CN106930198A - The processing method of modular bridge beam support and application - Google Patents

The processing method of modular bridge beam support and application Download PDF

Info

Publication number
CN106930198A
CN106930198A CN201710228285.8A CN201710228285A CN106930198A CN 106930198 A CN106930198 A CN 106930198A CN 201710228285 A CN201710228285 A CN 201710228285A CN 106930198 A CN106930198 A CN 106930198A
Authority
CN
China
Prior art keywords
bridge
bearing
plate
jacking
hydraulic jack
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201710228285.8A
Other languages
Chinese (zh)
Inventor
曹国辉
莫东山
蔡文武
何敏
韩传昌
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Hunan City University
Original Assignee
Hunan City University
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Hunan City University filed Critical Hunan City University
Priority to CN201710228285.8A priority Critical patent/CN106930198A/en
Publication of CN106930198A publication Critical patent/CN106930198A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D22/00Methods or apparatus for repairing or strengthening existing bridges ; Methods or apparatus for dismantling bridges
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D19/00Structural or constructional details of bridges
    • E01D19/04Bearings; Hinges

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Bridges Or Land Bridges (AREA)

Abstract

A kind of processing method of the modular bridge beam support processed the invention discloses disease bearing to rib beam type bridge or box beam formula bridge or board-like bridge it is characterized in that it include (1) installing jack-up system, (2) jacking, (3) bearing treatment, (4) unloading fall beam step;For board-like or pot rubber bearing the treatment under rib beam type bridge or each beam of box beam formula bridge or board-like bridge or plate;The present invention arranges a jacking method for jack using at interval of 1~2 bearing, and jack quantity can reduce 50 ﹪ or so, greatly reduce construction cost, improve economic benefit;From for structure stress angle, using the mechanics principle for being capable of Transfer of Shear between adjacent two panels beam, plate, in bridge lateral symmetrical arrangement jacking load, it is ensured that the tension that floorings occur is smaller or occurs without tension, makes bridge structure uniform force.

Description

The processing method of modular bridge beam support and application
Technical field
The present invention relates to a kind of combined bridge, the processing method of specifically a kind of modular bridge beam support and should With the combined type that more particularly to a kind of disease bearing to rib beam type bridge or box beam formula bridge or board-like bridge is processed The processing method of bridge pad and application.
Background technology
According to incompletely statistics, the Chinese seat of existing highway bridge quantity about more than 800,000, the bridge for putting into operation every year about more than 10,000 Seat.So huge quantity, while our convenient traffic are brought, also generates many urgent problems, its jackshaft The bearing problem of beam is the most thorny issue.
Bearing is the important feature part for connecting bridge superstructure and substructure, is subject to act on superstructure Various loads, and pier is passed it to, meanwhile, under load, temperature, concrete shrinkage and creep effect, adapt to top knot The corner of structure and displacement.Relevant investigation display:Due to the aspects such as design, processing and manufacturing, construction and maintenance, conventional public affairs There is serious problem of aging in the rubber support under road and bridge beam each beam, plate, often just occur bearing in using 3~5 years and take off The diseases such as empty, detrusion is excessive, the convex deformation of intermediate gelatine layer drum.Bearing as the most important load transfer device of bridge, its normal fortune Row directly decides the service life of bridge top and the bottom structure, to bridge structure and traffic safety important.Therefore, prop up The Disease Processing of seat needs urgently to be resolved hurrily.
Currently, the treatment to disease bearing is generally all using the method for bearing replacement.Existing bearing replacement method is equal It is that bearing replacement will be again carried out after combination beam, plate integral jacking, but the quantity of the method requirement jack and the quantity of bearing It is identical, therefore, substantial amounts of human and material resources, financial resources need to be expended, the shortcomings of economical, ageing poor.
For example, Cheng Wen is far away from its document " bridge integral jacking replacing time construction technology "(Architecture/engineering, 2007 16 phases, page 105,87)Open debate application of the integral jacking technology in Bridge Support Replacement.The technology is with cored slab Example is illustrated, and for jack arrangement, in single span, laterally two ultra-thin jack are arranged in each cored slab one end, that is, Say each bearing one jack of correspondence.Jack with this arrangement no doubt can replacing time, but, the use of jack Quantity is more, economy, ageing poor.
The content of the invention
Enter it is an object of the invention to provide a kind of disease bearing to rib beam type bridge or box beam formula bridge or board-like bridge The processing method of the modular bridge beam support of row treatment and application.
The present invention adopts the following technical scheme that and realizes its goal of the invention, a kind for the treatment of side of modular bridge beam support Method, it comprises the following steps:
(1) jack-up system is installed:Jack-up system includes hydraulic jack, displacement meter and control device;Hydraulic jack is arranged on Near the bearing of beam or plate one end, and it is arranged on the same width of each beam or plate;Displacement meter is arranged in each beam or plate Bottom surface, and be arranged on the same width of each beam or plate;
For board-like bridge, a hydraulic jack is respectively arranged at the beam rib position on the outside of its side plate, it is then every to bridge center 1~2, interval bearing arranges a hydraulic jack, and is arranged symmetrically centered on bridge longitudinal axis or almost symmetry cloth Put;Displacement meter is arranged on the longitudinal axis of each plate;
For beam type bridge, a hydraulic jack is respectively arranged at the beam rib of its side bar or diaphragm position, then in bridge A hydraulic jack is arranged in centre at interval of 1~2 bearing, and is arranged symmetrically or almost symmetry centered on bridge longitudinal axis Arrangement;Displacement meter is disposed adjacent under the beam rib of bearing;
The across footpath of combined bridge of the present invention is less than or equal to 50m.
For freely-supported bridge, the corresponding position of another bridge or plate is also disposed with hydraulic jack to the present invention on same bridge pier Top and displacement meter.
In full-bridge integral jacking, hydraulic jack and displacement meter under all beams or plate are arranged in the present invention On same width and on same longitudinal direction.
(2) jacking:Under the control device control of jack-up system, each hydraulic jack is pushed up step by step simultaneously by jacking displacement Rise, ㎜~1.2 ㎜ of each jacking 0.8, the displacement difference between adjacent beams or plate is once observed per jacking, it is ensured that the position of its plate or beam Move difference and be no more than 0.2 ㎜~0.3 ㎜, the displacement of each hydraulic jack is controlled by the displacement meter under correspondence beam or plate, Until the bearing under each beam or plate departs from the bottom surface of beam or plate;
For freely-supported bridge, the jacking displacement difference of adjacent two panels beam or plate is no more than 0.1 ㎜ to the present invention on same bridge pier.
(3) bearing treatment:After completing lifting operation, temporary support is installed near each bearing, and according to the disease journey of bearing Degree carries out come to nothing treatment or replacing treatment to the disease bearing under each beam or plate;
(4) unload beam:After completing the Disease Processing of bearing, by (2) lifting operation reverse procedure unloads load hydraulic thousand step by step with step Jin top, makes each bearing be brought into close contact with corresponding beam or plate;
Repeat step (1)~(4), carry out down the treatment of a piece of beam or plate undersetting.
A kind of processing method of modular bridge beam support as described above is in rib beam type bridge or box beam formula bridge or board-like Applied in bridge, i.e., for the board-like or basin type rubber under rib beam type bridge or each beam of box beam formula bridge or board-like bridge or plate The treatment of bearing.
Due to using above-mentioned technical proposal, the present invention preferably realizes goal of the invention, using at interval of 1~2 bearing One jacking method of jack of arrangement, jack quantity can reduce 50 ﹪ or so, greatly reduce construction cost, improve through Ji benefit;From for structure stress angle, using the mechanics principle for being capable of Transfer of Shear between adjacent two panels beam, plate, in bridge The symmetrical jacking load of lateral arrangement, it is ensured that the tension that floorings occur is smaller or occurs without tension, receives bridge structure Power is uniform.
Brief description of the drawings
Fig. 1 is the structural representation of the embodiment of the present invention 1;
Fig. 2 is the structural representation of the embodiment of the present invention 2;
Fig. 3 is the structural representation of the embodiment of the present invention 3;
Fig. 4 is the structural representation of the embodiment of the present invention 4;
Fig. 5 is the structural representation of the embodiment of the present invention 5;
Fig. 6 is the structural representation of the embodiment of the present invention 6;
Fig. 7 is the structural representation of the embodiment of the present invention 7.
Specific embodiment
Below in conjunction with the accompanying drawings and embodiment the invention will be further described.
Embodiment 1:
A kind of processing method of modular bridge beam support, it comprises the following steps:
(1) jack-up system is installed:Jack-up system includes hydraulic jack 1, displacement meter 2 and control device;Hydraulic jack 1 is pacified Near the bearing of beam or plate one end, and it is arranged on the same width of each beam or plate;Displacement meter 2 is arranged in each beam Or the bottom surface of plate, and be arranged on the same width of each beam or plate;
For board-like bridge, a hydraulic jack 1 is respectively arranged at the beam rib position in its outside of side plate 4, then to bridge center A hydraulic jack 1 is arranged at interval of 1~2 bearing, and is arranged symmetrically or almost symmetry centered on bridge longitudinal axis Arrangement;Displacement meter 2 is arranged on the longitudinal axis of each plate;
In full-bridge integral jacking, hydraulic jack 1 and displacement meter 2 under all beams or plate are arranged in together the present invention On one width and on same longitudinal direction.
The across footpath of combined bridge of the present invention is less than or equal to 50m.
(2) jacking:Under the control device control of jack-up system, each hydraulic jack 1 is pushed up step by step simultaneously by jacking displacement Rise, ㎜~1.2 ㎜ of each jacking 0.8, the displacement difference between adjacent beams or plate is once observed per jacking, it is ensured that the position of its plate or beam Move difference and be no more than 0.2 ㎜~0.3 ㎜, the displacement of each hydraulic jack 1 is controlled by the displacement meter 2 under correspondence beam or plate System, until the bearing under each beam or plate departs from the bottom surface of beam or plate;
(3) bearing treatment:After completing lifting operation, temporary support is installed near each bearing 3, and according to the degree of disease of bearing 3 Come to nothing treatment or replacing treatment are carried out to the disease bearing under each beam or plate;
(4) unload beam:After completing the Disease Processing of bearing 3, by (2) lifting operation reverse procedure unloads load hydraulic thousand step by step with step Jin top 1, makes each bearing 3 be brought into close contact with corresponding beam or plate;
Repeat step (1)~(4), carry out down the treatment of a piece of beam or plate undersetting.
Bridge described in the present embodiment is hollow slab type bridge, and a width of 8m of bridge, single span span length 20m are disposed with 6 cored slabs, Method Pre-stress Concrete Hollow Slab 0.95m high, bridge floor is continuous.Treatment each bearing 3 under the cored slab on abutment.
The first step, installs jack-up system.As shown in figure 1, each near 1#, 4#, 5# plate left side bearing 3 arrange one Hydraulic jack 1, respectively arranges a hydraulic jack 1 near bearing 3 on the right of 2#, 6# plate, and displacement meter 2 is arranged in every sky On the longitudinal axis of core bottom surface, each hydraulic jack 1, displacement meter 2 are on same width.Although hydraulic jack 1 Arrangement does not accomplish absolute symmetrical, but tends to almost symmetry arrangement, can protect the premise of positive bridge structure safe Under, smoothly process each bearing 3 under cored slab.To ensure concrete strength more than the pressure that local pressure face is born, and jacking During each cored slab uniform force, the top of hydraulic jack 1 is provided with jacking steel plate, and jacking steel plate is put down with cored slab bottom surface Row is close to.
Second step, lifting operation, for hollow slab type bridge, top lifting height is controlled in 3 ㎜ or so.In the control of jack-up system Under device control processed, whether examination jacking, the jacking simultaneously of each hydraulic jack 1, it is therefore an objective to detect jack-up system state are carried out first Space good and between the elimination top steel plate of hydraulic jack 1 and cored slab.After the completion of examination jacking, each hydraulic jack 1 is same When jacking step by step, each jacking displacement be 0.8 ㎜~1.2 ㎜(The present embodiment is 1.0 ㎜), adjacent panels are once observed per jacking Between displacement difference, control the displacement difference between adjacent two plate to be not more than 0.2 ㎜, until each cored slab jacking is to each bearing under plate 3 are loosened, and the displacement of each hydraulic jack 1 is controlled by corresponding displacement meter 2.Each actual jacking displacement data of cored slab such as table 1 It is shown.
Table 1:The actual jacking displacement of each cored slab(Unit:㎜)
Plate is numbered 1# 2# 3# 4# 5# 6#
Actual jacking displacement 3.13 3.02 3.10 3.05 3.06 3.16
From the point of view of jacking result, although being fitted without hydraulic jack 1 under 3# plates, itself and adjacent two panels cored slab are utilized Between connection 3# plates are raised up, and connection between adjacent two sheet being capable of Transfer of Shear, it is ensured that bridge structure transverse direction Tension is smaller or occurs without tension.Meanwhile, the present embodiment only needs to arrange 5 hydraulic jacks that relatively conventional method is every Individual bearing is disposed about a hydraulic jack and compares, and The present invention reduces 7 hydraulic jacks, substantially increases economic effect Benefit.
3rd step, bearing treatment.It is such as completely loose first with the loosening situation for striking bar each bearing 3 of inspection after the completion of jacking It is dynamic, jacking step by step individually is carried out to the hydraulic jack 1 near the bearing 3, until the bearing 3 loosens completely.During construction, first Temporary support is placed on bent cap, the failure of hydraulic jack 1 occurs surprisingly, and according to the disease of bearing 3 in preventing work progress Degree carries out come to nothing treatment or replacing treatment to it, during replacing, takes centering, location measure to determine the riding position of new bearing 3.
4th step, unloads beam.After completing the treatment of each cored slab undersetting 3, slow unloading hydraulic jack 1, unloading Process is to lifting operation conversely, making each bearing 3 be brought into close contact with corresponding cored slab.
Repeating the above steps carries out the next pier of bridge, the treatment of table mount.
A kind of processing method of modular bridge beam support as described above is in rib beam type bridge or box beam formula bridge or board-like Applied in bridge, i.e., for the board-like or basin type rubber under rib beam type bridge or each beam of box beam formula bridge or board-like bridge or plate The treatment of bearing.
The present invention arranges a jacking method for jack using at interval of 1~2 bearing, and jack quantity can be reduced 50 ﹪ or so, greatly reduce construction cost, improve economic benefit;From for structure stress angle, using adjacent two panels beam, It is capable of the mechanics principle of Transfer of Shear between plate, in bridge lateral symmetrical arrangement jacking load, it is ensured that the drawing that floorings occur Stress is smaller or occurs without tension, makes bridge structure uniform force.
Embodiment 2:
Bridge described in the present embodiment is hollow slab type bridge, and a width of 12.5m of bridge, single span span length 20m are disposed with 9 cored slabs, empty Core plate 0.95m high, bridge floor is continuous.Treatment each bearing 3 under the cored slab on abutment.
The first step, installs jack-up system.As shown in Fig. 2 each near 1#, 6#, 7#, 8# plate left side bearing 3 arrange One hydraulic jack 1, respectively arranges a hydraulic jack 1, displacement meter 2 near bearing 3 on the right of 2#, 3#, 4#, 9# plate It is arranged on the every longitudinal axis of cored slab bottom surface, each hydraulic jack 1, displacement meter 2 are on same width.To ensure Concrete strength is more than the pressure that local pressure face is born, and each cored slab uniform force, hydraulic jack 1 during jacking Top be provided with jacking steel plate, jacking steel plate is parallel with cored slab bottom surface to be close to.
Second step, lifting operation, for hollow slab type bridge, top lifting height is controlled in 3 ㎜ or so.In the control of jack-up system Under device control processed, whether examination jacking, the jacking simultaneously of each hydraulic jack 1, it is therefore an objective to detect jack-up system state are carried out first Space good and between the elimination top steel plate of hydraulic jack 1 and cored slab.After the completion of examination jacking, each hydraulic jack 1 is same When jacking step by step, each jacking displacement be 0.8 ㎜~1.2 ㎜(The present embodiment is 1.0 ㎜), adjacent panels are once observed per jacking Between displacement difference, control the displacement difference between adjacent two plate to be not more than 0.2 ㎜, until each cored slab jacking is to each bearing under plate 3 are loosened, and the displacement of each hydraulic jack 1 is controlled by corresponding displacement meter 2.Each actual jacking displacement data of cored slab such as table 2 It is shown.
Table 2:The actual jacking displacement of each cored slab(Unit:㎜)
Plate is numbered 1# 2# 3# 4# 5# 6# 7# 8# 9#
Actual jacking displacement 3.17 3.04 3.09 3.12 3.09 3.27 3.33 3.16 3.24
From the point of view of jacking result, although being fitted without hydraulic jack 1 under 5# plates, itself and adjacent two panels cored slab are utilized Between connection 3# plates are raised up, and connection between adjacent two sheet being capable of Transfer of Shear, it is ensured that bridge structure transverse direction Tension is smaller or occurs without tension.Meanwhile, the present embodiment only needs to arrange 8 hydraulic jacks that relatively conventional method is every Individual bearing is disposed about a hydraulic jack and compares, and The present invention reduces 10 hydraulic jacks, substantially increases economic effect Benefit.
3rd step, bearing treatment.It is such as completely loose first with the loosening situation for striking bar each bearing 3 of inspection after the completion of jacking It is dynamic, jacking step by step individually is carried out to the hydraulic jack 1 near the bearing 3, until the bearing 3 loosens completely.During construction, first Temporary support is placed on bent cap, the failure of hydraulic jack 1 occurs surprisingly, and according to the disease of bearing 3 in preventing work progress Degree carries out come to nothing treatment or replacing treatment to it, during replacing, takes centering, location measure to determine the riding position of new bearing 3.
4th step, unloads beam.After completing the treatment of each cored slab undersetting 3, slow unloading hydraulic jack 1, unloading Process is to lifting operation conversely, making each bearing 3 be brought into close contact with corresponding cored slab.
Repeating the above steps carries out the next pier of bridge, the treatment of table mount.
Remaining same embodiment 1.
Embodiment 3:
For beam type bridge, a hydraulic jack is respectively arranged at the beam rib of its side bar 5 or diaphragm position, then in bridge A hydraulic jack 1 is arranged in centre at interval of 1~2 bearing, and is arranged symmetrically centered on bridge longitudinal axis or substantially right Claim arrangement;Displacement meter 2 is disposed adjacent under the beam rib of bearing 3;
Bridge described in the present embodiment is rib beam type bridge, and the girt strip is T beams, and a width of 12.5m of bridge, single span span length 30m are disposed with 6 T beams, deck-molding 2.0m, bridge floor is continuous.Treatment each bearing 3 under the T beams on abutment.
The first step, installs jack-up system.As shown in figure 3, each near 1#, 3#, 4#, 6# beam support 3 arrange one Hydraulic jack 1, displacement meter 2 is arranged near every T soffits bearing 3, and each hydraulic jack 1, displacement meter 2 are in same width On degree direction.To ensure concrete strength more than the pressure that local pressure face is born, and each T beam stress is equal during jacking Even, the top of hydraulic jack 1 is provided with jacking steel plate, and jacking steel plate is parallel with T soffits to be close to.
Second step, lifting operation, for T beam type bridges, top lifting height is controlled in 3.5 ㎜ or so.In the control of jack-up system Under device control processed, whether examination jacking, the jacking simultaneously of each hydraulic jack 1, it is therefore an objective to detect jack-up system state are carried out first Space good and between the elimination top steel plate of hydraulic jack 1 and T beams.Examination jacking after the completion of, each hydraulic jack 1 simultaneously by Level jacking, each jacking displacement is 0.8 ㎜~1.2 ㎜(The present embodiment is 1.0 ㎜), once observed per jacking between adjacent beams Displacement difference, control the displacement difference between adjacent two beam to be not more than 0.3 ㎜, until each bearing 3 loosens under each T backs rise to beam, The displacement of each hydraulic jack 1 is controlled by corresponding displacement meter 2.Each actual jacking displacement data of T beams is as shown in table 3.
Table 3:The actual jacking displacement of each T beams(Unit:㎜)
Beam is numbered 1# 2# 3# 4# 5# 6#
Actual jacking displacement 3.53 3.66 3.87 3.82 3.63 3.58
From the point of view of jacking result, although being fitted without hydraulic jack 1 under 2#, 5# beam, itself and adjacent two panels T beams are utilized Between connection 2#, 5# beam are raised up, and connection between adjacent two panels beam being capable of Transfer of Shear, it is ensured that bridge structure Horizontal tensile stress is smaller or occurs without tension.Meanwhile, the present embodiment only needs to arrange 4 hydraulic jacks, relatively conventional side Method each bearing is disposed about a hydraulic jack and compares, and The present invention reduces 2 hydraulic jacks, substantially increases economy Benefit.
3rd step, bearing treatment.It is such as completely loose first with the loosening situation for striking bar each bearing 3 of inspection after the completion of jacking It is dynamic, jacking step by step individually is carried out to the hydraulic jack 1 near the bearing 3, until the bearing 3 loosens completely.During construction, first Temporary support is placed on bent cap, the failure of hydraulic jack 1 occurs surprisingly, and according to the disease of bearing 3 in preventing work progress Degree carries out come to nothing treatment or replacing treatment to it, during replacing, takes centering, location measure to determine the riding position of new bearing 3.
4th step, unloads beam.After completing the treatment of each T beams undersetting 3, slow unloading hydraulic jack 1, uninstall process To lifting operation conversely, making each bearing 3 be brought into close contact with corresponding T beams.
Repeating the above steps carries out the next pier of bridge, the treatment of table mount.
Remaining same embodiment 1.
Embodiment 4:
Bridge described in the present embodiment is rib beam type bridge, and the girt strip is T beams, and a width of 10.5m of bridge, single span span length 25m are disposed with 5 T beams, deck-molding 1.7m, bridge floor is continuous.Treatment each bearing 3 under the T beams on abutment.
The first step, installs jack-up system.As shown in figure 4, respectively arranging a hydraulic pressure near 1#, 3#, 5# beam support 3 Jack 1, displacement meter 2 is arranged near every T soffits bearing 3, and each hydraulic jack 1, displacement meter 2 are in same width side Upwards.To ensure concrete strength more than the pressure that local pressure face is born, and each T beam stress is uniform during jacking, liquid The top of jack 1 is pressed to be provided with jacking steel plate, jacking steel plate is parallel with T soffits to be close to.
Second step, lifting operation, for T beam type bridges, top lifting height is controlled in 3.5 ㎜ or so.In the control of jack-up system Under device control processed, whether examination jacking, the jacking simultaneously of each hydraulic jack 1, it is therefore an objective to detect jack-up system state are carried out first Space good and between the elimination top steel plate of hydraulic jack 1 and T beams.Examination jacking after the completion of, each hydraulic jack 1 simultaneously by Level jacking, each jacking displacement is 0.8 ㎜~1.2 ㎜(The present embodiment is 1.0 ㎜), once observed per jacking between adjacent beams Displacement difference, control the displacement difference between adjacent two beam to be not more than 0.3 ㎜, until each bearing 3 loosens under each T backs rise to beam, The displacement of each hydraulic jack 1 is controlled by corresponding displacement meter 2.Each actual jacking displacement data of T beams is as shown in table 4.
Table 4:The actual jacking displacement of each T beams(Unit:㎜)
Beam is numbered 1# 2# 3# 4# 5#
Actual jacking displacement 3.64 3.66 3.73 3.51 3.72
From the point of view of jacking result, although being fitted without hydraulic jack 1 under 2#, 4# beam, itself and adjacent two panels T beams are utilized Between connection 2#, 4# beam are raised up, and connection between adjacent two panels beam being capable of Transfer of Shear, it is ensured that bridge structure Horizontal tensile stress is smaller or occurs without tension.Meanwhile, the present embodiment only needs to arrange 3 hydraulic jacks, relatively conventional side Method each bearing is disposed about a hydraulic jack and compares, and The present invention reduces 2 hydraulic jacks, substantially increases economy Benefit.
3rd step, bearing treatment.It is such as completely loose first with the loosening situation for striking bar each bearing 3 of inspection after the completion of jacking It is dynamic, jacking step by step individually is carried out to the hydraulic jack 1 near the bearing 3, until the bearing 3 loosens completely.During construction, first Temporary support is placed on bent cap, the failure of hydraulic jack 1 occurs surprisingly, and according to the disease of bearing 3 in preventing work progress Degree carries out come to nothing treatment or replacing treatment to it, during replacing, takes centering, location measure to determine the riding position of new bearing 3.
4th step, unloads beam.After completing the treatment of each T beams undersetting 3, slow unloading hydraulic jack 1, uninstall process To lifting operation conversely, making each bearing 3 be brought into close contact with corresponding T beams.
Repeating the above steps carries out the next pier of bridge, the treatment of table mount.
Remaining same embodiment 1.
Embodiment 5:
Bridge described in the present embodiment is rib beam type bridge, and the girt strip is box beam, a width of 23.0m of bridge, single span span length 25m, arrangement There are 6 box beams, deck-molding 1.4m, bridge floor is continuous.Treatment each bearing 3 under the box beam on abutment.
The first step, installs jack-up system.As shown in figure 5, each near bearing 3 on the right of 1#, 4#, 5# box beam arrange one Individual hydraulic jack 1, respectively arranges a hydraulic jack 1 near 2#, 3#, 6# box beam left side bearing 3, and displacement meter 2 is arranged Between hydraulic jack 1 and corresponding bearing 3, and near bearing 3, each hydraulic jack 1, displacement meter 2 are in same width On degree direction.To ensure concrete strength more than the pressure that local pressure face is born, and each box beam stress is equal during jacking Even, the top of hydraulic jack 1 is provided with jacking steel plate, and jacking steel plate is parallel with box beam bottom surface to be close to.
Second step, lifting operation, for rib beam type bridge, top lifting height is controlled in 3.5 ㎜ or so.In the control of jack-up system Under device control processed, whether examination jacking, the jacking simultaneously of each hydraulic jack 1, it is therefore an objective to detect jack-up system state are carried out first Space good and between the elimination top steel plate of hydraulic jack 1 and box beam.After the completion of examination jacking, each hydraulic jack 1 is simultaneously Jacking step by step, each jacking displacement is 0.8 ㎜~1.2 ㎜(The present embodiment is 1.0 ㎜), per jacking once observe adjacent beams it Between displacement difference, control the displacement difference between adjacent two beam to be not more than 0.3 ㎜, until each box beam jacking is to the pine of each bearing under beam 3 Dynamic, the displacement of each hydraulic jack 1 is controlled by corresponding displacement meter 2.Each actual jacking displacement data of box beam is as shown in table 5.
Table 5:The actual jacking displacement of each box beam(Unit:㎜)
Beam is numbered 1# 2# 3# 4# 5# 6#
Actual jacking displacement 3.57 3.79 3.82 3.84 3.73 3.55
From the point of view of jacking result, although being fitted without hydraulic jack 1 under 2#, 4# box beam, itself and adjacent two panels are utilized Connection between box beam raises up 2#, 4# box beam, and connection between adjacent two panels beam being capable of Transfer of Shear, it is ensured that bridge Girder construction horizontal tensile stress is smaller or occurs without tension.Meanwhile, the present embodiment only needs to arrange 6 hydraulic jacks, relatively Conventional method each bearing is disposed about a hydraulic jack and compares, and The present invention reduces 6 hydraulic jacks, greatly improves Economic benefit.
3rd step, bearing treatment.It is such as completely loose first with the loosening situation for striking bar each bearing 3 of inspection after the completion of jacking It is dynamic, jacking step by step individually is carried out to the hydraulic jack 1 near the bearing 3, until the bearing 3 loosens completely.During construction, first Temporary support is placed on bent cap, the failure of hydraulic jack 1 occurs surprisingly, and according to the disease of bearing 3 in preventing work progress Degree carries out come to nothing treatment or replacing treatment to it, during replacing, takes centering, location measure to determine the riding position of new bearing 3.
4th step, unloads beam.After completing the treatment of each box beam undersetting 3, slow unloading hydraulic jack 1 was unloaded Journey is to lifting operation conversely, making each bearing 3 be brought into close contact with corresponding box beam.
Repeating the above steps carries out the next pier of bridge, the treatment of table mount.
Remaining same embodiment 1.
Embodiment 6:
For freely-supported bridge, the corresponding position of another bridge or plate is also disposed with hydraulic jack 1 to the present invention on same bridge pier With displacement meter 2.
For freely-supported bridge, the jacking displacement difference of adjacent two panels beam or plate is no more than 0.1 ㎜ to the present invention on same bridge pier.
Bridge described in the present embodiment is hollow slab type bridge, and a width of 8m of bridge, single span span length 20m are disposed with 6 cored slabs, Method Pre-stress Concrete Hollow Slab 0.95m high, bridge floor is continuous.Treatment each bearing 3 under the cored slab on bridge pier.
The first step, installs jack-up system.As shown in fig. 6, each near A sides 1#, 4#, 5# plate left side bearing 3 arrange one Individual hydraulic jack 1, respectively arranges a hydraulic jack 1 near bearing 3 on the right of 2#, 6# plate, and displacement meter 2 is arranged in every On the longitudinal axis of cored slab bottom surface, each hydraulic jack 1, displacement meter 2 are on same width.Meanwhile, to prevent entirety Formula floorings ftracture, and for freely-supported bridge, the corresponding position of another across cored slab B sides is also disposed with hydraulic pressure thousand on same bridge pier Jin top 1 and displacement meter 2.Although the arrangement of hydraulic jack 1 does not accomplish absolute symmetrical, tend to symmetrical cloth Put, can smoothly process each bearing 3 under cored slab on the premise of positive bridge structure safe is protected.To ensure that concrete strength is more than The pressure that local pressure face is born, and each cored slab uniform force during jacking, the top of hydraulic jack 1 is provided with top Steel plate is risen, jacking steel plate is parallel with cored slab bottom surface to be close to.
Second step, lifting operation, for hollow slab type bridge, top lifting height is controlled in 3 ㎜ or so.In the control of jack-up system Under device control processed, whether examination jacking, the jacking simultaneously of each hydraulic jack 1, it is therefore an objective to detect jack-up system state are carried out first Space good and between the elimination top steel plate of hydraulic jack 1 and cored slab.After the completion of examination jacking, each hydraulic jack 1 is same When jacking step by step, each jacking displacement be 0.8 ㎜~1.2 ㎜(The present embodiment is 1.0 ㎜), adjacent panels are once observed per jacking Between displacement difference, control the displacement difference between laterally adjacent two plate to be not more than 0.2 ㎜, the displacement difference between longitudinally adjacent two plate No more than 0.1 ㎜, until each cored slab jacking to each bearing 3 under plate loosens, the displacement of each hydraulic jack 1 is by corresponding position Meter 2 is moved to control.Each actual jacking displacement data of cored slab is as shown in table 6.
Table 6:The actual jacking displacement of each cored slab(Unit:㎜)
Plate is numbered 1# 2# 3# 4# 5# 6#
Actual jacking displacement A sides 3.10 3.17 3.22 3.28 3.19 3.02
Actual jacking displacement B sides 3.09 3.21 3.28 3.31 3.25 3.10
It is empty with adjacent two panels using it although being fitted without hydraulic jack 1 under 3# cored slabs from the point of view of jacking result Connection between core raises up 3# cored slabs, and connection between adjacent two panels cored slab being capable of Transfer of Shear, it is ensured that Bridge structure horizontal tensile stress is smaller or occurs without tension.Meanwhile, the present embodiment only needs to arrange 10 hydraulic jacks, phase A hydraulic jack is disposed about to conventional method each bearing to compare, The present invention reduces 14 hydraulic jacks, significantly Improve economic benefit.
3rd step, bearing treatment.It is such as completely loose first with the loosening situation for striking bar each bearing 3 of inspection after the completion of jacking It is dynamic, jacking step by step individually is carried out to the hydraulic jack 1 near the bearing 3, until the bearing 3 loosens completely.During construction, first Temporary support is placed on bent cap, the failure of hydraulic jack 1 occurs surprisingly, and according to the disease of bearing 3 in preventing work progress Degree carries out come to nothing treatment or replacing treatment to it, during replacing, takes centering, location measure to determine the riding position of new bearing 3.
4th step, unloads beam.After completing the treatment of each cored slab undersetting 3, slow unloading hydraulic jack 1, unloading Process is to lifting operation conversely, making each bearing 3 be brought into close contact with corresponding cored slab.
Repeating the above steps carries out the next pier of bridge, the treatment of table mount.
Remaining same embodiment 1.
Embodiment 7:
Bridge described in the present embodiment is rib beam type bridge, and the girt strip is T beams, and a width of 12.5m of bridge, single span span length 30m are disposed with 6 T beams, deck-molding 2.0m, bridge structure is continuous, and bridge floor is continuous.Treatment each bearing 3 under the T beams on abutment.
The first step, installs jack-up system.As shown in fig. 7, respectively being arranged under diaphragm near the right side of 1#, 4# beam support 3 One hydraulic jack 1, a hydraulic jack 1 is respectively arranged under diaphragm near the left side of 3#, 6# beam support 3;Displacement meter 2 It is arranged between hydraulic jack 1 and corresponding bearing 3, and near bearing 3, each hydraulic jack 1, displacement meter 2 are same On one width.To ensure concrete strength more than the pressure that local pressure face is born, and each T beam stress during jacking Uniformly, the top of hydraulic jack 1 is provided with jacking steel plate, and jacking steel plate is parallel with T soffits to be close to.
Second step, lifting operation, for T beam type bridges, top lifting height is controlled in 3.5 ㎜ or so.In the control of jack-up system Under device control processed, whether examination jacking, the jacking simultaneously of each hydraulic jack 1, it is therefore an objective to detect jack-up system state are carried out first Space good and between the elimination top steel plate of hydraulic jack 1 and T beams.Examination jacking after the completion of, each hydraulic jack 1 simultaneously by Level jacking, each jacking displacement is 0.8 ㎜~1.2 ㎜(The present embodiment is 1.0 ㎜), once observed per jacking between adjacent beams Displacement difference, control the displacement difference between adjacent two beam to be not more than 0.3 ㎜, until each bearing 3 loosens under each T backs rise to beam, The displacement of each hydraulic jack 1 is controlled by corresponding displacement meter 2.Each actual jacking displacement data of T beams is as shown in table 7.
Table 7:The actual jacking displacement of each T beams(Unit:㎜)
Beam is numbered 1# 2# 3# 4# 5# 6#
Actual jacking displacement 3.62 3.67 3.89 3.86 3.62 3.59
It is empty with adjacent two panels using it although being fitted without hydraulic jack 1 under 2#, 5#T beam from the point of view of jacking result Connection between core raises up 2#, 5#T beam, and connection between adjacent two panels T beams being capable of Transfer of Shear, it is ensured that bridge Girder construction horizontal tensile stress is smaller or occurs without tension.Meanwhile, the present embodiment only needs to arrange 4 hydraulic jacks, relatively Conventional method each bearing is disposed about a hydraulic jack and compares, and The present invention reduces 2 hydraulic jacks, greatly improves Economic benefit.
3rd step, bearing treatment.It is such as completely loose first with the loosening situation for striking bar each bearing 3 of inspection after the completion of jacking It is dynamic, jacking step by step individually is carried out to the hydraulic jack 1 near the bearing 3, until the bearing 3 loosens completely.During construction, first Temporary support is placed on bent cap, the failure of hydraulic jack 1 occurs surprisingly, and according to the disease of bearing 3 in preventing work progress Degree carries out come to nothing treatment or replacing treatment to it, during replacing, takes centering, location measure to determine the riding position of new bearing 3.
4th step, unloads beam.After completing the treatment of each T beams undersetting 3, slow unloading hydraulic jack 1, uninstall process To lifting operation conversely, making each bearing 3 be brought into close contact with corresponding T beams.
Repeating the above steps carries out the next pier of bridge, the treatment of table mount.
Remaining same embodiment 1.

Claims (6)

1. a kind of processing method of modular bridge beam support, it is characterized in that it comprises the following steps:
(1) jack-up system is installed:Jack-up system includes hydraulic jack, displacement meter and control device;Hydraulic jack is arranged on Near the bearing of beam or plate one end, and it is arranged on the same width of each beam or plate;Displacement meter is arranged in each beam or plate Bottom surface, and be arranged on the same width of each beam or plate;
For board-like bridge, a hydraulic jack is respectively arranged at the beam rib position on the outside of its side plate, it is then every to bridge center 1~2, interval bearing arranges a hydraulic jack, and is arranged symmetrically centered on bridge longitudinal axis or almost symmetry cloth Put;Displacement meter is arranged on the longitudinal axis of each plate;
For beam type bridge, a hydraulic jack is respectively arranged at the beam rib of its side bar or diaphragm position, then in bridge A hydraulic jack is arranged in centre at interval of 1~2 bearing, and is arranged symmetrically or almost symmetry centered on bridge longitudinal axis Arrangement;Displacement meter is disposed adjacent under the beam rib of bearing;
(2) jacking:Under the control device control of jack-up system, each hydraulic jack presses the jacking step by step simultaneously of jacking displacement, often ㎜~1.2 ㎜ of secondary jacking 0.8, the displacement difference between adjacent beams or plate is once observed per jacking, it is ensured that the displacement difference of its plate or beam No more than 0.2 ㎜~0.3 ㎜, the displacement of each hydraulic jack is controlled by the displacement meter under correspondence beam or plate, until Bearing under each beam or plate departs from the bottom surface of beam or plate;
(3) bearing treatment:After completing lifting operation, temporary support is installed near each bearing, and according to the degree of disease pair of bearing Disease bearing under each beam or plate carries out come to nothing treatment or replacing treatment;
(4) unload beam:After completing the Disease Processing of bearing, by (2) lifting operation reverse procedure unloads load hydraulic thousand step by step with step Jin top, makes each bearing be brought into close contact with corresponding beam or plate;
Repeat step (1)~(4), carry out down the treatment of a piece of beam or plate undersetting.
2. the processing method of modular bridge beam support according to claim 1, it is characterized in that for freely-supported bridge, same bridge The corresponding position of another bridge or plate is also disposed with hydraulic jack and displacement meter on pier.
3. the processing method of modular bridge beam support according to claim 1, it is characterized in that the combined bridge across Footpath is less than or equal to 50m.
4. the processing method of modular bridge beam support according to claim 1, it is characterized in that for freely-supported bridge, same bridge The jacking displacement difference of adjacent two panels beam or plate is no more than 0.1 ㎜ on pier.
5. the processing method of modular bridge beam support according to claim 1, it is characterized in that in full-bridge integral jacking, peace Hydraulic jack and displacement meter under all beams or plate be arranged on same width and same longitudinal direction on.
6. a kind of processing method of modular bridge beam support as described in claim 1 or 2 or 3 or 4 or 5 in rib beam type bridge or Applied in box beam formula bridge or board-like bridge, i.e., under rib beam type bridge or each beam of box beam formula bridge or board-like bridge or plate Board-like or pot rubber bearing treatment.
CN201710228285.8A 2017-04-10 2017-04-10 The processing method of modular bridge beam support and application Pending CN106930198A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710228285.8A CN106930198A (en) 2017-04-10 2017-04-10 The processing method of modular bridge beam support and application

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710228285.8A CN106930198A (en) 2017-04-10 2017-04-10 The processing method of modular bridge beam support and application

Publications (1)

Publication Number Publication Date
CN106930198A true CN106930198A (en) 2017-07-07

Family

ID=59425613

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710228285.8A Pending CN106930198A (en) 2017-04-10 2017-04-10 The processing method of modular bridge beam support and application

Country Status (1)

Country Link
CN (1) CN106930198A (en)

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104988853A (en) * 2015-05-26 2015-10-21 上海同罡建筑工程有限公司 Method for replacing and repairing supports
CN105297643A (en) * 2015-11-20 2016-02-03 湖南城市学院 Method for replacing support of hollow slab type bridge
KR20160026200A (en) * 2014-08-29 2016-03-09 이윤재 System for floating superstructure of bridge by using computer
CN105442461A (en) * 2015-11-20 2016-03-30 湖南城市学院 Jacking method for hollow boards of hollow board type bridge and application in support disengaging treatment
CN106284079A (en) * 2016-08-08 2017-01-04 中交三公局桥梁隧道工程有限公司 A kind of bridge break post replace classification synchronize integral jacking construction method

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20160026200A (en) * 2014-08-29 2016-03-09 이윤재 System for floating superstructure of bridge by using computer
CN104988853A (en) * 2015-05-26 2015-10-21 上海同罡建筑工程有限公司 Method for replacing and repairing supports
CN105297643A (en) * 2015-11-20 2016-02-03 湖南城市学院 Method for replacing support of hollow slab type bridge
CN105442461A (en) * 2015-11-20 2016-03-30 湖南城市学院 Jacking method for hollow boards of hollow board type bridge and application in support disengaging treatment
CN106284079A (en) * 2016-08-08 2017-01-04 中交三公局桥梁隧道工程有限公司 A kind of bridge break post replace classification synchronize integral jacking construction method

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
陈晓东: "同步顶升技术在广三高速扩建工程中的应用", 《中国新技术新产品》 *

Similar Documents

Publication Publication Date Title
CN206646417U (en) A kind of multispan concrete simply supported beam bridge integral jacking system
CN102477717B (en) A kind of bridge pushing construction method
CN103953078B (en) Pile tube resistance to plucking single pole power transmission experimental rig
CN111794127A (en) Counter-force prepressing system and prepressing method of ultrahigh suspension casting beam 0# block support
CN113668410A (en) Pier deviation rectifying method using main beam to provide counter force
CN106930198A (en) The processing method of modular bridge beam support and application
CN105297643B (en) Hollow slab type Bridge Support Replacement method
KR20090100476A (en) A bridge lifting apparatus and bridge lifting method using the same
CN105442461A (en) Jacking method for hollow boards of hollow board type bridge and application in support disengaging treatment
KR100865752B1 (en) Shift method of bridge bearing of railroad
JP4424744B2 (en) Bridge replacement method
CN208201670U (en) A kind of assembled T-type back liter auxiliary steel member
CN112761081B (en) Replacement structure and construction method for active ultra-wide beam body support
CN214328534U (en) 0# block bracket pre-pressing device of continuous rigid frame bridge
CN214328579U (en) Replacement structure for active ultra-wide beam body support
CN211547412U (en) Precise control bridge jacking system
CN206986701U (en) A kind of steel box girder bridge Program for structural Transformation system
TW201437457A (en) Jack stand for bridge lifting
CN209583522U (en) T-type beams of concrete jack-up system
CN109056658B (en) Concrete panel defect repairing construction method
CN208167496U (en) Cable-stayed bridge π type concrete girder combined type cast-in-place support
CN111549685B (en) Method for jacking box girder of old bridge
CN220767688U (en) Dual-purpose counterforce device capable of being used for fixing expansion joint
CN204455878U (en) Urban interchange maintenance is used can length travel temporary support system
CN114250721B (en) Construction method for jacking broken engineering column

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20170707