CN209027523U - A prestressed pipeline coordinate positioning ruler - Google Patents
A prestressed pipeline coordinate positioning ruler Download PDFInfo
- Publication number
- CN209027523U CN209027523U CN201822000540.6U CN201822000540U CN209027523U CN 209027523 U CN209027523 U CN 209027523U CN 201822000540 U CN201822000540 U CN 201822000540U CN 209027523 U CN209027523 U CN 209027523U
- Authority
- CN
- China
- Prior art keywords
- ruler
- construction
- detection
- coordinate positioning
- positioning
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
- 238000010276 construction Methods 0.000 claims abstract description 100
- 238000001514 detection method Methods 0.000 claims abstract description 76
- 229910000831 Steel Inorganic materials 0.000 claims abstract description 53
- 239000010959 steel Substances 0.000 claims abstract description 53
- 238000009434 installation Methods 0.000 abstract description 9
- 238000000034 method Methods 0.000 abstract description 8
- NJPPVKZQTLUDBO-UHFFFAOYSA-N novaluron Chemical compound C1=C(Cl)C(OC(F)(F)C(OC(F)(F)F)F)=CC=C1NC(=O)NC(=O)C1=C(F)C=CC=C1F NJPPVKZQTLUDBO-UHFFFAOYSA-N 0.000 abstract 4
- 125000006850 spacer group Chemical group 0.000 abstract 1
- 230000001788 irregular Effects 0.000 description 4
- 238000005336 cracking Methods 0.000 description 2
- 238000013461 design Methods 0.000 description 2
- 230000000694 effects Effects 0.000 description 2
- 238000004873 anchoring Methods 0.000 description 1
- 239000004567 concrete Substances 0.000 description 1
- 238000011161 development Methods 0.000 description 1
- 238000010586 diagram Methods 0.000 description 1
- 238000005516 engineering process Methods 0.000 description 1
- 238000007689 inspection Methods 0.000 description 1
- 238000011900 installation process Methods 0.000 description 1
- 239000000463 material Substances 0.000 description 1
- 238000005259 measurement Methods 0.000 description 1
- 238000012986 modification Methods 0.000 description 1
- 230000004048 modification Effects 0.000 description 1
- 239000011513 prestressed concrete Substances 0.000 description 1
- 230000000750 progressive effect Effects 0.000 description 1
Landscapes
- A Measuring Device Byusing Mechanical Method (AREA)
Abstract
Description
技术领域technical field
本实用新型涉及预应力工程检测技术领域,更具体的说是涉及一种预应力管道坐标定位尺。The utility model relates to the technical field of prestressed engineering detection, in particular to a prestressed pipeline coordinate positioning ruler.
背景技术Background technique
近年来,预应力混凝土结构由于具有充分利用材料的高强度性能,能够有效防止混凝土裂缝、减轻结构自重,增大桥梁跨径,刚度大,行车舒适等优点,在公路桥梁上得到普遍的应用。In recent years, prestressed concrete structures have been widely used in highway bridges due to their advantages of fully utilizing the high-strength properties of materials, effectively preventing concrete cracks, reducing the weight of the structure, increasing the bridge span, high rigidity, and driving comfort.
而桥梁预应力的准确定位是桥梁构造设计与施工的重要组成部分,如果在施工过程中存在预应力管道定位不准确的现象,往往导致梁体存在较大的安全隐患,甚至有可能降低梁体的整体安全性与使用年限。The accurate positioning of bridge prestress is an important part of bridge structural design and construction. If there is inaccurate positioning of prestressed pipes during the construction process, it will often lead to greater safety hazards in the beam body, and may even reduce the beam body. overall safety and service life.
目前,预应力工程主要应用有预应力桥梁和预应力梁板,随着设计和施工的不断发展,其检测技术也颇受重视,而施工过程中预应力管道定位不准确会引起梁体开裂、锚固端崩裂、跨中挠度过大等安全、质量隐患。At present, prestressed engineering is mainly used for prestressed bridges and prestressed beams and slabs. With the continuous development of design and construction, its detection technology has also received considerable attention. Inaccurate positioning of prestressed pipes during construction will cause beam cracking, Safety and quality hidden dangers such as cracking of the anchoring end and excessive mid-span deflection.
并且,施工场地往往错综复杂,且在施工过程中往往需要密布大量钢筋,由于受到施工场地和复杂工程结构的制约,所以给安设预应力工程管道的工作带来极大不便,致使工作效率低下,同时导致工人们仅仅凭借工作经验来定位和检测预应力工程管道的安装位置,使施工误差较大。In addition, the construction site is often intricate, and a large number of steel bars are often densely covered during the construction process. Due to the constraints of the construction site and the complex engineering structure, it brings great inconvenience to the installation of prestressed engineering pipelines, resulting in low work efficiency. At the same time, the workers only rely on their work experience to locate and detect the installation position of the prestressed engineering pipeline, which makes the construction error larger.
因此,如何提供一种准确定位预应力工程管道,同时方便管理人员检测预应力工程管道位置坐标值的工程坐标定位尺是本领域技术人员亟需解决的问题。Therefore, how to provide an engineering coordinate locating ruler that accurately locates the prestressed engineering pipeline and at the same time facilitates the management personnel to detect the position coordinate value of the prestressed engineering pipeline is an urgent problem to be solved by those skilled in the art.
实用新型内容Utility model content
有鉴于此,本实用新型提供了一种预应力管道坐标定位尺,不仅能够准确定位预应力工程管道,而且方便管理人员检测预应力工程管道位置坐标值,减少操作不规范引起的质量问题,提升安装质量,同时本实用新型的工程坐标定位尺结构简单,携带方便,使用方法简单方便。In view of this, the present utility model provides a prestressed pipeline coordinate positioning ruler, which can not only accurately locate the prestressed engineering pipeline, but also facilitate the management personnel to detect the position coordinate value of the prestressed engineering pipeline, reduce the quality problems caused by irregular operation, and improve the performance of the prestressed engineering pipeline. The installation quality is high, and the engineering coordinate positioning ruler of the utility model is simple in structure, convenient to carry, and simple and convenient to use.
为了实现上述目的,本实用新型采用如下技术方案:In order to achieve the above purpose, the utility model adopts the following technical solutions:
一种预应力管道坐标定位尺,包括施工坐标定位尺和检测坐标定位尺,从而本实用新型通过所述施工坐标定位尺定位预应力工程管道,提高预应力工程管道安装的准确度,并通过所述检测坐标定位尺检测预应力工程管道位置坐标值,方便了管理人员检测预应力工程管道位置坐标值,减少操作不规范引起的质量问题,提升安装质量;A prestressed pipeline coordinate positioning ruler includes a construction coordinate positioning ruler and a detection coordinate positioning ruler, so that the utility model locates the prestressed engineering pipeline through the construction coordinate positioning ruler, improves the installation accuracy of the prestressed engineering pipeline, and passes all the prestressed engineering pipelines. The above-mentioned detection coordinate positioning ruler detects the position coordinate value of the prestressed engineering pipeline, which is convenient for the management personnel to detect the position coordinate value of the prestressed engineering pipeline, reduces the quality problems caused by the irregular operation, and improves the installation quality;
其中,所述施工坐标定位尺包括施工主尺和施工水平底座,所述施工主尺垂直设置在所述施工水平底座上,且所述施工主尺上开设有多个定位孔,所述定位孔匹配连接定位钢筋,从而不仅使本实用新型结构简单,便于携带,而且使本实用新型能够将所述施工水平底座插入钢筋网底座中,保证所述施工坐标定位尺水平稳定,而预应力工程管道设置在钢筋网中,将所述定位钢筋与所述定位孔匹配连接,并将所述预应力工程管道按压在所述定位钢筋上,便能够在所述施工主尺上准确读出所述预应力工程管道的施工位置刻度值;Wherein, the construction coordinate positioning ruler includes a construction master ruler and a construction horizontal base, the construction master ruler is vertically arranged on the construction horizontal base, and a plurality of positioning holes are opened on the construction master ruler, and the positioning holes Matching and connecting the positioning steel bars not only makes the utility model simple in structure and easy to carry, but also enables the utility model to insert the construction level base into the steel mesh base to ensure that the construction coordinate positioning ruler is horizontally stable, and the prestressed engineering pipes Set in the steel mesh, match the positioning steel bar with the positioning hole, and press the prestressed engineering pipeline on the positioning steel bar, so that the prestressed construction can be accurately read on the construction master ruler. The scale value of the construction position of the stress engineering pipeline;
所述检测坐标定位尺包括检测主尺和检测水平底座,所述检测主尺垂直设置在所述检测水平底座上,且所述检测主尺上开设有多个限位卡槽,所述限位卡槽匹配连接钢尺,从而不仅使本实用新型结构简单,便于携带,而且使本实用新型能够将所述检测水平底座插入钢筋网底座中,保证所述检测坐标定位尺水平稳定,且将所述钢尺与所述限位卡槽匹配连接,使所述钢尺匹配连接在所述施工位置刻度值所对应的所述限位卡槽中,从而本实用新型只要对照所述钢尺与所述预应力工程管道底部位置之间的差值大小,便能准确快速检测出所述预应力工程管道定位是否符合规范要求。The detection coordinate positioning ruler includes a detection main ruler and a detection horizontal base, the detection main ruler is vertically arranged on the detection horizontal base, and a plurality of limit slots are opened on the detection main ruler, and the limit The card slot is matched to connect the steel ruler, so that the utility model not only has a simple structure and is easy to carry, but also enables the utility model to insert the detection level base into the steel mesh base, so as to ensure that the detection coordinate positioning ruler is horizontally stable, and all the The steel ruler is matched and connected with the limit slot, so that the steel ruler is matched and connected in the limit slot corresponding to the scale value of the construction position, so that the utility model only needs to compare the steel ruler with the limit slot. By determining the difference between the bottom positions of the prestressed engineering pipeline, it can be accurately and quickly detected whether the positioning of the prestressed engineering pipeline meets the requirements of the specification.
优选的,所述施工坐标定位尺和所述检测坐标定位尺的结构和大小均相同,保证了定位所述预应力工程管道和检测所述预应力工程管道在同一标准下进行,有效提高了安装所述预应力工程管道的准确性。Preferably, the structure and size of the construction coordinate positioning ruler and the detection coordinate positioning ruler are the same, which ensures that the positioning of the prestressed engineering pipeline and the detection of the prestressed engineering pipeline are carried out under the same standard, which effectively improves the installation process. The accuracy of the prestressed engineering piping.
优选的,所述施工主尺和所述检测主尺上均设置有相同的刻度线,从而使所述施工主尺和所述检测主尺的刻度线具有统一刻度标准,使限位卡槽所对应的刻度值能够准确对应通过所述定位孔所获得的所述预应力工程管道施工位置刻度值,保证了定位所述预应力工程管道和检测所述预应力工程管道在同一标准下进行,有效提高了安装所述预应力工程管道的准确性。Preferably, the construction master ruler and the detection master ruler are both provided with the same scale line, so that the scale lines of the construction master ruler and the detection master ruler have a unified scale standard, so that the limit slot is The corresponding scale value can accurately correspond to the scale value of the construction position of the prestressed engineering pipeline obtained through the positioning hole, which ensures that the positioning of the prestressed engineering pipeline and the detection of the prestressed engineering pipeline are carried out under the same standard, which is effective. The accuracy of installing the prestressed engineering pipeline is improved.
优选的,所述施工水平底座包括两个垂直连接的施工支板,且两个所述施工支板均与所述施工主尺垂直连接,从而能够使所述施工水平底座能够完全插入至所述钢筋网底座中,使所述施工主尺与所述预应力工程管道的轴线垂直,从而通过所述施工主尺准确读取所述预应力工程管道的施工位置刻度值。Preferably, the construction horizontal base includes two vertically connected construction support plates, and both of the construction support plates are vertically connected with the construction master ruler, so that the construction horizontal base can be completely inserted into the In the steel mesh base, the construction master ruler is perpendicular to the axis of the prestressed engineering pipeline, so that the construction position scale value of the prestressed engineering pipeline can be accurately read through the construction master ruler.
优选的,所述检测水平底座包括两个垂直连接的检测支板,且两个所述检测支板均与所述检测主尺垂直连接,从而能够使所述检测水平底座能够完全插入至所述钢筋网底座中,使所述检测主尺与所述预应力工程管道的轴线垂直,从而通过所述检测主尺准确读出所述预应力工程管道的施工位置刻度值与所述预应力工程管道实际高度的差值,实现准确快速检测所述预应力工程管道定位是否符合规范要求的效果。Preferably, the detection level base includes two vertically connected detection support plates, and both of the detection support plates are vertically connected with the detection main ruler, so that the detection level base can be completely inserted into the detection level. In the steel mesh base, the main detection ruler is perpendicular to the axis of the prestressed engineering pipeline, so that the construction position scale value of the prestressed engineering pipeline and the prestressed engineering pipeline can be accurately read through the detection main ruler. The difference of the actual height achieves the effect of accurately and quickly detecting whether the positioning of the prestressed engineering pipeline meets the requirements of the specification.
优选的,所述定位钢筋可拆卸贯穿在所述定位孔中,一方面实现将所述预应力工程管道按压在所述定位钢筋上,便可以通过所述定位孔对应的刻度值来准确获得所述预应力工程管道施工位置刻度值的效果;另一方面,方便使所述定位钢筋匹配不同的所述定位孔,从而根据所述预应力工程管道施工位置的改变灵活准确调整所读取的所述预应力工程管道施工位置刻度值。Preferably, the positioning steel bar can be detachably penetrated through the positioning hole. On the one hand, the prestressed engineering pipeline can be pressed on the positioning steel bar, and the calibration value corresponding to the positioning hole can be used to accurately obtain the On the other hand, it is convenient to match the positioning steel bars with different positioning holes, so as to flexibly and accurately adjust the read data according to the change of the construction position of the prestressed engineering pipeline. The scale value of the construction position of the prestressed engineering pipeline.
优选的,所述钢尺可拆卸穿设在所述限位卡槽中,一方面方便所述钢尺穿过所述限位卡槽延伸至所述预应力工程管道底端,从而准确检测出所述预应力工程管道的施工位置刻度值与所述预应力工程管道实际高度的差值;另一方面,方便使所述钢尺匹配不同的所述限位卡槽,从而能够高效测量不同所述预应力工程管道的施工位置刻度值与所述预应力工程管道实际高度的差值,缩短整个工程的测量时间。Preferably, the steel ruler is detachably mounted in the limit slot, on the one hand, it is convenient for the steel ruler to extend through the limit slot to the bottom end of the prestressed engineering pipeline, so as to accurately detect The difference between the scale value of the construction position of the prestressed engineering pipeline and the actual height of the prestressed engineering pipeline; The difference between the scale value of the construction position of the prestressed engineering pipeline and the actual height of the prestressed engineering pipeline can shorten the measurement time of the entire project.
经由上述的技术方案可知,与现有技术相比,本实用新型公开提供了一种预应力管道坐标定位尺,可以实现如下技术效果:As can be seen from the above technical solutions, compared with the prior art, the present utility model discloses a prestressed pipeline coordinate positioning ruler, which can achieve the following technical effects:
①本实用新型包括施工坐标定位尺和检测坐标定位尺,从而本实用新型通过施工坐标定位尺定位预应力工程管道,提高预应力工程管道安装的准确度,并通过检测坐标定位尺检测预应力工程管道位置坐标值,方便了管理人员检测预应力工程管道位置坐标值,减少操作不规范引起的质量问题,提升安装质量①The utility model includes a construction coordinate positioning ruler and a detection coordinate positioning ruler, so that the utility model locates the prestressed engineering pipeline through the construction coordinate positioning ruler, improves the installation accuracy of the prestressed engineering pipeline, and detects the prestressed engineering pipe through the detection coordinate positioning ruler. The coordinate value of the pipeline position is convenient for the management personnel to detect the coordinate value of the pipeline position of the prestressed engineering, reduce the quality problems caused by the irregular operation, and improve the installation quality
②本实用新型的施工坐标定位尺包括施工主尺和施工水平底座,施工主尺垂直设置在施工水平底座上,且施工主尺上开设有多个定位孔,定位孔匹配连接定位钢筋,从而不仅使本实用新型结构简单,便于携带,而且使本实用新型能够将施工水平底座插入钢筋网底座中,保证施工坐标定位尺水平稳定,而预应力工程管道设置在钢筋网中,将定位钢筋与定位孔匹配连接,并将预应力工程管道按压在定位钢筋上,便能够在施工主尺上准确读出预应力工程管道的施工位置刻度值;② The construction coordinate positioning ruler of the present invention includes a construction master ruler and a construction horizontal base. The construction master ruler is vertically arranged on the construction horizontal base, and a plurality of positioning holes are opened on the construction master ruler. The positioning holes are matched to connect the positioning steel bars, thereby not only The utility model has a simple structure and is easy to carry, and the utility model can insert the construction level base into the steel mesh base to ensure the horizontal stability of the construction coordinate positioning ruler, and the prestressed engineering pipeline is arranged in the steel mesh, and the positioning steel bars and the positioning steel bars are arranged in the steel mesh. The holes are matched and connected, and the prestressed engineering pipeline is pressed on the positioning steel bar, so that the construction position scale value of the prestressed engineering pipeline can be accurately read on the construction master ruler;
③本实用新型的检测坐标定位尺包括检测主尺和检测水平底座,检测主尺垂直设置在检测水平底座上,且检测主尺上开设有多个限位卡槽,限位卡槽匹配连接钢尺,从而不仅使本实用新型结构简单,便于携带,而且使本实用新型能够将检测水平底座插入钢筋网底座中,保证检测坐标定位尺水平稳定,且将钢尺与限位卡槽匹配连接,使钢尺匹配连接在施工位置刻度值所对应的限位卡槽中,从而本实用新型只要对照钢尺与预应力工程管道底部位置之间的差值大小,便能准确快速检测出预应力工程管道定位是否符合规范要求。③ The detection coordinate positioning ruler of the present utility model includes a detection main ruler and a detection horizontal base, the detection main ruler is vertically arranged on the detection horizontal base, and a plurality of limit card slots are opened on the detection main ruler, and the limit card grooves are matched with the connecting steel. Therefore, the utility model not only has a simple structure and is easy to carry, but also enables the utility model to insert the detection level base into the steel mesh base, so as to ensure that the detection coordinate positioning ruler is horizontally stable, and the steel ruler is matched and connected with the limit slot. The steel ruler is matched and connected in the limit slot corresponding to the scale value of the construction position, so that the utility model can accurately and quickly detect the prestressed engineering as long as the difference between the steel ruler and the bottom position of the prestressed engineering pipeline is compared. Whether the pipe positioning meets the specification requirements.
附图说明Description of drawings
为了更清楚地说明本实用新型实施例或现有技术中的技术方案,下面将对实施例或现有技术描述中所需要使用的附图作简单地介绍,显而易见地,下面描述中的附图仅仅是本实用新型的实施例,对于本领域普通技术人员来讲,在不付出创造性劳动的前提下,还可以根据提供的附图获得其他的附图。In order to more clearly illustrate the embodiments of the present utility model or the technical solutions in the prior art, the following briefly introduces the accompanying drawings that need to be used in the description of the embodiments or the prior art. Obviously, the accompanying drawings in the following description It is only an embodiment of the present invention, and for those of ordinary skill in the art, other drawings can also be obtained according to the provided drawings without creative efforts.
图1附图为本实用新型一种预应力管道坐标定位尺的施工坐标定位尺的结构图;Fig. 1 accompanying drawing is the structural drawing of the construction coordinate positioning ruler of a kind of prestressed pipeline coordinate positioning ruler of the present utility model;
图2附图为本实用新型一种预应力管道坐标定位尺的检测坐标定位尺的结构图。The accompanying drawing of FIG. 2 is a structural diagram of a detection coordinate positioning ruler of a prestressed pipeline coordinate positioning ruler of the present invention.
具体实施方式Detailed ways
下面将结合本实用新型实施例中的附图,对本实用新型实施例中的技术方案进行清楚、完整地描述,显然,所描述的实施例仅仅是本实用新型一部分实施例,而不是全部的实施例。基于本实用新型中的实施例,本领域普通技术人员在没有做出创造性劳动前提下所获得的所有其他实施例,都属于本实用新型保护的范围。The technical solutions in the embodiments of the present utility model will be clearly and completely described below with reference to the accompanying drawings in the embodiments of the present utility model. Obviously, the described embodiments are only a part of the embodiments of the present utility model, rather than all the implementations. example. Based on the embodiments of the present invention, all other embodiments obtained by those of ordinary skill in the art without creative work fall within the protection scope of the present invention.
本实用新型提供了一种预应力管道坐标定位尺,不仅能够准确定位预应力工程管道,而且方便管理人员检测预应力工程管道位置坐标值,减少操作不规范引起的质量问题,提升安装质量,同时本实用新型的工程坐标定位尺结构简单,携带方便,使用方法简单方便。The utility model provides a prestressed pipeline coordinate positioning ruler, which can not only accurately locate the prestressed engineering pipeline, but also facilitates the management personnel to detect the position coordinate value of the prestressed engineering pipeline, reduces the quality problems caused by irregular operation, improves the installation quality, and at the same time The engineering coordinate positioning ruler of the utility model has the advantages of simple structure, convenient carrying and simple and convenient use method.
本实用新型实施例公开了一种预应力管道坐标定位尺,包括施工坐标定位尺和检测坐标定位尺;The embodiment of the utility model discloses a prestressed pipeline coordinate positioning ruler, which comprises a construction coordinate positioning ruler and a detection coordinate positioning ruler;
其中,施工坐标定位尺包括施工主尺1和施工水平底座2,施工主尺1垂直设置在施工水平底座2上,且施工主尺1上开设有多个定位孔11,定位孔11匹配连接定位钢筋111;Among them, the construction coordinate positioning ruler includes a construction master ruler 1 and a construction horizontal base 2. The construction master ruler 1 is vertically arranged on the construction horizontal base 2, and the construction master ruler 1 is provided with a plurality of positioning holes 11, and the positioning holes 11 are matched for connection and positioning steel bar 111;
检测坐标定位尺包括检测主尺3和检测水平底座4,检测主尺3垂直设置在检测水平底座4上,且检测主尺3上开设有多个限位卡槽31,限位卡槽31匹配连接钢尺121。The detection coordinate positioning ruler includes a detection main ruler 3 and a detection horizontal base 4. The detection main ruler 3 is vertically arranged on the detection horizontal base 4, and the detection main ruler 3 is provided with a plurality of limit slots 31, and the limit slots 31 match. Connect the steel ruler 121.
为了进一步优化上述技术方案,施工坐标定位尺和检测坐标定位尺的结构和大小均相同。In order to further optimize the above technical solution, the structure and size of the construction coordinate positioning ruler and the detection coordinate positioning ruler are the same.
为了进一步优化上述技术方案,施工主尺1和检测主尺3上均设置有相同的刻度线。In order to further optimize the above technical solution, the construction master ruler 1 and the inspection master ruler 3 are both provided with the same scale line.
为了进一步优化上述技术方案,施工水平底座2包括两个垂直连接的施工支板21,且两个施工支板21均与施工主尺1垂直连接。In order to further optimize the above technical solution, the construction horizontal base 2 includes two vertically connected construction support plates 21 , and both of the two construction support plates 21 are vertically connected with the construction master ruler 1 .
为了进一步优化上述技术方案,检测水平底座4包括两个垂直连接的检测支板41,且两个检测支板41均与检测主尺3垂直连接。In order to further optimize the above technical solution, the detection level base 4 includes two vertically connected detection support plates 41 , and both of the two detection support plates 41 are vertically connected with the detection main ruler 3 .
为了进一步优化上述技术方案,定位钢筋111可拆卸贯穿在定位孔11中。In order to further optimize the above technical solution, the positioning steel bar 111 is detachably penetrated through the positioning hole 11 .
为了进一步优化上述技术方案,钢尺121可拆卸穿设在限位卡槽12中。In order to further optimize the above technical solution, the steel ruler 121 is detachably inserted in the limit slot 12 .
实施例:Example:
结合说明书附图1-2,本实用新型实施例公开了一种预应力管道坐标定位尺,包括施工坐标定位尺和检测坐标定位尺,且施工坐标定位尺和检测坐标定位尺的结构和大小均相同;With reference to the accompanying drawings 1-2 of the specification, the embodiment of the present utility model discloses a prestressed pipeline coordinate positioning ruler, including a construction coordinate positioning ruler and a detection coordinate positioning ruler, and the construction coordinate positioning ruler and the detection coordinate positioning ruler are all of the same structure and size. same;
其中,施工坐标定位尺包括施工主尺1和施工水平底座2,施工主尺1垂直设置在施工水平底座2上,且施工主尺1上开设有多个定位孔11,定位孔11匹配连接定位钢筋111,定位钢筋111可拆卸贯穿在定位孔11中;Among them, the construction coordinate positioning ruler includes a construction master ruler 1 and a construction horizontal base 2. The construction master ruler 1 is vertically arranged on the construction horizontal base 2, and the construction master ruler 1 is provided with a plurality of positioning holes 11, and the positioning holes 11 are matched for connection and positioning Steel bars 111, the positioning steel bars 111 are detachably penetrated through the positioning holes 11;
检测坐标定位尺包括检测主尺3和检测水平底座4,检测主尺3垂直设置在检测水平底座4上,且检测主尺3上开设有多个限位卡槽31,限位卡槽31匹配连接钢尺121,钢尺121可拆卸穿设在限位卡槽12中。The detection coordinate positioning ruler includes a detection main ruler 3 and a detection horizontal base 4. The detection main ruler 3 is vertically arranged on the detection horizontal base 4, and the detection main ruler 3 is provided with a plurality of limit slots 31, and the limit slots 31 match. The steel ruler 121 is connected, and the steel ruler 121 is detachably inserted in the limit slot 12 .
本实用新型一种预应力管道坐标定位尺的具体操作过程如下:The specific operation process of a prestressed pipeline coordinate positioning ruler of the utility model is as follows:
S1:施工水平底座2插进钢筋网底板,并保持施工水平底座2水平稳定放置在钢筋网底板上;S1: The construction level base 2 is inserted into the steel mesh bottom plate, and the construction level base 2 is kept horizontally and stably placed on the steel mesh bottom plate;
S2:将定位钢筋111水平插入施工主尺1上的定位孔11中,并使定位钢S2: Insert the positioning steel bar 111 into the positioning hole 11 on the construction master ruler 1 horizontally, and make the positioning steel
筋111保持水平;Ribs 111 are kept horizontal;
S3:将预应力工程管道6按压在定位钢筋111上,同时将定位钢筋111烧S3: Press the prestressed engineering pipe 6 on the positioning steel bar 111, and at the same time burn the positioning steel bar 111
断并焊接在钢筋网上;broken and welded on the steel mesh;
S4:在施工主尺1上读取预应力工程管道6底部的施工位置刻度值;S4: Read the construction position scale value at the bottom of the prestressed engineering pipeline 6 on the construction master ruler 1;
S5:将检测水平底座4插进钢筋网底板,并保持检测水平底座4水平稳定S5: Insert the detection level base 4 into the steel mesh bottom plate, and keep the detection level base 4 horizontally stable
放置在钢筋网底板上;placed on the reinforced mesh bottom plate;
S6:将钢尺121穿设在对应施工位置刻度值的限位卡槽12中;S6: Wear the steel ruler 121 in the limit slot 12 corresponding to the scale value of the construction position;
S7:对照钢尺121与预应力工程管道6底部位置之间的差值大小,检测出S7: Check the difference between the steel ruler 121 and the bottom position of the prestressed engineering pipeline 6, and detect
预应力工程管道6定位是否符合规范要求。Whether the positioning of the prestressed engineering pipeline 6 meets the specification requirements.
本说明书中各个实施例采用递进的方式描述,每个实施例重点说明的都是与其他实施例的不同之处,各个实施例之间相同相似部分互相参见即可。对于实施例公开的装置而言,由于其与实施例公开的方法相对应,所以描述的比较简单,相关之处参见方法部分说明即可。The various embodiments in this specification are described in a progressive manner, and each embodiment focuses on the differences from other embodiments, and the same and similar parts between the various embodiments can be referred to each other. As for the device disclosed in the embodiment, since it corresponds to the method disclosed in the embodiment, the description is relatively simple, and the relevant part can be referred to the description of the method.
对所公开的实施例的上述说明,使本领域专业技术人员能够实现或使用本实用新型。对这些实施例的多种修改对本领域的专业技术人员来说将是显而易见的,本文中所定义的一般原理可以在不脱离本实用新型的精神或范围的情况下,在其它实施例中实现。因此,本实用新型将不会被限制于本文所示的这些实施例,而是要符合与本文所公开的原理和新颖特点相一致的最宽的范围。The above description of the disclosed embodiments enables those skilled in the art to implement or use the present invention. Various modifications to these embodiments will be readily apparent to those skilled in the art, and the generic principles defined herein may be implemented in other embodiments without departing from the spirit or scope of the present invention. Thus, the present invention is not intended to be limited to the embodiments shown herein, but is to be accorded the widest scope consistent with the principles and novel features disclosed herein.
Claims (7)
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201822000540.6U CN209027523U (en) | 2018-11-30 | 2018-11-30 | A prestressed pipeline coordinate positioning ruler |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201822000540.6U CN209027523U (en) | 2018-11-30 | 2018-11-30 | A prestressed pipeline coordinate positioning ruler |
Publications (1)
Publication Number | Publication Date |
---|---|
CN209027523U true CN209027523U (en) | 2019-06-25 |
Family
ID=66910704
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201822000540.6U Expired - Fee Related CN209027523U (en) | 2018-11-30 | 2018-11-30 | A prestressed pipeline coordinate positioning ruler |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN209027523U (en) |
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN109443328A (en) * | 2018-11-30 | 2019-03-08 | 宁夏路桥工程股份有限公司 | A kind of prestress pipe coordinate location ruler and its application method |
CN114953169A (en) * | 2022-06-10 | 2022-08-30 | 中铁十二局集团第三工程有限公司 | Positioning device and positioning method for checking slurry compactness and related to pore channel |
CN115106687A (en) * | 2022-07-14 | 2022-09-27 | 中交第二航务工程局有限公司 | Platform and method for machining steel box and socket type reinforcing mesh joint of underground diaphragm wall |
-
2018
- 2018-11-30 CN CN201822000540.6U patent/CN209027523U/en not_active Expired - Fee Related
Cited By (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN109443328A (en) * | 2018-11-30 | 2019-03-08 | 宁夏路桥工程股份有限公司 | A kind of prestress pipe coordinate location ruler and its application method |
CN109443328B (en) * | 2018-11-30 | 2024-03-22 | 宁夏公路桥梁建设有限公司 | Prestressed pipeline coordinate positioning ruler and use method thereof |
CN114953169A (en) * | 2022-06-10 | 2022-08-30 | 中铁十二局集团第三工程有限公司 | Positioning device and positioning method for checking slurry compactness and related to pore channel |
CN114953169B (en) * | 2022-06-10 | 2024-06-04 | 中铁十二局集团第三工程有限公司 | Positioning device and positioning method for detecting slurry compactness related to pore canal |
CN115106687A (en) * | 2022-07-14 | 2022-09-27 | 中交第二航务工程局有限公司 | Platform and method for machining steel box and socket type reinforcing mesh joint of underground diaphragm wall |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN209027523U (en) | A prestressed pipeline coordinate positioning ruler | |
CN104631419A (en) | Foundation pit top horizontal displacement monitoring method | |
CN105067513A (en) | Fastener type scaffold skidproof and damage-resistant testing device | |
CN214251817U (en) | Comprehensive test platform for steel pipe scaffold members and fasteners | |
CN203464889U (en) | Special-purpose building template verticality detection ruler | |
CN208458663U (en) | A kind of municipal works manhole cover, water grate residual deformation detection device | |
CN114737756A (en) | A construction method of a real-time monitoring system for the early dismantling support of the disk buckle | |
CN207300237U (en) | The quick monitoring device of pier slope | |
CN109443328B (en) | Prestressed pipeline coordinate positioning ruler and use method thereof | |
CN210002404U (en) | positioning device for precast tubular pile centering construction | |
CN208076290U (en) | A kind of device applying prestressing force and pull-out test | |
CN205138986U (en) | Fastener -style scaffold cling compound and anti destruction test device | |
CN205317108U (en) | Pier support preformed hole axis inspection device | |
CN205118441U (en) | Observe and control device that advances direction in push pipe top | |
CN211085207U (en) | Ultrasonic distance measuring sensor for monitoring relative settlement of full-hall support | |
CN210036740U (en) | Prefabricated wall body installation straightness measuring tool that hangs down | |
CN204854573U (en) | A multi -functional chi for piping installation | |
CN217686983U (en) | Double-metal mark manual and automatic vertical displacement monitoring device | |
CN206113928U (en) | Special detection instrument of template | |
CN211953973U (en) | Floor thickness measuring tool | |
CN206717353U (en) | Flange assembling process ruler based on ship piping system | |
CN111609779A (en) | Anchor pad fast acceptance device and detection method | |
CN110749264A (en) | Crack three-direction relative displacement measuring device and measuring method thereof | |
CN203785887U (en) | Straight-insertion disk-pin type template support node rotational stiffness test device | |
CN221811576U (en) | Simple vertical measuring device for building vertical pipe installation |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant | ||
TR01 | Transfer of patent right |
Effective date of registration: 20200814 Address after: 750001 room 1217, 12 / F, building 1, Fortune Center, Qingchun building, Xingqing District, Yinchuan City, Ningxia Hui Autonomous Region Patentee after: Ningxia Zhongda Highway Construction Co.,Ltd. Address before: 750000 Wanshou Road, Yinchuan City, the Ningxia Hui Autonomous Region, No. 142, Wanshou Road Patentee before: NINGXIA ROAD & BRIDGE ENGINEERING Co.,Ltd. |
|
TR01 | Transfer of patent right | ||
CP03 | Change of name, title or address |
Address after: Office building 2, Luqiao building, 142 Wanshou Road, Jinfeng District, Yinchuan City, Ningxia Hui Autonomous Region, 750004 Patentee after: Ningxia highway and Bridge Construction Co.,Ltd. Address before: 750001 room 1217, 12 / F, building 1, Fortune Center, Qingchun building, Xingqing District, Yinchuan City, Ningxia Hui Autonomous Region Patentee before: Ningxia Zhongda Highway Construction Co.,Ltd. |
|
CP03 | Change of name, title or address | ||
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20190625 |
|
CF01 | Termination of patent right due to non-payment of annual fee |