CN106930273A - Stake technique and prefabricated pile are planted in one kind drilling high pressure draught vibration - Google Patents
Stake technique and prefabricated pile are planted in one kind drilling high pressure draught vibration Download PDFInfo
- Publication number
- CN106930273A CN106930273A CN201710160932.6A CN201710160932A CN106930273A CN 106930273 A CN106930273 A CN 106930273A CN 201710160932 A CN201710160932 A CN 201710160932A CN 106930273 A CN106930273 A CN 106930273A
- Authority
- CN
- China
- Prior art keywords
- pile
- stake
- high pressure
- pressure draught
- planted
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D5/00—Bulkheads, piles, or other structural elements specially adapted to foundation engineering
- E02D5/22—Piles
- E02D5/24—Prefabricated piles
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D7/00—Methods or apparatus for placing sheet pile bulkheads, piles, mouldpipes, or other moulds
Landscapes
- Engineering & Computer Science (AREA)
- Structural Engineering (AREA)
- Life Sciences & Earth Sciences (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Mining & Mineral Resources (AREA)
- Paleontology (AREA)
- Civil Engineering (AREA)
- General Engineering & Computer Science (AREA)
- Placing Or Removing Of Piles Or Sheet Piles, Or Accessories Thereof (AREA)
- Earth Drilling (AREA)
- Piles And Underground Anchors (AREA)
Abstract
Stake technique and prefabricated pile are planted the invention discloses one kind drilling high pressure draught vibration, overcomes that noise pollution in the prior art is big, there is a problem of soil compaction effect, be prevented effectively from the influence to ground and adjacent stake, concrete scheme is as follows:Technique discharges the soil body using after rig pore-forming to set depth;Using mixing pile machine in step 1) continue on the basis of hole to drill, and cement grout is injected in hole, cement grout is mixed to form cement grout with the soil body in hole;3) by prefabricated pile implantation step 2) in hole in.
Description
Technical field
The invention belongs to foundation pit enclosure pile construction technology field, stake work is planted in more particularly to a kind of drilling high pressure draught vibration
Skill and prefabricated pile.
Background technology
Precast concrete pile is prefabricated in the factory shaping, by the side such as hammering, static pressure or prebored hole after transport to job site
Formula is implanted into stratum, good with pile quality, and speed of application is fast, the features such as high financial profit, in the construction of building and structures
On be widely used.Pile body is implanted into stratum by hammering and static-pressure pile planting by ambient pressure, mud-less pollution in work progress, construction
Place Green civilization.
Meanwhile, there is some defects and deficiency in existing prefabricated pile pile sinking process:
1) it is larger to ground perturbation during stake lower using hammering vibration, and there is problem of noise pollution, be not suitable in residential block
And school area construction;Stake although noise without friction under Static pressure pile driver, but soil compaction effect is there is also, there is shadow to ground and adjacent stake
Ring.
2) prebored hole joints cement soil is planted the technique of stake and needs the cooperation on slurrying backstage, stirring concrete earth complex process, when
Easily efficiency of construction is influenceed when slurrying backstage goes wrong.
Even if it is not enough fundamentally to solve these using the plant piling method that prebored hole and vibrating static-pressure are combined.
The content of the invention
In order to overcome the deficiencies in the prior art, stake technique, the work are planted the invention provides one kind drilling high pressure draught vibration
First with drill hole of drilling machine in skill, with the discharge part soil body, then secondary drilling is carried out by mixing pile machine, effectively prevent soil compaction effect
Should, and then the influence to ground and adjacent stake is avoided, meanwhile, by being passed through for cement grout, without backstage coordinative construction, construction
Program is simplified.
The concrete scheme of the non-bearing type water tank for water heater is as follows:
Stake technique is planted in one kind drilling high pressure draught vibration, including:
1) using after rig pore-forming to set depth, the soil body is discharged;
2) using mixing pile machine in step 1) continue on the basis of hole to drill, and cement grout, water are injected in hole
Slurry liquid is mixed to form cement grout with the soil body in hole;
3) by prefabricated pile implantation step 2) in hole in.
In above-mentioned technique, by rig elder generation pore-forming, the soil body is discharged, then continue to drill by mixing pile machine, and in mixing pile
During machine drill hole, without discharging the soil body, to cement grout is injected in hole, cement is mixed to form water with the soil body in drilling
Soil slurries, intensity is more than the soil body after cement grout solidification, and intensity is high, and can be used to fill between drilling and prefabricated pile
Space, it is ensured that the stability of prefabricated pile supporting, cement grout is stirred without backstage again, simplifies work progress, meanwhile,
The presence of cement grout, effectively reduces vibration noise during stake is planted.
Wherein, in the step 3) in, during prefabricated pile is implanted, high pressure is exported by the pile top of prefabricated pile empty
Gas, to the resistance of prefabricated pile, is smoothed out plant stake process to reduce cement grout in hole, can accelerate to plant stake speed, it is ensured that pre-
Bottom hole designed elevation is smoothly sunk in stake processed.
In order to realize being passed through for high pressure draught, longitudinal direction is embedded with air delivering pipeline, air delivering pipeline top in the prefabricated pile
Portion can be connected with air compressor, and air delivering pipeline is set from prefabricated pile top to pile top, and high pressure draught is passed through by pile top, is reduced
Resistance between prefabricated pile and cement grout.
When prefabricated pile is single-unit stake, the air delivering pipeline is one;When prefabricated pile is more piece stake, the air delivering pipeline
The air hose in the stake of each section is distributed in including multistage, adjacent air hose is attached by connector.
In order to improve early stage drilling efficiency, the step 1) in rig be twist bit.
The pre-buried wireway of pile top of the prefabricated pile, wireway is connected with described air delivering pipeline, and the wireway is can
The wireway of longitudinal extension;Wireway is divided to two sections, is connected with air delivering pipeline in a section embedment pile top, and another section is scalable.Plant stake
When wireway stretch out high pressure draught exported outside stake, plant stake by pile body gravity and high pressure draught impact cement grout, pile body is reached
After designed elevation, pile body and pressure of the hole in the bottom are by portion in wireway jacked pile body.
Further, to prevent cement grout during lower stake from causing blocking into wireway, air guide tube side part is provided with outlet
Hole.
In order to coordinate above-mentioned construction technology, present invention also offers a kind of prefabricated pile for being passed through high pressure draught, this is pre-
Stake processed can be passed through high pressure draught, effectively reduce the resistance planted during stake, reduce and plant the noise that stake is produced, and the prefabricated pile can also
It is applied in other construction of prefabricated piles techniques.
A kind of prefabricated pile for being passed through high pressure draught, including pile body, pile body inside set the appendix of longitudinally through pile body
Road, air delivering pipeline top be connected with air compressor with by air delivering pipeline to pile top conveying high-pressure gas.
The pile body pile top sets telescopic wireway, and wireway is connected with described air delivering pipeline.
During lower stake, liquid blocks wireway in the soil body or drilling, and the wireway is provided with venthole,
Venthole is located at the both sides of wireway.
When prefabricated pile is single-unit stake, the air delivering pipeline is one;When prefabricated pile is more piece stake, the air delivering pipeline
The air hose in the stake of each section is distributed in including multistage, adjacent air hose is attached by connector.
Compared with prior art, the beneficial effects of the invention are as follows:
1) present invention by substep drilled, early stage can discharge part drilling in the soil body, coordinate cement grout, it is to avoid
Soil compaction effect, and then avoid the influence to ground and adjacent stake.
It is 2) of the invention by the way that to cement grout is injected in hole, cement is mixed to form cement grout with the soil body in drilling,
Cement grout simplifies work progress without backstage coordinative construction, meanwhile, the presence of cement grout, during stake is planted
Effectively reduce vibration noise;Additionally, the mud intensity of the general retaining wall of soil cement slurry liquor ratio is big, concentration is sticky, after solidification can with it is pre-
Stake processed forms compound pile body, enhances the stability of pile body.
3) present invention is passed through high pressure draught by during stake is planted, and effectively reduces in hole cement grout to prefabricated pile
Resistance, make plant stake process be smoothed out, improve prefabricated pile plant stake efficiency, meanwhile, the effect of high pressure draught is also effectively reduced
Plant the vibrating noise during stake.
Brief description of the drawings
The Figure of description for constituting the part of the application is used for providing further understanding of the present application, and the application's shows
Meaning property embodiment and its illustrated for explaining the application, does not constitute the improper restriction to the application.
Fig. 1 is construction flow chart of the present invention;
Fig. 2 is the profile of prefabricated pile of the present invention;
Wherein:1- long-spiral drilling machines, 2- long-spiral drilling machine drilling depths, 3- bottom projected depth, 4- cementing tanks, 5- stirrings
Stake machine, 6- cement grouts, 7- crawler cranes, 8- Pile feeders, 9- prefabricated piles, 10- air compressors, 11- is emitted, and stake is saved on 12-
Air hose, saves pile joint on 13-, 14- saves air hose joint up and down, and 15- pile joint connecting pin bolts save pile joint under 16-,
Stake air hose, 18- wireways are saved under 17-.
Specific embodiment
It is noted that described further below is all exemplary, it is intended to provide further instruction to the application.Unless another
Indicate, all technologies used herein and scientific terminology are with usual with the application person of an ordinary skill in the technical field
The identical meanings of understanding.
It should be noted that term used herein above is merely to describe specific embodiment, and be not intended to restricted root
According to the illustrative embodiments of the application.As used herein, unless the context clearly indicates otherwise, otherwise singulative
Be also intended to include plural form, additionally, it should be understood that, when in this manual use term "comprising" and/or " bag
Include " when, it indicates existing characteristics, step, operation, device, component and/or combinations thereof.
As background technology is introduced, there is soil compaction effect in the prior art, the big deficiency of stake noise planted, in order to solve
As above technical problem, stake technique and method are planted present applicant proposes one kind drilling high pressure draught vibration.
In a kind of typical implementation method of the application, as shown in figure 1, stake technique is planted in a kind of drilling high pressure draught vibration,
Including:
1) using after rig pore-forming to set depth, the soil body is discharged;
2) using mixing pile machine 5 in step 1) continue on the basis of hole to drill, and cement grout, water are injected in hole
Slurry liquid is provided by cementing tank 4, and cement grout is mixed to form cement grout 6 with the soil body in hole;
3) Pile feeder 8 is connected by the implant holes of prefabricated pile 9 using crawler crane 7, Pile feeder 8 and prefabricated pile 9 emit 11 by stake
Connection, a bottom projected depth 3 is delivered to by the pile body, needs Pile feeder 8 and vibration hammer etc. to coordinate lower stake when planting stake, and prefabricated pile 9 is adopted
With prefabrication, industrialization degree is high, and pile quality is good, and speed of application is fast, high financial profit.
In above-mentioned technique, by rig elder generation pore-forming, then continue to drill by mixing pile machine 5, and drilled in mixing pile machine 5
Cheng Zhong, to cement grout is injected in hole, cement is mixed to form cement grout with the soil body in drilling, and cement grout is without again
Backstage is stirred, and simplifies work progress, directly can inject cement grout by mixing pile machine 5, meanwhile, soil cement slurry
The presence of liquid, plant stake during effectively reduce vibration noise, the match ratio of cement grout 6 be slurries in cement, water and soil it is each
Accounting example, its reclaimed water and cement proportion can be controlled by mixing pile machine injection cement grout, and the match ratio of cement grout can pass through
The injection rate of long-spiral drilling machine drilling depth 2, stake bottom projected depth 3 and cement grout is controlled.
Wherein, in order to improve early stage drilling efficiency, the step 1) in rig be long-spiral drilling machine 1, in step 3) in,
During prefabricated pile 9 is implanted, export pressure-air by the pile top of prefabricated pile 9 to reduce in hole cement grout to pre-
The resistance of stake processed 9, is smoothed out plant stake process, improves prefabricated pile 9 and plants stake efficiency.
In order to realize being passed through for high pressure draught, longitudinal direction is embedded with air delivering pipeline in prefabricated pile 9, and air delivering pipeline top can
It is connected with air compressor 10, air delivering pipeline is set from the top of prefabricated pile 9 to pile top, and stake emits reserving hole at 11, can be by gas transmission
Pipeline is drawn, and is connected with air compressor 10.
When prefabricated pile 9 is single-unit stake, the air delivering pipeline is one;When prefabricated pile is more piece stake, the appendix
Road is distributed in the air hose in the stake of each section including multistage, and adjacent air hose is attached by connector, and connector is
The air hose of section up and down joint 14 in jointing, such as Fig. 2, by upper section pile joint 13 and lower section staking between more piece stake
First 16 are attached.
The pre-buried wireway 18 of pile top of prefabricated pile 9, wireway 18 is connected with described air delivering pipeline, and the wireway 18 is
Can longitudinal extension wireway;Wireway is divided to two sections, is connected with air delivering pipeline in a section embedment pile top, and another section is scalable.Plant
Wireway is stretched out and high pressure draught is exported outside stake during stake, and stake is planted by pile body gravity and high pressure draught impact cement grout, and pile body is arrived
Up to after designed elevation, pile body and pressure of the hole in the bottom are by portion in the jacked pile body of wireway 18.
To prevent cement grout during lower stake from causing blocking into wireway, air guide tube side part is provided with venthole.
In order to coordinate above-mentioned construction technology, present invention also offers a kind of prefabricated pile for being passed through high pressure draught, this is pre-
Stake processed can be passed through high pressure draught, effectively reduce the resistance planted during stake, reduce and plant the noise that stake is produced, and the prefabricated pile can also
It is applied in other construction of prefabricated piles techniques.
The construction technology be given in the present embodiment, specific following advantage:
1) substep that passes through of the invention is drilled, and early stage can the interior soil body of discharge part drilling, later stage continuation drilling, hydrous water
The setting of soil slurries, whole process vibration is small, and then avoids the influence to ground and adjacent stake, and effect on environment is small, after drilling
Plant stake, without friction, noise pollution.
It is 2) of the invention by the way that to cement grout is injected in hole, cement is mixed to form cement grout with the soil body in drilling,
Cement grout simplifies operational procedure without slurrying backstage coordinative construction, meanwhile, stake process is being planted in the presence of cement grout
In effectively reduce vibration noise.
3) present invention, because the setting of air delivering pipeline is passed through high pressure draught, effectively reduces hole Nei Shui by during stake is planted
Soil slurries are smoothed out plant stake process the resistance of prefabricated pile, improve prefabricated pile and plant stake efficiency, meanwhile, high pressure draught
Effect, also effectively reduces the vibrating noise planted during stake.
Additionally, present invention also provides another embodiment:
A kind of prefabricated pile for being passed through high pressure draught, as shown in Fig. 2 the prefabricated pile includes pile body, pile body inside sets vertical
To the air delivering pipeline of insertion pile body, air delivering pipeline may be disposed at the center of pile body, and air delivering pipeline top is connected with air compressor
With by air delivering pipeline to pile top conveying high-pressure gas.
The pile body pile top sets telescopic wireway, and wireway is connected with described air delivering pipeline.
During lower stake, liquid blocks wireway in the soil body or drilling, and the wireway is provided with venthole,
Venthole is located at the both sides of wireway.
When prefabricated pile is single-unit stake, the air delivering pipeline is one;When prefabricated pile is more piece stake, the air delivering pipeline
The air hose in the stake of each section is distributed in including multistage, adjacent air hose is attached by connector.
The preferred embodiment of the application is the foregoing is only, the application is not limited to, for the skill of this area
For art personnel, the application can have various modifications and variations.It is all within spirit herein and principle, made any repair
Change, equivalent, improvement etc., should be included within the protection domain of the application.
Claims (10)
1. stake technique is planted in a kind of drilling high pressure draught vibration, it is characterised in that including:
1) using after rig pore-forming to set depth, the soil body is discharged;
2) using mixing pile machine in step 1) continue on the basis of hole to drill, and cement grout, cement mortar are injected in hole
Liquid is mixed to form cement grout with the soil body in hole;
3) by prefabricated pile implantation step 2) in hole in.
2. stake technique is planted in a kind of drilling high pressure draught vibration according to claim 1, it is characterised in that in the step 3)
In, during prefabricated pile is implanted, pressure-air is exported to reduce cement grout pair in hole by the pile top of prefabricated pile
The resistance of prefabricated pile.
3. stake technique is planted in a kind of drilling high pressure draught vibration according to claim 1 and 2, it is characterised in that described prefabricated
Longitudinal direction is embedded with air delivering pipeline in stake.
4. stake technique is planted in a kind of drilling high pressure draught vibration according to claim 3, it is characterised in that when prefabricated pile is single
During section stake, the air delivering pipeline is one;When prefabricated pile is more piece stake, the air delivering pipeline is distributed in each section stake including multistage
Interior air hose, adjacent air hose is attached by connector.
5. stake technique is planted in a kind of drilling high pressure draught vibration according to claim 1, it is characterised in that the step 1) in
Rig is twist bit.
6. stake technique is planted in a kind of drilling high pressure draught vibration according to claim 3, it is characterised in that the prefabricated pile
The pre-buried wireway of pile top, wireway is connected with described air delivering pipeline.
7. stake technique is planted in a kind of drilling high pressure draught vibration according to claim 6, it is characterised in that the wireway is
Can longitudinal extension wireway;
Further, air guide tube side part is provided with venthole.
8. a kind of prefabricated pile for being passed through high pressure draught, it is characterised in that including pile body, pile body inside sets longitudinally through pile body
Air delivering pipeline.
9. a kind of prefabricated pile for being passed through high pressure draught as claimed in claim 8, it is characterised in that the pile body pile top is set
Telescopic wireway, wireway is connected with described air delivering pipeline.
10. a kind of prefabricated pile for being passed through high pressure draught as claimed in claim 8, it is characterised in that the wireway is provided with
Venthole.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201710160932.6A CN106930273A (en) | 2017-03-17 | 2017-03-17 | Stake technique and prefabricated pile are planted in one kind drilling high pressure draught vibration |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201710160932.6A CN106930273A (en) | 2017-03-17 | 2017-03-17 | Stake technique and prefabricated pile are planted in one kind drilling high pressure draught vibration |
Publications (1)
Publication Number | Publication Date |
---|---|
CN106930273A true CN106930273A (en) | 2017-07-07 |
Family
ID=59432921
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201710160932.6A Pending CN106930273A (en) | 2017-03-17 | 2017-03-17 | Stake technique and prefabricated pile are planted in one kind drilling high pressure draught vibration |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN106930273A (en) |
Citations (9)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN1335434A (en) * | 2001-09-01 | 2002-02-13 | 叶长生 | High-pressure mortar spraying deposition process of prefabricated steel bar reinforced concrete pile |
JP2004027610A (en) * | 2002-06-25 | 2004-01-29 | Asahi Kasei Construction Materials Co Ltd | Burying method for prefabricated pile |
CN2828145Y (en) * | 2005-10-19 | 2006-10-18 | 吴金水 | Water flushing gas-lift auxiliary static pressure pile sinking water flushing equipment |
CN101498129A (en) * | 2008-01-31 | 2009-08-05 | 黄秋生 | Water-gas mixing jet apparatus for pile sinking |
CN103243713A (en) * | 2013-05-07 | 2013-08-14 | 天津建城基业集团有限公司 | Method for planting prestressed pipe pile at one step |
CN103628473A (en) * | 2013-10-25 | 2014-03-12 | 天津建城基业集团有限公司 | Composite type combined piles and construction method thereof |
CN105064351A (en) * | 2015-08-14 | 2015-11-18 | 云南大学 | Pile planting method |
CN205776216U (en) * | 2016-06-13 | 2016-12-07 | 上海强劲地基工程股份有限公司 | A kind of implantation equipment of rigid pile |
CN106436692A (en) * | 2016-07-21 | 2017-02-22 | 杭州南联地基基础工程有限公司 | Convex four-shaft cement stirring soil implanted prefabricated reinforced concrete I-shaped pile enclosure wall |
-
2017
- 2017-03-17 CN CN201710160932.6A patent/CN106930273A/en active Pending
Patent Citations (9)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN1335434A (en) * | 2001-09-01 | 2002-02-13 | 叶长生 | High-pressure mortar spraying deposition process of prefabricated steel bar reinforced concrete pile |
JP2004027610A (en) * | 2002-06-25 | 2004-01-29 | Asahi Kasei Construction Materials Co Ltd | Burying method for prefabricated pile |
CN2828145Y (en) * | 2005-10-19 | 2006-10-18 | 吴金水 | Water flushing gas-lift auxiliary static pressure pile sinking water flushing equipment |
CN101498129A (en) * | 2008-01-31 | 2009-08-05 | 黄秋生 | Water-gas mixing jet apparatus for pile sinking |
CN103243713A (en) * | 2013-05-07 | 2013-08-14 | 天津建城基业集团有限公司 | Method for planting prestressed pipe pile at one step |
CN103628473A (en) * | 2013-10-25 | 2014-03-12 | 天津建城基业集团有限公司 | Composite type combined piles and construction method thereof |
CN105064351A (en) * | 2015-08-14 | 2015-11-18 | 云南大学 | Pile planting method |
CN205776216U (en) * | 2016-06-13 | 2016-12-07 | 上海强劲地基工程股份有限公司 | A kind of implantation equipment of rigid pile |
CN106436692A (en) * | 2016-07-21 | 2017-02-22 | 杭州南联地基基础工程有限公司 | Convex four-shaft cement stirring soil implanted prefabricated reinforced concrete I-shaped pile enclosure wall |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN1193141C (en) | Combined grouting construction process of reinforcing foundation | |
CN100455731C (en) | Guide pit type manual pot holing pile reinforing and underpinning method for building foundation and composite supporting pile | |
CN102691296A (en) | Pipe pile foundation for static-pressure grouting on pile side and rotary jet grouting at pile bottom and construction method thereof | |
CN107246267A (en) | Mine Shaft Lining, constructing device and method in a kind of poor strata | |
CN101899828B (en) | Construction method of bagged rammed small-diameter soil-cement pile composite foundation | |
CN112323823B (en) | Filling device and method for waste air-raid shelter of pile foundation construction site | |
CN110258538B (en) | Soil nail reinforced buffer type manual hole digging pile and construction method thereof | |
CN206784372U (en) | Injection forming club-footed pile | |
CN106284295A (en) | Multichannel high-pressure vibro-grouting jet groutinl construction method | |
CN109538295A (en) | Seal groundwater in mining area library system | |
CN106522191A (en) | Transformer substation foundation treatment method and application thereof | |
CN107060779A (en) | A kind of anti-cut construction method of narrow regions ultra-deep passage inclined shaft | |
CN111058443A (en) | Precast pile composite foundation construction method for eliminating loess collapsibility | |
KR101746654B1 (en) | Method for constructing pile for reinforce of mine hole | |
CN108385669A (en) | A kind of CFG pile driving constructions engineering method | |
CN110777775A (en) | Foundation pit structure and construction method thereof | |
CN213014295U (en) | A slip casting fills device for handling abandonment air-raid shelter | |
CN108570982A (en) | The quiet brill of one kind taking root in energy stake and its construction method | |
CN108894247A (en) | A kind of Metro Connection Passage periphery soil body subsidence pressure circle spray reinforcement structure and construction method | |
CN210216452U (en) | Old excavation supporting system reinforced structure | |
CN1078282A (en) | Pile shoe pouring process and special reinforcing steel cage thereof | |
CN106930273A (en) | Stake technique and prefabricated pile are planted in one kind drilling high pressure draught vibration | |
CN213869905U (en) | Large-section tunnel base anti-sedimentation structure under loose rock stack stratum | |
CN206233232U (en) | A kind of upper and lower part expansion type soil cement is combined pile tube | |
CN115199331A (en) | Carbon dioxide storage method based on deep goaf space of thick unconsolidated formation |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
RJ01 | Rejection of invention patent application after publication | ||
RJ01 | Rejection of invention patent application after publication |
Application publication date: 20170707 |