CN106884531A - Mark time and moldboard reinforcing tool and pour the mould and reinforcement means of Stereotype stairway - Google Patents

Mark time and moldboard reinforcing tool and pour the mould and reinforcement means of Stereotype stairway Download PDF

Info

Publication number
CN106884531A
CN106884531A CN201710110371.9A CN201710110371A CN106884531A CN 106884531 A CN106884531 A CN 106884531A CN 201710110371 A CN201710110371 A CN 201710110371A CN 106884531 A CN106884531 A CN 106884531A
Authority
CN
China
Prior art keywords
stair tread
tread formwork
support member
reinforcing
connector
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201710110371.9A
Other languages
Chinese (zh)
Inventor
樊敬涛
张苏
吴国秀
黄凯
钟云锋
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
ZHEJIANG HOLDLAND CONSTRUCTION CO Ltd
HWAKING CONSTRUCTION GROUP CO Ltd
Original Assignee
ZHEJIANG HOLDLAND CONSTRUCTION CO Ltd
HWAKING CONSTRUCTION GROUP CO Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by ZHEJIANG HOLDLAND CONSTRUCTION CO Ltd, HWAKING CONSTRUCTION GROUP CO Ltd filed Critical ZHEJIANG HOLDLAND CONSTRUCTION CO Ltd
Priority to CN201710110371.9A priority Critical patent/CN106884531A/en
Publication of CN106884531A publication Critical patent/CN106884531A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G13/00Falsework, forms, or shutterings for particular parts of buildings, e.g. stairs, steps, cornices, balconies foundations, sills
    • E04G13/06Falsework, forms, or shutterings for particular parts of buildings, e.g. stairs, steps, cornices, balconies foundations, sills for stairs, steps, cornices, balconies, or other parts corbelled out of the wall
    • E04G13/062Falsework, forms, or shutterings for particular parts of buildings, e.g. stairs, steps, cornices, balconies foundations, sills for stairs, steps, cornices, balconies, or other parts corbelled out of the wall for stairs or steps

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Mechanical Engineering (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Forms Removed On Construction Sites Or Auxiliary Members Thereof (AREA)

Abstract

Marked time moldboard reinforcing tool the invention discloses one kind, including support member, stair tread formwork reinforcing portion, connector, force transmission element, stair tread formwork reinforcing portion includes multiple reinforcing members, reinforcing member includes vertical reinforcing member and horizontal stiffener, and the end of vertical reinforcing member and horizontal stiffener is fixedly connected with support member respectively.The invention also discloses a kind of mould for pouring Stereotype stairway, including stair tread formwork reinforcement tools, stair tread formwork, side form template, multiple draw-in grooves are set in two side form templates, stair tread formwork is installed in draw-in groove, and stair tread formwork reinforcement tools are placed between two side form templates and vertical reinforcing member pressing stair tread formwork.Moldboard reinforcing tool of marking time is integrally light, simple operation, and is not in obscission.

Description

Mark time and moldboard reinforcing tool and pour the mould and reinforcement means of Stereotype stairway
Technical field
The present invention relates to cast-in-situ stair technical field, refer to specifically a kind of stair tread formwork reinforcement tools and contain this The mould for pouring Stereotype stairway of reinforcement tools and the method reinforced with the reinforcement tools.
Background technology
For construction, particularly creating high-quality project, the construction quality of stair can most test the management of unit in charge of construction Level and construction ability.For the fixation of stair tread formwork, traditional stair tread formwork reinforcement tools generally comprise stair Template mark time in itself, stair tread formwork is typically directly attached with the reinforcement feature of reinforcement tools, with reference to Authorization Notice No. For CN2345624Y and CN2532175Y, application publication number are the patent document of CN102912977A and CN104878924A.Cause Stair tread formwork matches with numbers of steps, and overall quantity is more, causes whole reinforcement tools weight weight, structure complicated, in behaviour It is heavier when making, it is not convenient enough.And the reinforcing connector being directly connected to stair tread formwork on most of reinforcement tools is in The state of upward projection is simultaneously individually stretched out upwards, is easily mutually impeded with other peripheral things or staff in operation, is existed Potential safety hazard, application reference publication No. is the patent document of CN102912977A.More it is noted that in work progress due to Pressure is excessive, adds whole setting tool and supports load without external force, it is possible to cause the overall landing of setting tool.
The content of the invention
It is an object of the invention to provide a kind of stair tread formwork reinforcement tools and for pour Stereotype stairway mould and Reinforcement means, it can at least in part alleviate or eliminate one or more in above-mentioned the problems of the prior art.
According to the stair tread formwork reinforcement tools that the present invention is provided, including two support members for inclining and be arrangeding in parallel, also include Be fixed on support member and be integrally located at stair tread formwork reinforcing portion below support member, for connecting two support members and with two The connector of the removable connection of support member, one end and the removable connection of connector and the other end and the removable connection of peripheral shear wall Force transmission element, described stair tread formwork reinforcing portion includes that multiple incline directions along support member are stepped and sets in succession Reinforcing member, described reinforcing member includes the vertical reinforcing member and the horizontal stiffener that are fixedly connected, wherein vertical reinforcing member and level The end of reinforcing member is fixedly connected with support member respectively.
It is removable between described force transmission element and peripheral shear wall to be connected with adjustable support support, it is easy to adjustment length and convenient dress On peripheral shear wall.
Described support member, connector, force transmission element, vertical reinforcing member and horizontal stiffener are steel pipe fittings, and described Vertical reinforcing member and horizontal stiffener caliber of the caliber less than support member, steel pipe fittings be hardly damaged and it is repeatable utilize, And vertical reinforcing member easily can be fixedly connected less than the caliber of support member with the caliber of horizontal stiffener by way of welding On support member, and entirety can effectively reduce weight.
The quantity of described connector is preferably provided with two, wherein the top for being located at support member, and another is located at The bottom of support member, connector connection and reasonable arrangement more can guarantee that the steady of whole reinforcement tools.
Stair tread formwork reinforcement tools overall structure of the invention is very succinct, by support member, stair tread formwork Reinforcing portion, connector, the setting of force transmission element just can form the required reinforcement tools for reinforcing stair tread formwork, and entirely Reinforcement tools are separately provided with respect to stair tread form plate, do not realize being directly connected to stair tread formwork, and overall weight is significantly Mitigate, operate light.And stair tread formwork reinforcing portion is integrally located at the lower section of support member, does not protrude support member and set Put, peripheral things or staff will not be impacted, more safety is secure.Reinforcement tools of the invention utilize force transmission element Pressure major part reached into peripheral shear wall, it is to avoid the overall landing of reinforcement tools.
The present invention also provides a kind of mould for pouring Stereotype stairway, including described stair tread formwork reinforces work The side form template that tool, stair tread formwork, two parallel obliques are set, equidistantly multiple is symmetrical arranged in two described side form templates Draw-in groove, the end of described stair tread formwork is installed in draw-in groove one by one, and described stair tread formwork reinforcement tools are placed in Between two side form templates and vertical reinforcing member stair tread formwork one by one described in pressing.
Described draw-in groove is vertical slot, and the groove depth of the vertical slot is consistent, and has ensured the sag of stair.
The present invention also provides a kind of reinforcement means, comprises the following steps:
(1)Stair tread formwork is installed in the draw-in groove of side form template one by one;
(2)Integral support member will be fixedly connected in stair tread formwork reinforcement tools and stair tread formwork reinforcing portion is placed in In stair tread formwork, and make vertical reinforcing member pressing stair tread formwork one by one;
(3)Two support members are attached with connector;
(4)Force transmission element is attached with peripheral shear wall and corresponding connector.
Brief description of the drawings
With reference to the accompanying drawing for showing embodiments of the invention, these and other side of the invention will be described in further detail now Face, wherein accompanying drawing are not necessarily to scale drafting, but focus in diagram principle of the invention.In the accompanying drawings:
Fig. 1 schematically shows the use state of the stair tread formwork reinforcement tools of the embodiment provided according to the present invention Floor map.
Fig. 2 schematically shows the use shape of the stair tread formwork reinforcement tools of the embodiment provided according to the present invention The side structure schematic view of state.
Fig. 3 schematically shows the side-looking of the stair tread formwork reinforcement tools of the embodiment provided according to the present invention Partial structural diagram.
Fig. 4 schematically shows the side structure schematic view of the side form template of the embodiment provided according to the present invention.
As shown in the figure:1st, support member, 2 stair tread formwork reinforcing portions, 2.1 vertical reinforcing members, 2.2 horizontal stiffeners, 3 connect Fitting, 4 force transmission elements, 5 adjustable support supports;
10 stair tread formwork reinforcement tools, 20 stair tread formworks, 30 side form templates, 30.1 draw-in grooves.
Specific embodiment
Below, specific embodiment of the invention is described in detail by way of example.It should be appreciated that of the invention Embodiment is not limited to the example of act set forth below, and those skilled in the art can be to being retouched using principle of the invention or spirit Each embodiment stated is modified and modification, obtains the different other embodiments of form, it is clear that these embodiments both fall within this hair Bright claimed scope.
Furthermore, it is necessary to explanation, accompanying drawing referred herein is for the need of description and interpretation embodiments of the invention Will, the shape of each part that accompanying drawing is embodied, the connection between size and different parts are used only for schematically illustrating Embodiments of the invention, do not constitute the limitation to protection scope of the present invention.
In the embodiment of stair tread formwork reinforcement tools provided by the present invention, including two branch for inclining and be arrangeding in parallel Support member 1, the stair tread formwork reinforcing portion 2 for being fixed on support member 1 and being integrally located at the lower section of support member 1, for connecting two The connector 3, one end and connector 3 of support member 1 are connected and force transmission element 4 that the other end is connected with peripheral shear wall.
Described stair tread formwork reinforcing portion 2 includes that multiple incline directions along support member 1 are stepped and sets in succession Reinforcing member, described reinforcing member includes the vertical reinforcing member 2.1 and horizontal stiffener 2.2 of connection, wherein vertical reinforcing member 2.1 End with horizontal stiffener 2.2 is connected with support member 1 respectively.
More specifically, with reference to Fig. 1, Fig. 2 and Fig. 3, in this embodiment, support member 1 uses round steel pipe, and support member 1 is inclined Gradient it is consistent with the stair gradient that need to be poured.Stair tread formwork reinforcing portion 2 is integrally located at the lower section of support member 1, not convex Go out support member, will not peripheral things and wage personnel be caused to impede, relatively safety.Connector 3 be also adopted by round steel pipe make and Into the optional round steel pipe suitable with support member caliber of its caliber.The quantity of connector 3 sets two, wherein one is located at support The top of part 1, and another bottom for being located at support member 1, and connector 3 is attached by fastener and support member, fastener connects Connect convenient.Force transmission element 4 is also adopted by connecting adjustable support support 5, adjustable support between round steel pipe making, and force transmission element 4 and peripheral shear wall Support 5 can realize the connection with peripheral shear wall with adjustment length, when the length of force transmission element 4 is inadequate by adjustable support support, pass The setting of power part 4, peripheral shear wall is transferred to by the pressure produced in work progress by reinforcement tools, be effectively prevent because adding Gu tool pressure is excessive and the overall phenomenon for sliding occurs.Vertical reinforcing member 2.1 and horizontal stiffener 2.2 are using caliber than supporting The small round steel pipe of the caliber of part 1 is made.L-shaped is formed after vertical reinforcing member 2.1 and the connection of the vertical welding of horizontal stiffener 2.2, And the outer end of vertical reinforcing member 2.1 and horizontal stiffener 2.2 is then respectively welded on the lower wall of support member 1.In the embodiment In, fastener also may be selected between connector and force transmission element and be attached, so far support member, reinforcing member, connector and force transmission element are whole Body is equipped mutually to constitute a complete reinforcement tools.
In a kind of embodiment for pouring the mould of Stereotype stairway provided by the present invention, including described stair are stepped on The side form template 30 that step moldboard reinforcing tool 10, stair tread formwork 20, two parallel obliques are set.Two described side form templates 30 On be equidistantly symmetrical arranged multiple draw-in grooves 30.1, the end of described stair tread formwork 20 is installed in draw-in groove 30.1 one by one. Described stair tread formwork reinforcement tools 10 are placed between two side form templates 30 and vertical reinforcing member 2.1 is one by one described in pressing Stair tread formwork 20.
More specifically, described draw-in groove 30.1 is vertical slot, the groove depth of the vertical slot is consistent.
The reinforcement means of stair tread formwork is reinforced with reinforcement tools of the present invention, is comprised the following steps:
(1)Stair tread formwork 20 is installed in the draw-in groove 30.1 of side form template 30 one by one;
(2)Integral support member 1 and stair tread formwork reinforcing portion 2 will be fixedly connected in stair tread formwork reinforcement tools 10 It is placed in stair tread formwork 20, and makes the pressing stair tread formwork 20 one by one of vertical reinforcing member 2.1;
(3)Two support members 1 are carried out into removable connection with connector 3 and fastener;
(4)Force transmission element 4 is carried out into removable connection by fastener with corresponding connector 3, while being sheared in force transmission element 4 and periphery Adjustable support support 5 is connected between wall.Certainly, if the support of adjustable support is not provided with, force transmission element can be made directly removable with peripheral shear wall Formula is connected, wherein removable connection can be realized by fastener.
Reinforcement tools of the invention, it is only support member and stair tread formwork reinforcing portion to be fixedly connected integral, and nothing Remainder such as connector and force transmission element overall carrying and operation need to be carried out, only part and force transmission element need to be attached when reinforcing Connection, so either carry or operation all become very light.Reinforcement tools entirety parts of the invention are few, Simple for structure, it is convenient to make, and the setting for passing through force transmission element, can have pressure transmission suffered when reinforcing to peripheral shear wall Effect avoids the landing of whole reinforcement tools.

Claims (7)

1. one kind is marked time moldboard reinforcing tool, including two support members for inclining and be arrangeding in parallel(1), it is characterised in that:Also include It is fixed on support member(1)Go up and be integrally located at support member(1)The stair tread formwork reinforcing portion of lower section(2), for connect two Support member(1)And with two support members(1)The connector of removable connection(3), one end and connector(3)It is removable connection and it is another End and the force transmission element of the removable connection of peripheral shear wall(4), described stair tread formwork reinforcing portion(2)Including multiple along support Part(1)The stepped reinforcing member for setting in succession of incline direction, described reinforcing member includes the vertical reinforcing member being fixedly connected (2.1)And horizontal stiffener(2.2), wherein vertical reinforcing member(2.1)And horizontal stiffener(2.2)End respectively with support member (1)It is fixedly connected.
2. moldboard reinforcing tool of marking time according to claim 1, it is characterised in that:Described force transmission element(4)Cut with periphery Adjustable support support is connected between power wall(5).
3. moldboard reinforcing tool of marking time according to claim 1, it is characterised in that:Described support member(1), connector (3), force transmission element(4), vertical reinforcing member(2.1)And horizontal stiffener(2.2)It is steel pipe fittings, and described vertical reinforcing member (2.1)And horizontal stiffener(2.2)Caliber be less than support member(1)Caliber.
4. moldboard reinforcing tool of marking time according to claim 1, it is characterised in that:Described connector(3)Quantity set Two are put, wherein one is located at support member(1)Top, and another be located at support member(1)Bottom.
5. a kind of mould for pouring Stereotype stairway, it is characterised in that:Including described stair tread formwork reinforcement tools(10), building Ladder rung template(20), two parallel obliques set side form template(30), described two side form templates(30)It is upper equidistantly symmetrical Multiple draw-in grooves are set(30.1), described stair tread formwork(20)End be installed in draw-in groove one by one(30.1)In, it is described Stair tread formwork reinforcement tools(10)It is placed in two side form templates(30)Between and vertical reinforcing member(2.1)One by one described in pressing Stair tread formwork(20).
6. the mould for pouring Stereotype stairway according to claim 5, it is characterised in that:Described draw-in groove(30.1)For vertical Groove, the groove depth of the vertical slot is consistent.
7. a kind of reinforcement means, it is characterised in that:Comprise the following steps:
(1)By stair tread formwork(20)Side form template is installed in one by one(30)Draw-in groove(30.1)In;
(2)By stair tread formwork reinforcement tools(10)In be fixedly connected integral support member(1)With stair tread formwork plus Gu portion(2)It is placed in stair tread formwork(20)On, and make vertical reinforcing member(2.1)Pressing stair tread formwork one by one(20);
(3)Use connector(3)By two support members(1)It is attached;
(4)By force transmission element(4)With peripheral shear wall and corresponding connector(3)It is attached.
CN201710110371.9A 2017-02-28 2017-02-28 Mark time and moldboard reinforcing tool and pour the mould and reinforcement means of Stereotype stairway Pending CN106884531A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710110371.9A CN106884531A (en) 2017-02-28 2017-02-28 Mark time and moldboard reinforcing tool and pour the mould and reinforcement means of Stereotype stairway

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710110371.9A CN106884531A (en) 2017-02-28 2017-02-28 Mark time and moldboard reinforcing tool and pour the mould and reinforcement means of Stereotype stairway

Publications (1)

Publication Number Publication Date
CN106884531A true CN106884531A (en) 2017-06-23

Family

ID=59179523

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710110371.9A Pending CN106884531A (en) 2017-02-28 2017-02-28 Mark time and moldboard reinforcing tool and pour the mould and reinforcement means of Stereotype stairway

Country Status (1)

Country Link
CN (1) CN106884531A (en)

Citations (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
ATA18090A (en) * 1990-01-26 1991-09-15 Manfred Urak FORMWORK AND METHOD FOR SHAPING A STAIR
CN202787971U (en) * 2012-07-29 2013-03-13 山西四建集团有限公司 Stair step reinforcing part
CN203008370U (en) * 2012-11-30 2013-06-19 山河建设集团有限公司 Stair tread pouring formwork
CN203640278U (en) * 2013-12-20 2014-06-11 茂名市建筑集团有限公司 Stair construction die shelf
CN104074354A (en) * 2014-06-30 2014-10-01 上海中锦建设集团股份有限公司 Plate-insertion type cast-in-place staircase template and use method of plate-insertion type cast-in-place staircase template
CN204059962U (en) * 2014-09-03 2014-12-31 中建新疆建工(集团)有限公司 A kind of Cast-in-place concrete tread embedded side template
CN204059961U (en) * 2014-08-11 2014-12-31 泰昌建设有限公司 The formwork erecting structure of stair tread
CN105839916A (en) * 2016-05-31 2016-08-10 上海宝冶集团有限公司 Socket type stair step template for residential building and mounting process of socket type stair step template
CN206545393U (en) * 2017-02-28 2017-10-10 华锦建设集团股份有限公司 Stair tread formwork reinforcement tools and the mould for pouring Stereotype stairway

Patent Citations (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
ATA18090A (en) * 1990-01-26 1991-09-15 Manfred Urak FORMWORK AND METHOD FOR SHAPING A STAIR
CN202787971U (en) * 2012-07-29 2013-03-13 山西四建集团有限公司 Stair step reinforcing part
CN203008370U (en) * 2012-11-30 2013-06-19 山河建设集团有限公司 Stair tread pouring formwork
CN203640278U (en) * 2013-12-20 2014-06-11 茂名市建筑集团有限公司 Stair construction die shelf
CN104074354A (en) * 2014-06-30 2014-10-01 上海中锦建设集团股份有限公司 Plate-insertion type cast-in-place staircase template and use method of plate-insertion type cast-in-place staircase template
CN204059961U (en) * 2014-08-11 2014-12-31 泰昌建设有限公司 The formwork erecting structure of stair tread
CN204059962U (en) * 2014-09-03 2014-12-31 中建新疆建工(集团)有限公司 A kind of Cast-in-place concrete tread embedded side template
CN105839916A (en) * 2016-05-31 2016-08-10 上海宝冶集团有限公司 Socket type stair step template for residential building and mounting process of socket type stair step template
CN206545393U (en) * 2017-02-28 2017-10-10 华锦建设集团股份有限公司 Stair tread formwork reinforcement tools and the mould for pouring Stereotype stairway

Similar Documents

Publication Publication Date Title
CN103967050B (en) Construction system of subway station
CN102472050B (en) Slab formwork system
CN106869489A (en) Super High Core Walls Structure level and vertical synchronous construction top module system and construction method
CN107605177A (en) The construction method of efficient precast floor slab and its independent support frame
CN106192758A (en) A kind of construction method utilizing the cantilever form large-scale high pier stud of construction
CN105586833B (en) Stiff skeleton steel reinforcement cage global formation large-scale cast-in-place tall pier and thin wall construction method
CN107060327A (en) Detachable tripod post-cast strip independence support system and its application method
CN105649348A (en) Method for hosting and mounting steel tube column casings
CN110528739A (en) FS keeps the temperature the integrated construction technique of exterior sheathing, aluminum alloy mould plate and climbing frame
CN102337782A (en) Lift system for constructing truss platform on top of tall and large space and construction method for lift system
CN206545393U (en) Stair tread formwork reinforcement tools and the mould for pouring Stereotype stairway
CN202064281U (en) Slip form frame
CN109869153A (en) The whole of rapid construction vertical shaft lining cutting promotes cantilever form device and construction method
CN106223960A (en) High ferro major long tunnel inverted arch moves integrally mould bases construction
CN104499706B (en) Hoistway formwork platform and construction method thereof
CN106884531A (en) Mark time and moldboard reinforcing tool and pour the mould and reinforcement means of Stereotype stairway
CN203795311U (en) Multi-leg high pier and slip form construction device
CN202401753U (en) Sliding die device
CN210239225U (en) Interim steel construction stair that building engineering used
CN104878926B (en) One kind hangs template system construction method and can have enough to meet the need rest
CN207564680U (en) A kind of form removal equipment for T-shaped beam
CN205314566U (en) Cone makes up wall screw
CN205477665U (en) Removable tunnel lining platform truck of side form board
CN209633300U (en) A kind of template of the adjustable riser height of precast stair
CN203613461U (en) Slip form construction lifting system

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20170623

RJ01 Rejection of invention patent application after publication