foundation construction platform and method
CN108179735B (en) * 2018-02-28 2023-09-08 中国葛洲坝集团路桥工程有限公司 Pebble layer large-scale deep water foundation construction platform and pebble layer large-scale deep water foundation construction method
CN109469085A (en) * 2018-08-13 2019-03-15 中建三局第三建设工程有限责任公司 A kind of embedding rock cushion cap foundation construction method of deep water
CN109469084B (en) * 2018-09-21 2020-10-16 中交武汉港湾工程设计研究院有限公司 Construction method of deep water hard rock embedded bearing platform
CN109469084A (en) * 2018-09-21 2019-03-15 中交武汉港湾工程设计研究院有限公司 The embedded construction method of deep water hard rock
CN109707307A (en) * 2018-12-11 2019-05-03 中铁五局集团贵州工程有限公司 At the construction method of polygon annular groove on a kind of rock stratum under water
CN111119213A (en) * 2019-12-18 2020-05-08 中建三局基础设施建设投资有限公司 Double-wall steel cofferdam with open edge feet and construction method thereof
CN111608173A (en) * 2020-06-04 2020-09-01 石家庄铁道大学 Construction method and device for deep water steep slope bare rock drilled pile
CN112411593A (en) * 2020-11-26 2021-02-26 中国铁建大桥工程局集团有限公司 Construction method of steel sleeve box for rock-socketed bearing platform construction under water level change
CN113585302A (en) * 2021-07-22 2021-11-02 中交第二航务工程局有限公司 Construction method of bottom-sealing-free concrete double-wall steel cofferdam for deep water bare rock geology

Similar Documents

Publication Publication Date Title
CN106968176A (en) A kind of embedding batholith foundation construction of bridge deepwater
CN102704957B (en) Shed-frame method for shallowly burying large-sized underground structure construction
CN106381866A (en) Construction method of ultra-deep underground diaphragm wall in water-rich soft-soil area
CN104612143B (en) Composite pile constructed in drilled hole structure under a kind of solution cavity/soil cave geological conditions
CN104846829B (en) Shield-reserved penetration composite type foundation pit support wall and construction method thereof
CN102966108B (en) Construction method of deep foundation pit close to building and adopting underground structure as internal support
CN104099943B (en) Diaphram wall and discarded underground civil defense engineering intersection processing method
CN105239578B (en) Water-rich sand layer deep foundation pit underwater construction method
CN104947649A (en) Control method for open caisson back soil deformation caused by pipe-jacking construction
CN106930276A (en) The deep hole blasting of rotary digging bored concrete pile and the construction method of conduit rotary digging removing obstacles
CN112031017A (en) Construction method suitable for deep water pile foundation steel casing under bare rock geological condition
CN102134853A (en) CT sealed steel pipe pile foundation pit water stop supporting device and construction method thereof
CN106592605A (en) Construction method of foundation pit bracing with tri-axial stirring piles overlapped with reinforced concrete cast-in-place piles to be driven
CN107059900A (en) The construction method that a kind of Double-wall sin-gle-image radiography quickly sinks in sand-pebble layer
CN202809629U (en) Pressure-reduction and dewatering supplementary well completion structure in disturbance stratum inside foundation pit
CN209260739U (en) A kind of foundation pit water-stopping system close to river permeable stratum
CN104452776B (en) Meet with the one construction Treatment Methods of diaphragm wall during boulder
CN204252148U (en) High artesian thick sand-pebble layer deep foundation ditch slip casting back cover structure
Viggiani et al. Geotechnical aspects of underground railway construction in the urban environment: the examples of Rome and Naples
CN107012792B (en) A kind of construction method of bridge substructure
CN106049467A (en) Method for treating slurry leakage of bored pile through percussion drill under complex geology
CN205296194U (en) Rich irrigated land layer undercut tunnel interlock pipe curtain
CN205999924U (en) A kind of Metro station excavation blast working safeguard structure
CN104863188A (en) Self-ballasting type anti-floating construction method
CN110258521A (en) Ground-connecting-wall encloses well construction

Legal Events

Date Code Title Description
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20170721

RJ01 Rejection of invention patent application after publication