CN106931720A - A kind of thermal-insulating body and logistics transportation equipment - Google Patents

A kind of thermal-insulating body and logistics transportation equipment Download PDF

Info

Publication number
CN106931720A
CN106931720A CN201710137875.XA CN201710137875A CN106931720A CN 106931720 A CN106931720 A CN 106931720A CN 201710137875 A CN201710137875 A CN 201710137875A CN 106931720 A CN106931720 A CN 106931720A
Authority
CN
China
Prior art keywords
memory block
temperature
thermal
insulating body
buffering area
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201710137875.XA
Other languages
Chinese (zh)
Inventor
周旭
徐景美
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shunqihe Shenzhen Technology Co Ltd
Original Assignee
SF Express Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by SF Express Co Ltd filed Critical SF Express Co Ltd
Priority to CN201710137875.XA priority Critical patent/CN106931720A/en
Publication of CN106931720A publication Critical patent/CN106931720A/en
Pending legal-status Critical Current

Links

Classifications

    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F25REFRIGERATION OR COOLING; COMBINED HEATING AND REFRIGERATION SYSTEMS; HEAT PUMP SYSTEMS; MANUFACTURE OR STORAGE OF ICE; LIQUEFACTION SOLIDIFICATION OF GASES
    • F25DREFRIGERATORS; COLD ROOMS; ICE-BOXES; COOLING OR FREEZING APPARATUS NOT OTHERWISE PROVIDED FOR
    • F25D31/00Other cooling or freezing apparatus
    • F25D31/005Combined cooling and heating devices
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B60VEHICLES IN GENERAL
    • B60HARRANGEMENTS OF HEATING, COOLING, VENTILATING OR OTHER AIR-TREATING DEVICES SPECIALLY ADAPTED FOR PASSENGER OR GOODS SPACES OF VEHICLES
    • B60H1/00Heating, cooling or ventilating [HVAC] devices
    • B60H1/00478Air-conditioning devices using the Peltier effect
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B60VEHICLES IN GENERAL
    • B60HARRANGEMENTS OF HEATING, COOLING, VENTILATING OR OTHER AIR-TREATING DEVICES SPECIALLY ADAPTED FOR PASSENGER OR GOODS SPACES OF VEHICLES
    • B60H1/00Heating, cooling or ventilating [HVAC] devices
    • B60H1/32Cooling devices
    • B60H1/3204Cooling devices using compression
    • B60H1/3232Cooling devices using compression particularly adapted for load transporting vehicles
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B60VEHICLES IN GENERAL
    • B60PVEHICLES ADAPTED FOR LOAD TRANSPORTATION OR TO TRANSPORT, TO CARRY, OR TO COMPRISE SPECIAL LOADS OR OBJECTS
    • B60P3/00Vehicles adapted to transport, to carry or to comprise special loads or objects
    • B60P3/20Refrigerated goods vehicles

Landscapes

  • Engineering & Computer Science (AREA)
  • Physics & Mathematics (AREA)
  • Mechanical Engineering (AREA)
  • Thermal Sciences (AREA)
  • Chemical & Material Sciences (AREA)
  • Combustion & Propulsion (AREA)
  • General Engineering & Computer Science (AREA)
  • Health & Medical Sciences (AREA)
  • Public Health (AREA)
  • Transportation (AREA)
  • Devices That Are Associated With Refrigeration Equipment (AREA)

Abstract

This application discloses a kind of thermal-insulating body and logistics transportation equipment.A kind of thermal-insulating body, including:Storage box, the storage box includes the separate and closed memory block of two or more, and each memory block has and the extraneous door body for directly communicating;At least one first temperature equipments, each described memory block is corresponding with least one of first temperature equipment, and first temperature equipment carries out temperature adjusting to the memory block.A kind of logistics transportation equipment, including delivery vehicles and thermal-insulating body.The technical scheme of the application can be realized carrying out each memory block independent temperature adjustment, and reach the effect of fast regulating temperature.

Description

A kind of thermal-insulating body and logistics transportation equipment
Technical field
This disclosure relates to a kind of thermal-insulating body and logistics transportation equipment.
Background technology
Cold Chain Logistics be to keep low temperature environment as the logistics progress of core requirement, its be with science and technology progress with And Refrigeration Technique fast development and grow up, and be based on refrigerating process, Refrigeration Technique be the low temperature of means Supply chain system.Cold Chain Logistics increased the regulation to temperature and controlling unit, with cold chain transportation compared with common logistics Thing increasingly numerous and complicated, it is desirable to which Cold Chain Logistics vehicle structure can preferably meet the particular/special requirement such as transport and handling.For example, Current Cold Chain Logistics car needs to transport multiclass product simultaneously, or needs to transport product to multiple clients simultaneously.
In actual shipment, because existing Cold Chain Logistics car, usually need to switch car repeatedly especially when end is sent with charge free Door, and close door necessarily greatly increases energy consumption repeatedly, and, interval time when compartment was closed when being again turned on last time Shorter, temperature cannot be down in the short time and require temperature in compartment, and the constant temperature thus resulted in compartment is raised, and is easily caused Cargo damage.
The content of the invention
In view of drawbacks described above of the prior art or deficiency, expect to provide a kind of thermal-insulating body and logistics transportation equipment, energy Solve to cause the rising of case body temperature to be difficult to recover required temperature in a short time because frequently opening cabinet door in the prior art Problem so that fast cooling can be realized when cabinet door is shut.
To reach above-mentioned purpose, present invention generally provides following technical scheme:
In a first aspect, embodiments of the invention provide a kind of thermal-insulating body, including:
Storage box, the storage box includes the separate and closed memory block of two or more, each memory block have with The door body that the external world directly communicates;
At least one first temperature equipments, each described memory block is right with least one of first temperature equipment Should, first temperature equipment carries out temperature adjusting to the memory block.
The object of the invention to solve the technical problems can also be applied to the following technical measures to achieve further.
Preferably, first temperature equipment carries out interruption temperature adjusting to the memory block.
Preferably, the storage box also includes at least one buffering area, and the buffering area is connected with the memory block, institute State the first temperature equipment carries out temperature adjusting by the buffering area to the memory block.
Preferably, the number is identical with the memory block quantity, and the buffering area and the memory block one One correspondence.
Preferably, first temperature equipment includes cold/heat source and injection apparatus;
One end of the injection apparatus connects with the cold/heat source, and the other end is corresponding with the memory block/buffering area, institute Cold/heat source is stated to spray cold air or hot gas to the memory block by the injection apparatus to adjust the temperature of the memory block.
Preferably, first temperature equipment also includes control device, and the control device includes controlling switch, the control System switch is connected with the injection apparatus, for controlling the injection apparatus to be turned on and off.
Preferably, the control device also includes sensor, and the sensor is electrically connected with the controlling switch.
Preferably, the cold/heat source is refrigerating/heating material.
Preferably, the refrigerating/heating material is phase-change material or semiconductor chilling plate.
Preferably, the phase-change material is liquid nitrogen or dry ice.
Preferably, also including the second temperature equipment, second temperature equipment is corresponding with the memory block/buffering area, institute State the second temperature equipment carries out sustaining temperature control to the memory block/buffering area.
Preferably, second temperature equipment is refrigeration plant.
Preferably, second temperature equipment is slab refrigeration plant.
Second aspect, an alternative embodiment of the invention provides a kind of logistics transportation equipment, including delivery vehicles and above-mentioned Thermal-insulating body.
According to the technical scheme that the embodiment of the present application is provided, it is separate and close that two or more is set in the storage box The memory block closed, each described memory block is corresponding with least one of first temperature equipment.Due to each memory block tool Have and the extraneous door body for directly communicating, when door body is opened, the air generation outside air meeting and memory block in the memory block Heat exchange, has the temperature difference so as to cause the actual temperature in the memory block and target set temperature, and by first temperature adjustment Equipment can carry out fast temperature regulation and control to the memory block, so that the temperature in memory block has difference with target set temperature When other, the temperature of the memory block can be rapidly achieved target set temperature.Simultaneously as the memory block be two or more and It is separate, therefore, it can carry out independent temperature adjustment, convenient use to each memory block.Solve and need in the prior art repeatedly Temperature cannot be down in the short time and require temperature in the compartment that close door is caused, and be easily caused the problem of cargo damage.Reach The effect of fast regulating temperature.Further, according to some embodiments of the application, the buffering connected with memory block by setting Area, moreover it is possible to solve local temperature change in memory block too fast so that local temperature temporarily exceedes target set temperature in memory block Problem, obtains the uniform effect of buffering.
Brief description of the drawings
By the detailed description made to non-limiting example made with reference to the following drawings of reading, the application other Feature, objects and advantages will become more apparent upon:
Fig. 1 is a kind of structural representation of thermal-insulating body of one embodiment offer of the application;
Fig. 2 is a kind of flow chart of thermal-insulating body of one embodiment offer of the application;
Fig. 3 is a kind of flow chart of thermal-insulating body of one embodiment offer of the application;
Fig. 4 is a kind of flow chart of thermal-insulating body of one embodiment offer of the application;
Fig. 5 is a kind of flow chart of thermal-insulating body of one embodiment offer of the application;
Fig. 6 is a kind of structural representation of logistics transportation equipment of another embodiment offer of the application.
Specific embodiment
The application is described in further detail with reference to the accompanying drawings and examples.It is understood that this place is retouched The specific embodiment stated is used only for explaining related invention, rather than the restriction to the invention.It also should be noted that, in order to It is easy to description, the part related to invention is illustrate only in accompanying drawing.
It should be noted that in the case where not conflicting, the feature in embodiment and embodiment in the application can phase Mutually combination.Describe the application in detail below with reference to the accompanying drawings and in conjunction with the embodiments.
Refer to shown in Fig. 1 and Fig. 2, embodiments of the invention provide a kind of thermal-insulating body, including storage box 1 and at least One the first temperature equipment 20.The storage box 1 includes the separate and closed memory block 10 of two or more.For example, can be with First dividing plate 12 is set in the storage box 1, the storage box is isolated by more than two storages by the first dividing plate 12 Area 10.Each memory block 10 has the door body 11 directly communicated with the external world, and each memory block 10 can be made individually to be communicated with the external world, The convenient taxonomy of goods management placed.As shown in Fig. 2 in each described memory block 10 and first temperature equipment 20 at least One corresponding, first temperature equipment 20 is carried out temperature adjusting to the memory block 10.
According to the technical scheme that the embodiment of the present application is provided, it is separate and close that two or more is set in the storage box The memory block closed, each described memory block is corresponding with least one of first temperature equipment.Due to each memory block tool Have and the extraneous door body for directly communicating, when door body is opened, the air generation outside air meeting and memory block in the memory block Heat exchange, has the temperature difference so as to cause the actual temperature in the memory block and target set temperature, and by first temperature adjustment Equipment can carry out temperature adjusting to the memory block, so that the temperature in memory block has difference with target set temperature When, the temperature of the memory block can be rapidly achieved target set temperature.Simultaneously as the memory block is two or more and phase It is mutually independent, therefore, it can carry out independent temperature adjustment, convenient use to each memory block.To solve need in the prior art and open repeatedly Temperature cannot be down in the short time and require temperature in the compartment that the door that cut-offs is caused, and be easily caused the problem of cargo damage.Reach The effect of fast regulating temperature.
Preferably, first temperature equipment can carry out discontinuously temperature adjusting to the memory block.Need exist for Bright, so-called interruption temperature adjusting is the temperature adjusting taken according to the temperature variations in the memory block 10.Example Such as, when in memory block actual temperature it is larger with target set temperature T2 difference, and need to quickly recover to goal-setting temperature in short-term During degree T2, you can opening described first temperature temperature equipment, 20 pairs of memory blocks 10 carries out temperature adjustment.
As depicted in figs. 1 and 2, the storage box can include 4 memory blocks 10, be respectively successively the firstth area, the secondth area, 3rd area and the 4th area, need not emphasize which is the firstth area here, and which is the secondth area, and which is the 3rd area, and which is the 4th Area, it is only for description below is got up convenient.First temperature equipment 20 can be one, first temperature equipment 20 The temperature in firstth area, the secondth area, the 3rd area and the 4th area can be individually adjusted respectively.During concrete application, can be combined with The door body on off state of each memory block 10 is controlled.For example, by picking or arrangement of goods cause door body opening when institute State the temperature change in memory block larger, it is necessary to open first temperature equipment 20, can wait after shutting door body, be then turned on institute State the first temperature equipment 20.In case door body opens first temperature equipment 20 when opening causes energy waste.
Preferably, as shown in figures 1 and 3, the storage box 1 can also include at least one buffering area 30.The buffering Area 30 can be arranged between first temperature equipment 20 and the memory block 10, and the buffering area 30 and the storage Area 10 connects.As shown in figure 1, be provided with dividing plate 13 between the buffering area 30 and the memory block 10, can be with the dividing plate Setting communicating door 40 makes each memory block 10 be connected with the buffering area 30.As shown in figures 1 and 3, the buffering area 30 can be with It it is one, now the buffering area 30 can be connected with memory block described at least one 10 as needed.Certainly, the buffering area 30 can also be two or more, and now each buffering area 30 can be connected with memory block described at least one 10 as needed.And And more than two buffering areas 30 can be connected with identical memory block 10, it is also possible to connected from different memory blocks 10. Because first temperature equipment 20 is corresponding with the buffering area 30, therefore first temperature equipment 20 can be by described slow Rushing 30 pairs, the area memory block 10 carries out temperature adjusting.Specifically, first temperature equipment 20 can first adjust the buffering Temperature in area 30 reaches the first temperature T1, and then the buffering area 30 carries out heat exchange with the memory block 10 again, makes described Memory block 10 reaches target set temperature T2.The buffering area connected with memory block by setting, can solve local temperature in memory block Degree change is too fast to cause that local temperature is temporarily more than the problem of target set temperature in memory block, obtains the uniform effect of buffering.
Preferably, as shown in figure 4, the quantity of the buffering area 30 can be identical with the quantity of the memory block 10, and institute Buffering area 30 is stated to be corresponded with the memory block 10.For example, the memory block 10 in Fig. 4 is four, it is respectively the firstth area, second Area, the 3rd area and the 4th area.Correspond, the buffering area 30 also there are four, be respectively first buffering area, the second buffering Area, the 3rd buffering area and the 4th buffering area.And first buffering area connection corresponding with the firstth area, second buffering area is corresponding with the secondth area Connection, the connection corresponding with the 3rd area of the 3rd buffering area, the connection corresponding with the 4th area of the 4th buffering area.Equally, also do not emphasize here Which is specifically first buffering area, and which is second buffering area, and which is the 3rd buffering area, and which is the 4th buffering area, only It is for convenience.
Explanation is needed exist for, the buffering area 30 can be various with the position relationship of the memory block 10.For example, The first can be, as shown in figure 1, the buffering area 30 is located at the outside of the memory block 10 and is interconnected;Second can To be, the buffering area 30 is located at the inside of the memory block 10, but the buffering area 30 is kept apart with the memory block 10, And the position of reserved connection.The arrangement of more than two memory blocks 10 can be any, for example, can such as the arrangement mode of Fig. 1, Can be such as the arrangement mode of Fig. 5.Flexible design arrangement according to actual needs, is not specifically limited here.
Preferably, as shown in figure 1, first temperature equipment 20 can include cold/heat source 21 and injection apparatus 22.It is described One end of injection apparatus 22 connects with the cold/heat source 21, the other end of the injection apparatus 22 and the memory block 10 or slow The correspondence of area 30 is rushed, the cold/heat source 21 sprays cold by the injection apparatus 22 to the memory block 10 or the buffering area 30 Gas or hot gas.Specifically, the injection apparatus 22 can include connecting line 221 and injector head 222, the connecting line 221 The cold/heat source 21 and the injector head 222 are connected, the injector head 222 sprays to the memory block 10 or the buffering area 30 Penetrate cold air or hot gas.When the injection apparatus 22 and the memory block 10 pairs are corresponding, the cold/heat source 21 is by the injection dress 22 are put to spray cold air or hot gas to the memory block 10 directly to adjust the temperature of the memory block 10.When the injection apparatus 22 When corresponding with the buffering area 30 pairs the cold/heat source 21 by the injection apparatus 22 to the buffering area 30 spray cold air or Hot gas, then the buffering area 30 heat exchange is carried out with the memory block 10 again to adjust the temperature of the memory block 10 indirectly.
Setting an effect of the buffering area 30 is:If low temperature cold source is introduced directly into memory block, storage can be caused Local temperature supercooling in area, if the frozen goods for having lower limit demand to temperature in refrigerated storage area (0-10 ° of environment) and part are come Say, this mode can cause product in memory block to occur damaging.Therefore, the buffering area is increased in the middle of low-temperature receiver and memory block, Make first to carry out directed energy transmission (i.e. by the direction of low-temperature receiver to buffering area) between low temperature cold source and the buffering area 30, and in institute Stating carries out temperature buffer in buffering area, that is, lead to too small amount of low temperature cold source and obtain the first temperature T1 in the buffering area first. Meanwhile, the buffering area 30 carries out bidirectional energy and exchanges with the memory block 10, when fluctuation occurs in temperature in memory block 10, leads to Crossing low temperature cold source carries out the quick supplement of energy, to be rapidly achieved the target set temperature T2 of memory block.
When low temperature cold source energy is very big, the first temperature T1 of the buffering area can be substantially kept, while T1 < T2.
It should be noted that if thermal source, then the first temperature T1 of the buffering area>T2.
Preferably, first temperature equipment 20 can also include control device (not shown), the control device Controlling switch can be included, the controlling switch is connected with the injection apparatus 22, for controlling the injection apparatus 22 to open Or close.
Preferably, the control device can also include sensor, and the sensor can be arranged on the memory block 10 In interior or buffering area 30, for monitoring the temperature change in the memory block 10 or buffering area 30, and the sensor and institute State controlling switch electrical connection.For example, a kind of situation is, the sensor can include temperature sensor, when the TEMP When the actual temperature in the memory block that device is monitored is changed greatly with its target set temperature T2, the temperature sensor can The control device is sent to by information and instruction, make the controlling switch control first temperature equipment to open.It is another Kind of situation is, meanwhile, the sensor can also include infrared sensor, and the infrared sensor monitors the shape of the door body 11 State.When the temperature sensor monitors to temperature change need to open the first temperature equipment, while the infrared sensor is monitored When being shut to the door body, controlling switch is just set to control first temperature equipment to open.Obviously, second situation is compared with the first Situation more energy saving, reduces loss.Certainly, for monitoring during the door body on off state, or other sensors, Here it is not specifically limited.
Preferably, the cold/heat source can be refrigerating/heating material.For example, the refrigerating/heating material can be phase Become material or semiconductor.Phase-change material refers to vary with temperature and change state of matter and can provide the material of latent heat.Transformation thing The process of rationality matter is referred to as phase transition process, and at this moment phase-change material will absorb or discharge substantial amounts of latent heat.Phase-change material mainly includes Inorganic phase-changing material, organic phase change material and the class of composite phase-change material three.Wherein, inorganic phase-changing material mainly has crystalline hydrate salt Class, molten salts, metal or alloy class etc.;Organic phase change material mainly includes paraffin, acetic acid and other organic matters;Composite phase-change Heat accumulating arises at the historic moment, and it can effectively overcome the shortcoming that single inorganic matter or organic matter phase-change heat-storage material are present, The application effect of phase-change material can be improved again and its range of application is expanded.For example, the phase-change material can for liquid nitrogen or Dry ice.Liquid nitrogen and dry ice belong to inorganic phase-changing material, are two kinds of relatively common phase-change materials.
In addition, the refrigerating/heating material can also be semiconductor chilling plate.Semiconductor chilling plate, is also thermoelectric cooling Piece, is a kind of heat pump.It is using Peltier (Peltier) effect of semi-conducting material, when direct current is by two kinds of differences half Conductor material in series into galvanic couple when, the two ends of galvanic couple can respectively absorb heat and release heat, it is possible to achieve refrigeration Purpose.Semiconductor chilling plate has two kinds of functions, can freeze, and can heat.
Preferably, the thermal-insulating body can also include the second temperature equipment (not shown), and second temperature adjustment sets It is standby can be corresponding with the memory block 10 or buffering area 30, second temperature equipment enters to the memory block 10 or buffering area 30 Capable constantly temperature control.For example, when second temperature equipment is refrigeration plant, slab refrigeration plant can be specially. Slab refrigeration plant is a kind of phase-change material for cold storage.I.e. the material undergoes phase transition rear storage energy at a certain temperature, works as environment When temperature is less than phase transition temperature, material carries out cold-storage in energy accumulating state;When environment temperature is higher than material phase transformation temperature, material In energy release conditions.The material realizes refrigeration by cold-storage and exoergic.The technical program passes through phase-change material at low temperature Cold-storage, in storage exoergic realization is freezed.Certainly, limitation does not use slab refrigeration plant here, can also be that other are made Cool equipment, the principle or the principle of air-conditioning temperature-reducing that can be for example refrigerated according to refrigerator freezing are using compressor and evaporator etc..
The thermal-insulating body of the application frequently switches on the situation for causing the memory block temperature change too big particularly suitable for door body. Temperature caused by door is frequently switched on due to when the more than one piece product of a memory block memory storage different clients is dispensed, easily causing Degree fluctuation.Therefore, during concrete application, refrigerator car can be made similar this junior unit of honeycomb cabinet, each junior unit is one Memory block.The commodity of different clients are stored into different memory blocks, or the product of different temperatures requirement is respectively stored in not In same memory block, the number of times of switch gate can be so reduced, temperature and target set temperature in the memory block are made as far as possible The T2 temperature difference reduces, can be with reducing energy consumption.
Fig. 6 is refer to, an alternative embodiment of the invention provides a kind of logistics transportation equipment, including the He of delivery vehicles 100 It is arranged on the thermal-insulating body 200 on the delivery vehicles 100.
Wherein, the thermal-insulating body 200 includes:
Storage box, the storage box includes the separate and closed memory block of two or more, each memory block have with The door body that the external world directly communicates;
At least one first temperature equipments, each described memory block is right with least one of first temperature equipment Should, first temperature equipment carries out temperature adjusting to the memory block.
The specific embodiment of the thermal-insulating body refers to the specific embodiment in one embodiment, does not do superfluous here State.
The delivery vehicles 100 can send car with charge free for end.For example, express delivery needs to deliver to each client's during transporting End link needs to use end to send car with charge free.
According to the technical scheme that the embodiment of the present application is provided, it is separate and close that two or more is set in the storage box The memory block closed, each described memory block is corresponding with least one of first temperature equipment.Due to each memory block tool Have and the extraneous door body for directly communicating, when door body is opened, the air generation outside air meeting and memory block in the memory block Heat exchange, has the temperature difference so as to cause the actual temperature in the memory block and target set temperature, and by first temperature adjustment Equipment can carry out temperature adjusting to the memory block, so that the temperature in memory block has difference with target set temperature When, the temperature of the memory block can be rapidly achieved target set temperature.Simultaneously as the memory block is two or more and phase It is mutually independent, therefore, it can carry out independent temperature adjustment, convenient use to each memory block.To solve need in the prior art and open repeatedly Temperature cannot be down in the short time and require temperature in the compartment that the door that cut-offs is caused, and be easily caused the problem of cargo damage.Reach The effect of fast regulating temperature.
Above description is only the preferred embodiment and the explanation to institute's application technology principle of the application.People in the art Member is it should be appreciated that involved invention scope in the application, however it is not limited to the technology of the particular combination of above-mentioned technical characteristic Scheme, while should also cover in the case where the inventive concept is not departed from, is carried out by above-mentioned technical characteristic or its equivalent feature Other technical schemes for being combined and being formed.Such as features described above has similar work(with (but not limited to) disclosed herein The technical scheme that the technical characteristic of energy is replaced mutually and formed.

Claims (14)

1. a kind of thermal-insulating body, it is characterised in that including:
Storage box, the storage box includes the separate and closed memory block of two or more, and each memory block has and the external world The door body for directly communicating;
At least one first temperature equipments, each described memory block is corresponding with least one of first temperature equipment, institute State the first temperature equipment carries out temperature adjusting to the memory block.
2. thermal-insulating body according to claim 1, it is characterised in that
First temperature equipment carries out interruption temperature adjusting to the memory block.
3. thermal-insulating body according to claim 2, it is characterised in that the storage box also includes at least one buffering area, The buffering area is connected with the memory block, and first temperature equipment carries out temperature by the buffering area to the memory block Degree regulation and control.
4. thermal-insulating body according to claim 3, it is characterised in that the number and the memory block quantity phase Together, and the buffering area is corresponded with the memory block.
5. thermal-insulating body according to claim 3, it is characterised in that first temperature equipment includes cold/heat source and spray Injection device;
One end of the injection apparatus connects with the cold/heat source, and the other end is corresponding with the memory block/buffering area, it is described it is cold/ Thermal source sprays cold air or hot gas to adjust the temperature of the memory block by the injection apparatus to the memory block/buffering area.
6. thermal-insulating body according to claim 5, it is characterised in that first temperature equipment also includes control device, The control device includes controlling switch, and the controlling switch is connected with the injection apparatus, for controlling the injection apparatus It is turned on and off.
7. thermal-insulating body according to claim 6, it is characterised in that the control device also includes sensor, the biography Sensor is electrically connected with the controlling switch.
8. thermal-insulating body according to claim 5, it is characterised in that the cold/heat source is refrigerating/heating material.
9. thermal-insulating body according to claim 8, it is characterised in that the refrigerating/heating material is phase-change material or half Conductor cooling piece.
10. thermal-insulating body according to claim 9, it is characterised in that the phase-change material is liquid nitrogen or dry ice.
11. thermal-insulating bodies according to claim 3, it is characterised in that also including the second temperature equipment, second temperature adjustment Equipment is corresponding with the memory block/buffering area, and second temperature equipment carries out sustaining temperature control to the memory block/buffering area System.
12. thermal-insulating bodies according to claim 11, it is characterised in that second temperature equipment is refrigeration plant.
13. thermal-insulating bodies according to claim 12, it is characterised in that second temperature equipment is that slab refrigeration sets It is standby.
14. a kind of logistics transportation equipment, it is characterised in that including any one of delivery vehicles and the claims 1~13 Described thermal-insulating body.
CN201710137875.XA 2017-03-09 2017-03-09 A kind of thermal-insulating body and logistics transportation equipment Pending CN106931720A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710137875.XA CN106931720A (en) 2017-03-09 2017-03-09 A kind of thermal-insulating body and logistics transportation equipment

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710137875.XA CN106931720A (en) 2017-03-09 2017-03-09 A kind of thermal-insulating body and logistics transportation equipment

Publications (1)

Publication Number Publication Date
CN106931720A true CN106931720A (en) 2017-07-07

Family

ID=59432091

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710137875.XA Pending CN106931720A (en) 2017-03-09 2017-03-09 A kind of thermal-insulating body and logistics transportation equipment

Country Status (1)

Country Link
CN (1) CN106931720A (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108253679A (en) * 2017-12-28 2018-07-06 广州齐天冷链科技有限公司 A kind of non-transformer cold-accumulating box of temperature-adjustable
CN110132338A (en) * 2019-04-11 2019-08-16 广州奥松电子有限公司 A kind of sensor automatic calibration device
CN110986318A (en) * 2019-12-10 2020-04-10 珠海格力电器股份有限公司 Air conditioner control method and device based on temperature buffering and air conditioner

Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US5729983A (en) * 1993-12-13 1998-03-24 The Boc Group Plc Storage of perishable foodstuffs
JPH1179331A (en) * 1997-09-16 1999-03-23 Sanyo Electric Co Ltd Physical distribution device and physical distribution system using thereof
US6408640B1 (en) * 1999-06-04 2002-06-25 The Boc Group, Plc Cryogenic refrigeration of goods
WO2007049380A1 (en) * 2005-10-26 2007-05-03 Costem Inc. Constant-temperature cold-reserving box and method of reserving cold at constant temperature
WO2012059332A2 (en) * 2010-11-03 2012-05-10 BSH Bosch und Siemens Hausgeräte GmbH Refrigeration appliance comprising a buffer store
CN203388175U (en) * 2013-07-23 2014-01-15 上海浩爽实业有限公司 Fruit and vegetable fresh-keeping refrigerating device
CN105300005A (en) * 2014-08-12 2016-02-03 苏州麦科威电气技术有限公司 Static-wind chilling refrigerator
CN206695504U (en) * 2017-03-09 2017-12-01 顺丰速运有限公司 A kind of thermal-insulating body and logistics transportation equipment

Patent Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US5729983A (en) * 1993-12-13 1998-03-24 The Boc Group Plc Storage of perishable foodstuffs
JPH1179331A (en) * 1997-09-16 1999-03-23 Sanyo Electric Co Ltd Physical distribution device and physical distribution system using thereof
US6408640B1 (en) * 1999-06-04 2002-06-25 The Boc Group, Plc Cryogenic refrigeration of goods
WO2007049380A1 (en) * 2005-10-26 2007-05-03 Costem Inc. Constant-temperature cold-reserving box and method of reserving cold at constant temperature
WO2012059332A2 (en) * 2010-11-03 2012-05-10 BSH Bosch und Siemens Hausgeräte GmbH Refrigeration appliance comprising a buffer store
CN203388175U (en) * 2013-07-23 2014-01-15 上海浩爽实业有限公司 Fruit and vegetable fresh-keeping refrigerating device
CN105300005A (en) * 2014-08-12 2016-02-03 苏州麦科威电气技术有限公司 Static-wind chilling refrigerator
CN206695504U (en) * 2017-03-09 2017-12-01 顺丰速运有限公司 A kind of thermal-insulating body and logistics transportation equipment

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108253679A (en) * 2017-12-28 2018-07-06 广州齐天冷链科技有限公司 A kind of non-transformer cold-accumulating box of temperature-adjustable
CN110132338A (en) * 2019-04-11 2019-08-16 广州奥松电子有限公司 A kind of sensor automatic calibration device
CN110986318A (en) * 2019-12-10 2020-04-10 珠海格力电器股份有限公司 Air conditioner control method and device based on temperature buffering and air conditioner

Similar Documents

Publication Publication Date Title
CN106931720A (en) A kind of thermal-insulating body and logistics transportation equipment
US20150316311A1 (en) Multi-temperature transport refrigeration system
WO2014055525A1 (en) Periodic system diagnostic of a transport refrigeration system
EP3680117B1 (en) Methods and systems for energy efficient defrost of a transport climate control system evaporator
CN103411360B (en) Refrigeration system and method
CN206695504U (en) A kind of thermal-insulating body and logistics transportation equipment
CN105437916B (en) A kind of vehicle-mounted high energy cold accumulation system
KR101506187B1 (en) Hybrid cold storage system.
CN109442849B (en) Preservation box based on phase-change material and control system thereof
CN102183114B (en) Cold charging method for cold accumulation material
CN207955453U (en) A kind of cold storage refrigerator car of solar energy
CN202048741U (en) Charge device of cold accumulation material
CN209009275U (en) A kind of Cold Chain Logistics case
KR102065492B1 (en) Movable refrigerator
WO2007042162A1 (en) Refrigerator vehicle and process for distributing food products
CN205066294U (en) Domestic refrigerator with cold volume recovery unit
CN103692950A (en) Coil evaporative mobile refrigerator
CN111017413A (en) Ice box cold accumulation system
CN209079595U (en) A kind of cold-chain box based on liquid nitrogen cold-storage and spray cooling
CN211845700U (en) Ice box cold accumulation system
CN217325614U (en) Constant-temperature energy-saving water supply system
CN203672014U (en) Defrosting device
CN214822848U (en) Movable cold station
CN215260721U (en) Fixed cold station system
CN206797211U (en) The built-in type ice cold-storage car refrigerator of active refrigeration

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
TA01 Transfer of patent application right

Effective date of registration: 20190527

Address after: 518000 Guangdong Province Nanshan District Yuehai Street Coastal Community High-tech Nanshidao 81, 83, 85 Software Industry Base 1 B1002

Applicant after: Shunqihe (Shenzhen) Technology Co.,Ltd.

Address before: 518128 No. 1111, No. 4 Road, Baoan International Airport Terminal, Shenzhen City, Guangdong Province

Applicant before: SF EXPRESS Co.,Ltd.

TA01 Transfer of patent application right
RJ01 Rejection of invention patent application after publication

Application publication date: 20170707

RJ01 Rejection of invention patent application after publication