CN106894454A - 一种塔基基础后加固处理方法 - Google Patents

一种塔基基础后加固处理方法 Download PDF

Info

Publication number
CN106894454A
CN106894454A CN201710112256.5A CN201710112256A CN106894454A CN 106894454 A CN106894454 A CN 106894454A CN 201710112256 A CN201710112256 A CN 201710112256A CN 106894454 A CN106894454 A CN 106894454A
Authority
CN
China
Prior art keywords
muscle
apeak
processing method
present
column foot
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201710112256.5A
Other languages
English (en)
Inventor
陈辰
李杨
黄书宇
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
NANTONG PANGYUAN MACHINERY ENGINEERING Co Ltd
Original Assignee
NANTONG PANGYUAN MACHINERY ENGINEERING Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by NANTONG PANGYUAN MACHINERY ENGINEERING Co Ltd filed Critical NANTONG PANGYUAN MACHINERY ENGINEERING Co Ltd
Priority to CN201710112256.5A priority Critical patent/CN106894454A/zh
Publication of CN106894454A publication Critical patent/CN106894454A/zh
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D37/00Repair of damaged foundations or foundation structures
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D27/00Foundations as substructures
    • E02D27/32Foundations for special purposes
    • E02D27/42Foundations for poles, masts or chimneys

Landscapes

  • Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Foundations (AREA)

Abstract

本发明涉及了一种塔基基础后加固处理方法,包括如下步骤:A、钻孔并清理内孔壁,清理后注入直筋用胶水;B、将螺纹钢筋折弯成立锚筋,将立锚筋放入孔内,置放24小时,待胶水凝固;C、布筋,将上层钢筋与立锚筋绑扎固定;D、放支模后浇筑混凝土。本发明具有方法简单、操作方便、性能可靠的优点。

Description

一种塔基基础后加固处理方法
技术领域:
本发明涉及一种塔基基础后加固处理方法。
背景技术:
塔机基础是塔式起重机的根本,实践证明有不少重大安全事故都是由于塔吊基础存在问题而引起的,它是影响塔吊整体稳定性的一个重要因素。塔机预埋式螺栓基础,一旦浇筑混凝土凝固后,预埋螺栓发生断裂就很难处理,处理不妥当对塔机的安全使用存在严重隐患。
发明内容:
为了克服现有加工技术的不足,提供一种方法简单、操作方便、性能可靠的塔基基础后加固处理方法。
发明的目的通过以下技术方案来实现:一种塔基基础后加固处理方法,包括如下步骤:
A、钻孔并清理内孔壁,清理后注入直筋用胶水;
B、将螺纹钢筋折弯成立锚筋,将立锚筋放入孔内,置放24小时,待胶水凝固;
C、布筋,将上层钢筋与立锚筋绑扎固定;
D、放支模后浇筑混凝土。
本发明与现有技术相比具有以下特点:
方法简单、操作方便、性能可靠。
具体实施方式:
为了加深对本发明的理解,下面将结合实施例对本发明作进一步详述,该实施例仅用于解释本发明,并不构成对本发明保护范围的限定。
本发明一种塔基基础后加固处理方法的具体实施方式:包括如下步骤:
A、钻孔并清理内孔壁,清理后注入直筋用胶水;
B、将螺纹钢筋折弯成立锚筋,将立锚筋放入孔内,置放24小时,待胶水凝固;
C、布筋,将上层钢筋与立锚筋绑扎固定;
D、放支模后浇筑混凝土。
本发明具有方法简单、操作方便、性能可靠的优点。
申请人又一声明,本发明通过上述实施例来说明本发明的实现方法及装置结构,但本发明并不局限于上述实施方式,即不意味着本发明必须依赖上述方法及结构才能实施。所属技术领域的技术人员应该明了,对本发明的任何改进,对本发明所选用实现方法等效替换及步骤的添加、具体方式的选择等,均落在本发明的保护范围和公开的范围之内。
本发明并不限于上述实施方式,凡采用和本发明相似结构及其方法来实现本发明目的的所有方式,均在本发明的保护范围之内。

Claims (1)

1.一种塔基基础后加固处理方法,其特征在于:包括如下步骤:
A、钻孔并清理内孔壁,清理后注入直筋用胶水;
B、将螺纹钢筋折弯成立锚筋,将立锚筋放入孔内,置放24小时,待胶水凝固;
C、布筋,将上层钢筋与立锚筋绑扎固定;
D、放支模后浇筑混凝土。
CN201710112256.5A 2017-02-28 2017-02-28 一种塔基基础后加固处理方法 Pending CN106894454A (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710112256.5A CN106894454A (zh) 2017-02-28 2017-02-28 一种塔基基础后加固处理方法

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710112256.5A CN106894454A (zh) 2017-02-28 2017-02-28 一种塔基基础后加固处理方法

Publications (1)

Publication Number Publication Date
CN106894454A true CN106894454A (zh) 2017-06-27

Family

ID=59184742

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710112256.5A Pending CN106894454A (zh) 2017-02-28 2017-02-28 一种塔基基础后加固处理方法

Country Status (1)

Country Link
CN (1) CN106894454A (zh)

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE202010007750U1 (de) * 2010-06-09 2010-08-19 Hce Ingenieursgesellschaft Mbh Ertüchtigtes Fundament
CN101899868A (zh) * 2009-05-26 2010-12-01 内蒙古兴泰建筑有限责任公司 一种后植墙体拉结钢筋施工方法
CN103938664A (zh) * 2014-05-09 2014-07-23 南通庞源机械工程有限公司 一种塔机基础后加固的处理方法
CN205604283U (zh) * 2016-04-28 2016-09-28 福建江夏学院 一种建筑植筋混凝土柱

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101899868A (zh) * 2009-05-26 2010-12-01 内蒙古兴泰建筑有限责任公司 一种后植墙体拉结钢筋施工方法
DE202010007750U1 (de) * 2010-06-09 2010-08-19 Hce Ingenieursgesellschaft Mbh Ertüchtigtes Fundament
CN103938664A (zh) * 2014-05-09 2014-07-23 南通庞源机械工程有限公司 一种塔机基础后加固的处理方法
CN205604283U (zh) * 2016-04-28 2016-09-28 福建江夏学院 一种建筑植筋混凝土柱

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
卫龙武等: "《建筑物评估、加固与改造(第2版)》", 31 January 2006, 江苏科学技术出版社 *

Similar Documents

Publication Publication Date Title
CN201546370U (zh) 一种新型的抗震加固构造柱
CN204753628U (zh) 一种可周转的逆作法钢管柱调垂导向装置
CN205063057U (zh) 一种小型洞口的封堵装置
CN106894454A (zh) 一种塔基基础后加固处理方法
CN205000252U (zh) 高墩钢筋绑扎体外劲性骨架
CN207436503U (zh) 高效预制楼板施工的吊模组件
CN103498567B (zh) 砌筑墙体内后增暗圈梁抗震加固方法及其加固结构
CN203593556U (zh) 高安全塔吊
CN207469718U (zh) 一种可周转使用的外墙脚手架拉结装置
CN103938664A (zh) 一种塔机基础后加固的处理方法
CN204186004U (zh) 多功能混凝土马凳
CN204023791U (zh) 地脚螺栓预埋装置
CN106639344A (zh) 混凝土露筋、孔洞修补方案
CN107762135A (zh) 建筑物外墙脚手架连墙件的施工方法
CN206815795U (zh) 一种新型悬挑脚手架构件
CN103410344B (zh) 一种钢筋混凝土墙梁增强加固装置和墙梁增强方法
CN206246133U (zh) 一种隧道防岩爆支护系统及隧道结构
CN205134921U (zh) 建筑外墙混凝土构造柱悬挂施工平台
CN206571135U (zh) 一种不影响施工的外脚手架连墙件
CN109184564A (zh) 一种旋挖钻机成孔中遇斜岩层时的纠偏方法
CN202969304U (zh) 一种栏杆
CN206616851U (zh) 一种钢管脚手架的连墙装置
CN106761542A (zh) 水泥砂浆封孔工艺方法
CN206053381U (zh) 一种砼浇筑操作平台
CN105544533A (zh) 桩板墙挖孔桩护壁贴板

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20170627