CN106964808A - Bent axle puncher - Google Patents

Bent axle puncher Download PDF

Info

Publication number
CN106964808A
CN106964808A CN201710314329.9A CN201710314329A CN106964808A CN 106964808 A CN106964808 A CN 106964808A CN 201710314329 A CN201710314329 A CN 201710314329A CN 106964808 A CN106964808 A CN 106964808A
Authority
CN
China
Prior art keywords
borehole drill
drill construction
bent axle
frame
puncher according
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201710314329.9A
Other languages
Chinese (zh)
Inventor
赵文兴
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Zhejiang Jinlan Auto Part Co Ltd
Original Assignee
Zhejiang Jinlan Auto Part Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Zhejiang Jinlan Auto Part Co Ltd filed Critical Zhejiang Jinlan Auto Part Co Ltd
Priority to CN201710314329.9A priority Critical patent/CN106964808A/en
Publication of CN106964808A publication Critical patent/CN106964808A/en
Pending legal-status Critical Current

Links

Classifications

    • BPERFORMING OPERATIONS; TRANSPORTING
    • B23MACHINE TOOLS; METAL-WORKING NOT OTHERWISE PROVIDED FOR
    • B23BTURNING; BORING
    • B23B41/00Boring or drilling machines or devices specially adapted for particular work; Accessories specially adapted therefor
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B23MACHINE TOOLS; METAL-WORKING NOT OTHERWISE PROVIDED FOR
    • B23BTURNING; BORING
    • B23B2215/00Details of workpieces
    • B23B2215/20Crankshafts

Landscapes

  • Engineering & Computer Science (AREA)
  • Mechanical Engineering (AREA)
  • Earth Drilling (AREA)

Abstract

The invention discloses a kind of bent axle puncher, including frame, the first borehole drill construction and be fixed in frame be used for drive the first borehole drill construction move up and down drive mechanism, the frame is provided with frame the second borehole drill construction of sliding up and down back to the side of the first borehole drill construction, the frame, which is located to be provided with guiding mechanism, the guiding mechanism at the first borehole drill construction and the second borehole drill construction top, is equipped with the chain that two ends connect the first borehole drill construction and the second borehole drill construction respectively.Alternately two crankshaft drillings are processed by the first borehole drill construction and the second borehole drill construction, the operating efficiency of puncher is effectively improved.

Description

Bent axle puncher
Technical field
The present invention relates to a kind of Crankshaft Machining equipment, more specifically, it relates to a kind of bent axle puncher.
Background technology
Bent axle is most important part in engine.It bears the power that connecting rod is transmitted, and is transformed into torque and passes through song Axle exports and drives other annexes on engine to work.Bent axle is by the centrifugal force of gyrating mass, the gas inertia of mechanical periodicity The collective effect of power and reciprocal inertia force, makes bent axle bear the effect of flexion torsion load.Therefore it is required that bent axle has enough strong Degree and rigidity, journal surface need wear-resisting, the uniform, balance that works good.
And bent axle during processing, it is necessary to crankshaft surface carry out Drilling operation, current bent axle is all by bent axle Puncher is drilled, and the structure of bent axle puncher is as shown in the Chinese patent of Application No. 201521033948.3, its work It is that the first drive mechanism drives borehole drill construction towards Crankshaft motion as process, so that Drilling operation is carried out to bent axle, and in order that Drive mechanism can the motion of fast driving borehole drill construction, balance drawstring and balance weight is connected with borehole drill construction, passes through balance The weight of block offsets a part of weight of borehole drill construction, so that the first drive mechanism realizes the fast driving to borehole drill construction.
But, it in the equipment, can only process after a bent axle, the bent axle is disassembled into the next bent axle of reprocessing, Cause the reduction in machine work efficiency.
The content of the invention
It is an object of the invention to provide a kind of bent axle puncher, it can be processed to two rotating shafts simultaneously, work effect Rate is high.
The present invention above-mentioned technical purpose technical scheme is that:A kind of bent axle puncher, including Frame, the first borehole drill construction and be fixed in frame be used for drive the first borehole drill construction move up and down drive mechanism, the machine The side of frame back to the first borehole drill construction is provided with frame the second borehole drill construction of sliding up and down, and the frame is located at first It is provided with above borehole drill construction and the second borehole drill construction on guiding mechanism, the guiding mechanism and is equipped with two ends and connects the respectively The chain of one borehole drill construction and the second borehole drill construction.
By above-mentioned setting, before puncher work, first in the lower section of the first borehole drill construction and the second borehole drill construction Bent axle to be processed is placed at place, and then drive mechanism works, and the first borehole drill construction of driving is moved downward to one of bent axle It is processed, at the same time, the second borehole drill construction can be moved upwards;And in the first borehole drill construction to Crankshaft Machining a period of time Afterwards, drive mechanism can drive the first borehole drill construction to move upwards, and because the first borehole drill construction by chain is connected with second Borehole drill construction, therefore the second borehole drill construction can balance the weight of a part of first borehole drill construction, so that driving Mechanism can the borehole drill construction of fast driving first move upwards;And when the first borehole drill construction is moved upwards, the second drilling Mechanism can be moved downward, so as to be processed to bent axle below, and so on be carried out, and two bent axles can be carried out simultaneously Processing, effectively improves the operating efficiency of equipment to a certain extent.
It is preferred that, the guiding mechanism includes and chain meshed gears.
By above-mentioned setting, during the first borehole drill construction moves up and down, corresponding motion occurs in chain, passes through The cooperation of chain and gear, can make the frictional force suffered by the process of chain movement smaller, effectively improve the use longevity of chain Life.
It is preferred that, the dovetail chute of vertical direction extension is provided with the frame, second borehole drill construction is provided with The dovetail slide block coordinated is slid with dovetail chute.
By above-mentioned setting, the cooperation of dovetail slide block and dovetail chute so that the second borehole drill construction can only be along vertical side To motion, whole motion process is reliable and stable, so that the second borehole drill construction also can be more steady to the process of bent axle It is fixed reliable.
It is preferred that, it is provided with the stopper slot parallel with dovetail chute, second borehole drill construction and sets in the frame Have and slide the limited block coordinated with stopper slot, the length of the stopper slot is less than the length of dovetail chute.
By above-mentioned setting, the cooperation of limited block and stopper slot, so that the second borehole drill construction has a up stroke Extreme position and down stroke extreme position, and then the high-low limit position of the first borehole drill construction and the second borehole drill construction is limited Position, prevents the first borehole drill construction and the second borehole drill construction hyperkinesia and gets into frame, has reached the first borehole drill construction of protection With the purpose of the second borehole drill construction.
It is preferred that, the two ends of the limited block are provided with and can offseted with spacing groove sidewall with buffer limit block and spacing groove sidewall Between impulsive force arc buffering portion.
By above-mentioned setting, when limited block moves to extreme position, limited block can be produced with the side wall of stopper slot Hit, and this impact can make frame or the second borehole drill construction produce it is certain rock, this, which is rocked, to add to bent axle Work precision affects.
It is preferred that, the arc buffering portion includes multiple arc sheet rubbers being arranged successively.
By above-mentioned setting, when limited block will knock stopper slot, outmost arc sheet rubber can first with it is spacing The side wall of groove offsets, so that the phenomenon of deformation occurs in outmost arc sheet rubber, other subsequent sheet rubbers also can gradually go out Existing deformation phenomenon, the effect of a buffering can be produced to limited block, limited block and stopper slot are reduced to a certain extent successively The impulsive force produced during side wall impact, it is ensured that the stability of equipment Drilling operation.
It is preferred that, piston rod is provided with the frame and the second borehole drill construction offsets to push down on the second borehole drill construction Pusher cylinder.
Pass through above-mentioned setting, during the second borehole drill construction is moved downward and is processed to bent axle, pusher cylinder work Make, its piston rod is moved downward to offset with the second borehole drill construction, so that the power pushed down on is produced to the second borehole drill construction, Ensure Drilling operation of second borehole drill construction to bent axle;And after the second borehole drill construction processes a period of time, it needs first to exit Its hole processed, now pusher cylinder piston rod retraction, then drive mechanism drive the first borehole drill construction move downward, this When the second borehole drill construction can move upwards.
It is preferred that, second borehole drill construction is provided with the rubber ring with pusher cylinder piston rod interference fits.
Pass through above-mentioned setting, when the piston rod and the second borehole drill construction of pusher cylinder offset, the piston rod of pusher cylinder It can snap onto in rubber ring and complete interference fits with rubber ring;And when the second borehole drill construction needs upward motion, by In the cooperation of rubber ring and piston rod, when it can produce a pull-up to the second borehole drill construction, this when drive mechanism Mechanism works, and it can promote the first drive mechanism to move downward faster, and because the movement velocity of cylinder piston rod compares It hurry up, therefore during piston rod movement, piston rod can be separated with rubber ring, cylinder will not downwards be transported in the second drive mechanism Impacted when dynamic.
It is preferred that, it is provided with the first magnetic portion, second borehole drill construction and sets on the piston rod of the pusher cylinder There is the second magnetic portion repelled each other with the first magnetic portion.
By above-mentioned setting, during the second borehole drill construction is moved downward, pusher cylinder work, its piston rod is downward Motion;And mutually exclusive power can be produced in this process, between the first magnetic portion and the second magnetic portion, so that second bores Holes mechanism can produce the bigger power pullled upwards to the first borehole drill construction, enable the first borehole drill construction faster upward Motion, reduces load suffered during drive mechanism the first borehole drill construction of driving.
It is preferred that, the sliding groove of horizontal direction extension is provided with second borehole drill construction, second magnetic portion is slided Shifting is arranged in sliding groove, and the elastic component for making the second magnetic areas immediately below the first magnetic portion is provided with the sliding groove.
By above-mentioned setting, during the second borehole drill construction is moved downward, pusher cylinder work, its piston rod can be to Lower motion;And during this motion, due to the distance between pusher cylinder piston rod and the second borehole drill construction constantly It is close, therefore repulsive force between the first magnetic portion and the second magnetic portion can be increasing, can increase to a certain extent Two borehole drill constructions pull power to the first borehole drill construction, the first borehole drill construction is faster resetted;With row Sliding phenomenon can occur in chute in the gradually increase of repulsion, the second magnetic portion, so that the first magnetic portion is no longer just to second Magnetic portion, now repulsive force become very little, the piston rod of pusher cylinder can gradually be pressed on the second borehole drill construction surface, it is ensured that The stability that two borehole drill constructions are processed to crankshaft drilling.And after the second borehole drill construction processes one end time, the second borehole drill construction Need to move one end distance upwards, the piston rod of pusher cylinder can be separated first with the second borehole drill construction, drive mechanism driving first Borehole drill construction is moved downward, and the first borehole drill construction is moved upwards by the borehole drill construction of chain-driving second again, and in this process In, the distance between the first magnetic portion and second magnetic portion can constantly increase, the row between the first magnetic portion and the second magnetic portion Repulsion can be less and less, and now the second magnetic portion under the action of the spring, can be pushed to the underface of the first magnetic portion again, Ensure the stable progress of lower task.
In summary, the invention has the advantages that:
1. alternately carrying out Drilling operation to two bent axles by the first borehole drill construction and the second borehole drill construction, drilling machine is effectively improved Operating efficiency, and two borehole drill constructions mutually pull, therefore, it is possible to bore the drive first of drive mechanism more convenient and quicker Holes mechanism is moved;
2. by setting pusher cylinder, it ensure that the second borehole drill construction is processed to the stable of bent axle;
3. the presence of stopper slot, the high-low limit travel position formation of the second borehole drill construction can be limited, so as to reach to the The restriction of one borehole drill construction and the second borehole drill construction range of movement.
Brief description of the drawings
Fig. 1 is the structure chart of embodiment one;
Fig. 2 is the structure chart of the first borehole drill construction in embodiment one;
Fig. 3 is the structure chart of the second borehole drill construction in embodiment one;
Fig. 4 is the explosive view of embodiment one, for embodying dovetail chute and stopper slot;
Fig. 5 is the backside structure figure of the second sliding seat, for embodying dovetail slide block and limited block;
Fig. 6 is the structure chart of embodiment two.
In figure:1st, chain;2nd, the first borehole drill construction;21st, the first sliding seat;22nd, the first bore motor;23rd, the first drill bit; 3rd, the second borehole drill construction;31st, the second sliding seat;311st, sliding groove;32nd, the second bore motor;33rd, the second drill bit;4th, Guiding machine Structure;41st, first gear;42nd, second gear;5th, frame;51st, dovetail chute;52nd, stopper slot;6th, drive mechanism;61st, electricity is driven Machine;62nd, screw mandrel;7th, pusher cylinder;8th, rubber ring;9th, dovetail slide block;10th, limited block;11st, arc buffering portion;12nd, the first magnetic Iron;13rd, the second magnet;14th, spring.
Embodiment
The present invention is described in further detail below in conjunction with accompanying drawing.
Embodiment one:
A kind of bent axle puncher, reference picture 1, including frame 5, the first borehole drill construction 2, be fixed in frame 5 be used for drive first The borehole drill construction 3 of drive mechanism 6 and second that borehole drill construction 2 moves up and down.Wherein, reference picture 2, drive mechanism 6 includes being fixed on Motor 61 in frame 5, is fixed on the screw mandrel 62 on the output shaft of motor 61;First borehole drill construction 2 includes and frame 5 Slide the first sliding seat 21 set, the first bore motor 22 being fixedly installed on the first sliding seat 21 and be fixed on the first brill The first drill bit 23 on the output shaft of hole motor 22, the first sliding seat 21 is threadedly coupled with screw mandrel 62;Reference picture 3, the second drilling machine Structure 3 includes the second sliding seat 31 that sliding is arranged in frame 5, the second bore motor being fixedly installed on the second sliding seat 31 32 and the second drill bit 33 for being fixed on the output shaft of the second bore motor 32.
The dovetail chute 51 and parallel with dovetail chute 51 of vertical direction extension is provided with reference picture 4 and Fig. 5, frame 5 Stopper slot 52, the length of stopper slot 52, which is less than on the length of dovetail chute 51, the second sliding seat 31, to be provided with and dovetail chute The dovetail slide block 9 and stopper slot 52 that 51 slidings coordinate slide the limited block 10 coordinated.Arc is provided with the two ends of limited block 10 Shape buffer part 11, the arc buffering portion 11 includes the sheet rubber that several are arranged and are each attached on limited block 10 successively.
Guiding mechanism 4 is additionally provided with reference picture 1, Fig. 2 and Fig. 3, frame 5, guiding mechanism 4 includes gear, and gear includes First gear 41 and second gear 42, wherein, first gear 41 is rotatably arranged on the surface of the first sliding seat 21, second gear 42 are rotatably arranged on the surface of the second sliding seat 31.It is arranged with what is engaged with both in first gear 41 and second gear 42 Chain 1, the two ends of chain 1 are fixedly connected with the first sliding seat 21 and the second sliding seat 31 respectively.
Reference picture 3, is further fixedly arranged on pusher cylinder 7 in frame 5, and pusher cylinder 7 is located at the upper of the second sliding seat 31 The piston rod of side and pusher cylinder 7 is just set to the second sliding seat 31, is located at pusher cylinder 7 in the upper surface of the second sliding seat 31 The rubber ring 8 with the piston rod interference fits of pusher cylinder 7 is provided with immediately below piston rod.
The course of work:First placed respectively at the underface of the first borehole drill construction 2 and the second borehole drill construction 3 one it is to be processed Bent axle, the first drill bit 23 and the second drill bit 33 is respectively aligned to need the position of drilling on bent axle, then motor 61 drives Dynamic screw mandrel 62 is rotated, and the first sliding seat 21 is moved downward in the presence of screw mandrel 62;At the same time, the first bore motor 22 drives First drill bit 23 is rotated, and the first sliding seat 21 drives the second motion upwards of sliding seat 31 by chain 1.And with the first sliding seat 21 continuous decrease, the first drill bit 23 can be contacted with bent axle, so as to carry out Drilling operation to bent axle.
And, it is necessary to the first drill bit 23 is pulled up into one end distance after processing a period of time, therefore motor 61 is inverted, It can drive the motion upwards of the first sliding seat 21, because now the second borehole drill construction 3 makes hanging, therefore the second borehole drill construction 3 A pull-up can be played a part of to the first borehole drill construction 2, enable motor 61 drive the first borehole drill construction 2 quick to Upper motion.
And while the second sliding seat 31 is moved downward, pusher cylinder 7 works, its piston rod the second sliding seat 31 of direction Move and offseted with the second sliding seat 31, so as to reach the purpose for promoting the second sliding seat 31 to move downward;At the same time, second Bore motor 32 works, and drives the second drill bit 33 to rotate, after the second sliding seat 31 has moved a segment distance, the second drill bit 33 Contacted with bent axle, so as to carry out Drilling operation to bent axle, and the presence of pusher cylinder 7, its piston rod moment pushes down on slip Seat, so as to ensure the stability that the second drill bit 33 is processed to crankshaft drilling to a certain extent.And due to the effect of piston rod moment One power gives the second sliding seat 31, therefore now piston rod can be with the interference fits of rubber ring 8.
After the second drill bit 33 machined one end time, the piston rod of pusher cylinder 7 is withdrawn, due to piston rod and rubber Enclose 8 interference fits, therefore it can produce the power of a pull-up to the second sliding seat 31, at the same time, the driving of motor 61 the One motion upwards of sliding seat 21, due to the effect of pusher cylinder 7, the pulling force of second 3 pair of first borehole drill construction 2 of borehole drill construction can become It is small, therefore, it is possible to the load born when effectively reduction motor 61 just starts, improve the service life of motor 61; And because the speed of the piston rod of pusher cylinder 7 withdrawal is greater than the movement velocity of the second sliding seat 31, therefore the work of pusher cylinder 7 Stopper rod can be separated with rubber ring 8, so as to ensure that pusher cylinder 7 will not be impacted to the subsequent motion of the second sliding seat 31.
And so on move, realize the Drilling operation to two bent axles, and bored by the first drill bit 23 and the second drill bit 33 After the time of hole one end, processed hole is exited, then proceeds into the hole of generation processing and continues to process, people's processing through hole is imitated Process, improve the crudy of through hole, and intermittent processing can also effectively improve the first drill bit 23 and the second drill bit 33 service life.
Embodiment two:
A kind of bent axle puncher, reference picture 6, the present embodiment and the difference of embodiment one are that second in the present embodiment slides Rubber ring 8 is not set on seat 31, the substitute is, the first magnetic is provided with the lower surface of the piston rod of pusher cylinder 7 Property portion, first magnetic portion be the first magnet 12, be provided with the second sliding seat 31 horizontal direction extension sliding groove 311, Slided in sliding groove 311 and be provided with second magnetic portion mutually exclusive with the first magnet 12, the second magnetic portion is the second magnet 13, Elastic component is additionally provided with sliding groove 311, the elastic component is spring 14, one end of spring 14 is fixed with the second magnetic portion to be connected Connect, the other end is fixedly connected with the side wall of sliding groove 311.
It is mutual by the first magnet 12 and the second magnet 13 in driving 21 motion upwards of the first sliding seat of motor 61 The power of repulsion, make 3 pair of first borehole drill construction 2 of the second borehole drill construction produce it is bigger pull power so that drive mechanism 6 can be more Quickly and easily drive the first motion upwards of sliding seat 21.And when the repulsive force between the first magnet 12 and the second magnet 13 reaches When certain value, the second magnet 13 can be in the inner slide of sliding groove 311, so that between the first magnet 12 and the second magnet 13 Repulsive force reduces so that the piston rod of pusher cylinder 7 can offset with the second sliding seat 31, it is ensured that the second 3 pairs of borehole drill construction song The stable Drilling operation of axle;And during the second sliding seat 31 upwards motion, the piston rod of pusher cylinder 7 and the second sliding block Dynamic to be rapidly directed away from, now, the second magnet 13 is understood under the underface that motion under action from the spring 14 is back to the first magnet 12, convenience Secondary processing.
This specific embodiment is only explanation of the invention, and it is not limitation of the present invention, people in the art Member can make the modification without creative contribution to the present embodiment as needed after this specification is read, but as long as at this All protected in the right of invention by Patent Law.

Claims (10)

1. a kind of bent axle puncher, including frame (5), the first borehole drill construction (2) and it is fixed in frame (5) and is used to drive first The drive mechanism (6) that borehole drill construction (2) moves up and down, it is characterized in that:The frame (5) is back to the one of the first borehole drill construction (2) Side is provided with frame (5) the second borehole drill construction (3) of sliding up and down, the frame (5) be located at the first borehole drill construction (2) and It is provided with above second borehole drill construction (3) on guiding mechanism (4), the guiding mechanism (4) and is equipped with two ends and connects the respectively The chain (1) of one borehole drill construction (2) and the second borehole drill construction (3).
2. bent axle puncher according to claim 1, it is characterized in that:The guiding mechanism (4) includes engaging with chain (1) Gear.
3. bent axle puncher according to claim 1, it is characterized in that:Vertical direction extension is provided with the frame (5) Dovetail chute (51), second borehole drill construction (3) be provided with dovetail chute (51) slide coordinate dovetail slide block (9).
4. bent axle puncher according to claim 3, it is characterized in that:It is provided with and dovetail chute on the frame (5) (51) it is provided with parallel stopper slot (52), second borehole drill construction (3) and slides the limited block coordinated with stopper slot (52) (10), the length of the stopper slot (52) is less than the length of dovetail chute (51).
5. bent axle puncher according to claim 4, it is characterized in that:The two ends of the limited block (10) provided with can with it is spacing Groove (52) side wall offsets with the arc buffering portion (11) of impulsive force between buffer limit block (10) and stopper slot (52) side wall.
6. bent axle puncher according to claim 5, it is characterized in that:The arc buffering portion (11) covers successively including multiple If arc sheet rubber.
7. bent axle puncher according to claim 1, it is characterized in that:Piston rod and second are provided with the frame (5) Borehole drill construction (3) offsets to push down on the pusher cylinder (7) of the second borehole drill construction (3).
8. bent axle puncher according to claim 7, it is characterized in that:Second borehole drill construction (3) is provided with and promotion The rubber ring (8) of cylinder (7) piston rod interference fits.
9. bent axle puncher according to claim 7, it is characterized in that:It is provided with the piston rod of the pusher cylinder (7) The second magnetic portion repelled each other with the first magnetic portion is provided with first magnetic portion, second borehole drill construction (3).
10. bent axle puncher according to claim 9, it is characterized in that:Level is provided with second borehole drill construction (3) The sliding groove (311) of direction extension, the second magnetic portion sliding is arranged in sliding groove (311), in the sliding groove (311) It is provided with the elastic component for making the second magnetic areas immediately below the first magnetic portion.
CN201710314329.9A 2017-05-06 2017-05-06 Bent axle puncher Pending CN106964808A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710314329.9A CN106964808A (en) 2017-05-06 2017-05-06 Bent axle puncher

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710314329.9A CN106964808A (en) 2017-05-06 2017-05-06 Bent axle puncher

Publications (1)

Publication Number Publication Date
CN106964808A true CN106964808A (en) 2017-07-21

Family

ID=59331195

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710314329.9A Pending CN106964808A (en) 2017-05-06 2017-05-06 Bent axle puncher

Country Status (1)

Country Link
CN (1) CN106964808A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN116619580A (en) * 2023-07-21 2023-08-22 四川玄科环保科技有限公司 Basalt fiber box integrated punching tool and use method

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
GB1218012A (en) * 1967-01-03 1971-01-06 Boulton Aircraft Ltd Drilling apparatus
CN201277019Y (en) * 2008-09-19 2009-07-22 康雄雄 Self-driving interactive energy-saving pumping unit
CN202591664U (en) * 2012-06-03 2012-12-12 卞博钧 Multiway independent drilling machine implemented through programmable logic controller
CN104020015A (en) * 2014-06-17 2014-09-03 哈尔滨工业大学 Ultrasonic drilling sampling testing experiment platform
CN205200600U (en) * 2015-12-12 2016-05-04 浙江金兰汽车零部件有限公司 Bent axle puncher

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
GB1218012A (en) * 1967-01-03 1971-01-06 Boulton Aircraft Ltd Drilling apparatus
CN201277019Y (en) * 2008-09-19 2009-07-22 康雄雄 Self-driving interactive energy-saving pumping unit
CN202591664U (en) * 2012-06-03 2012-12-12 卞博钧 Multiway independent drilling machine implemented through programmable logic controller
CN104020015A (en) * 2014-06-17 2014-09-03 哈尔滨工业大学 Ultrasonic drilling sampling testing experiment platform
CN205200600U (en) * 2015-12-12 2016-05-04 浙江金兰汽车零部件有限公司 Bent axle puncher

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN116619580A (en) * 2023-07-21 2023-08-22 四川玄科环保科技有限公司 Basalt fiber box integrated punching tool and use method

Similar Documents

Publication Publication Date Title
CN206898427U (en) A kind of synchronous pulley drilling machine
CN202097602U (en) Balancing device of spindle box of floor-mounted boring and milling machine
CN203109293U (en) Deep hole drilling machine
CN106964808A (en) Bent axle puncher
CN202129879U (en) Eccentric reaming device of back-bolt hole drilling machine for stones
CN103306606B (en) Planetary gear train energy-saving dual-layer drill for drilling of deep oil gas well
CN101532475B (en) Periodical cease device
CN114850372B (en) Resonant radial forging machine and forging application thereof
CN202378014U (en) Electric hammer
CN115126412A (en) Device for stabilizing angle adjustment of drilling machine
CN111425157B (en) Hydraulic oscillation system
CN203925277U (en) A kind of adjusting microinching formula drilling well helicoid hydraulic motor
CN205179953U (en) Miniature tree machine that moves
CN204308244U (en) Speed change hand drill
CN104061297A (en) Rotation and axial vibration combined motion mechanism based on friction transmission
CN209742799U (en) Power head sliding frame on drilling machine
CN109736308B (en) Shallow layer quick pile driver suitable for soft earth's surface
CN210087235U (en) Drilling machine for road construction
CN102554878B (en) A kind of electric hammer
CN105265278A (en) Miniature tree moving machine
CN221256653U (en) Power device for rotary drilling machine
CN216478627U (en) Compound magnetic force adjusting drill bit impact damping device
CN110529099A (en) Calculation method for accumulated static friction resistance in static friction area and method for reducing friction resistance
CN219316883U (en) Impact structure of drilling acceleration tool
CN1031764C (en) Remote-control well signals and the receiver thereof

Legal Events

Date Code Title Description
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
AD01 Patent right deemed abandoned
AD01 Patent right deemed abandoned

Effective date of abandoning: 20190611