CN106906833A - A kind of contrary sequence method underground engineering dewatering well for not influenceing traffic - Google Patents

A kind of contrary sequence method underground engineering dewatering well for not influenceing traffic Download PDF

Info

Publication number
CN106906833A
CN106906833A CN201510966044.4A CN201510966044A CN106906833A CN 106906833 A CN106906833 A CN 106906833A CN 201510966044 A CN201510966044 A CN 201510966044A CN 106906833 A CN106906833 A CN 106906833A
Authority
CN
China
Prior art keywords
well
dewatering well
drainpipe
underground engineering
sequence method
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201510966044.4A
Other languages
Chinese (zh)
Inventor
宋威
张志敏
王湫
王瑜
谭志斌
李博
从定炜
冯桢
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China MCC20 Group Corp Ltd
Original Assignee
China MCC20 Group Corp Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China MCC20 Group Corp Ltd filed Critical China MCC20 Group Corp Ltd
Priority to CN201510966044.4A priority Critical patent/CN106906833A/en
Publication of CN106906833A publication Critical patent/CN106906833A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D19/00Keeping dry foundation sites or other areas in the ground
    • E02D19/06Restraining of underground water
    • E02D19/10Restraining of underground water by lowering level of ground water

Abstract

The present invention relates to reverse construction, more particularly to a kind of contrary sequence method underground engineering well.A kind of contrary sequence method underground engineering dewatering well for not influenceing traffic, the drainpipe of the dewatering well is horizontally installed in roadbase, and water in dewatering well is discharged to the rain double-edged fine-toothed comb well for closing on, and the drainpipe is steel wire rubber drainpipe.Dewatering well after present invention construction does not expose the part on road surface; thoroughly solve obstacle of the precipitation to motor way travel road surface; not by the obstacle of warning bucket; original car lane can all be utilized; the dewatering well top for reducing every 10 ~ 15m mono- along original sets original lane width that warning bucket, drainage pipeline etc. occupy; avoid and possibility that dewatering well road surface safeguard measure is repeatedly damaged, reduce multiple the artificial of replacing, material cost input.

Description

A kind of contrary sequence method underground engineering dewatering well for not influenceing traffic
Technical field
The present invention relates to reverse construction, more particularly to a kind of contrary sequence method underground engineering well.
Background technology
With continuing to develop for China's urban construction, land resource it is gradually rare, consider wartime and people's air defense needs usually, increasing one, tier 2 cities build underground civil defense engineering under the commercial street road of ripe prosperity.Because of the particularity in residing geographical position, influence of the new construction to surrounding environment is reduced in order to try one's best, reverse construction is used more such underground engineering.First construct top board, recover after road surface is open to traffic, then wall of constructing(Post), base plate of finally constructing.
The dewatering operation of later stage top board sub-body structure construction premise, certainly will will have great difficulty in such bustling shopping street construction, especially the large-scale well point in marble road motor vehicle road in both sides of the road per 10 ~ 15m of extensions or so(The precipitation radiation scope of conventional large-scale well point)A dewatering well need to be laid, construction operation and prior to main body construction finishes that rear is dismountable with main structure construction, and recovers the pavement of road at the position of well point, and the cycle is more long.What extensions both sides were so many in marble road motor vehicle road go out road surface well point will all bring detrimental effect to the image of the trip of common people, the smooth of automobile traffic, urban civilization modernization, especially at large-scale retail shop square and intersection position, the influence of the special circumstances such as parking lot rotation angle position is more obvious.
Conventional method is to take the method for setting up the eye-catcher for putting a security warning barrel separately in each dewatering well outlet face now, but quantity is more, density is big, take the current area of road, and drainage pipeline crosses the influence to car lane such as road and still exists, simply serve the safe warning function of certain effect, but privileged sites automobile traffic obstacle can not be released at all, over time, inevitably by people, it is destroyed in the time period of wagon flow peak period, the phenomenon such as break, in order to reach the effect of civilized town road and security warning, certainly will will have to again to destroy warning bucket carry out it is secondary, three inferior replacings are installed.Also have and dewatering well is arranged in greenbelt, but due to place limitation, it is also infeasible.
The content of the invention
Present invention seek to address that the drawbacks described above of prior art, there is provided a kind of contrary sequence method underground engineering dewatering well for not influenceing traffic.Dewatering well after present invention construction does not expose the part on road surface; thoroughly solve obstacle of the precipitation to motor way travel road surface; not by the obstacle of warning bucket; original car lane can all be utilized; the dewatering well top for reducing every 10 ~ 15m mono- along original sets original lane width that warning bucket, drainage pipeline etc. occupy; avoid and possibility that dewatering well road surface safeguard measure is repeatedly damaged, reduce multiple the artificial of replacing, material cost input.
What the present invention was realized in:A kind of contrary sequence method underground engineering dewatering well for not influenceing traffic, the drainpipe of the dewatering well is horizontally installed in roadbase, and water in dewatering well is discharged to the rain double-edged fine-toothed comb well for closing on, and the drainpipe is steel wire rubber drainpipe.
A kind of described contrary sequence method underground engineering dewatering well for not influenceing traffic, the drainpipe is laid out pre-buried in advance when roadbase is constructed.
By well, the dewatering well selects DN500 spheroidal graphite cast-iron heavy well cover and supporting bearing to a kind of described contrary sequence method underground engineering for not influenceing traffic.
A kind of described contrary sequence method underground engineering for not influenceing traffic by well, before Paving roadways pitch reserve by the well lid and walling crib position, and bitumen layer starts to install well lid after completing and concrete walling crib of constructing is fixed.
¢ 50mm are selected in the outer draining of downcast well pipe of the present invention(Depending on geological condition)Transparent wire rubber pipe, roadbase is laid out pre-buried in advance when constructing, and drainpipe is connected to close inlet for stom water(Rain grate well).Choose DN500 spheroidal graphite cast-iron heavy well cover and supporting bearing(Well lid is neglected greatly depending on well casing diameter, and well lid type is depending on highway layout load).Well lid and walling crib position are reserved before Paving roadways pitch, bitumen layer starts to install well lid after completing and concrete walling crib of constructing is fixed, protection precipitation well head, process maintenance, road normal pass are played a part of with this.
People, wagon flow traffic reach barrier free accessibility in the present invention, have recovered the due magnitude of traffic flow in original track;Later stage dewatering construction is convenient and swift, can greatly reduce people, machine, the multiple input of material in work progress, increases economic efficiency;Potential safety hazard is excluded, and dewatering operation effect is ensured, civilized road surface, harmonious traffic, business are shared.
Brief description of the drawings
Fig. 1 is schematic diagram of the invention.
Specific embodiment
As shown in figure 1, a kind of contrary sequence method underground engineering dewatering well for not influenceing traffic, the drainpipe 2 of the dewatering well 1 is horizontally installed in roadbase 3, and water in dewatering well is discharged to the rain double-edged fine-toothed comb well for closing on, and the drainpipe is steel wire rubber drainpipe.
A kind of described contrary sequence method underground engineering dewatering well for not influenceing traffic, the drainpipe is laid out pre-buried in advance when roadbase 3 is constructed.
By well, the dewatering well selects DN500 spheroidal graphite cast-iron heavy well cover 4 and supporting bearing 5 to a kind of described contrary sequence method underground engineering for not influenceing traffic.
A kind of described contrary sequence method underground engineering for not influenceing traffic by well, before Paving roadways pitch reserve by the well lid and walling crib position, and bitumen layer 6 starts to install well lid after completing and concrete walling crib of constructing is fixed.

Claims (4)

1. a kind of contrary sequence method underground engineering dewatering well for not influenceing traffic, it is characterised in that the drainpipe of the dewatering well is horizontally installed in roadbase, and water in dewatering well is discharged to the rain double-edged fine-toothed comb well for closing on, and the drainpipe is steel wire rubber drainpipe.
2. a kind of contrary sequence method underground engineering dewatering well for not influenceing traffic according to claim 1, it is characterised in that the drainpipe is laid out pre-buried in advance when roadbase is constructed.
3. a kind of contrary sequence method underground engineering for not influenceing traffic according to claim 1 is by well, it is characterised in that the dewatering well selects DN500 spheroidal graphite cast-iron heavy well cover and supporting bearing.
4. a kind of contrary sequence method underground engineering for not influenceing traffic according to claim 3 is by well, it is characterised in that the well lid and walling crib position are reserved before Paving roadways pitch, and bitumen layer starts to install well lid after completing and concrete walling crib of constructing is fixed.
CN201510966044.4A 2015-12-22 2015-12-22 A kind of contrary sequence method underground engineering dewatering well for not influenceing traffic Pending CN106906833A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201510966044.4A CN106906833A (en) 2015-12-22 2015-12-22 A kind of contrary sequence method underground engineering dewatering well for not influenceing traffic

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201510966044.4A CN106906833A (en) 2015-12-22 2015-12-22 A kind of contrary sequence method underground engineering dewatering well for not influenceing traffic

Publications (1)

Publication Number Publication Date
CN106906833A true CN106906833A (en) 2017-06-30

Family

ID=59199267

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201510966044.4A Pending CN106906833A (en) 2015-12-22 2015-12-22 A kind of contrary sequence method underground engineering dewatering well for not influenceing traffic

Country Status (1)

Country Link
CN (1) CN106906833A (en)

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101691756A (en) * 2009-09-17 2010-04-07 上海市第二市政工程有限公司 Construction method of foundation pit confined water inrushing emergency water-lowering well
JP5034581B2 (en) * 2007-03-15 2012-09-26 株式会社大林組 Underground structure construction method and underground structure constructed by the method
CN102839682A (en) * 2011-06-24 2012-12-26 中国二十冶集团有限公司 Method for protecting large well point dewatering road surface during reverse construction
CN104499560A (en) * 2014-12-22 2015-04-08 洛阳城市建设勘察设计院有限公司 Combined rainwater seepage well and construction method

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP5034581B2 (en) * 2007-03-15 2012-09-26 株式会社大林組 Underground structure construction method and underground structure constructed by the method
CN101691756A (en) * 2009-09-17 2010-04-07 上海市第二市政工程有限公司 Construction method of foundation pit confined water inrushing emergency water-lowering well
CN102839682A (en) * 2011-06-24 2012-12-26 中国二十冶集团有限公司 Method for protecting large well point dewatering road surface during reverse construction
CN104499560A (en) * 2014-12-22 2015-04-08 洛阳城市建设勘察设计院有限公司 Combined rainwater seepage well and construction method

Similar Documents

Publication Publication Date Title
CN204370384U (en) A kind of mud-rock flow classified energy-dissipation exhaust system
JP6093871B2 (en) Urban intersection structure
KR20100081655A (en) The free crossing system in the urban construction
CN102912701B (en) Multi-functional left-turn directional interchange overpass
CN105350416A (en) Method for solving urban road traffic jam
CN106906833A (en) A kind of contrary sequence method underground engineering dewatering well for not influenceing traffic
CN206396565U (en) A kind of city multilayer interchange overpass
CN102337712A (en) Crossed directional barrier-free overpass
CN211690084U (en) Pavement additional paving structure using existing waveform guard bar
CN109537471B (en) Dangerous chemical leakage emergency treatment system crossing sensitive water bridge and construction method
CN208136650U (en) A kind of highway subgrade safeguard structure
CN203096539U (en) Three-dimensional transportation system for urban trunk road
CN209227356U (en) A kind of piping lane foundation pit employment row suspension bridge
CN202164518U (en) Cross directional barrier-free overpass
CN201924270U (en) Environmental-protection ecological assembled bridge
CN206503042U (en) Micro-overpass
CN103966933B (en) A kind of underground passage travelled for dilly
CN204252260U (en) Multi-functional flood control gully structure
CN217149857U (en) Temporary bridge convenient to tunnel construction
CN205206425U (en) City minor road sky parking field
CN102839682A (en) Method for protecting large well point dewatering road surface during reverse construction
CN216585990U (en) Road surface laying structure based on box culvert
CN215802205U (en) Drainage device for municipal works
CN220301493U (en) Municipal works drainage pipe way mouth device
CN201962982U (en) Sky parking space

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination