CN106930333B CN201710138823.4A CN201710138823A CN106930333B CN 106930333 B CN106930333 B CN 106930333B CN 201710138823 A CN201710138823 A CN 201710138823A CN 106930333 B CN106930333 B CN 106930333B
Authority
CN
China
Prior art keywords
steel
pipe pile
positioning plate
position fix
wharf
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201710138823.4A
Other languages
Chinese (zh)
Other versions
CN106930333A (en
Inventor
张章
吴锋
邱松
卓杨
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Construction Third Engineering Bureau Co Ltd
CCCC Shanghai Third Harbor Engineering Science and Technology Research Institute Co Ltd
CCCC Shanghai Harbour Engineering Design and Research Institute Co Ltd
Original Assignee
China Construction Third Engineering Bureau Co Ltd
CCCC Shanghai Third Harbor Engineering Science and Technology Research Institute Co Ltd
CCCC Shanghai Harbour Engineering Design and Research Institute Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Construction Third Engineering Bureau Co Ltd, CCCC Shanghai Third Harbor Engineering Science and Technology Research Institute Co Ltd, CCCC Shanghai Harbour Engineering Design and Research Institute Co Ltd filed Critical China Construction Third Engineering Bureau Co Ltd
Priority to CN201710138823.4A priority Critical patent/CN106930333B/en
Publication of CN106930333A publication Critical patent/CN106930333A/en
Application granted granted Critical
Publication of CN106930333B publication Critical patent/CN106930333B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D33/00Testing foundations or foundation structures

Landscapes

  • Engineering & Computer Science (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Piles And Underground Anchors (AREA)

Abstract

The present invention provides a kind of steel pipe piles at wharf test fixtures, are applied in steel-pipe pile, wherein the positioning device includes: multiple positioning plates, and positioning plate at least has an inner concave, and offers a test position fix hole.The fixation kit for being connected with each positioning plate and being used to be fixed on each positioning plate on steel-pipe pile.Wherein, after each positioning plate is being fixed component and is fixed on steel-pipe pile, the stake circumferential surface of inner concave and steel-pipe pile fits, and the center in each test position fix hole is respectively positioned on same plane, and the plane is perpendicular to the axial direction of steel-pipe pile.Compared with the existing technology, the present invention can facilitate staff to paste foil gauge on steel-pipe pile according to the position in each test position fix hole, to prevent from not causing measurement result deviation occur due in same level because of the center in each test position fix hole, and then improve the precision of test.

Description

Steel pipe piles at wharf test fixture
Technical field
The present invention is more particularly directed to building field more particularly to a kind of steel pipe piles at wharf test fixtures.
Background technique
Important component of the steel-pipe pile as dock structure subjects from vertical, horizontally load action and bank slope The effect of deformation.Understand the actual stress situation in dock structure, either all may be used to its Bearing capacity assessment, maintenance or reinforcing To provide most directly with reliable foundation, there is very important engineering significance.
When determining the existing stress of structural elements, it is particularly significant that test method is reasonably selected for specific operating condition, is considered as The various conditions such as the adaptability of the degree, the influence that metallicity changes, on-the-spot test that allow structural damage to hurt.With scientific skill The appearance of the continuous development of art, new physical principle also provides new developing direction for the measurement of existing stress, but from conversion At the practical methods with operability, there are also a distances.
In the prior art, actual stress test usually is carried out to steel-pipe pile with Blind Hole Method, specific way is in steel pipe Strain rosette (being connected and composed by multiple foil gauges) and in the centre-drilling hole of strain rosette is pasted in stake, passes through releasing before and after testing bore holes Strain is put to calculate the actual stress of bore position.However, determining the bore position on steel-pipe pile by the way of manually drawing lines With the paste position of foil gauge, it is difficult to ensure that drilling is in the same horizontal plane, so as to cause arranging that foil gauge is surveyed on steel-pipe pile When pilot, even if the stress value measured on each foil gauge is accurate, but the assessment of final pile body force-bearing situation is also inaccurate.Separately Outside, the unstability and manually-operated deviation due to steel-pipe pile when being tested, easily causes the stickup of foil gauge Position generates deviation, so that precision of measured result causes influence when carrying out the test of stress blind hole on it.
Therefore, it how to be lifted at measuring accuracy when carrying out the test of stress blind hole to steel-pipe pile, is that the present invention to be solved The problem of.
Summary of the invention
The present invention In view of the above shortcomings of the prior art, proposes a kind of steel pipe piles at wharf test fixture, Measuring accuracy when carrying out the test of stress blind hole to steel-pipe pile can be lifted at.
The present invention is achieved by the following technical solutions, and the present invention provides a kind of steel pipe piles at wharf test harbour steel Tubular pole test fixture is applied in steel-pipe pile, and the steel pipe piles at wharf test fixture includes: N number of positioning plate, And the positioning plate at least has an inner concave, and offers a test position fix hole;
The fixation kit for being connected with each positioning plate and being used to be fixed on each positioning plate on the steel-pipe pile;
Wherein, the N is the positive integer greater than 1, and when each positioning plate is being fixed on the steel pipe by the fixation kit After in stake, the stake circumferential surface of inner concave and the steel-pipe pile fits, and the center in each test position fix hole is respectively positioned on same plane, And the plane is perpendicular to the axial direction of the steel-pipe pile.
Compared with prior art, the present invention is fixed on steel-pipe pile by the assignment test tooling by each positioning plate, and So that the center that each test position fix hole can be realized is respectively positioned on perpendicular to steel-pipe pile axial direction after its inner concave and stake circumferential surface fit Same plane on, so as to facilitate staff to paste foil gauge on steel-pipe pile according to the position in each test position fix hole, with It prevents from not causing measurement result deviation occur due in same level because of the center in each test position fix hole, and then improves pile foundation The precision of blind hole stress test.
Preferably, the positioning plate includes: with engraving in order to meet the design in practical application, processing and assembly demand The body member in empty portion, the locating piece for being arranged in the hollow-out parts and being detachably connected with the body member;It, the test is fixed Position Kong Jun is provided on corresponding locating piece.
Preferably, at least partially using the center in its test position fix hole as coordinate origin on the locating piece, and it is vertical along it To with laterally outward protrude the holding section extended to form;The edge of the hollow-out parts of the body member has for accommodating the card The card slot in conjunction portion.To pass through the mutual cooperation of holding section and card slot, staff can be facilitated to carry out locating piece and body member Quick assembly and disassembly, to meet different testing requirements.It simultaneously can also be by the setting direction of holding section to subsequent strain The installation site of piece plays the role of a positioning.
Preferably, the locating piece and the body member are being cut preceding integrated molding.So as to which production can be greatly reduced Cost economizes on resources.
Preferably, the locating piece at least offers K mounting hole, detects the steel-pipe pile for installing and be perforated when institute By the foil gauge of stress, and the center line of the mounting hole of each locating piece and the center line in its test position fix hole are in corresponding throwing Projection in shadow plane is located at same straight line;Wherein, K is positive integer.So as to which production cost can be greatly reduced, economize on resources.
Preferably, the K is 3, and the center line of two adjacent mounting holes is between the projection on the projection plane Angle be followed successively by 90 degree, 135 degree, 135 degree.Calculating demand when meeting to steel-pipe pile progress blind hole stress test, and nothing Setting angle between foil gauge need to be measured and be calculated, so as to avoid the error generated by manual operation.
Preferably, in order to enable at least there are two be the axis for testing steel-pipe pile when being perforated in above-mentioned foil gauge To the angle with the stress in cross-sectional direction, the projection be 90 degree two mounting holes center line in the positioning plate quilt When being fixed on the steel-pipe pile, projection is parallel to each other with the axial direction of the steel-pipe pile and vertical respectively.
Preferably, projection of shape of the mounting hole on the projection plane is rectangle, the shape in the test position fix hole Shape is circle, and the extended line of a rectangle at least rectangular edges may make up the tangent line in corresponding test position fix hole.With The distance between foil gauge and test position fix hole are measured convenient for staff.
Preferably, the positioning plate is arc panel, and the surface of each locating piece offers graduation mark, and the graduation mark with The extended line is coplanar.Thus staff can pass through the correspondence on graduation mark after foil gauge is fixed on mounting hole Numerical value accurately knows the surface distance between the center of foil gauge and test position fix hole center on the locating piece, so as to In subsequent calculating.
Preferably, the N is equal to 3, and two of them positioning plate is symmetrically set using the center of the steel-pipe pile as symmetrical centre It sets, and the perpendicular bisector of the connecting line between two opposite location holes passes through the center of the location hole of another positioning plate.With full The needs of sufficient steel-pipe pile blind hole stress test.
Preferably, the curved rod that the fixation kit is connected with each positioning plate respectively by M is constituted, and the song of each curved rod The curvature at the fitting position on the corresponding steel-pipe pile of rate is identical;Wherein, M is positive integer greater than 1, and an at least arc Bar is dismountable.Thus preferably positioning plate can be firmly fixed on steel-pipe pile by curved rod, and with its steel Tubular pole is bonded, and is dismountable due to wherein at least there is a curved rod, thus staff can be convenient for harbour steel Tubular pole is mounted on steel-pipe pile with test fixture, or is dismantled to it.
Preferably, the curved rod is the curved rod main body of two parallel side-by-sides, a successively equidistant arrangement setting of J in two arcs Connector between shape bar main body is constituted.It may make curved rod when steel-pipe pile is perforated and generates vibration, be not likely to produce deformation, To guarantee the measuring accuracy of each foil gauge on positioning plate, wherein J is the positive integer greater than 1.
Preferably, the M is equal to 2N, and the plane that each curved rod is constituted using the center line of each positioning plate is symmetrical as the plane of symmetry Setting.So that each curved rod is when steel-pipe pile carries out punching test, stress is more uniformly not likely to produce sliding, in turn Improve the integrally-built stability of steel pipe piles at wharf test fixture.
Detailed description of the invention
By reading a detailed description of non-restrictive embodiments in the light of the attached drawings below, of the invention other Feature, objects and advantages will become more apparent upon:
Fig. 1 is the assembling schematic diagram of the steel pipe piles at wharf test fixture of first embodiment of the invention;
Fig. 2 is the structural schematic diagram of the body member of the positioning plate of first embodiment of the invention;
Fig. 3 is the top view of the locating piece of first embodiment of the invention;
Fig. 4 is the top view of the locating piece of second embodiment of the invention.
Specific embodiment
Technical solution in order to enable those skilled in the art to better understand the present invention, below in conjunction with of the invention real The attached drawing in example is applied, technical scheme in the embodiment of the invention is clearly and completely described, it is clear that described implementation Example is only a part of the embodiment of the present invention, instead of all the embodiments.Based on the embodiments of the present invention, this field is common Technical staff's every other embodiment obtained without making creative work, all should belong to protection of the present invention Range.
Present invention is further described in detail with reference to the accompanying drawing.
As depicted in figs. 1 and 2, a kind of steel pipe piles at wharf that the first embodiment of the present invention provides is filled with test position fix It sets, is applied to stake on steel-pipe pile 1.The positioning device is mainly connected by multiple positioning plates 2, with each positioning plate 2 and for will be each fixed The fixation kit that position plate 2 is fixed on steel-pipe pile 1 is constituted, wherein each positioning plate 2 at least has an inner concave, and offers One for carrying out the test position fix hole 3 of positioning drilling.
Wherein, when each positioning plate 2 is after being fixed on steel-pipe pile 1, and the stake circumferential surface of inner concave and steel-pipe pile 1 is affixed It closes, and the center in each test position fix hole 3 is respectively positioned on same plane, and the plane is perpendicular to the axial direction of steel-pipe pile 1.And it needs to illustrate , in the present embodiment, preferably, the number of positioning plate 2 is 3, also, two of them positioning plate 2 is with steel-pipe pile 1 Center be symmetrical arranged for symmetrical centre, and the perpendicular bisector of the connecting line between two opposite test position fix holes 3 is by another The center in the test position fix hole 3 of a positioning plate 2, to meet the needs of 1 blind hole stress test of steel-pipe pile.
In summary, in practical set, by the steel pipe piles at wharf test fixture, consolidate by each positioning plate 2 It is scheduled on steel-pipe pile 1, and after the stake circumferential surface of its inner concave and steel-pipe pile 1 is fitted, each test position fix hole 3 can be realized Center is respectively positioned in the plane perpendicular to 1 axial direction of steel-pipe pile, so as to facilitate staff according to the position in each test position fix hole 3 Foil gauge is pasted on steel-pipe pile 1, to prevent from not causing measurement to be tied due in same level because of the center in each test position fix hole 3 There is deviation in fruit, and then improves the precision of pile foundation blind hole stress test.Also, it is filled by the steel pipe piles at wharf with test position fix After the section that setting can choose on the steel-pipe pile 1 to same specification carries out drilling and blind hole stress test, can quickly it choose In addition a section carries out blind hole stress test and improves work efficiency to greatly save the time.
Specifically, in the present embodiment, in order to meet the design in practical application, processing and assembly demand, such as Fig. 2 and figure Shown in 3, above-mentioned positioning plate 2 be by with hollow-out parts 8 body member 21, be arranged in hollow-out parts 8 and with body member 21 it is detachable The locating piece 22 of connection is constituted.Wherein, above-mentioned test position fix hole 3 is provided on corresponding locating piece 22.
Also, as shown in figure 3, at least part is using the center in its test position fix hole 3 as coordinate original on above-mentioned locating piece 22 Point, and the holding section 23 extended to form is outwardly protruded along its vertical and horizontal.The edge of the hollow-out parts 8 of body member 21 is useful In the card slot (not indicated in figure) for accommodating holding section 23.To pass through the mutual cooperation of holding section 23 and card slot, work can be facilitated Personnel carry out quick assembly and disassembly to locating piece 22 and body member 21, to meet different testing requirements, i.e., in same rule Different types of locating piece 22, the different positioning of the diameter in the test position fix hole 3 such as opened up are assembled on the body member 21 of lattice Part 22.Simultaneously as holding section 23 is extended to form along the longitudinal direction and projecting axially outward in the test position fix hole 3 of locating piece 22, Thus also it can play the role of a positioning to the installation site of subsequent foil gauge by the setting direction of holding section 23.Wherein, In the present embodiment, it preferably, as shown in figure 3, the number of holding section 23 is four, and is oppositely arranged, meanwhile, relatively Two holding sections 23 between the line of centres when locating piece 22 is bonded with steel-pipe pile 1, be parallel to each other with the axial direction of steel-pipe pile 1 Or it is vertical.
It is noted that in the present embodiment, preferably, above-mentioned locating piece 22 and body member 21 are before being cut It is integrally formed.So as to which production cost can be greatly reduced, economize on resources.Also, positioning plate 2 is arc panel, and on arc panel Inner concave is arc-shaped curved surface.Obviously, in the present embodiment, locating piece 22 is also possible to individually designed and manufacture, similarly, engaging Portion 23 can be made of the individually designed projection piece on locating piece 22, and present embodiment does not make this specifically to limit and say It is bright.
In addition, in the present embodiment, preferably, the line of centres between above-mentioned two opposite holding sections 23 is distinguished It is overlapped with the center line of locating piece 22, also, the center of locating piece 22 is overlapped with the center of positioning plate 2, so that blind in progress When the stress test of hole, the stress in all directions of locating piece 22 is more uniform, and is not easy to be shaken to fall.
As shown in figure 3, in order to further staff is convenient for install foil gauge on steel-pipe pile 1, and working efficiency is improved, It offers multiple mounting holes 9 in the present embodiment on locating piece 22, is answered for installing suffered stress when detection steel-pipe pile 1 is perforated Become piece, and the center line of the mounting hole 9 of each locating piece 22 and the center line in its test position fix hole 3 are in corresponding projection plane On projection be located at same straight line.
It follows that due to offering the mounting hole 9 for installing foil gauge on locating piece 22, so that staff Without dismantling positioning plate 2, foil gauge can be mounted on to steel-pipe pile 1, and due to the center line of mounting hole 9 and each test position fix The center in hole 3 is located at same straight line, so that the Impact direction of adaptability to changes and steel-pipe pile 1 are carried out by test position fix hole 3 The stress direction being subject to when punching is consistent, to promote the measuring accuracy of foil gauge.
In detail, in the present embodiment, preferably, the quantity of above-mentioned mounting hole 9 is 3, also, adjacent two Angle of the center line of mounting hole 9 between the projection on above-mentioned projection plane is followed successively by 90 degree, 135 degree, 135 degree, to meet Calculating demand when blind hole stress test is carried out to steel-pipe pile 1, without measuring to the setting angle between foil gauge and It calculates, so as to avoid the error generated by manual operation.
Meanwhile in order to enable at least there are two be the axial direction for testing steel-pipe pile 1 when being perforated in above-mentioned foil gauge It is fixed on the center line of the stress in cross-sectional direction, two mounting holes that the angle of above-mentioned projection is 90 degree in positioning plate When on steel-pipe pile, projection is parallel to each other with the axial direction of steel-pipe pile and vertical respectively, in order to the Stress calculation in practical application And testing requirement.As shown in figure 3, for the design in further satisfaction practical application and assembling demand, the angle of projection is The center line of 90 degree of two mounting holes can the line of centres respectively between corresponding two holding sections 23 it is coplanar.
In addition, in order to further staff is convenient for be accurately positioned and measure the installation site of foil gauge, it is each fixed The center of each mounting hole on the part 22 of position is equal to the distance between the center in its corresponding test position fix hole 3.
Also, in the present embodiment, preferably, projection of shape of each mounting hole 9 on above-mentioned projection plane is square Shape, the shape in each test position fix hole 3 are circle, and the extended line of a rectangle at least rectangular edges may make up it is corresponding The tangent line in test position fix hole 3.In order to which staff measures the distance between foil gauge and test position fix hole 3.
In addition, it is necessary to explanation, as depicted in figs. 1 and 2, preferably, above-mentioned fixation kit can be by multiple difference The curved rod 4 that is connected with each positioning plate 2 is constituted, and the fitting position on the corresponding steel-pipe pile 1 of curvature of each curved rod 4 Curvature is identical, wherein at least a curved rod 4 is dismountable, as at least one section is arranged to knot that can be undone by a pull in the curved rod 4 (not indicated in figure) connection.
It follows that since the curvature at the fitting position on the corresponding steel-pipe pile 1 of the curvature of each curved rod 4 is identical, Preferably positioning plate 2 can be thus firmly fixed on steel-pipe pile 1 by curved rod 4, and be pasted with its steel-pipe pile 1 It closes, and is dismountable due to wherein at least there is a curved rod 4, thus can test steel pipe piles at wharf convenient for staff Positioning device is mounted on steel-pipe pile 1, or dismantles to it.
In detail, above-mentioned curved rod 4 is mainly set by the curved rod main body 41 of two parallel side-by-sides, multiple successively equidistant arrangements It sets connector 42 between two curved rod main bodys 41 to constitute, wherein in the present embodiment, can be with as preferred connector 42 It is made of the cylindrical member welded with curved rod main body 41, such as short muscle.
It follows that may make curved rod 4 when steel-pipe pile 1 is perforated and generates vibration by this structure, being not easy to produce Change shape, to guarantee the measuring accuracy of each foil gauge on positioning plate 2.
Also, in the present embodiment, preferably, the quantity of curved rod 4 is twice of 2 quantity of positioning plate, also, it is each Curved rod 4 is symmetrical arranged using the plane that the center line of each positioning plate 2 is constituted as the plane of symmetry.So that each curved rod 4 is in steel pipe When stake 1 carries out punching test, stress is more uniformly not likely to produce sliding, and then improves steel pipe piles at wharf test position fix The integrally-built stability of device.
In addition, being worth one to say, one end that each curved rod 4 is connected with each positioning plate 2 (is not marked by articulation piece in figure Show) it is connected, so that each curved rod 4 be free to be rotated, convenient for staff to steel pipe piles at wharf test position fix Device is folded and is carried.Also, with this configuration, staff also may make to be finely adjusted the elasticity of curved rod 4, To meet the needs of practical set.
Furthermore, it is desirable to which explanation, in this example, above-mentioned fixation kit can also be realized by components such as lantern rings and be positioned Fixation and fitting of the plate on steel-pipe pile, therefore, the present embodiment can also be made of fixation kit which component not to be made More illustration and description.
The second embodiment of the present invention provides a kind of steel pipe piles at wharf test fixture, and of the invention second implements Example is the further improvement to the first embodiment of the present invention, it is improved in that as shown in figure 4, of the invention second In embodiment, the surface of each locating piece 22 offers graduation mark 5, and the graduation mark 5 is coplanar with above-mentioned extended line.
It follows that by offering graduation mark 5 on locating piece 22, thus foil gauge is being fixed on installation by staff After on hole 9, can by the correspondence numerical value on graduation mark 5, the center for knowing foil gauge and 3 center of test position fix hole of preparation it Between distance, in order to subsequent calculating.
Also, being worth mentioning is, above-mentioned locating piece 22 is integrally formed with body member 21, therefore, in the present embodiment, positioning Part 22 is arc panel, thus graduation mark 5 is the graduation mark 5 of arc.
Also, in the present embodiment, preferably, the width of above-mentioned rectangle is equal to the straight of corresponding test position fix hole 3 Diameter size, in order to which staff can select the suitable long fitting foil gauge of arc side on mounting hole, and protect according to practical situation Projection of the card foil gauge at least on one side with arc side length coincides.
It is obvious to a person skilled in the art that invention is not limited to the details of the above exemplary embodiments, Er Qie In the case where without departing substantially from spirit or essential attributes of the invention, the present invention can be realized in other specific forms.Therefore, no matter From the point of view of which point, the present embodiments are to be considered as illustrative and not restrictive, and the scope of the present invention is by appended power Benefit requires rather than above description limits, it is intended that all by what is fallen within the meaning and scope of the equivalent elements of the claims Variation is included in the present invention.Any reference signs in the claims should not be construed as limiting the involved claims.

Claims (10)

1. a kind of steel pipe piles at wharf test fixture is applied on steel-pipe pile, which is characterized in that the steel pipe piles at wharf is used Test fixture includes: N number of positioning plate, and the positioning plate at least has an inner concave, and offers a test position fix hole;
The fixation kit for being connected with each positioning plate and being used to be fixed on each positioning plate on the steel-pipe pile;
Wherein, the N is the positive integer greater than 1, and when each positioning plate is fixed on the steel-pipe pile by the fixation kit Afterwards, the stake circumferential surface of inner concave and the steel-pipe pile fits, and the center in each test position fix hole is respectively positioned on same plane, and institute Plane is stated perpendicular to the axial direction of the steel-pipe pile.
2. steel pipe piles at wharf test fixture according to claim 1, which is characterized in that the positioning plate includes: Body member with hollow-out parts, the locating piece for being arranged in the hollow-out parts and being detachably connected with the body member;
Wherein, the test position fix hole is provided on corresponding locating piece.
3. steel pipe piles at wharf test fixture according to claim 2, which is characterized in that on the locating piece at least There is part using the center in its test position fix hole as coordinate origin, and outwardly protrudes the engaging extended to form along its vertical and horizontal Portion;
The edge of the hollow-out parts of the body member has the card slot for accommodating the holding section.
4. steel pipe piles at wharf test fixture according to claim 3, which is characterized in that the locating piece with it is described Body member is being cut preceding integrated molding.
5. the steel pipe piles at wharf test fixture according to any one of claim 2-4, which is characterized in that described Locating piece at least offers K mounting hole, for installing the foil gauge for detecting steel-pipe pile suffered stress when being perforated, and Projection of the center in the center line of the mounting hole of each locating piece and its test position fix hole on corresponding projection plane is located at Same straight line;Wherein, K is positive integer.
6. steel pipe piles at wharf test fixture according to claim 5, which is characterized in that the K is 3, and every phase Angle of the center line of two adjacent mounting holes between the projection on the projection plane is followed successively by 90 degree, 135 degree, 135 degree.
7. steel pipe piles at wharf test fixture according to claim 6, which is characterized in that the angle of the projection is The center line of 90 degree of two mounting holes when the positioning plate is fixed on the steel-pipe pile, projection respectively with the steel The axial direction of tubular pole is parallel to each other and vertically.
8. steel pipe piles at wharf test fixture according to claim 6, which is characterized in that the mounting hole is described Projection of shape on projection plane is rectangle, and the shape in the test position fix hole is round, and a rectangle at least rectangle The extended line on side may make up the tangent line in corresponding test position fix hole.
9. steel pipe piles at wharf test fixture according to claim 1, which is characterized in that the N is equal to 3, and its In two positioning plates be symmetrical arranged by symmetrical centre of the center of the steel-pipe pile, and between two opposite test position fix holes The center that the perpendicular bisector of connecting line passes through the test position fix hole of another positioning plate.
10. steel pipe piles at wharf test fixture according to claim 1, which is characterized in that the fixation kit is by M A curved rod for being connected respectively with each positioning plate is constituted, and the fitting position on the corresponding steel-pipe pile of curvature of each curved rod Curvature it is identical;
Wherein, M is the positive integer greater than 1, and at least a curved rod is dismountable.
CN201710138823.4A 2017-03-09 2017-03-09 Steel pipe piles at wharf test fixture Active CN106930333B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710138823.4A CN106930333B (en) 2017-03-09 2017-03-09 Steel pipe piles at wharf test fixture

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710138823.4A CN106930333B (en) 2017-03-09 2017-03-09 Steel pipe piles at wharf test fixture

Publications (2)

Publication Number Publication Date
CN106930333A CN106930333A (en) 2017-07-07
CN106930333B true CN106930333B (en) 2019-03-29

Family

ID=59432970

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710138823.4A Active CN106930333B (en) 2017-03-09 2017-03-09 Steel pipe piles at wharf test fixture

Country Status (1)

Country Link
CN (1) CN106930333B (en)

Families Citing this family (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108532651A (en) * 2018-04-19 2018-09-14 东南大学 The device of frictional resistance inside and outside a kind of detection steel-pipe pile
CN110158672B (en) * 2019-06-05 2021-04-20 江苏省第二地质工程勘察院 Method for mounting foundation pile high-strain stress sensor

Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2008286679A (en) * 2007-05-18 2008-11-27 Japan Pile Corp Dynamic horizontal loading test method, and dynamic horizontal loading test device for pile
CN205561839U (en) * 2015-12-29 2016-09-07 江苏瑞沃建设集团有限公司 Steel protects a section of thick bamboo or prism positioner that uses of steel -pipe pile

Patent Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2008286679A (en) * 2007-05-18 2008-11-27 Japan Pile Corp Dynamic horizontal loading test method, and dynamic horizontal loading test device for pile
CN205561839U (en) * 2015-12-29 2016-09-07 江苏瑞沃建设集团有限公司 Steel protects a section of thick bamboo or prism positioner that uses of steel -pipe pile

Also Published As

Publication number Publication date
CN106930333A (en) 2017-07-07

Similar Documents

Publication Publication Date Title
CN101915558B (en) Geometric linear detection method of bridge member
CN106930333B (en) Steel pipe piles at wharf test fixture
CN201434755Y (en) Measuring device for structural deflection increment
CN201909599U (en) Direct-reading type plate thickness tester
CN210154486U (en) Height difference measuring device
CN204142246U (en) A kind of guiding ruler gradient measurer
KR101306307B1 (en) Clinometer apparatus
CN102680667A (en) Concrete early-age crack resistance testing device capable of directly determining cracking position
CN109386298A (en) A kind of prefabricated tunnel steel arch frame with monitoring device
CN107905108B (en) Tubular arch bolted web member hole group's accuracy control method
CN209027523U (en) A kind of prestress pipe coordinate location ruler
CN106767314B (en) Large and medium-sized casting hole position detection tool
CN201983745U (en) Angle measurement instrument
CN202002600U (en) Inspection protractor
CN205642267U (en) Plastic corrugated pipe internal diameter warp measuring device
CN205300593U (en) Automatic keep vertically engineering survey sighting rod
CN210513117U (en) Pole gradient measuring tool
TWI359223B (en)
CN209214486U (en) A kind of high tool of section survey based on rail level
CN209469445U (en) A kind of prefabricated tunnel steel arch frame with monitoring device
CN207832093U (en) A kind of bar spacing aligner
CN203758513U (en) Conversion device for different reflecting prisms on pier
CN205669980U (en) A kind of row pitch checking tool
CN209745143U (en) measuring scale for improving installation precision of prestressed pipeline of prefabricated box girder
CN204036422U (en) The assembled frock of marking time in column crane mast section

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
TA01 Transfer of patent application right

Effective date of registration: 20170628

Address after: 200030 No. 139, Xuhui District, Shanghai, Pingjiang Road

Applicant after: China Construction Third Engineering Division Co., Ltd.

Applicant after: Shanghai Third Harbor Engineering Science Technology Research Institute Co., Ltd., China Communications Construction Group

Applicant after: CCCC Shanghai Harbour Engineering Design & Research Institute Co., Ltd.

Address before: 200030, 829 Jia Jia Road, Shanghai, Xuhui District

Applicant before: Shanghai Third Harbor Engineering Science Technology Research Institute Co., Ltd., China Communications Construction Group

Applicant before: CCCC Shanghai Harbour Engineering Design & Research Institute Co., Ltd.

TA01 Transfer of patent application right
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant