CN106284079A - A kind of bridge break post replace classification synchronize integral jacking construction method - Google Patents

A kind of bridge break post replace classification synchronize integral jacking construction method Download PDF

Info

Publication number
CN106284079A
CN106284079A CN201610641356.2A CN201610641356A CN106284079A CN 106284079 A CN106284079 A CN 106284079A CN 201610641356 A CN201610641356 A CN 201610641356A CN 106284079 A CN106284079 A CN 106284079A
Authority
CN
China
Prior art keywords
jacking
jack
steel
bridge
pier
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201610641356.2A
Other languages
Chinese (zh)
Inventor
王伟方
邢占军
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Middle Friendship Three Gong Ju Bridge Tunnel Engineering Co Ltd
Original Assignee
Middle Friendship Three Gong Ju Bridge Tunnel Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Middle Friendship Three Gong Ju Bridge Tunnel Engineering Co Ltd filed Critical Middle Friendship Three Gong Ju Bridge Tunnel Engineering Co Ltd
Priority to CN201610641356.2A priority Critical patent/CN106284079A/en
Publication of CN106284079A publication Critical patent/CN106284079A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D21/00Methods or apparatus specially adapted for erecting or assembling bridges

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Bridges Or Land Bridges (AREA)

Abstract

The invention discloses a kind of bridge break post replace classification synchronize integral jacking construction method, the key technology of the present invention is to use multiple safety supports, position limiting structure;Multi-faceted synchronization monitoring, monitoring means;Multiple safety locking motion;High-accuracy electronics calculates update the system automatically, and overall process, omnibearing synchronous collaboration complete integral jacking.Use full-automatic 180 high accuracy of domestic advanced person simultaneously, the PLC hydraulic synchronization lifting control system operation of big stroke, synchronous control accuracy reaches ± 2 millimeters, PLC hydraulic synchronization controls to be configured with hydraulic lock and mechanical lock double insurance device, and measurement and the monitoring system in each parts key position installation settings precision, overall process, done with high accuracy is to top lifting height and the Synchronization Control of displacement, can be efficient, securely achieve high headroom, large area, heavy weight bridge Integral synchronous lifting operation, also can be as bridge jacking, pushing tow, the construction of correction is used for reference, there is good society and economic worth.

Description

A kind of bridge break post replace classification synchronize integral jacking construction method
Technical field
The present invention relates to technical field of building construction, be specifically related to the construction method of a kind of bridge Integral synchronous jacking.
Background technology
The needs quickly increased due to China's reform and opening-up and economy, last century, the nineties middle and late stage started on a large scale Infrastructure construction, most road and bridges were built this period, based on designing technique at that time, construction operation technology, executed Construction equipment, vehicle flowrate, the impact of urban development planning and the dynamics of investment of limitation, especially urban construction, Bridge Design grade, Linear and circuit Longitudinal Slope Design is the most on the low side.
But along with the enhancing of China's overall national strength, world multi-polarization and economic globalization, culture variation, social informatization Deep development, Highway Cause either construction scale or construction criteria have a large span, unconventional development, due to Old bridge capacity reduction, bridge settlement, the swift and violent growth of the volume of traffic, navigation grade raising, the raising of underway grade, road Line transformation etc. causes under-clearance not enough, and bridge uses function just can not meet requirement.If simply because be linearly unsatisfactory for, under bridge Headroom is unsatisfactory for requiring just to remove reconstruction, can cause huge waste.In order to meet urban road Fast Construction, quickly be open to traffic, Avoiding congestion in road, reduce overlapping investment, bridge jacking technology is also arisen at the historic moment.
Summary of the invention
It is an object of the invention to provide a kind of bridge break post replace classification synchronize integral jacking construction method, this construction Method solves bridge beam body entirety top, fall during a synchronization displacement difficult problem, the integral jacking of bridge is served key Effect.
For achieving the above object, the present invention provide a kind of bridge break post replace classification synchronize integral jacking construction method, It is characterized in that, construction method includes:
(1), prepare before construction;
(2), traffic close, the traffic around enclosed bridge;
(3), the counter-force foundation construction of lifting-up support;
(4), jacking support system installs and stopping means is installed, and jacking support system is used for supporting jack-up system, spacing Device is used for preventing bridge lateral and length travel;
(5), jacking control system and monitoring system install, jacking control system includes PLC jack-up system, PLC jacking system System includes that first group of jack, second group of jack and displacement transducer, first group of jack and second group of jack are positioned at top Rise between support system and bridge coping;
(6), the pier stud of bridge is blocked;
(7), alternately classification Integral synchronous jacking, including a, examination jacking, b, drive first group of jack synchronization of jacking up bridge Beam, adds pading plate during jacking below the hydraulic cylinder of jack, uses the jacking of displacement sensor bridge simultaneously Highly, after one stroke of bridge jacking, take out steel plate and below the hydraulic cylinder of second group of jack pad set bracing members cushion block, make The top of the hydraulic cylinder of second group of jack flushes with the top of the hydraulic cylinder of first group of jack;C, drive second group of jack Jacking bridge, one stroke of bridge jacking, and control first group of jack receipts cylinder, at the lower section pad of first group of jack hydraulic cylinder If bracing members cushion block, the top of hydraulic cylinder of first group of jack is made to flush with the top of the hydraulic cylinder of second group of jack;d、 Repeat step b and step c until jacking is to the top lifting height designed;
(8), pier stud is increased;
(9), dismounting all devices.
Preferably, the counter-force basis in step (3) is various ways, and abutment position uses cushion cap to expand concrete foundation work Put forth effort basis for lattice steel pipe, use pre-buried ring flange to bolt with lattice steel pipe column;Pier column height smaller part lattice steel Tubing string uses cast-in-place pillar concrete foundation;Pier column height larger part directly uses lower wing shape steel hoop as counter-force base Plinth.
Preferably, in step (4), jacking support system includes that wing shape steel hoop support system, wing shape steel hoop are passed Structure steel pipe column combined support system and lattice steel tubing string bar shaped support system.
Preferably, in step (4), in dish wing steel hoop support system, steel hoop uses 36 groups of high-strength bolt fastenings, sets altogether Counting 4 wings to install 2 groups of synchronous jack, supporting the main steel plate a plurality of strength rib of welding up and down and ensureing its bearing capacity, lower steel Anchor ear wing billet installed above, billet is installed again and reinforces brace steel post, installs jacking above steel column after fulcrum steel plate Device, it lays billet and is supported in steel hoop formation stress system.
Preferably, step (4) is wing by Force system in wing shape steel hoop and lattice steel pipe column combined support system Shape steel hoop, uses 3 Φ 609 pipe stiffener steel pipes to be formed stable by channel-section steel stull and diagonal brace welding below single wing Grid-system is as by Force system, and each component contact position is respectively mounted billet.
Preferably, lattice steel tubing string bar shaped support system in step (4), lower stress system uses many group Φ 609 steel pipe lattice Structure system, jack-up system installed above, jack-up system 60# installed above puts more energy into I-steel crossbeam, and each component contact position is all pacified Steel loading backing plate.
Preferably, step (4) is installed longitudinal limiting device, first by beam-ends head amputation 2cm after bridge floor cuts, and Installing longitudinal spacing pull bar (using the pre-stretch-draw of prestressing force) between two bridge, during reducing jacking, beam body floor projection increases Amount, stopping means uses high-strength bolt to be installed on design top surface of the beam position, and both sides spacing hole steel strand also uses punching jack Anchoring.
Preferably, in step (4), horizontal limit devices includes that concrete foundation, the spacing main body of steel pipe lattice, beam-ends are spacing Draw-in groove, steel pipe top steel strand wires stop and steel strand wires, the spacing main body of steel pipe lattice is positioned at bent cap both sides, and exists with high-strength bolt Bent cap side is installed spacing draw-in groove and is blocked steel pipe supervisor, and the upper welded limiting device of steel pipe supervisor, both sides stop steel strand is with thousand The anchoring of jin top, forms cross spacing system.
Preferably, in step (5) jacking control system mainly by oil pump, overflow valve, reversal valve, Pressure gauge, branching block, height Pressure flexible pipe, control valve group, hydraulic control one-way valve, jacking cylinder, jack, pressure transducer, displacement transducer, holding wire, display, Controller, power supply box, sub-control box, self-locking device and warning devices composition, can be automatically finished synchronous shift, it is achieved power and position Move control, the several functions such as operation locking, process show, fault alarm.
Preferably, in step (5), jacking control system uses monomer 600T, the jack of maximum 300mm stroke to amount to 180 Platform, often place's abutment arranges that 8 jack set 16 altogether;Squat pier every bent cap arranges that 16 jack lay 128 altogether;High pier is every Root bent cap arranges that 18 jack lay 36 altogether;Amount to 180, jack, be divided into two groups of alternately synchronizations of jacking up, jacking Time according to jacking stroke, until the position that design requires.
Preferably, in step (5), jacking control system is along with the increase of top lifting height, and eccentric compression occurs in jack, side Method uses following measures to ensure jack Vertical Compression: 1. jack self carries out 3 °~5 ° of tilt adjustment, and 2. abutment position increases If spherical hinge, 3. synchronous shift during bridge pier jacking, 4. jack uses along bridge to bar with reaction frame and distribution beam mounting flange Shape hole, it is ensured that slip, can carry out trace regulation.
Preferably, for ensureing that the overall gesture stability of bridge exists during in step (5), monitoring system refers to bridge jacking The technical monitoring carried out in the set goal state, and to various issuable unexpected adverse effects in work progress Safety monitoring, is a dynamic process, and along with the lifting of beam, the vertically and horizontally deviation etc. of beam can occur large change, the supporting of beam Beam stress state will be changed by the change relatively of point.A whole set of monitoring system is set for this, and to set necessity Early warning value and ultimate value, in order to attitude data is fed back to construction loading process, more effectively ensure jack-up construction quality and execute Work safety.Monitor including floor elevation;Soffit absolute altitude monitoring;Beam vertically and horizontally displacement observation;Beam body stress;The prison of support system Survey;Weather monitoring.
Preferably, in step (5), floor elevation monitoring lays 48 hydrostatic levels at bridge floor, is allowed to and benchmark monitor Communicate, as the datum mark of hydrostatic level monitoring, and be connected with many coal bodies network monitoring system and tele-control system and carry out Full automatic data monitoring and calculating.
Preferably, in step (5), absolute altitude monitoring in soffit is to more precisely detect jacking absolute altitude, at each beam of bridge The upstream and downstream of support position respectively arranges a stay-supported sensor, totally 24 measuring points, uses total powerstation and stay-supported sensor, with Track measures jacking precise height, provides foundation for lifting operation, it is possible to carries out supplementing to floor elevation test and checks.
Preferably, the vertically and horizontally displacement observation of step (5) central sill, arrange 14 monitoring points in beam body side altogether, use full station Instrument is tracked monitoring in the jacking full stage, utilizes coordinate method to calculate the vertically and horizontally displacement of beam, by indulging jacking process central sill The monitoring of transverse horizontal displacement, it is ensured that the horizontal displacement deviation of beam is in controlled range.
Preferably, step (5) central sill body stress is monitored, and is i.e. selecting at bearing and spaning middle section laying type vibration wire stress Meter, beam body spaning middle section, each cross section 12 longitudinal strain measuring points of layout, two transverse strain measuring points, altogether 13 cross sections, 156 measuring points, monitor in real time to vibratory stress gauge.By to beam body stress monitor, beam body can be grasped in jacking The uneven stress of the strong point in journey, to control jacking attitude.
Preferably, step (5) central sill support system is monitored, and lays vibratory string at 4 for the support system at the bottom of each jack Formula stressometer, by monitoring, stress and the deformation that can grasp support system in time take measures to control support system in time Deflection, make construction carry out in the environment of safely controllable.Vibratory stress gauge can be used to be tracked monitoring, and assist Appearance deformation detects, and grasps the duty of strutting system timely and accurately.
Preferably, weather monitoring in step (5), owing to girder is during jacking, it is in the free state of motion, level The constraint in direction is only by the frictional resistance at jacking.Whether sidesway or inclination can occur in beam wind effect, need wind-force is carried out Monitoring in real time.Bridge floor is arranged intelligence Pressure testing instrument, lifting operation overall process is carried out Pressure testing, calculate according to blast Formula, converses bridge lateral wind force value, effectively instructs jack-up construction operation.
Preferably, in step (6), pier stud cutting uses diamond chain saw cutting technique, i.e. diamond rope is at hydraulic motor Grinding pier stud around facet high-speed motion under driving, complete to cut work, pier stud can be cut under the most undisturbed state Separating, the diamond rope of cutting process high speed operating is by water cooling, and is taken away by grinding chip, is arranged by jacking impetus In bent cap bottom surface, raising bridge floor by jacking bent cap, jacking connects high pier shaft after completing again.
Preferably, in step (7), 0#~4# pier notch cuttype classification synchronization of jacking up program is: 1.: 4#, 3#, 2#, 1#, 0# pier Synchronization carries out 4 circulations jacking (25+25+25+15.2cm), completes 4# pier top liter, and 4# pier jack-up system exits jacking work. 2.: 3#, 2#, 1#, 0# pier synchronizes to carry out 5 jackings circulation (25+25+25+25+10.8cm), completes 3# pier top liter, 3# pier top liter System exits jacking work.3.: 2#, 1#, 0# pier synchronizes to carry out 6 jackings circulation (25+25+25+25+25+20.6cm), completes 2# pier top liter, 2# pier jack-up system exits jacking work.4.: 1#, 0# pier synchronizes to carry out 7 jacking circulation (25+25+25+25+ 25+25+6.6cm), completing 1# pier top liter, 1# pier jack-up system exits jacking work.5.: 0# pier is synchronized to carry out 7 jackings and follows Ring (25+25+25+25+25+25+16.8cm), completes 0# pier top liter, completes full-bridge jacking.
Preferably, in step (7) during jacking, due to access bridge girder, need to adjust longitudinal gradient, top lifting height higher, because of This, beam body security and stability and the balance of beam body during jacking have just become a problem that must assure that, otherwise can Cause beam body planar distortion, cause unstability and the cracking of beam body, cause the permanent damage of structure.Construction method is by using specially The PLC control system of industry, it has automatic compensation function, this device synchroballistic jack, uses PLC to control hydraulic synchronization system System is a kind of power and displacement with dual control system, and synchronization accuracy is ± 2.0mm, plays the effect of bit shift compensation, supervises whole shifting beam Whether process beam body is in 3 poised states, and maintains 3 poised states, thus can well ensure to push up act process Synchronicity, it is ensured that the safety of structure.
Bridge of the present invention break post alternately classification synchronize integral jacking construction method have the advantage that
The operation principle of " disconnected post classification synchronization of jacking up " is that jacking impetus is arranged on bent cap bottom surface, is initially switched off pier stud, Raising bridge floor by jacking bent cap, jacking connects high pier shaft after completing again.Classification synchronization of jacking up is as entirety using access bridge, will top Rise is divided into multistage stroke, and each jack is all according to identical formation synchronous parallel jacking.During jacking, jacking is high The one of degree minimum is across rotating around rotary shaft, until jacking puts in place, and other synchronization of jacking up that collapses simultaneously;After being cross over position when one, then with just Jacking put in place across bent cap center be rotary shaft, next across rotate jacking put in place, other synchronization of jacking up simultaneously;By that analogy.Directly Put in place to last across jacking.
" alternately classification synchronization of jacking up " operation principle is to use PLC hydraulic synchronization to replace jacking.Alternately jacking is every Two groups of jack that can actively apply top lift are installed at the layout of individual support summit, and are controlled hydraulic power unit driving two by control station Group jack carries out alternately and repeatedly jacking, and every 25cm is as a stroke.In implementation process, first by first group of jack jacking one Individual stroke, gradually adds pading plate during jacking simultaneously, in case beam body is fallen suddenly when jack lost efficacy.One stroke completes After, controlling hydraulic power unit by control station and drive second group of jack, cylinder received by first group of jack simultaneously, and at its piston underlay If the steel cushion block of corresponding height supports.Repeat above step, until completing whole jacking process.All jack pass through PLC liquid Pressure synchronous control system is controlled jacking speed and stroke, and synchronous control accuracy reaches ± 2 millimeters.
" Integral synchronous jacking " operation principle is to use infrared ambulator and laser on the basis of original bridge jacking Sensor observation monitoring change in displacement, and utilize the change of magnetic flux to carry out Non-Destructive Testing, by modern advanced optical fiber and numeral Monitoring transmission, hydraulic pressure drive control system, computer model treatment technology are integrated, and by mechanical equipment system and traditional bridge structure Analyze and maintenance technology be to combination, solve bridge beam body entirety top, fall during a shifted synchronous difficult problem, the entirety to bridge Jacking serves critical effect.
Accompanying drawing explanation
Fig. 1 is the schematic flow sheet of a kind of detailed description of the invention of construction method of the present invention;
Fig. 2 is the structural representation of wing shape a kind of detailed description of the invention of anchor ear support system of the present invention;
Fig. 3 is wing shape anchor ear of the present invention and the structure of lattice steel pipe post a kind of detailed description of the invention of combined support system Schematic diagram;
Fig. 4 is the structural representation of lattice steel pile tube a kind of detailed description of the invention of bar shaped support system of the present invention;
Fig. 5 is the structural representation of a kind of detailed description of the invention of longitudinal limiting device of the present invention;
Fig. 6 is the structural representation of a kind of detailed description of the invention of horizontal limit devices of the present invention;
Fig. 7 is the structural representation of a kind of detailed description of the invention of hydrostatic level of the present invention;
Fig. 8 is the layout schematic diagram of a kind of detailed description of the invention of floor elevation monitoring stations of the present invention;
Fig. 9 is the layout schematic diagram of a kind of detailed description of the invention of bottom elevation monitoring stations of the present invention;
Figure 10 is the layout schematic diagram of box beam of the present invention vertically and horizontally displacement observation a kind of detailed description of the invention of point;
Figure 11 is the layout schematic diagram of beam body stress monitoring a kind of detailed description of the invention of point of the present invention.
In Fig. 2: 101. times wing shape steel hoop 102. connects 103. times billet 104. hydraulic jack of high steel pipe post Wing shape steel hoop 107. column 108. bent cap 109. vibratory stress gauge on billet 106. in liter system 105.;
In Fig. 3: 201. Φ 609 steel pipe column 202. channel-section steel stulls and 203. times pading plate 204. hydraulic jacks of diagonal brace Wing shape steel hoop 207. column 208. bent cap 209. type vibration wire stress on a pading plate 206. on jack-up system 205. Meter;
In Fig. 4: 301. Φ 609 steel pipe column 302. channel-section steel stulls and 303. times pading plate 304. hydraulic jacks of diagonal brace I-steel transverse distribution beam 307. vibratory stress gauge on a pading plate 306. on jack-up system 305.;
In Fig. 5: 401. beam slab 402. expansion joint 403. stopper slot 404. anchor bolt 405. jack 406. in advance should Power steel strand wires;
In Fig. 6: 501. beam slab 502. concrete foundation 503. Φ 609 steel pipe column 504. channel-section steel stull and diagonal braces 505. Bent cap spacing draw-in groove 506. cross spacing device 507. jack 508. prestress wire 509. bent cap;
In Fig. 7: 1, liquid level sensor 2. protective cover 3. nut 4. bolt 5. fluid cylinder 6. floating drum 7. foundation bolt 8. Gas-tpe fitting 9. liquid pipe connection 10. trachea 11. liquid pipe 12. anti-icing fluid 13. wire 14.PVC wired hose 15. trachea blocks up 16. liquid pipe plugs;
In Fig. 8: 601, beam slab 602. bent cap 603. hydrostatic level layout points;
In Fig. 9: 701, beam slab 702. bent cap 703. column 704. stay wire sensor;
In Figure 10: 801, beam slab 802. bent cap 803. monitoring points of displacement;
In Figure 11: 901. beam slab 902. bridge substructure 903. vibratory stress gauges.
Detailed description of the invention
Detailed description below is used for illustrating the present invention, but is not limited to the scope of the present invention.
In the present invention, " bigger " refers to that, more than 50%, " less " refers to less than 50%.
The detailed description of the invention of the construction method of the present invention is as follows:
1, prepare before construction
Prepare before construction to refer to by equipment, material, personnel and the data etc. of construction on deck, generally can include as follows Usual procedure: measurement is checked, data compilation, technique preparation, monitoring device prepare, jack-up system prepares, component and fitting processing prepares, Construction machinery prepares, transport prepares, construction material prepares, safety devices prepare.
2, traffic is closed
Traffic is closed for the sake of being in order at safety, prevents from, during bridge construction, vehicle accident occurs, generally comprises the most common arranging Execute: contact Competent Authorities of Transport and Communications carries out traffic closing, safe enclosing, safety sign board arranges installation, security protection is implemented to arrange.
3, counter-force foundation construction
Counter-force basis refers to prevent from producing built on the sand bottom lifting-up support subsiding or offseting, common lifting-up support Counter-force basis can use following Three models:
1), bar shaped Extended chemotherapy
As a example by the Xin Bei viaduct of Chengdu, 0#, 22# abutment, the left width of 1#, 2#, 21# pier without cushion cap pier at, first carry out Foundation bearing capacity raising processes, then pours bar shaped Extended chemotherapy, pre-buried bracing frame ground glue bolt.
2), increasing section cushion cap foundation
Original cushion cap excavation, surface dabbing, bar planting, assembling reinforcement, pre-embedded anchoring bolts, concreting, with former cushion cap Shape all-in-one-piece expands cushion cap counter-force basis.For the right width of 1#, 2#, 21# pier.
3), butterfly steel hoop
At the round pier stud that cushion cap end face above pier stud height is bigger, block position at pier stud and steel hoop, jacking are installed up and down Stand steel pipe is arranged on steel hoop, uses the frictional resistance of upper and lower steel hoop to undertake jacking weight.
4, support system, stopping means are installed
Support system is for supporting lifting-up support and the pier stud after blocking, common for bracing members bracket system and pier stud butterfly Shape steel hoop support system.
1), bracing members bracket system may include that pre-buried base, supporting steel pipe, temporary cushion block, level connection joint tie-rod, top Portion supports distribution beam.Steel pipe support uses triangular lattice steel pipe column, and for strengthening its stability, upper and lower two joint steel pipes pass through shaped steel Lateral Flange joint, whole supporting steel pipe and stablize steel pipe and form lattice, additionally the design high standard of 25cm by shaped steel lateral Steel pad is supported increasing of system.
2), pier stud butterfly steel hoop support system
Pier stud butterfly steel hoop is divided into upper and lower two kinds, lower steel hoop be equivalent to counter-force basis, upper steel hoop at the bottom of bent cap with Pier stud junction, steel hoop uses steel pipe to form steel construction with Plate Welding, and anchor ear two halves interannular uses high-strength bolt to connect, and embraces Arranging four steel corbels outside hoop iron pipe, bracket base plate is connected with jack base by bolt.
Stopping means is installed and is used for preventing during bridge jacking offseting, and common mainly includes that longitudinal limiting device is installed Install with horizontal limit devices.
1), longitudinal limiting device is installed
Along with the jacking of bridge, bridge projection is elongated, needs to ensure the width at position, expansion joint, ensures that bridge can not nothing simultaneously The length travel limited, installs push-pull device at fixed in expansion joint position.I.e. at girder span end per pass expansion joint setting many groups longitudinal spacing System, per pass caging system is made up of stretch-draw seat board, steel strand wires, food-through tension jack, oil pump etc., is first cut by bridge floor After, cm is filled in beam-ends head amputation 2, interspaces in advance, and synchronous tension longitudinal spacing jack during jacking, to control level Projection increases, it is ensured that the pretty good head of pier stud, it is ensured that jacking safety.
2), horizontal limit devices is installed
Bridge jacking is a dynamic process, needs real-time ensuring beam body not produce transverse horizontal displacement, particularly exists The abutment position that top lifting height is maximum.Cross spacing column is formed lattice by 3 steel pipe posts, shaped steel horizontal-associate.Same bent cap two The limited support top of end uses steel strand wires to pulling into entirety, draws wind, stopping means to be arranged on bent cap end along bridge to arranging eight words Head, spacing column is installed and is embedded in stopper slot, it is ensured that superstructure direction across bridge during jacking occurs without skew.
5, jacking control system, monitoring system are installed
1), synchronous jacking system is installed
Multi-point synchronization jacking system is mainly by control chamber, hydraulic power unit, displacement transducer, pressure transducer, high speed electrohydraulic Valve, switching valve, jack composition.When support system is installed, jack is installed, after completing, carries out jack-up system oil circuit, survey Amount, the loop configuration that controls are installed, pumping plant is installed.
1.. jack is installed: due to beam body axial elongation, jack center can be deviateed support center, be needed jack Adjusting centering and support center, simultaneously during Rotation of beam, jack has rotation simultaneously, needs at jack steel plate setting up and down cushion block Dispersion concentration power, and increase wedge leveling jack at afterbody.
Integral synchronous jack and oil pump are arranged: 0#, 22# abutment is often located abutment and arranged that 8 jack set 16 altogether; 1#~4# pier and 19#~21# pier, every bent cap arranges that 16 jack lay 128 altogether;5#~6# pier and 7#~8# pier, often Root bent cap arranges that 18 jack lay 36 altogether;Amount to 180 jack of jack, 0#~4#, each pier of 19#~22# pier It is equipped with two oil pumps, altogether 18 oil pumps.It is divided into two groups of alternating synchronization jackings.
2. .PLC jack-up system installation and debugging: PLC controls hydraulic synchronization lifting is a kind of power and the top of displacement Comprehensive Control The system of liter, by high pressure hydraulic jack, accurately according to the actual loading of beam, smoothly beam body is lifted on top, makes jacking process central sill The additional internal stress that body is subject to drops to minimum, and hydraulic jack is divided into group according to distributing position simultaneously, with displacement transducer group Become position closed loop, in order to control displacement and the attitude of jacking, it is ensured that the synchronicity of jacking process, it is ensured that the safety of structure.System Unite and be made up of hydraulic system (oil pump, oil cylinder etc.), detection several part such as sensor, computer control system.Hydraulic system by Computer controls, and can be automatically finished synchronous shift, it is achieved power and Bit andits control, operation locking, process show, fault alarm Deng several functions.
2), monitoring system is installed
1.. floor elevation monitoring device
Bridge elevation observation station is used for calculating the actual top lifting height of each bridge pier.Arranging floor elevation observation station can essence The true actual top lifting height knowing each bridge pier, after making jacking put in place, floor elevation is effectively controlled, and at jack-up construction Engineering effectively monitors bridge linear deviation.
Hydrostatic level is used to carry out floor elevation monitoring as it is shown on figure 3, floor elevation monitoring is main.Use static level Instrument can be convenient reading, quick to floor elevation whole day 24 hours monitoring in real time, and its precision is high, can reach 0.01mm.
2.. soffit absolute altitude monitoring device
Test to bridge bottom elevation, main total powerstation and the stay-supported sensor of using, tracking measurement jacking precise height, In order to lifting operation provides foundation, it is possible to carry out supplementing to floor elevation test and check.
Stay wire displacement sensor is that mechanical displacement is converted into the signal of telecommunication gageable, linearly.When tested When object produces displacement, pull coupled sensor rope, cable tie dynamic sensor drive mechanism and decoders-Synchronous Rotate;When displacement is reversely moved, the automatic revolving gear of sensor internal will automatically retract rope, and stretch receipts process at rope Its tension force of middle holding is constant;Thus export one and the directly proportional signal of telecommunication of rope amount of movement.In order to more precisely detect Jacking absolute altitude, we respectively arrange a stay-supported sensor, totally 24 measuring points at the upstream and downstream in each beam support position of bridge.
3.. beam vertically and horizontally displacement observation device
By the total powerstation monitoring to jacking process central sill vertically and horizontally horizontal displacement, it is ensured that the horizontal displacement deviation of beam is can In the range of control.Use total powerstation to be tracked monitoring in the jacking full stage, utilize coordinate method to calculate the vertically and horizontally displacement of beam.
4.. beam body monitor for stress
Beam body stress monitoring uses arranges that strain gauge monitors in real time.Sensor is by a root length degree, area and matter The steel wire composition that amount all determines, when certain pretension, this sensor has a fundamental frequency.When measured object stress is produced During the shape that changes, sensor can deform together, and the pulling force of steel wire produces change at that time, thus the frequency of sensor there occurs change, from And the frequency of sensor there occurs change, read this frequency change, it is possible to be converted into tested stress.By to beam body stress Monitoring, can grasp the beam body uneven stress of the strong point during jacking, to control jacking attitude.
According to bridge structure form and the interface feature of girder, selecting to layout at bearing and spaning middle section, beam body span centre cuts Face, 12 longitudinal strain measuring points, two transverse strain measuring points, altogether 13 cross sections, 156 measuring points are arranged in each cross section.
5.. the monitoring device of support system
Support system stress monitoring uses arranges that strain gauge monitors in real time.By monitoring, can grasp in time and prop up The stress of support body system and deformation take measures to control the deflection of support system in time, make construction at safely controllable environment Under carry out.Vibratory stress gauge can be used to be tracked monitoring, and assist appearance deformation to detect, grasp support timely and accurately The duty of system.
6.. weather monitoring device
Owing to girder is during jacking, being in the free state of motion, the constraint of horizontal direction is only rubbed by jacking Resistance.Whether sidesway or inclination can occur in beam wind effect, need wind-force is monitored in real time.Intelligence need to be arranged on bridge floor Energy Pressure testing instrument, carries out Pressure testing to lifting operation overall process, according to blast computing formula, converses bridge Cross Wind Force Value, efficiently controls jack-up construction homework precision.
6, pier stud blocks
Pier stud cutting uses diamond chain saw cutting technique, i.e. diamond rope high around facet under fluid motor-driven Pier stud is ground in speed motion, completes to cut work, and pier stud can be cut separation under the most undisturbed state, high in cutting process The diamond rope of speed operating is by water cooling, and is taken away by grinding chip.
7, classification Integral synchronous jacking is replaced
Utilize support synchronization of jacking up with " jacking Bit andits control be main lift-up pressure control be auxiliary " method strictly control.Directly The position required to design, should notice during jacking whether the elevation change of point of observation position and the change of power meet at any time and want Ask, and observe the works such as beam body with or without cracking phenomena until beam body jacking is to design attitude.
1), examination jacking
Carry out trying jacking before formal jacking, for observing and examine the duty of whole jack-up construction system, formally Before jacking, carrying out trying jacking, examination top lifting height is 20cm, and whether the service behaviour observing each work package meets requirement, inspection Look into whether whole jacking control system controls effectively.
1.. personnel, material and equipment preparation check, workmen and management personnel are carried out safety education, and right Points for attention during jacking are told somebody what one's real intentions are, and the preparation that torr turns equipment checks, to jack-up system and monitoring system System is debugged.
2.. cut off before jacking between bridge floor and contact, it is ensured that bearing replacement do not interfere with adjacent across structure, investigation bridge contact Releasing situation meets the requirements.
3.. cross spacing and longitudinal limiting device are checked, carries out close observation in the examination top stage, check limit body It is the most properly functioning.
4.. the lifting-up support set up is guided and supported and checks, it is ensured that its enough intensity, rigidity, stability, support span centre Amount of deflection want < 10mm, it is ensured that beam do not collapsed by support during jack-up, do not tilt, settle less and uniform.
2), jacking one-stroke work flow
Jacking prepares: transmitter receiver debugging, jack-up system debugging, jacking packet numbering, lift-up pressure, displacement setting and record Table;
Jacking operator and testing staff are in place: management is in place, testing staff is in place, the emergent group of jacking is in place;
Jacking commander's calling respond confirms: pauses the most immediately if any line pressure shift, adds by jacking form classification in stroke Carrying and record line pressure shift, following item has to come to nothing and pauses immediately;
Jacking axle casing attitude record;
Second stroke jacking prepares;
First stroke falls item;
Increase the first stroke support system;
Next stroke replaces jacking.
3), jacking one-stroke operating principle
Bridge Integral synchronous jacking is in the state that 2 groups of jack alternately support:
1.. 2 groups of jack are installed in the bottom needing jacking bridge structure, make the piston of jack arrange down, piston bottom Contour bracing members cushion block put by portion's pad.
2.. multiple displacement transducer is set in this bridge structure, in order to measure the top lifting height of bridge structure in real time.
3.. control hydraulic power unit by control station, drive the 1st group of jack to carry out a stroke of jacking bridge structure, During jacking, progressively add stablizing of support when pading plate jack lost efficacy simultaneously, after jacking a to stroke completes, take out Steel plate also sets the bracing members cushion block of corresponding height at the piston pad of the 2nd group of jack.
4.. control hydraulic power unit by control station, drive the 2nd group of jack to carry out the next row of jacking bridge structure Journey, controls the 1st group of jack simultaneously and receives cylinder, and sets the bracing members of corresponding height at the piston underlay of the 1st group of jack receiving cylinder Cushion block.
5.. repeat step 3,4, to carry out alternately and repeatedly jacking, until by bridge structure jacking to design altitude, in construction In connected by connecting bolt between stacked pad sets up and down bracing members cushion block fixing, between adjacent bracing members cushion block also by Connecting rod reinforcement by connection becomes lattice form.
4), notch cuttype classification synchronization of jacking up,
1. .0#~4# pier notch cuttype classification synchronization of jacking up:
The first step: 4# pier top liter is put in place;4# pier top rise is 90.2cm, is divided into 4 jacking circulation (25+25+25 + 15.2), 4#, 3#, 2#, 1#, 0# pier synchronizes to carry out above 4 circulation jackings, completes 4# pier top liter, and 4# pier jack-up system exits Jacking works.
Second step: 3# pier top liter is put in place;3# pier residue top lifting height is 110.8cm, is divided into 5 jacking circulation (25+ 25+25+25+10.8), 3#, 2#, 1#, 0# pier synchronizes to carry out above 5 circulation jackings, completes 3# pier top liter, 3# pier jack-up system Exit jacking work.
3rd step: 2# pier top liter is put in place;2# pier residue top lifting height is 145.6cm, is divided into 6 jacking circulation (25+ 25+25+25+25+20.6), 2#, 1#, 0# pier synchronizes to carry out above 6 circulation jackings, completes 2# pier top liter, 2# pier jack-up system Exit jacking work.
4th step: 1# pier top liter is put in place;1# pier residue top lifting height is 156.6cm, is divided into 7 jacking circulation (25+ 25+25+25+25+25+6.6), 1#, 0# pier synchronizes to carry out above 7 circulation jackings, completes 1# pier top liter, 1# pier jack-up system Exit jacking work.
5th step: 0# pier top liter is put in place;0# pier residue top lifting height is 166.8cm, is divided into 7 jacking circulation (25+ 25+25+25+25+25+16.8), 0# pier synchronizes to carry out above 7 circulation jackings, completes 0# pier top liter, and 0# pier jack-up system moves back Go out jacking work.
2. .19#~22# pier notch cuttype classification synchronization of jacking up:
The first step: 19# pier top liter is put in place;19# pier top rise is 112.4cm, is divided into 5 jacking circulation (25+25 + 25+25+12.4), 19#, 20#, 21#, 22# pier synchronizes to carry out above 5 circulation jackings, completes 19# pier top liter, 19# pier top liter System exits jacking work.
Second step: 20# pier top liter is put in place;20# pier residue top lifting height is 125.9cm, is divided into 5 jacking circulations (25+25+25+25+25.9), last circulation top lifting height is 25.9cm, beyond predetermined stroke 0.9cm, completes finally Pad 0.9cm steel cushion block below jack in advance before one circulation, then carry out jacking, 20#, 21#, 22# pier synchronizes to carry out Above 5 circulation jackings, complete 19# pier top liter, and 20# pier jack-up system exits jacking work.
3rd step: 21# pier top liter is put in place;21# pier residue top lifting height is 148.4cm, is divided into 6 jacking circulations (25+25+25+25+25+23.4), 21#, 22# pier synchronizes to carry out above 6 circulation jackings, completes 21# pier top liter, 21# pier top The system of liter exits jacking work.
4th step: 22# pier top liter is put in place;22# pier residue top lifting height is 152.6cm, is divided into 7 jacking circulations (25+25+25+25+25+25+2.6), 22# pier synchronizes to carry out above 7 circulation jackings, completes 22# pier top liter, 22# pier top liter System exits jacking work.
8, pier stud is increased
After bridge Integral synchronous jacking completes, carry out pier stud and connect height, extension supporting steel pipe in pier stud, upper and lower truncated position reinforcing bar Dabbing, at spreading, main muscle is consistent with former pier stud bar diameter, uses the bar weldering of two-sided side and upper and lower reinforcement welding molding, Zhi Limo Plate, pours from close formula high-performance pumping concrete, and outside steel pipe carries out consolidation process.
9. pier stud and bent cap connect high construction.
10, unloading and remaining engineering construction are synchronized
1) all devices such as jack and synchronous jacking system is removed after, 5#, 6#, 17#, 18# pier replacing time completes;
2), jack synchronizes entirety unloading after the pier stud concrete strength such as 0#~4# pier, 19#~22# pier reaches requirement, removes thousand All devices and the steel pipe supports etc. such as jin top and synchronous jacking system;
3), to carry out 0# pier, 22# pier adjacent across new prefabricated case beam installation, carries out the bridge deck such as deck paving, expansion joint And appurtenant work construction.
The present invention is further illustrated below in conjunction with accompanying drawing, but not thereby limiting the invention.
Fig. 2 is the structural representation of wing shape a kind of detailed description of the invention of anchor ear support system of the present invention.As in figure 2 it is shown, Having many to connect high steel pipe post 102 around 108 times box type columns 107 of bent cap, connecing high steel pipe post 102 top has upper wing shape steel to embrace Hoop 106 will connect high steel pipe post 102 and hold tightly with column 107, and connecing high steel pipe post 102 bottom has lower wing shape steel hoop 101 to incite somebody to action Connect high steel pipe post 102 to hold tightly with column 107, be provided with down between lower wing shape steel hoop 101 and upper wing shape steel hoop 106 Billet 103, hydraulic jack jacking system 104 and upper billet 105.Connect be additionally provided with on high steel pipe post 102 type vibration wire should Power meter 109.
Fig. 3 is wing shape anchor ear of the present invention and the structure of lattice steel pipe post a kind of detailed description of the invention of combined support system Schematic diagram.Connect as it is shown on figure 3, lower wing shape steel hoop 101 is replaced with many by Fig. 3 by channel-section steel stull and diagonal brace 202 Φ 609 steel pipe column 201.
Fig. 4 is the structural representation of lattice steel pile tube a kind of detailed description of the invention of bar shaped support system of the present invention.Such as Fig. 4 institute Showing, the lower section of upper I-steel transverse distribution beam 306 is supported by Φ 609 steel pipe column 301, has hydraulic pressure above Φ 609 steel pipe column 301 Very heavy jack-up system 304.
Fig. 5 is the structural representation of a kind of detailed description of the invention of longitudinal limiting device of the present invention.As it is shown in figure 5, adjacent beams Expansion joint 402 between plate 401 is connected by prestress wire 406, stopper slot 403, and prestress wire 406 is by anchoring spiral shell Bolt 404 is fixed on stopper slot 403.
Fig. 6 is the structural representation of a kind of detailed description of the invention of horizontal limit devices of the present invention.As shown in Figure 6, beam slab 501 Opposite sides is connected by cross spacing device 506 prestress wire 508.
Fig. 7 is the structural representation of a kind of detailed description of the invention of hydrostatic level of the present invention.As it is shown in fig. 7, shown static(al) Level gauge include liquid level sensor 1, protective cover, nut, bolt, fluid cylinder, floating drum, foundation bolt, gas-tpe fitting, liquid pipe connection, Trachea, liquid pipe, anti-icing fluid, wire, PVC wired hose, trachea plug, liquid pipe plug.
Fig. 8 is the layout schematic diagram of a kind of detailed description of the invention of floor elevation monitoring stations of the present invention.Pass through static level Hydrostatic level monitoring floor elevation is arranged in instrument layout points 603.
Fig. 9 is the layout schematic diagram of a kind of detailed description of the invention of bottom elevation monitoring stations of the present invention.As it is shown in figure 9, it is logical Cross stay wire sensor 704 and monitor bottom elevation.
Figure 10 is the layout schematic diagram of box beam of the present invention vertically and horizontally displacement observation a kind of detailed description of the invention of point.Such as Figure 10 institute Show, by arranging the observation box beam vertically and horizontally displacement of displacement observation device on monitoring points of displacement.
Figure 11 is the layout schematic diagram of beam body stress monitoring a kind of detailed description of the invention of point of the present invention.As shown in figure 11, exist It is distributed vibratory stress gauge 903 on beam slab 901 and monitors beam body stress.
Although, the present invention is described in detail to have used general explanation and specific embodiment, but at this On the basis of invention, can make some modifications or improvements it, this will be apparent to those skilled in the art.Therefore, These modifications or improvements without departing from theon the basis of the spirit of the present invention, belong to the scope of protection of present invention.

Claims (8)

1. the bridge post that breaks replaces classification and synchronizes the construction method of integral jacking, it is characterised in that described construction method includes:
(1), prepare before construction;
(2), traffic close, the traffic around enclosed bridge;
(3), the counter-force foundation construction of lifting-up support;
(4), jacking support system installs and stopping means is installed, and jacking support system is used for supporting jack-up system, stopping means For preventing bridge lateral and length travel;
(5), jacking control system and monitoring system install, jacking control system includes PLC jack-up system, described PLC jacking system System includes that first group of jack, second group of jack and displacement transducer, first group of jack and second group of jack are positioned at institute State between jacking support system and bridge coping;
(6), the pier stud of bridge is blocked;
(7), alternately classification Integral synchronous jacking, including a, examination jacking, b, drive first group of jack synchronization of jacking up bridge, Below the hydraulic cylinder of jack, add pading plate during jacking, use the top lifting height of displacement sensor bridge simultaneously, After one stroke of bridge jacking, take out steel plate and below the hydraulic cylinder of second group of jack pad set bracing members cushion block, make second The top of hydraulic cylinder of group jack flushes with the top of the hydraulic cylinder of first group of jack;C, drive second group of jack jacking Bridge, one stroke of bridge jacking, and control first group of jack receipts cylinder, the lower section pad at first group of jack hydraulic cylinder sets steel Lip block, makes the top of hydraulic cylinder of first group of jack flush with the top of the hydraulic cylinder of second group of jack;D, repetition Step b and step c are until jacking is to the top lifting height designed;
(8), pier stud is increased;
(9), dismounting all devices.
Construction method the most according to claim 1, it is characterised in that the counter-force basis described in step (3) is multiple shape Formula, abutment position uses cushion cap to expand concrete foundation to put forth effort basis as lattice steel pipe, use pre-buried ring flange and lattice Steel pipe column bolts;Pier column height smaller part lattice steel tubing string uses cast-in-place pillar concrete foundation;Pier column height is relatively General goal directly uses lower wing shape steel hoop as counter-force basis.
Construction method the most according to claim 1, it is characterised in that described in step (4), jacking support system includes butterfly Wing steel hoop support system, wing shape steel hoop and lattice steel pipe column combined support system and lattice steel tubing string bar shaped supporter System;Wherein, in wing shape steel hoop support system, steel hoop uses 36 groups of high-strength bolt fastenings, and 4 wings of design are to pacify altogether Fill 2 groups of synchronous jack, support main steel plate up and down and weld a plurality of strength rib, lower steel hoop wing billet installed above, billet On again install reinforce brace steel post, above steel column after fulcrum steel plate install jacking apparatus, it lays billet and is supported in Steel hoop forms stress system;It is that wing shape steel is embraced by Force system on wing shape steel hoop and lattice steel pipe column combined support system Hoop, uses 3 Φ 609 pipe stiffener steel pipes to form stable lattice body by channel-section steel stull and diagonal brace welding below single wing System is as by Force system, and each component contact position is respectively mounted billet;Lattice steel tubing string bar shaped support system, lower stress system is adopted With many group Φ 609 steel pipe grid-systems, jack-up system installed above, jack-up system 60# installed above puts more energy into I-steel crossbeam, respectively Component contact position is respectively mounted billet.
Construction method the most according to claim 1, it is characterised in that install longitudinal limiting device described in step (4), first First after bridge floor cuts, beam-ends head is amputated 2cm, and uses prestressing force pre-stretch-draw that longitudinal spacing pull bar is installed between two bridge, Stopping means uses high-strength bolt to be installed on design top surface of the beam position, both sides spacing hole steel strand with punching jack anchor Gu;Horizontal limit devices includes that concrete foundation, the spacing main body of steel pipe lattice, the spacing draw-in groove of beam-ends, steel pipe top steel strand wires limit Position device and steel strand wires, the spacing main body of steel pipe lattice is positioned at bent cap both sides, and installs spacing draw-in groove with high-strength bolt at bent cap side Blocking steel pipe supervisor, the upper welded limiting device of steel pipe supervisor, stop steel strand jack in both sides anchors, and forms cross spacing System.
Construction method the most according to claim 1, it is characterised in that described in step (5), jacking control system includes oil Pump, overflow valve, reversal valve, Pressure gauge, branching block, high-pressure hose, control valve group, hydraulic control one-way valve, jacking cylinder, jack, pressure Force transducer, displacement transducer, holding wire, display, controller, power supply box, sub-control box, self-locking device and warning devices.
Construction method the most according to claim 1, it is characterised in that jacking control system described in step (5) uses single Body 600T, the jack of maximum 300mm stroke amount to 180, and often place's abutment arranges that 8 jack set 16 altogether;Squat pier every Bent cap arranges that 16 jack lay 128 altogether;Every bent cap of high pier arranges that 18 jack lay 36 altogether;Amount to jack 180, it is divided into two groups of alternately synchronizations of jacking up, according to jacking stroke during jacking, until the position that design requires.
Construction method the most according to claim 1, it is characterised in that system of monitoring described in step (5) includes bridge floor mark High monitoring, the monitoring of soffit absolute altitude, beam vertically and horizontally displacement observation, beam body stress, the monitoring of support system and weather monitoring.
Construction method the most according to claim 1, it is characterised in that PLC jack-up system synchronization accuracy is ± 2.0mm.
CN201610641356.2A 2016-08-08 2016-08-08 A kind of bridge break post replace classification synchronize integral jacking construction method Pending CN106284079A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201610641356.2A CN106284079A (en) 2016-08-08 2016-08-08 A kind of bridge break post replace classification synchronize integral jacking construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201610641356.2A CN106284079A (en) 2016-08-08 2016-08-08 A kind of bridge break post replace classification synchronize integral jacking construction method

Publications (1)

Publication Number Publication Date
CN106284079A true CN106284079A (en) 2017-01-04

Family

ID=57666233

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201610641356.2A Pending CN106284079A (en) 2016-08-08 2016-08-08 A kind of bridge break post replace classification synchronize integral jacking construction method

Country Status (1)

Country Link
CN (1) CN106284079A (en)

Cited By (17)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106930198A (en) * 2017-04-10 2017-07-07 湖南城市学院 The processing method of modular bridge beam support and application
CN107476597A (en) * 2017-07-12 2017-12-15 杭州圣基建筑特种工程有限公司 Integral roof synchronization of jacking up method
CN107642077A (en) * 2017-08-24 2018-01-30 中国海洋石油总公司 A kind of maintenance intervention method of drilling platforms cantilever beam
CN108677765A (en) * 2018-08-03 2018-10-19 中水电第十工程局(郑州)有限公司 A kind of bridge Integral synchronous jacking bearing replaces system and construction method
CN108978496A (en) * 2018-08-07 2018-12-11 湖南联智智能科技有限公司 A kind of bridge intelligence incremental launching construction system and its push construction method
CN109518607A (en) * 2018-11-23 2019-03-26 云南建投基础工程有限责任公司 A kind of oblique jack-up construction method of bridge based on FEM Simulation
CN109577209A (en) * 2018-12-22 2019-04-05 中国二十二冶集团有限公司 Large-tonnage unit equipment vertical synchronization relay jack-up construction method
CN110424243A (en) * 2019-08-08 2019-11-08 中铁二十局集团第一工程有限公司 A kind of Long span Tied-Arch Bridge Main Bridge jack-up system and jack-up construction method
CN110565543A (en) * 2019-08-02 2019-12-13 中铁四院集团岩土工程有限责任公司 Correcting system and correcting method for bridge structure of operation railway
CN110565548A (en) * 2019-10-17 2019-12-13 北京市市政四建设工程有限责任公司 method for monitoring supporting and reinforcing construction of inclined leg rigid frame bridge
CN110700117A (en) * 2019-08-30 2020-01-17 中铁十四局集团第四工程有限公司 Integral synchronous jacking transformation method for overpass
CN111829594A (en) * 2020-07-29 2020-10-27 中铁二院工程集团有限责任公司 Railway bridge top beam detection system and method
CN112227234A (en) * 2020-10-20 2021-01-15 河南省交通勘察设计有限公司 Construction method for lifting and transforming bridge
CN113338160A (en) * 2020-09-29 2021-09-03 山西省交通科技研发有限公司 T-shaped rigid frame bridge broken pier jacking construction method based on zero stress increment
CN113845056A (en) * 2021-09-22 2021-12-28 江苏虹一工程建设有限公司 Method and system for synchronous alternate jacking based on single action
CN115262415A (en) * 2022-09-06 2022-11-01 中铁北京工程局集团第五工程有限公司 Intelligent jacking method and device for bridge construction
CN116339224A (en) * 2023-02-14 2023-06-27 深圳市曜麒科技有限公司 Jacking operation monitoring system and control method for single-pier bridge reinforcing device

Citations (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN201400997Y (en) * 2009-03-06 2010-02-10 江都揽月机械有限公司 Stepping type alternate supporting platform device
WO2011021740A1 (en) * 2009-08-19 2011-02-24 주식회사 제일엔지니어링 Weight body conveying device
JP5124303B2 (en) * 2008-02-06 2013-01-23 株式会社Ihiインフラシステム Bridge girder rearrangement method and apparatus
CN103205940A (en) * 2013-04-22 2013-07-17 成都建筑工程集团总公司 Slope-variable proportional alternate jacking construction method for continuous beam bridges
CN103352437A (en) * 2013-06-19 2013-10-16 北京市政路桥管理养护集团有限公司 Quick beam lowering method based on bridge synchronous jacking and overall replacement
CN203256626U (en) * 2013-04-22 2013-10-30 成都建筑工程集团总公司 Bridge jacking system
JP5399202B2 (en) * 2009-10-21 2014-01-29 大成建設株式会社 How to replace the bridge
CN104562942A (en) * 2014-12-31 2015-04-29 中交第三航务工程局有限公司 Bridge alternative lifting construction bracket system and construction method
CN204675740U (en) * 2015-05-15 2015-09-30 武汉二航路桥特种工程有限责任公司 A kind of alternately spacing stretching type continuance lifting jack

Patent Citations (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP5124303B2 (en) * 2008-02-06 2013-01-23 株式会社Ihiインフラシステム Bridge girder rearrangement method and apparatus
CN201400997Y (en) * 2009-03-06 2010-02-10 江都揽月机械有限公司 Stepping type alternate supporting platform device
WO2011021740A1 (en) * 2009-08-19 2011-02-24 주식회사 제일엔지니어링 Weight body conveying device
JP5399202B2 (en) * 2009-10-21 2014-01-29 大成建設株式会社 How to replace the bridge
CN103205940A (en) * 2013-04-22 2013-07-17 成都建筑工程集团总公司 Slope-variable proportional alternate jacking construction method for continuous beam bridges
CN203256626U (en) * 2013-04-22 2013-10-30 成都建筑工程集团总公司 Bridge jacking system
CN103352437A (en) * 2013-06-19 2013-10-16 北京市政路桥管理养护集团有限公司 Quick beam lowering method based on bridge synchronous jacking and overall replacement
CN104562942A (en) * 2014-12-31 2015-04-29 中交第三航务工程局有限公司 Bridge alternative lifting construction bracket system and construction method
CN204675740U (en) * 2015-05-15 2015-09-30 武汉二航路桥特种工程有限责任公司 A kind of alternately spacing stretching type continuance lifting jack

Non-Patent Citations (3)

* Cited by examiner, † Cited by third party
Title
刘长卿: "成都市二环路红牌楼立交引桥整体顶升关键技术", 《施工技术》 *
蒋建军等: "成都市二环路北新立交引桥顶升改造关键技术", 《市政技术》 *
蒋建军等: "成都市北新立交引桥"断柱分级同步顶升"施工关键技术", 《西南公路》 *

Cited By (24)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106930198A (en) * 2017-04-10 2017-07-07 湖南城市学院 The processing method of modular bridge beam support and application
CN107476597A (en) * 2017-07-12 2017-12-15 杭州圣基建筑特种工程有限公司 Integral roof synchronization of jacking up method
CN107642077A (en) * 2017-08-24 2018-01-30 中国海洋石油总公司 A kind of maintenance intervention method of drilling platforms cantilever beam
CN107642077B (en) * 2017-08-24 2019-09-06 中国海洋石油集团有限公司 A kind of maintenance intervention method of drilling platforms cantilever beam
CN108677765B (en) * 2018-08-03 2023-12-01 中电建十一局工程有限公司 Bridge integral synchronous jacking support replacing system and construction method
CN108677765A (en) * 2018-08-03 2018-10-19 中水电第十工程局(郑州)有限公司 A kind of bridge Integral synchronous jacking bearing replaces system and construction method
CN108978496A (en) * 2018-08-07 2018-12-11 湖南联智智能科技有限公司 A kind of bridge intelligence incremental launching construction system and its push construction method
CN108978496B (en) * 2018-08-07 2023-11-17 湖南联智智能科技有限公司 Intelligent pushing construction system and method for bridge
CN109518607A (en) * 2018-11-23 2019-03-26 云南建投基础工程有限责任公司 A kind of oblique jack-up construction method of bridge based on FEM Simulation
CN109577209A (en) * 2018-12-22 2019-04-05 中国二十二冶集团有限公司 Large-tonnage unit equipment vertical synchronization relay jack-up construction method
CN110565543A (en) * 2019-08-02 2019-12-13 中铁四院集团岩土工程有限责任公司 Correcting system and correcting method for bridge structure of operation railway
CN110565543B (en) * 2019-08-02 2021-05-11 中铁四院集团工程建设有限责任公司 Correcting system and correcting method for bridge structure of operation railway
CN110424243A (en) * 2019-08-08 2019-11-08 中铁二十局集团第一工程有限公司 A kind of Long span Tied-Arch Bridge Main Bridge jack-up system and jack-up construction method
CN110700117A (en) * 2019-08-30 2020-01-17 中铁十四局集团第四工程有限公司 Integral synchronous jacking transformation method for overpass
CN110565548B (en) * 2019-10-17 2020-06-26 北京市市政四建设工程有限责任公司 Method for monitoring supporting and reinforcing construction of inclined leg rigid frame bridge
CN110565548A (en) * 2019-10-17 2019-12-13 北京市市政四建设工程有限责任公司 method for monitoring supporting and reinforcing construction of inclined leg rigid frame bridge
CN111829594A (en) * 2020-07-29 2020-10-27 中铁二院工程集团有限责任公司 Railway bridge top beam detection system and method
CN113338160A (en) * 2020-09-29 2021-09-03 山西省交通科技研发有限公司 T-shaped rigid frame bridge broken pier jacking construction method based on zero stress increment
CN112227234A (en) * 2020-10-20 2021-01-15 河南省交通勘察设计有限公司 Construction method for lifting and transforming bridge
CN113845056A (en) * 2021-09-22 2021-12-28 江苏虹一工程建设有限公司 Method and system for synchronous alternate jacking based on single action
CN113845056B (en) * 2021-09-22 2022-07-26 江苏虹一工程建设有限公司 Method and system based on single-action synchronous alternate jacking
CN115262415A (en) * 2022-09-06 2022-11-01 中铁北京工程局集团第五工程有限公司 Intelligent jacking method and device for bridge construction
CN115262415B (en) * 2022-09-06 2023-10-24 中铁北京工程局集团第五工程有限公司 Intelligent jacking method and device for bridge construction
CN116339224A (en) * 2023-02-14 2023-06-27 深圳市曜麒科技有限公司 Jacking operation monitoring system and control method for single-pier bridge reinforcing device

Similar Documents

Publication Publication Date Title
CN106284079A (en) A kind of bridge break post replace classification synchronize integral jacking construction method
CN109778721A (en) Synchronization of jacking up bridge top and the bottom structure carries out the method that bridge increases transformation
CN105421248B (en) Large-Span Continuous girder span building up station turns and closure construction method
CN104264592B (en) A kind of continuous beam construction method
CN105648926B (en) Large-Span Continuous girder span building up station rotation swivel construction method
CN102808383B (en) Curved bridge counter-slope jacking construction process
CN101230563B (en) Method for replacing bridge bearing without traffic interruption and special device thereof
CN106702910A (en) Main girder construction process for extradosed cable-stayed bridge with double towers and double cable planes
CN108004928B (en) A kind of asymmetric rigid frame-continuous girder construction technology
CN106522096A (en) Curved incremental launching construction technology for 48m-long-span railway simply-supported box girders and high piers
CN105735139B (en) Supporting system for construction of cast-in-situ box beam in overpass and construction method of box beam
CN104328744B (en) Construction method of anchorage steel pull rod anchoring system of ground anchor type suspension bridge
CN103757993A (en) System and method for high-speed railway subgrade settlement restoration
CN112176867A (en) Single-track single-span railway steel truss girder dragging, installing and constructing method and single-track single-span railway
CN205591131U (en) Whole superelevation of multispan case roof beam is jacking construction system in turn
CN105507168A (en) Multi-span box girder integral ultrahigh alternate jacking construction system and method
CN106758879A (en) A kind of method for runing the correction of high-speed railway bridge ballastless track structure
CN109295982A (en) The construction method of binder steel jacket box in water
CN106245529A (en) Railway tee girder falls beam method safely and fast
CN107620261A (en) Based on the horizontal existing railway track reinforcement means for holding formula just beam
CN102296542A (en) Method for constructing high pier capping beams
CN102797223B (en) Construction method for cast-in-place of continuous beam at turnout junction for passenger transport line in seawall area by false work method
CN107476597A (en) Integral roof synchronization of jacking up method
CN102733307B (en) Method for constructing cast-in-place beam falsework
CN112627055A (en) Bridge bent cap formwork support adjusting device and bridge bent cap construction method

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20170104