CN106869489A - Super High Core Walls Structure level and vertical synchronous construction top module system and construction method - Google Patents
Super High Core Walls Structure level and vertical synchronous construction top module system and construction method Download PDFInfo
- Publication number
- CN106869489A CN106869489A CN201710170869.4A CN201710170869A CN106869489A CN 106869489 A CN106869489 A CN 106869489A CN 201710170869 A CN201710170869 A CN 201710170869A CN 106869489 A CN106869489 A CN 106869489A
- Authority
- CN
- China
- Prior art keywords
- vertical
- horizontal
- formwork
- vertical wall
- aluminium alloy
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04G—SCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
- E04G11/00—Forms, shutterings, or falsework for making walls, floors, ceilings, or roofs
- E04G11/02—Forms, shutterings, or falsework for making walls, floors, ceilings, or roofs for rooms as a whole by which walls and floors are cast simultaneously, whole storeys, or whole buildings
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04B—GENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
- E04B1/00—Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
- E04B1/16—Structures made from masses, e.g. of concrete, cast or similarly formed in situ with or without making use of additional elements, such as permanent forms, substructures to be coated with load-bearing material
- E04B1/161—Structures made from masses, e.g. of concrete, cast or similarly formed in situ with or without making use of additional elements, such as permanent forms, substructures to be coated with load-bearing material with vertical and horizontal slabs, both being partially cast in situ
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04G—SCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
- E04G11/00—Forms, shutterings, or falsework for making walls, floors, ceilings, or roofs
- E04G11/06—Forms, shutterings, or falsework for making walls, floors, ceilings, or roofs for walls, e.g. curved end panels for wall shutterings; filler elements for wall shutterings; shutterings for vertical ducts
- E04G11/20—Movable forms; Movable forms for moulding cylindrical, conical or hyperbolical structures; Templates serving as forms for positioning blocks or the like
- E04G11/28—Climbing forms, i.e. forms which are not in contact with the poured concrete during lifting from layer to layer and which are anchored in the hardened concrete
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04G—SCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
- E04G19/00—Auxiliary treatment of forms, e.g. dismantling; Cleaning devices
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04G—SCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
- E04G19/00—Auxiliary treatment of forms, e.g. dismantling; Cleaning devices
- E04G19/003—Arrangements for stabilising the forms or for moving the forms from one place to another
Landscapes
- Engineering & Computer Science (AREA)
- Architecture (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Mechanical Engineering (AREA)
- Physics & Mathematics (AREA)
- Electromagnetism (AREA)
- Forms Removed On Construction Sites Or Auxiliary Members Thereof (AREA)
Abstract
Description
技术领域technical field
本发明涉及建筑领域,尤其涉及一种超高层核心筒水平与竖向同步施工顶模系统及施工方法。The invention relates to the field of construction, in particular to a top form system and a construction method for synchronous horizontal and vertical construction of a super high-rise core tube.
背景技术Background technique
目前国内在建的所有“钢框架+混凝土核心筒”超高层结构施工均采取核心筒先行,外框钢柱、钢梁、组合楼板(或钢筋桁架楼承板)后施工的“不等高同步攀升”的施工组织形式,核心筒持续领先塔楼外框结构10层~15层左右的施工步距。而在核心筒施工工艺选择中,由于顶模施工工艺相较爬模、提模等在众多环节上进行了创新,迎合了建筑形状复杂变化、高度不断攀升、功能多样化、结构复杂化的发展趋势,同时极大的提高了施工工效,并实现了两天半一个结构层的建设新速度,因此,顶模施工工艺日益成为超高层施工技术的主流施工工艺。At present, all "steel frame + concrete core tube" super high-rise structures under construction in China adopt the core tube first, and the outer frame steel columns, steel beams, and composite floors (or steel truss floor decks) are constructed after the "synchronous construction of different heights". Ascending" construction organization form, the core tube continues to lead the construction pace of the outer frame structure of the tower by about 10 to 15 floors. In the selection of core tube construction technology, since the construction technology of top formwork has been innovated in many links compared with climbing formwork and lifting formwork, it caters to the development of complex shape changes, rising heights, diversified functions, and complex structures. At the same time, the construction efficiency has been greatly improved, and a new construction speed of one structural layer in two and a half days has been realized. Therefore, the top form construction technology has increasingly become the mainstream construction technology of super high-rise construction technology.
但是,在目前普遍应用的顶模技术中,采用“不等高同步攀升”施工组织形式,顶模施工均是核心筒竖向结构先行施工,水平结构或单独组织滞后竖向结构4-7层单独进行施工,此时外框钢结构及组合楼板施工仍滞后竖向结构10-15层,形成三个梯级的施工组织,水平结构的整体组织难度较大;或水平结构与外框水平结构同步施工,滞后竖向结构10-15层。而核心筒竖向结构的施工速度最快可达到了2天半一个结构层的施工速度,但是后续的水平结构因考虑上下垂直交叉作业物体打击危险控制、核心筒板面高差、梁定位多变的特性,楼板结构施工速度往往很难与外框的组合楼板施工速度匹配,形成相互制约,因水平结构无法及时完成导致超高层施工中的机电设备安装、电梯安装等的后期的关键工序不能及时插入,最终不能最大效用的发挥前期竖向结构的工期优势。因此,在超高层核心筒施工中迫切需要一种核心筒水平结构与竖向结构同步施工的顶模技术,以此来发挥顶模的最大优势。However, in the currently commonly used top formwork technology, the construction organization form of "synchronous climbing with different heights" is adopted. The top formwork construction is the construction of the vertical structure of the core tube first, and the horizontal structure or a separate organization lags behind the vertical structure by 4-7 floors. Construction is carried out separately. At this time, the construction of the steel structure of the outer frame and the composite floor still lags behind the vertical structure by 10-15 floors, forming a three-step construction organization. The overall organization of the horizontal structure is more difficult; or the horizontal structure and the horizontal structure of the outer frame are synchronized. Construction lags behind the vertical structure by 10-15 floors. The construction speed of the vertical structure of the core tube can reach the construction speed of one structural layer in 2 and a half days at the fastest, but the follow-up horizontal structure is due to the consideration of the risk control of the vertical crossing operation objects, the height difference of the core tube slab surface, and the positioning of beams. Due to the variable characteristics, the construction speed of the floor structure is often difficult to match with the construction speed of the combined floor of the outer frame, forming mutual constraints. Because the horizontal structure cannot be completed in time, the key processes in the later stage of the super high-rise construction, such as the installation of electromechanical equipment and elevator installation, cannot be completed. If inserted in time, the construction period advantage of the vertical structure in the early stage cannot be fully utilized in the end. Therefore, in the super high-rise core tube construction, there is an urgent need for a top form technology for simultaneous construction of the core tube horizontal structure and vertical structure, so as to maximize the advantages of the top form.
发明内容Contents of the invention
本发明的主要目的在于提供一种超高层核心筒水平与竖向同步施工顶模系统及施工方法,旨在实现核心筒水平结构与竖向结构同步施工。The main purpose of the present invention is to provide a super high-rise core tube horizontal and vertical synchronous construction top form system and construction method, aiming to realize the simultaneous construction of the core tube horizontal structure and vertical structure.
为实现上述目的,本发明提供一种超高层核心筒水平与竖向同步施工顶模系统,包括桁架平台系统、挂架围护系统、支撑系统、模板系统以及液压控制系统,所述模板系统为铝合金模板系统,所述铝合金模板系统包括竖向墙体模板和水平模板,其中,In order to achieve the above object, the present invention provides a super high-rise core tube horizontal and vertical synchronous construction top formwork system, including truss platform system, hanger enclosure system, support system, formwork system and hydraulic control system, the formwork system is Aluminum alloy formwork system, the aluminum alloy formwork system includes vertical wall formwork and horizontal formwork, wherein,
所述竖向墙体模板包括多个横向拼接的铝合金标准单元板以及位于所述铝合金标准单元板上方的铝合金C槽;The vertical wall formwork includes a plurality of horizontally spliced aluminum alloy standard unit panels and an aluminum alloy C-groove above the aluminum alloy standard unit panels;
所述水平模板由多个铝合金散拼板拼接而成,不同层的水平模板采用不同数量的铝合金散拼板拼接而成,所述水平模板通过铝合金C槽与所述竖向墙体模板连接;The horizontal formwork is spliced by a plurality of aluminum alloy loose panels. The horizontal formwork of different layers is spliced by different numbers of aluminum alloy loose panels. The horizontal formwork is connected to the vertical wall through the aluminum alloy C groove. template connection;
所述竖向墙体模板通过吊点悬挂于桁架平台系统下弦,所述水平模板通过模板支撑立杆支承于下一层楼板上。The vertical wall formwork is suspended from the lower chord of the truss platform system through hanging points, and the horizontal formwork is supported on the next floor through formwork support poles.
优选地,所述支撑系统布置于核心筒永久电梯井筒内以避免占用水平楼板位置;所述桁架平台系统的主桁架和次桁架与结构墙体不处于同一个平面投影线上。Preferably, the support system is arranged in the permanent elevator shaft of the core tube to avoid occupying the horizontal floor position; the main truss and secondary truss of the truss platform system are not on the same plane projection line as the structural wall.
优选地,所述桁架平台系统上预留有水平结构钢筋下料口;所述桁架平台系统还设置有串筒,混凝土通过所述串筒直达楼层浇筑面以避免污染上部已绑扎钢筋。Preferably, the truss platform system is reserved with a horizontal structural reinforcement discharge opening; the truss platform system is also provided with a stringer, through which the concrete directly reaches the pouring surface of the floor to avoid contamination of the upper bound steel bars.
优选地,所述水平模板的铝合金散拼板通过销钉和销片与铝合金C槽可拆卸连接;相邻两所述铝合金标准单元板之间通过偏心U型卡和螺栓可拆卸连接;双槽钢背楞连接所述竖向墙体模板同一高度上的所有偏心U型卡。Preferably, the aluminum alloy loose panels of the horizontal formwork are detachably connected to the aluminum alloy C groove through pins and pin pieces; two adjacent aluminum alloy standard unit plates are detachably connected through eccentric U-shaped clips and bolts; The double-channel steel back flute connects all eccentric U-shaped clips on the same height of the vertical wall formwork.
优选地,所述挂架系统为多个标准件可拆卸连接而成。Preferably, the hanger system is formed by detachable connection of multiple standard parts.
优选地,所述竖向墙体模板的竖向高度可调整。Preferably, the vertical height of the vertical wall formwork is adjustable.
优选地,所述竖向墙体模板还包括位于铝合金标准单元板下方的补偿模板以及连接所述补偿模板和铝合金标准单元板的加强肋,所述补偿模板与铝合金标准单元板可拆卸连接,所述补偿模板的数量与铝合金标准单元板的数量相等,两块所述铝合金标准单元板夹住加强肋的一端,两块所述补偿模板夹住加强肋的另一端。Preferably, the vertical wall formwork also includes a compensation formwork located below the aluminum alloy standard unit plate and a reinforcing rib connecting the compensation formwork and the aluminum alloy standard unit plate, and the compensation formwork and the aluminum alloy standard unit plate are detachable The number of the compensation templates is equal to the number of the aluminum alloy standard unit plates, two of the aluminum alloy standard unit plates clamp one end of the reinforcing rib, and two of the compensation templates clamp the other end of the reinforcing rib.
优选地,所述支撑系统在核心筒竖向墙体上的支点为可拆分组合支撑钢腿。Preferably, the fulcrum of the support system on the vertical wall of the core tube is a detachable combined support steel leg.
本发明进一步提出一种基于上述的超高层核心筒水平与竖向同步施工顶模系统的施工方法,包括以下步骤:The present invention further proposes a construction method based on the above-mentioned super high-rise core tube horizontal and vertical synchronous construction top formwork system, comprising the following steps:
第n层混凝土浇筑完成后,进行核心筒第n+1层钢筋绑扎、埋件安装固定以及竖向墙体模板和水平模板的拆模工作;After the concrete pouring of the nth layer is completed, the steel bar binding of the n+1th layer of the core tube, the installation and fixing of the embedded parts, and the demolition of the vertical wall formwork and the horizontal formwork are carried out;
在第n层水平模板拆模完成后,将其迅速翻转至已浇筑的混凝土楼板,在地面将多个铝合金散拼板拼接成第n+1层水平模板,并将拼装后的水平模板与悬挂的铝合金C槽连接成整体并吊装于桁架平台系统下方;After the removal of the horizontal formwork on the nth floor is completed, it is quickly turned over to the poured concrete floor, and multiple aluminum alloy loose panels are spliced on the ground to form the n+1th floor horizontal formwork, and the assembled horizontal formwork is combined with the The suspended aluminum alloy C-channel is connected as a whole and hoisted under the truss platform system;
待钢筋工程和埋件安装验收完毕后,进行顶膜顶升;After the installation and acceptance of the reinforcement works and embedded parts are completed, the roof membrane shall be lifted;
顶升完成后,竖向墙体模板达到第n+1层高度后,进行墙模板合模及加固,并调整第n+1层竖向墙体模板和水平模板的标高,在进行第n+1层竖向模板加固与水平模板安装的同时,其上部第n+2层竖向钢筋继续绑扎;After the jacking is completed, after the vertical wall formwork reaches the height of the n+1th floor, the wall formwork is clamped and reinforced, and the elevation of the vertical wall formwork and horizontal formwork on the n+1th floor is adjusted. While the vertical formwork on the first floor is reinforced and the horizontal formwork is installed, the vertical steel bars on the n+2th floor on the upper part continue to be bound;
水平模板的标高调整完成后,绑扎水平结构梁板钢筋,并通过在桁架平台系统上布置的串筒,将混凝土浇筑至第n+1层竖向墙体及水平梁板。After the elevation adjustment of the horizontal formwork is completed, the steel bars of the horizontal structural beams and slabs are bound, and the concrete is poured to the vertical wall and horizontal beams and slabs of the n+1th floor through the string tubes arranged on the truss platform system.
优选地,当核心筒墙体截面收缩时,利用竖向墙体模板的竖向高度可调整,来实现模板整体尺寸的调节。Preferably, when the section of the wall of the core tube shrinks, the vertical height of the vertical wall formwork can be adjusted to realize the adjustment of the overall size of the formwork.
本发明提出的超高层核心筒水平与竖向同步施工顶模系统,具有以下有益效果:The super-high-rise core tube horizontal and vertical synchronous construction top form system proposed by the present invention has the following beneficial effects:
(1)在不同层核心筒水平结构发生变化时,因水平模板由多个铝合金散拼板拼接而成,可随时进行水平模板的结构调整,突破了传统顶模只能施工核心筒竖向结构、核心筒水平结构必须滞后于竖向结构单独组织施工的工艺现状,避免了水平结构滞后施工带来的水平梁板处墙体混凝土面打凿及凿毛处理、钢筋二次连接,减少了建筑垃圾的产生量及能源消耗量,施工过程更加绿色环保;同时优化了常规住宅铝合金模板只能人工逐块翻模安装的工艺,实现了竖向墙体模板与水平模板整体提升,节省大量人工工作量;(1) When the horizontal structure of the core tube of different layers changes, because the horizontal formwork is spliced by multiple aluminum alloy loose panels, the structure of the horizontal formwork can be adjusted at any time, breaking through the traditional top formwork that can only construct the vertical core tube The structure and the horizontal structure of the core tube must lag behind the current technological status of the vertical structure, which avoids the concrete surface of the horizontal beam and slab and the secondary connection of steel bars caused by the lagging construction of the horizontal structure. The production of construction waste and energy consumption make the construction process more environmentally friendly; at the same time, the process of conventional residential aluminum alloy formwork can only be manually turned over and installed piece by piece is optimized, and the overall improvement of vertical wall formwork and horizontal formwork is realized, saving a lot of money. manual workload;
(2)实现了铝合金模板快拆体系工艺与顶模系统工艺的完美融合。核心筒水平结构滞后于竖向结构施工的传统顶模施工方法中,核心筒竖向结构施工速度可达4天/层。本实施例中,带水平结构模板的铝合金模板作为快拆体系,充分发挥其支撑立杆保留、梁板底部模板先拆的特点,可通过采取两层钢筋连续绑扎、竖向墙体模板与水平模板整体同时提升优化顶模施工工艺亦保证了核心筒竖向结构与水平结构同步施工情况下,施工速度可达到4天/层;(2) The perfect integration of the aluminum alloy formwork quick release system technology and the top mold system technology has been realized. In the traditional top form construction method in which the horizontal structure of the core tube lags behind the construction of the vertical structure, the construction speed of the vertical structure of the core tube can reach 4 days/floor. In this embodiment, the aluminum alloy formwork with horizontal structural formwork is used as a quick-release system to give full play to its characteristics of retaining the supporting poles and dismantling the formwork at the bottom of the beam slab first. It can be achieved by continuously binding two layers of steel bars, vertical wall formwork and The overall simultaneous upgrade of the horizontal formwork and optimization of the top formwork construction process also ensures that the construction speed can reach 4 days per floor under the condition of simultaneous construction of the vertical structure and horizontal structure of the core tube;
(3)规避了施工过程中建筑结构受力形式不同于原设计意图所带来的安全风险,减小了核心筒后期收口补洞难度,提高了超高层核心筒施工综合施工效率,降低工程施工成本;(3) It avoids the safety risk caused by the force form of the building structure different from the original design intention during the construction process, reduces the difficulty of closing the hole in the later stage of the core tube, improves the comprehensive construction efficiency of the super high-rise core tube construction, and reduces the construction cost. cost;
(4)竖向墙体模板为铝合金标准单元板拼装而成,可根据核心筒墙体变化进行相应的调节,具有竖向高度可调、墙厚变化可调、自重轻的特点,绿色节能环保。(4) The vertical wall formwork is assembled from aluminum alloy standard unit boards, which can be adjusted according to the changes in the core wall. It has the characteristics of adjustable vertical height, adjustable wall thickness, and light weight. It is green and energy-saving Environmental friendly.
附图说明Description of drawings
图1为本发明超高层核心筒水平与竖向同步施工顶模系统在标准层作业时顶模系统即将顶升状态时的剖面图;Fig. 1 is the sectional view when the top formwork system of the present invention is about to lift when the top formwork system is in the standard layer operation in the horizontal and vertical synchronous construction of the super high-rise core tube;
图2为本发明超高层核心筒水平与竖向同步施工顶模系统应用于某工程时支撑系统的平面布置示意图Fig. 2 is a schematic diagram of the plane layout of the support system when the super-high-rise core tube horizontal and vertical synchronous construction top form system of the present invention is applied to a certain project
图3为本发明超高层核心筒水平与竖向同步施工顶模系统应用于某工程时桁架平台系统的平面布置示意图Fig. 3 is a schematic diagram of the plane layout of the truss platform system when the super high-rise core tube horizontal and vertical synchronous construction top formwork system of the present invention is applied to a certain project
图4-A为本发明超高层核心筒水平与竖向同步施工顶模系统应用于某工程且在初次安装挂架时的分布示意图;Figure 4-A is a schematic diagram of the distribution of the super high-rise core tube horizontal and vertical synchronous construction top form system applied to a certain project and when the hanger is installed for the first time;
图4-B为本发明超高层核心筒水平与竖向同步施工顶模系统应用于某工程且在第一次核心筒水平结构变化时挂架的分布示意图;Fig. 4-B is a schematic diagram of the distribution of hangers when the super high-rise core tube horizontal and vertical synchronous construction top form system of the present invention is applied to a certain project and the horizontal structure of the core tube changes for the first time;
图4-C为本发明超高层核心筒水平与竖向同步施工顶模系统应用于某工程且在第二次核心筒水平结构变化时挂架的分布示意图;Fig. 4-C is a schematic diagram of the distribution of hangers when the horizontal and vertical synchronous construction top formwork system of the super high-rise core tube of the present invention is applied to a certain project and the horizontal structure of the core tube is changed for the second time;
图5为本发明超高层核心筒水平与竖向同步施工顶模系统中挂架系统的构造大样图;Fig. 5 is a large sample diagram of the structure of the hanger system in the horizontal and vertical synchronous construction top formwork system of the super high-rise core tube of the present invention;
图6为本发明超高层核心筒水平与竖向同步施工顶模系统中竖向墙体模板的构造示意图;Fig. 6 is the structural schematic diagram of the vertical wall formwork in the super high-rise core tube horizontal and vertical synchronous construction top formwork system of the present invention;
图7-A为本发明超高层核心筒水平与竖向同步施工顶模系统中偏心U型卡与铝合金大模板、双槽钢背楞的固定立面图;Fig. 7-A is a fixed elevation view of the eccentric U-shaped card, the aluminum alloy large formwork, and the double-channel steel back corrugated in the super-high-rise core tube horizontal and vertical synchronous construction top formwork system of the present invention;
图7-B为本发明超高层核心筒水平与竖向同步施工顶模系统中偏心U型卡与铝合金大模板、双槽钢背楞的固定平面图;Fig. 7-B is a fixed plan view of the eccentric U-shaped card, the aluminum alloy large formwork, and the double-channel steel back corrugated in the top formwork system of the super high-rise core tube of the present invention, which is constructed simultaneously in horizontal and vertical directions;
图7-C为本发明超高层核心筒水平与竖向同步施工顶模系统中偏心U型卡的结构示意图;Fig. 7-C is a structural schematic diagram of the eccentric U-shaped card in the super-high-rise core tube horizontal and vertical synchronous construction top form system of the present invention;
图8为本发明超高层核心筒水平与竖向同步施工顶模系统中竖向墙体模板与水平模板的组合示意图;Fig. 8 is a schematic diagram of the combination of the vertical wall formwork and the horizontal formwork in the super high-rise core tube horizontal and vertical synchronous construction top formwork system of the present invention;
图9为本发明超高层核心筒水平与竖向同步施工顶模系统中的墙体模板剖面图;Fig. 9 is a cross-sectional view of the wall formwork in the super high-rise core tube horizontal and vertical synchronous construction top formwork system of the present invention;
图10为本发明超高层核心筒水平与竖向同步施工顶模系统中水平模板临时悬挂于顶模的示意图;Fig. 10 is a schematic diagram of the horizontal template temporarily suspended on the top mold in the horizontal and vertical synchronous construction top mold system of the super high-rise core tube of the present invention;
图11为本发明超高层核心筒水平与竖向同步施工顶模系统中可拆分组合支撑钢腿示意图。Fig. 11 is a schematic diagram of detachable and combined support steel legs in the top formwork system for simultaneous horizontal and vertical construction of super high-rise core tubes according to the present invention.
图中,1-支撑系统,2-桁架平台系统,3-钢筋下料口,4-串筒,5-上部钢筋,6-挂架系统,7-1840型方通,8-740型方通,9-T型铝,10-走道板,11-翻板,12-模板系统,13-竖向墙体模板,14-核心筒水平同步施工楼板,15-铝合金散拼板,16-铝合金C槽,17-吊点,18-支撑立杆,19-铝合金标准单元板,20-偏心U型卡,21-螺栓,22-双槽钢背楞,23-K板,24-F脚,25-补偿模板,26-加强肋,27-核心筒竖向墙体,28-支撑钢腿,29-液压控制系统。In the figure, 1-support system, 2-truss platform system, 3-steel bar discharge port, 4-string tube, 5-upper steel bar, 6-hanger system, 7-1840 type square pass, 8-740 type square pass , 9-T-type aluminum, 10-walkway slab, 11-turning plate, 12-formwork system, 13-vertical wall formwork, 14-core tube horizontal synchronous construction floor, 15-aluminum alloy scattered board, 16-aluminum Alloy C groove, 17-lifting point, 18-supporting pole, 19-aluminum alloy standard unit plate, 20-eccentric U-shaped card, 21-bolt, 22-double channel steel back flute, 23-K plate, 24-F Foot, 25-compensation formwork, 26-strengthening rib, 27-vertical wall of core tube, 28-supporting steel leg, 29-hydraulic control system.
本发明目的的实现、功能特点及优点将结合实施例,参照附图做进一步说明。The realization of the purpose of the present invention, functional characteristics and advantages will be further described in conjunction with the embodiments and with reference to the accompanying drawings.
具体实施方式detailed description
应当理解,此处所描述的具体实施例仅仅用以解释本发明,并不用于限定本发明。It should be understood that the specific embodiments described here are only used to explain the present invention, not to limit the present invention.
参照图1、图6至图10,本优选实施例中,一种超高层核心筒水平与竖向同步施工顶模系统,包括桁架平台系统2、挂架围护系统、支撑系统1、模板系统12以及液压控制系统29,模板系统12为铝合金模板系统,铝合金模板系统包括竖向墙体模板13(用于核心筒外墙及井筒竖向墙体)和水平模板(用于水平同步施工楼板、与梁板连接的墙体及楼梯),其中,Referring to Fig. 1, Fig. 6 to Fig. 10, in this preferred embodiment, a super-high-rise core tube horizontal and vertical synchronous construction top formwork system includes a truss platform system 2, a hanger enclosure system, a support system 1, and a formwork system 12 and hydraulic control system 29, the formwork system 12 is an aluminum alloy formwork system, and the aluminum alloy formwork system includes a vertical wall formwork 13 (for the outer wall of the core tube and the vertical wall of the well shaft) and a horizontal formwork (for horizontal synchronous construction floors, walls connected to beams and stairs), where,
竖向墙体模板13包括多个横向拼接的铝合金标准单元板19以及位于铝合金标准单元板19上方的铝合金C槽16;The vertical wall formwork 13 includes a plurality of horizontally spliced aluminum alloy standard unit panels 19 and an aluminum alloy C-groove 16 above the aluminum alloy standard unit panels 19;
水平模板由多个铝合金散拼板15拼接而成,不同层的水平模板采用不同数量的铝合金散拼板15拼接而成,水平模板通过铝合金C槽16与竖向墙体模板13连接;The horizontal formwork is spliced by a plurality of aluminum alloy loose panels 15, and the horizontal formwork of different layers is spliced by different numbers of aluminum alloy loose panels 15, and the horizontal formwork is connected with the vertical wall formwork 13 through the aluminum alloy C groove 16 ;
竖向墙体模板13通过吊点17悬挂于桁架平台系统2下弦,水平模板通过模板支撑立杆18支承于下一层楼板上。The vertical wall formwork 13 is suspended on the lower chord of the truss platform system 2 through the hanging point 17, and the horizontal formwork is supported on the next floor through the formwork support pole 18.
参照图6,在竖向墙体模板13上口的铝合金C槽16按一定间距设置有吊点17,每个吊点17安装一个两端套丝的U型圆钢;葫芦悬挂在桁架平台系统2下弦,葫芦倒链挂住U型圆钢。铝合金标准单元板19和铝合金散拼板15可设置成相同的结构。Referring to Fig. 6, the aluminum alloy C groove 16 on the top of the vertical wall formwork 13 is provided with lifting points 17 at a certain interval, and each lifting point 17 is installed with a U-shaped round steel with two ends; the gourd is suspended on the truss platform System 2 lowers the chord, and the hoist hangs on the U-shaped round steel with its chain upside down. The aluminum alloy standard unit plate 19 and the aluminum alloy loose panel 15 can be set to the same structure.
具体地,水平模板的铝合金散拼板15通过销钉和销片与铝合金C槽16可拆卸连接,因此,拆卸与连接铝合金散拼板15和铝合金C槽16的工作非常方便。另外,相邻两铝合金标准单元板19之间通过偏心U型卡20和螺栓21可拆卸连接;双槽钢背楞22连接竖向墙体模板13同一高度上的所有偏心U型卡20。Specifically, the aluminum alloy loose panels 15 of the horizontal formwork are detachably connected to the aluminum alloy C-groove 16 through pins and pins, so the work of disassembling and connecting the aluminum alloy loose panels 15 and the aluminum alloy C-groove 16 is very convenient. In addition, two adjacent aluminum alloy standard unit plates 19 are detachably connected by eccentric U-shaped clips 20 and bolts 21; double-channel steel back corrugated 22 connects all eccentric U-shaped clips 20 on the same height of the vertical wall formwork 13 .
参照图7-A、图7-B和图7-C,在组装竖向墙体模板13时,将多个铝合金标准单元板19组拼在一起后,偏心U型卡20通过螺栓21与铝合金标准单元板19固定,再将双槽钢背楞22卡住偏心U型卡20,最终形成整体大模板。使用偏心U型卡20连接方式确保了竖向墙体模板13连接牢固且拆改方便,当核心筒无水平梁板区域随结构高度增加变成有水平梁板,则此处竖向墙体模板13需拆改为铝合金散拼模板,此时,只需松开偏心U型卡20,取出双槽钢背楞22,再卸除偏心U型卡20与铝合金标准单元板19连接的螺栓21,竖向墙体模板13即成为多个铝合金标准单元板19。竖向墙体模板13拆改成核心筒水平同步施工楼板14相连墙体的散拼模板时,需拆掉K板23,增加F脚24。Referring to Figure 7-A, Figure 7-B and Figure 7-C, when assembling the vertical wall formwork 13, after a plurality of aluminum alloy standard unit plates 19 are put together, the eccentric U-shaped clip 20 is connected with the bolt 21 The aluminum alloy standard unit plate 19 is fixed, and then the double-channel steel back corrugated 22 is clamped to the eccentric U-shaped clamp 20, finally forming an overall large formwork. The use of eccentric U-shaped card 20 connection method ensures that the vertical wall formwork 13 is firmly connected and easy to disassemble. 13 needs to be disassembled and replaced with an aluminum alloy loose formwork. At this time, it is only necessary to loosen the eccentric U-shaped card 20, take out the double-channel steel back corrugated 22, and then remove the bolts connecting the eccentric U-shaped card 20 and the aluminum alloy standard unit plate 19 21. The vertical wall formwork 13 becomes a plurality of aluminum alloy standard unit panels 19 . When the vertical wall formwork 13 is disassembled and changed into a loose formwork for the core tube horizontal synchronous construction floor 14 connected to the wall, the K board 23 needs to be removed and the F foot 24 is increased.
另外,核心筒电梯前室两侧均为电梯井道的区域,可实现水平模板的整体提升:水平模板拆模完成后,迅速翻转至上一层结构,按照配模图地面拼装水平模板,并将其临时挂至桁架平台系统2的下弦吊点17上,等待随顶模同步提升。In addition, both sides of the elevator front room in the core tube are the areas of the elevator shaft, which can realize the overall promotion of the horizontal formwork: after the horizontal formwork is removed, it is quickly turned over to the upper structure, and the horizontal formwork is assembled on the ground according to the formwork diagram, and its Temporarily hang on the lower string hanging point 17 of the truss platform system 2, and wait for synchronous lifting with the top form.
具体地,为了实现超高层核心筒水平与竖向同步施工,支撑系统1和桁架平台系统2设计需考虑核心筒结构避让原则,即:支撑系统1布置于核心筒永久电梯井筒内以避免占用水平楼板位置。桁架平台系统2布置因遵循纵横桁架、主次桁架排布合理原则,即:桁架平台系统2的主桁架和次桁架与结构墙体不处于同一个平面投影线上。Specifically, in order to realize the simultaneous horizontal and vertical construction of the super high-rise core tube, the design of the support system 1 and the truss platform system 2 needs to consider the principle of avoidance of the core tube structure, that is, the support system 1 is arranged in the permanent elevator shaft of the core tube to avoid occupying the horizontal Floor location. The layout of the truss platform system 2 follows the principle of reasonable arrangement of vertical and horizontal trusses, primary and secondary trusses, that is, the main trusses and secondary trusses of the truss platform system 2 are not on the same plane projection line as the structural wall.
进一步地,桁架平台系统2上预留有水平结构钢筋下料口3。水平结构钢筋原材长度一般为12m,为减少钢筋浪费,工程现场加工钢筋放样下料时采取居中断料的方式,钢筋成品长度一般为6m,因此水平结构钢筋下料口3和长方向长度不宜小于6.5m。Further, the truss platform system 2 is reserved with a horizontal structural reinforcement discharge port 3 . The raw material length of the horizontal structural steel bar is generally 12m. In order to reduce the waste of steel bar, the method of cutting off the material is adopted when the steel bar is set out and cut off during the on-site processing of the project. The length of the finished steel bar is generally 6m. Less than 6.5m.
进一步地,桁架平台系统2按照核心筒墙体暗柱分布及水平结构区设置有串筒4,混凝土通过串筒4直达楼层浇筑面以避免污染上部已绑扎钢筋。Further, the truss platform system 2 is provided with stringers 4 according to the distribution of the hidden columns of the core wall and the horizontal structure area, and the concrete passes through the stringers 4 directly to the pouring surface of the floor to avoid contamination of the upper bound steel bars.
进一步地,参照图5,挂架系统6为多个标准件可拆卸连接而成。具体地,挂架系统6由标准化的1840型方通7、740型方通8、T型铝9、走道板10及翻板11通过螺栓21连接,安拆方便,现场施工时根据核心筒水平结构的变化进行挂架系统6的快速增补。现场施工时根据核心筒水平结构的变化进行挂架系统6的快速增补,提高了顶模构件在单个建筑工程的重复利用率,进一步降低顶模使用成本,使得本顶膜系统易于推广。Further, referring to FIG. 5 , the hanger system 6 is composed of a plurality of standard parts detachably connected. Specifically, the hanger system 6 is connected by the standardized 1840-type square tube 7, 740-type square tube 8, T-shaped aluminum 9, walkway plate 10, and flap 11 through bolts 21, which is easy to install and disassemble. Structural changes carry out rapid additions to the pylon system 6 . During on-site construction, the hanger system 6 is quickly supplemented according to the change of the horizontal structure of the core tube, which improves the reuse rate of the top form components in a single construction project, further reduces the use cost of the top form, and makes the top formwork system easy to promote.
进一步地,竖向墙体模板13的竖向高度可调整。具体地,竖向墙体模板13还包括位于铝合金标准单元板19下方的补偿模板25以及连接所述补偿模板25和铝合金标准单元板19的加强肋26,补偿模板25与铝合金标准单元板19可拆卸连接,所述补偿模板25的数量与铝合金标准单元板19的数量相等,所述两块铝合金标准单元板19夹住加强肋26的一端,两块所述补偿模板25夹住加强肋26的另一端。根据超高层核心筒层高变化规律设计补偿模板25,通过与铝合金标准单元板19拼形成竖向高度可调模板,在层高发生变化时只需拆除补偿模板25即可。因竖向墙体模板13竖向无加固背楞,本实施例中,在铝合金标准单元板19与补偿模板25连接处的侧边增加一块6mm厚的加强肋26进行模板加固。Further, the vertical height of the vertical wall formwork 13 can be adjusted. Specifically, the vertical wall formwork 13 also includes a compensation formwork 25 positioned below the aluminum alloy standard unit plate 19 and a reinforcing rib 26 connecting the compensation formwork 25 and the aluminum alloy standard unit plate 19, the compensation formwork 25 and the aluminum alloy standard unit The plates 19 are detachably connected, the number of the compensation formwork 25 is equal to the number of the aluminum alloy standard unit plates 19, the two aluminum alloy standard unit plates 19 clamp one end of the reinforcing rib 26, and the two compensation formworks 25 clamp Live the other end of reinforcing rib 26. The compensation formwork 25 is designed according to the changing law of the super high-rise core tube floor height, and the vertical height-adjustable formwork is formed by combining with the aluminum alloy standard unit plate 19. When the storey height changes, the compensation formwork 25 only needs to be removed. Because the vertical wall formwork 13 has no vertical reinforcement, in this embodiment, a 6mm thick reinforcing rib 26 is added to the side of the connection between the aluminum alloy standard unit plate 19 and the compensation formwork 25 for formwork reinforcement.
水平模板的铝合金散拼板15设计有0.04m高F脚24。考虑核心筒水平结构混凝土楼板面标高不一致的问题,在有水平结构区域墙体散拼模板的最下部(即墙体根部)设置有F脚24用于调节模板高度,理论上F脚24下口离混凝土楼板面0.010m(混凝土楼板面为设计理论高度时),因此F脚24具有了0.001m~0.010m调节范围。The aluminum alloy loose jigsaw panel 15 of the horizontal formwork is designed with a height of 0.04m and an F foot 24. Considering the inconsistency of the elevation of the concrete floor of the horizontal structure of the core tube, F feet 24 are set at the lowest part of the wall loose formwork in the area with horizontal structures (that is, the root of the wall) to adjust the height of the formwork. Theoretically, the lower opening of F feet 24 0.010m away from the concrete floor surface (when the concrete floor surface is the design theoretical height), so the F foot 24 has an adjustment range of 0.001m~0.010m.
参照图11,另外,支撑系统1在核心筒竖向墙体27上的支点为可拆分组合支撑钢腿,支撑钢腿28在核心筒竖向墙体27上按照顶模顶升步距同时安装三道,最下面一道用于支承下箱梁,中间一道用于支承上箱梁,上面一道用于顶模顶升时进行周转。本实施例中,通过采用支撑钢腿28,避免了对结构墙体的损伤或者开洞,实现对结构的零损伤,保证竖向结构与水平结构一次浇筑施工成型。Referring to Fig. 11, in addition, the fulcrum of the support system 1 on the vertical wall 27 of the core tube is a detachable combined support steel leg, and the support steel leg 28 is on the vertical wall 27 of the core tube according to the jacking step of the top form at the same time. Install three, the bottom one is used to support the lower box girder, the middle one is used to support the upper box girder, and the upper one is used for turnover when the top form is lifted. In this embodiment, by using the supporting steel legs 28, the damage or opening of the structural wall is avoided, zero damage to the structure is achieved, and the vertical structure and the horizontal structure are guaranteed to be formed in one pouring construction.
本超高层核心筒水平与竖向同步施工顶模系统的施工方法如下:The construction method of the super high-rise core tube horizontal and vertical simultaneous construction top formwork system is as follows:
1)第n层混凝土浇筑完成,继续绑扎第n+1层余下钢筋(在第n层混凝土浇筑之间已绑扎部分第n+1钢筋)。在标准层施工周期中,钢筋绑扎属于连续作业,在提前绑扎第n+1层钢筋时,如图1所示,墙体底部预留500mm作为第n层混凝土浇筑施工时振捣棒施工范围,将箍筋、水平筋全部重叠绑扎在一起,混凝土浇筑完毕后按图纸设计间距恢复;1) After the concrete pouring of the nth floor is completed, continue to bind the remaining steel bars of the n+1th floor (the part of the n+1th steel bar that has been bound between the nth floor concrete pouring). In the construction period of the standard layer, the reinforcement binding is a continuous operation. When the n+1th layer of steel bars is bound in advance, as shown in Figure 1, 500mm is reserved at the bottom of the wall as the construction range of the vibrator during the nth layer of concrete pouring construction. The stirrups and horizontal bars are all overlapped and tied together, and the spacing is restored according to the drawing design after the concrete is poured;
2)第n层混凝土达到强度要求后,进行竖向墙体模板13和水平模板的拆模工作。如图1和图10所示,核心筒电梯前室两侧均为电梯井道的区域,可实现水平模板的整体提升。水平模板拆模完成后,迅速翻转至已浇筑的混凝土楼板,通过桁架平台系统2下挂葫芦吊挂铝合金C槽16,在地面进行相应部位铝合金散拼板15的拼装(参照图3至图4-C),并将拼装后的水平模板与悬挂的铝合金C槽16连接成整体并吊装于桁架平台系统2下方;2) After the nth layer of concrete meets the strength requirements, the vertical wall formwork 13 and the horizontal formwork are removed. As shown in Figure 1 and Figure 10, both sides of the elevator front room of the core tube are the areas of the elevator shaft, which can realize the overall lifting of the horizontal formwork. After the formwork removal of the horizontal formwork is completed, quickly turn it over to the poured concrete floor, hang the aluminum alloy C groove 16 through the truss platform system 2 and hang the gourd, and assemble the aluminum alloy loose panels 15 at the corresponding parts on the ground (refer to Figure 3 to Figure 4-C), and the assembled horizontal formwork is connected with the suspended aluminum alloy C groove 16 as a whole and hoisted under the truss platform system 2;
3)跟随钢筋绑扎进度,完成在核心筒第n+1层所有涉及的埋件,诸如顶模埋件,钢结构、机电等预埋件,所有埋件均需安装固定于钢筋上。在绑扎第n+1层墙体钢筋时,根据埋件定位确定钢筋预留后绑范围,埋件固定后再对该区域进行加固处理;3) Following the progress of steel bar binding, complete all embedded parts involved in the n+1 layer of the core tube, such as top form embedded parts, steel structure, electromechanical and other embedded parts, all embedded parts need to be installed and fixed on the steel bars. When tying the steel bars of the n+1th layer wall, determine the reserved area of the reinforcement according to the positioning of the embedded parts, and then reinforce the area after the embedded parts are fixed;
4)筋工程、埋件安装验收完毕后方可准备顶升。顶模顶升前,需做好所有顶升前准备工作,确保拆分牛腿支座安装完成,填写顶升前检查验收表。顶升过程中,安排专人负责照管顶模挂架系统6和模板系统12,防止挂架系统6、模板系统12与核心筒结构发生碰撞。顶模顶升完成后,检查翻板11是否恢复,防坠落装置是否锁定;4) After the installation and acceptance of rib engineering and embedded parts are completed, the jacking can be prepared. Before jacking up the top formwork, all preparations before jacking up must be done to ensure that the installation of the split corbel support is completed, and the inspection and acceptance form before jacking up should be filled out. During the jacking process, assign special personnel to take care of the top mold hanger system 6 and formwork system 12 to prevent the hanger system 6, formwork system 12 from colliding with the core tube structure. After the lifting of the top mold is completed, check whether the flap 11 is restored and whether the anti-falling device is locked;
5)顶升完成后,铝合金模板系统达到第n+1层高度,此时进行墙模板合模及加固。如图6所示,竖向墙体模板13利用铝模锁脚螺杆对其进行临时固定,并利用吊点17对其标高进行调整;如图9所示,内墙的散拼模板则以竖向墙体模板13标高作为参照,调节F脚24来控制水平模板的标高。墙体模板合模时同时进行连梁底模支设,连梁钢筋绑扎完成后,梁侧模待顶模顶升就位后再行封闭;核心筒墙体截面收缩时,利用竖向墙体模板13为可拆分式特性,拆除相应补偿模板25,实现模板整体尺寸的调节;楼层层高变化时,利用模板竖向高度可调特性,拆除对应补偿模板25,从而实现模板高度的调节。如图1所示,竖向墙体模板13合模时,调节水平模板在铝合金C槽16的吊点17葫芦来调整其标高,同时根据墙体定位及模板拼装图在地面放出水平模板支撑点的定位图,在竖向墙体模板13完成合模进行模板加固时同步进行水平模板的支设。水平模板的标高调整基本到位后,与竖向墙体模板13进行临时连接,然后根据支撑点定位线安装水平模板支撑;5) After the jacking is completed, the aluminum alloy formwork system reaches the height of the n+1th floor, and at this time, the wall formwork is clamped and reinforced. As shown in Figure 6, the vertical wall formwork 13 is temporarily fixed by the aluminum mold locking screw, and its elevation is adjusted by the hanging point 17; as shown in Figure 9, the loose formwork of the inner wall is vertically To the wall formwork 13 elevation as a reference, adjust the F foot 24 to control the elevation of the horizontal formwork. When the wall formwork is closed, the bottom formwork of the coupling beam is supported at the same time. After the reinforcement of the coupling beam is bound, the beam side formwork is closed after the top formwork is lifted into place; when the core wall section shrinks, use the vertical wall The formwork 13 is detachable, and the corresponding compensation formwork 25 is removed to adjust the overall size of the formwork; when the floor height changes, the vertical height adjustment of the formwork is used to remove the corresponding compensation formwork 25, thereby realizing the adjustment of the formwork height. As shown in Figure 1, when the vertical wall formwork 13 is closed, adjust the hoisting point 17 of the horizontal formwork in the aluminum alloy C groove 16 to adjust its elevation, and at the same time release the horizontal formwork support on the ground according to the wall positioning and formwork assembly diagram The positioning diagram of the point, when the vertical wall formwork 13 completes mold closing and carries out formwork reinforcement, the support of the horizontal formwork is carried out synchronously. After the elevation adjustment of the horizontal formwork is basically in place, it is temporarily connected with the vertical wall formwork 13, and then the horizontal formwork support is installed according to the support point positioning line;
6)如图1和图12所示,根据挂架围护系统的挂架可满足两层同时作业特性,在进行第n+1层竖向模板加固与水平模板安装的同时,其上部第n+2层竖向钢筋继续绑扎。竖向钢筋在最下面一道箍筋与第n+2层楼板面预留不少于500mm距离。6) As shown in Figure 1 and Figure 12, according to the hanger of the hanger enclosure system, the hanger can meet the characteristics of simultaneous operation of two floors. +2 layers of vertical reinforcement continue to be tied. The distance between the bottommost stirrup and the floor surface of the n+2th floor shall not be less than 500mm for the vertical reinforcement.
7)水平模板标高调整完成后,绑扎水平结构梁板钢筋,经验收合格后,浇筑第n+1层混凝土。如图1所示,通过在桁架平台系统2上布置的串筒4,将混凝土浇筑至第n+1层竖向墙体及水平梁板,同时不污染第n+2层已绑扎钢筋。第n+1层结构混凝土浇筑期间,钢筋绑扎作业暂停;7) After the adjustment of the level of the horizontal formwork is completed, the steel bars of the horizontal structural beam and slab are bound, and after passing the acceptance, the n+1th layer of concrete is poured. As shown in Figure 1, through the string tube 4 arranged on the truss platform system 2, the concrete is poured to the vertical wall and horizontal beam plate of the n+1th floor without polluting the bound steel bars of the n+2th floor. During the concrete pouring of the n+1th floor structure, the reinforcement binding operation is suspended;
8)第n+1层混凝土浇筑完成后,重复步骤1~7直至浇筑完成。8) After the concrete pouring of the n+1th floor is completed, repeat steps 1~7 until the pouring is completed.
本实施例提出的超高层核心筒水平与竖向同步施工顶模系统,具有以下有益效果:The super high-rise core tube horizontal and vertical synchronous construction top form system proposed in this embodiment has the following beneficial effects:
(1)在不同层核心筒水平结构发生变化时,因水平模板由多个铝合金散拼板15拼接而成,可随时进行水平模板的结构调整,突破了传统顶模只能施工核心筒竖向结构、核心筒水平结构必须滞后于竖向结构单独组织施工的工艺现状,避免了水平结构滞后施工带来的水平梁板处墙体混凝土面打凿及凿毛处理、钢筋二次连接,减少了建筑垃圾的产生量及能源消耗量,施工过程更加绿色环保;同时优化了常规住宅铝合金模板只能人工逐块翻模安装的工艺,实现了竖向墙体模板13与水平模板整体提升,节省大量人工工作量;(1) When the horizontal structure of the core tube in different layers changes, because the horizontal formwork is spliced by a plurality of aluminum alloy loose panels 15, the structure of the horizontal formwork can be adjusted at any time, breaking through the traditional top formwork that can only construct the vertical core tube. The vertical structure and the horizontal structure of the core tube must lag behind the current technological status of the vertical structure, which avoids the concrete surface of the horizontal beam and slab and the secondary connection of the steel bar caused by the lagging construction of the horizontal structure. The generation of construction waste and energy consumption are reduced, and the construction process is more environmentally friendly; at the same time, the process of conventional residential aluminum alloy formwork can only be manually turned over and installed piece by piece is optimized, and the vertical wall formwork 13 and the horizontal formwork are upgraded as a whole. Save a lot of manual work;
(2)实现了铝合金模板快拆体系工艺与顶模系统工艺的完美融合。核心筒水平结构滞后于竖向结构施工的传统顶模施工方法中,核心筒竖向结构施工速度可达4天/层。本实施例中,带水平结构模板的铝合金模板作为快拆体系,充分发挥其支撑立杆保留、梁板底部模板先拆的特点,可通过采取两层钢筋连续绑扎、竖向墙体模板13与水平模板整体同时提升优化顶模施工工艺亦保证了核心筒竖向结构与水平结构同步施工情况下,施工速度可达到4天/层;(2) The perfect integration of the aluminum alloy formwork quick release system technology and the top mold system technology has been realized. In the traditional top form construction method in which the horizontal structure of the core tube lags behind the construction of the vertical structure, the construction speed of the vertical structure of the core tube can reach 4 days/floor. In this embodiment, the aluminum alloy formwork with a horizontal structure formwork is used as a quick-release system to give full play to its characteristics of retaining the support poles and dismantling the formwork at the bottom of the beam slab first. It can be achieved by continuously binding two layers of steel bars and vertical wall formwork 13 Simultaneously upgrading and optimizing the construction process of the top formwork with the horizontal formwork also ensures that the construction speed can reach 4 days/floor under the condition of simultaneous construction of the vertical structure and the horizontal structure of the core tube;
(3)规避了施工过程中建筑结构受力形式不同于原设计意图所带来的安全风险,减小了核心筒后期收口补洞难度,提高了超高层核心筒施工综合施工效率,降低工程施工成本;(3) It avoids the safety risk caused by the force form of the building structure different from the original design intention during the construction process, reduces the difficulty of closing the hole in the later stage of the core tube, improves the comprehensive construction efficiency of the super high-rise core tube construction, and reduces the construction cost. cost;
(4)竖向墙体模板13为铝合金标准单元板19拼装而成,可根据核心筒墙体变化进行相应的调节,具有竖向高度可调、墙厚变化可调、自重轻的特点,绿色节能环保。(4) The vertical wall formwork 13 is assembled from aluminum alloy standard unit plates 19, which can be adjusted according to the changes of the core tube wall. It has the characteristics of adjustable vertical height, adjustable wall thickness, and light weight. Green energy saving and environmental protection.
本发明进一步提出一种超高层核心筒水平与竖向同步施工顶模系统的施工方法。The present invention further proposes a construction method of a super high-rise core tube horizontally and vertically synchronously constructing a top formwork system.
本优选实施例中,一种基于上述超高层核心筒水平与竖向同步施工顶模系统的施工方法,包括以下步骤:In this preferred embodiment, a construction method based on the above-mentioned super-high-rise core tube horizontal and vertical synchronous construction top form system includes the following steps:
第n层混凝土浇筑完成后,进行核心筒第n+1层钢筋绑扎、埋件安装固定以及竖向墙体模板和水平模板的拆模工作;After the concrete pouring of the nth layer is completed, the steel bar binding of the n+1th layer of the core tube, the installation and fixing of the embedded parts, and the demolition of the vertical wall formwork and the horizontal formwork are carried out;
在第n层水平模板拆模完成后,将其迅速翻转至已浇筑的混凝土楼板,在地面将多个铝合金散拼板拼接成第n+1层水平模板,并将拼装后的水平模板与悬挂的铝合金C槽连接成整体并吊装于桁架平台系统下方;After the removal of the horizontal formwork on the nth floor is completed, it is quickly turned over to the poured concrete floor, and multiple aluminum alloy loose panels are spliced on the ground to form the n+1th floor horizontal formwork, and the assembled horizontal formwork is combined with the The suspended aluminum alloy C-channel is connected as a whole and hoisted under the truss platform system;
待钢筋工程和埋件安装验收完毕后,进行顶膜顶升;After the installation and acceptance of the reinforcement works and embedded parts are completed, the roof membrane shall be lifted;
顶升完成后,竖向墙体模板达到第n+1层高度后,进行墙模板合模及加固,并调整第n+1层竖向墙体模板和水平模板的标高,在进行第n+1层竖向模板加固与水平模板安装的同时,其上部第n+2层竖向钢筋继续绑扎;After the jacking is completed, after the vertical wall formwork reaches the height of the n+1th floor, the wall formwork is clamped and reinforced, and the elevation of the vertical wall formwork and horizontal formwork on the n+1th floor is adjusted. While the vertical formwork on the first floor is reinforced and the horizontal formwork is installed, the vertical steel bars on the n+2th floor on the upper part continue to be bound;
水平模板的标高调整完成后,绑扎水平结构梁板钢筋,并通过在桁架平台系统上布置的串筒,将混凝土浇筑至第n+1层竖向墙体及水平梁板。After the elevation adjustment of the horizontal formwork is completed, the steel bars of the horizontal structural beams and slabs are bound, and the concrete is poured to the vertical wall and horizontal beams and slabs of the n+1th floor through the string tubes arranged on the truss platform system.
另外,利用竖向墙体模板的竖向高度可调整,来实现模板整体尺寸的调节。In addition, the vertical height of the vertical wall formwork can be adjusted to realize the adjustment of the overall size of the formwork.
本实施例提出的超高层核心筒水平与竖向同步施工顶模系统的施工方法,具有以下有益效果:The construction method of the super high-rise core tube horizontal and vertical synchronous construction top form system proposed in this embodiment has the following beneficial effects:
(1)在不同层核心筒水平结构发生变化时,因水平模板由多个铝合金散拼板拼接而成,可随时进行水平模板的结构调整,突破了传统顶模只能施工核心筒竖向结构、核心筒水平结构必须滞后于竖向结构单独组织施工的工艺现状,避免了水平结构滞后施工带来的水平梁板处墙体混凝土面打凿及凿毛处理、钢筋二次连接,减少了建筑垃圾的产生量及能源消耗量,施工过程更加绿色环保;同时优化了常规住宅铝合金模板只能人工逐块翻模安装的工艺,实现了竖向墙体模板与水平模板整体提升,节省大量人工工作量;(1) When the horizontal structure of the core tube of different layers changes, because the horizontal formwork is spliced by multiple aluminum alloy loose panels, the structure of the horizontal formwork can be adjusted at any time, breaking through the traditional top formwork that can only construct the vertical core tube The structure and the horizontal structure of the core tube must lag behind the current technological status of the vertical structure, which avoids the concrete surface of the horizontal beam and slab and the secondary connection of steel bars caused by the lagging construction of the horizontal structure. The production of construction waste and energy consumption make the construction process more environmentally friendly; at the same time, the process of conventional residential aluminum alloy formwork can only be manually turned over and installed piece by piece is optimized, and the overall improvement of vertical wall formwork and horizontal formwork is realized, saving a lot of money. manual workload;
(2)实现了铝合金模板快拆体系工艺与顶模系统工艺的完美融合。核心筒水平结构滞后于竖向结构施工的传统顶模施工方法中,核心筒竖向结构施工速度可达4天/层。本实施例中,带水平结构模板的铝合金模板作为快拆体系,充分发挥其支撑立杆保留、梁板底部模板先拆的特点,可通过采取两层钢筋连续绑扎、竖向墙体模板与水平模板整体同时提升优化顶模施工工艺亦保证了核心筒竖向结构与水平结构同步施工情况下,施工速度可达到4天/层;(2) The perfect integration of the aluminum alloy formwork quick release system technology and the top mold system technology has been realized. In the traditional top form construction method in which the horizontal structure of the core tube lags behind the construction of the vertical structure, the construction speed of the vertical structure of the core tube can reach 4 days/floor. In this embodiment, the aluminum alloy formwork with horizontal structural formwork is used as a quick-release system to give full play to its characteristics of retaining the supporting poles and dismantling the formwork at the bottom of the beam slab first. It can be achieved by continuously binding two layers of steel bars, vertical wall formwork and The overall simultaneous upgrade of the horizontal formwork and optimization of the top formwork construction process also ensures that the construction speed can reach 4 days per floor under the condition of simultaneous construction of the vertical structure and horizontal structure of the core tube;
(3)规避了施工过程中建筑结构受力形式不同于原设计意图所带来的安全风险,减小了核心筒后期收口补洞难度,提高了超高层核心筒施工综合施工效率,降低工程施工成本;(3) It avoids the safety risk caused by the force form of the building structure different from the original design intention during the construction process, reduces the difficulty of closing the hole in the later stage of the core tube, improves the comprehensive construction efficiency of the super high-rise core tube construction, and reduces the construction cost. cost;
(4)竖向墙体模板为铝合金标准单元板拼装而成,可根据核心筒墙体变化进行相应的调节,具有竖向高度可调、墙厚变化可调、自重轻的特点,绿色节能环保。(4) The vertical wall formwork is assembled from aluminum alloy standard unit boards, which can be adjusted according to the changes in the core wall. It has the characteristics of adjustable vertical height, adjustable wall thickness, and light weight. It is green and energy-saving Environmental friendly.
以上仅为本发明的优选实施例,并非因此限制本发明的专利范围,凡是利用本发明说明书及附图内容所作的等效结构变换,或直接或间接运用在其他相关的技术领域,均同理包括在本发明的专利保护范围内。The above are only preferred embodiments of the present invention, and are not intended to limit the patent scope of the present invention. All equivalent structural transformations made by using the description of the present invention and the contents of the accompanying drawings, or directly or indirectly used in other related technical fields, are all the same. included in the scope of patent protection of the present invention.
Claims (10)
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN201710170869.4A CN106869489A (en) | 2017-03-21 | 2017-03-21 | Super High Core Walls Structure level and vertical synchronous construction top module system and construction method |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN201710170869.4A CN106869489A (en) | 2017-03-21 | 2017-03-21 | Super High Core Walls Structure level and vertical synchronous construction top module system and construction method |
Publications (1)
| Publication Number | Publication Date |
|---|---|
| CN106869489A true CN106869489A (en) | 2017-06-20 |
Family
ID=59171866
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| CN201710170869.4A Pending CN106869489A (en) | 2017-03-21 | 2017-03-21 | Super High Core Walls Structure level and vertical synchronous construction top module system and construction method |
Country Status (1)
| Country | Link |
|---|---|
| CN (1) | CN106869489A (en) |
Cited By (22)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN107130793A (en) * | 2017-07-14 | 2017-09-05 | 四川华西集团有限公司 | Form frame system with exactly vertical elevation and horizontal location function |
| CN107190975A (en) * | 2017-07-14 | 2017-09-22 | 四川华西集团有限公司 | Construction of super highrise building integrates form frame system |
| CN107246073A (en) * | 2017-06-14 | 2017-10-13 | 中建三局集团有限公司 | Core Walls Structure crossbar structure synchronous construction structure and method |
| CN107489214A (en) * | 2017-06-29 | 2017-12-19 | 深圳前海特辰科技有限公司 | The vertical flat bed construction method with horizontal structure of Core Walls Structure |
| CN107795121A (en) * | 2017-11-08 | 2018-03-13 | 山西建集团有限公司 | Agent structure increases a layer aluminum alloy mould plate jack-up construction method |
| CN108331336A (en) * | 2018-03-12 | 2018-07-27 | 上海建工建集团有限公司 | The integrated lifting steel plateform system and its construction method of floor synchronous construction |
| CN108331326A (en) * | 2018-03-12 | 2018-07-27 | 上海建工建集团有限公司 | Monoblock type mould bases and its construction method for Super High fission conjoined composite structure |
| CN110761402A (en) * | 2019-10-10 | 2020-02-07 | 上海欧跃建筑安装工程有限公司 | Concrete pouring construction method for hysteresis synchronization construction of same floor of building floor slab |
| CN110820941A (en) * | 2019-10-10 | 2020-02-21 | 中建三局第三建设工程有限责任公司 | Emergency system building method under synchronous construction of horizontal structure and top formwork of core barrel |
| CN110821151A (en) * | 2019-12-06 | 2020-02-21 | 荆门市佰思机械科技有限公司 | Self-elevating Climbing Formwork for Transportable Personnel |
| CN110863649A (en) * | 2019-12-09 | 2020-03-06 | 中建七局第四建筑有限公司 | Lightweight hydraulic jacking formwork system for super high-rise construction |
| CN110905189A (en) * | 2019-12-24 | 2020-03-24 | 荆门市佰思机械科技有限公司 | Climbing system of climbing formwork device |
| CN111058615A (en) * | 2019-12-05 | 2020-04-24 | 荆门市佰思机械科技有限公司 | Open-die type climbing formwork device for lifting tower crane body |
| CN111550052A (en) * | 2020-05-30 | 2020-08-18 | 深圳市建工集团股份有限公司 | Exposed buried type steel bar reservation and chiseling-free construction method for floor slab outside super high-rise core tube |
| CN113982115A (en) * | 2021-11-12 | 2022-01-28 | 中建科工集团有限公司 | Frame-core tube construction method |
| CN114427295A (en) * | 2021-12-31 | 2022-05-03 | 中国建筑第二工程局有限公司 | Pre-buried ground anchor pulling connection and holding column combined ultrahigh and ultralimit formwork system and construction method thereof |
| CN115288414A (en) * | 2022-09-13 | 2022-11-04 | 中国建筑第八工程局有限公司 | Construction method of hydraulic climbing operation frame for super high-rise core barrel special-shaped shaft |
| CN115288407A (en) * | 2022-07-25 | 2022-11-04 | 上海建工集团股份有限公司 | Construction method for horizontal structure of super high-rise core tube following vertical structure |
| CN116170564A (en) * | 2022-12-26 | 2023-05-26 | 中建三局第一建设工程有限责任公司 | Image acquisition system and method for core tube floor reinforcement in top formwork construction |
| WO2023102592A1 (en) * | 2021-12-07 | 2023-06-15 | Fabquip Holdings Pty Ltd | A climbing formwork assembly and associated method |
| CN116497946A (en) * | 2023-05-05 | 2023-07-28 | 中建三局集团(深圳)有限公司 | Tower separated synchronous growth construction method |
| CN119711620A (en) * | 2025-01-15 | 2025-03-28 | 上海建工集团股份有限公司 | Core tube hanging type modularized building |
Citations (10)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| SU1606636A1 (en) * | 1988-04-21 | 1990-11-15 | Институт по проектированию промышленных и транспортных объектов для городского хозяйства г.Москвы "Моспромпроект" | Method of erecting solid building |
| CN201883681U (en) * | 2010-10-23 | 2011-06-29 | 林淑芬 | Building wall form assembly |
| CN102433986A (en) * | 2011-08-23 | 2012-05-02 | 杨元东 | Multifunctional section-variable formwork |
| CN103243733A (en) * | 2013-05-09 | 2013-08-14 | 中铁六局集团天津铁路建设有限公司 | Pile foundation construction method for working mountainous areas foundation with multilayer distributing hard rock strata |
| CN103526929A (en) * | 2013-09-24 | 2014-01-22 | 浙江省建工集团有限责任公司 | Super high-rise steel pipe column interior concrete pouring construction method |
| CN203603455U (en) * | 2013-12-13 | 2014-05-21 | 中国建筑第四工程局有限公司 | Tool type hanger suitable for construction of vertical structure of super high-rise building |
| CN203821858U (en) * | 2014-04-21 | 2014-09-10 | 中建八局第二建设有限公司 | Novel concrete tumbling barrel |
| CN105019657A (en) * | 2015-08-07 | 2015-11-04 | 俊川建筑科技有限公司 | Building construction system |
| CN204876578U (en) * | 2015-08-07 | 2015-12-16 | 俊川建筑科技有限公司 | Building construction system |
| CN105298114A (en) * | 2015-02-11 | 2016-02-03 | 中建四局第三建筑工程有限公司 | Aluminum alloy formwork and climbing frame matched construction method |
-
2017
- 2017-03-21 CN CN201710170869.4A patent/CN106869489A/en active Pending
Patent Citations (10)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| SU1606636A1 (en) * | 1988-04-21 | 1990-11-15 | Институт по проектированию промышленных и транспортных объектов для городского хозяйства г.Москвы "Моспромпроект" | Method of erecting solid building |
| CN201883681U (en) * | 2010-10-23 | 2011-06-29 | 林淑芬 | Building wall form assembly |
| CN102433986A (en) * | 2011-08-23 | 2012-05-02 | 杨元东 | Multifunctional section-variable formwork |
| CN103243733A (en) * | 2013-05-09 | 2013-08-14 | 中铁六局集团天津铁路建设有限公司 | Pile foundation construction method for working mountainous areas foundation with multilayer distributing hard rock strata |
| CN103526929A (en) * | 2013-09-24 | 2014-01-22 | 浙江省建工集团有限责任公司 | Super high-rise steel pipe column interior concrete pouring construction method |
| CN203603455U (en) * | 2013-12-13 | 2014-05-21 | 中国建筑第四工程局有限公司 | Tool type hanger suitable for construction of vertical structure of super high-rise building |
| CN203821858U (en) * | 2014-04-21 | 2014-09-10 | 中建八局第二建设有限公司 | Novel concrete tumbling barrel |
| CN105298114A (en) * | 2015-02-11 | 2016-02-03 | 中建四局第三建筑工程有限公司 | Aluminum alloy formwork and climbing frame matched construction method |
| CN105019657A (en) * | 2015-08-07 | 2015-11-04 | 俊川建筑科技有限公司 | Building construction system |
| CN204876578U (en) * | 2015-08-07 | 2015-12-16 | 俊川建筑科技有限公司 | Building construction system |
Non-Patent Citations (3)
| Title |
|---|
| 何昌杰等: "铝合金模板内支外爬体系在超高层建筑核心筒结构施工中的应用", 《建筑施工》 * |
| 李文睿等: "运用新型顶模系统实现超高层建筑绿色施工创新", 《新常态下绿色建筑发展理论与实践——第五届中国中西部地区土木建筑学术年会论文集 》 * |
| 王建春等: "超高层核心筒混凝土水平楼板跃层施工技术", 《施工技术》 * |
Cited By (32)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN107246073A (en) * | 2017-06-14 | 2017-10-13 | 中建三局集团有限公司 | Core Walls Structure crossbar structure synchronous construction structure and method |
| CN107489214A (en) * | 2017-06-29 | 2017-12-19 | 深圳前海特辰科技有限公司 | The vertical flat bed construction method with horizontal structure of Core Walls Structure |
| CN107190975A (en) * | 2017-07-14 | 2017-09-22 | 四川华西集团有限公司 | Construction of super highrise building integrates form frame system |
| CN107130793A (en) * | 2017-07-14 | 2017-09-05 | 四川华西集团有限公司 | Form frame system with exactly vertical elevation and horizontal location function |
| CN107130793B (en) * | 2017-07-14 | 2023-08-25 | 华西工程科技(深圳)股份有限公司 | Die carrier system with accurate vertical elevation and horizontal positioning functions |
| CN107795121B (en) * | 2017-11-08 | 2019-07-26 | 山西一建集团有限公司 | Main structure increases a layer aluminum alloy mould plate jack-up construction method |
| CN107795121A (en) * | 2017-11-08 | 2018-03-13 | 山西建集团有限公司 | Agent structure increases a layer aluminum alloy mould plate jack-up construction method |
| CN108331326A (en) * | 2018-03-12 | 2018-07-27 | 上海建工建集团有限公司 | Monoblock type mould bases and its construction method for Super High fission conjoined composite structure |
| CN108331326B (en) * | 2018-03-12 | 2023-11-28 | 上海建工一建集团有限公司 | Integral die carrier for super high-rise split conjoined combination structure and construction method thereof |
| CN108331336A (en) * | 2018-03-12 | 2018-07-27 | 上海建工建集团有限公司 | The integrated lifting steel plateform system and its construction method of floor synchronous construction |
| CN110761402A (en) * | 2019-10-10 | 2020-02-07 | 上海欧跃建筑安装工程有限公司 | Concrete pouring construction method for hysteresis synchronization construction of same floor of building floor slab |
| CN110820941A (en) * | 2019-10-10 | 2020-02-21 | 中建三局第三建设工程有限责任公司 | Emergency system building method under synchronous construction of horizontal structure and top formwork of core barrel |
| CN110761402B (en) * | 2019-10-10 | 2020-12-29 | 上海欧跃建筑安装工程有限公司 | Concrete pouring construction method for lag and synchronous construction on the same floor of house building |
| CN111058615A (en) * | 2019-12-05 | 2020-04-24 | 荆门市佰思机械科技有限公司 | Open-die type climbing formwork device for lifting tower crane body |
| CN110821151B (en) * | 2019-12-06 | 2021-03-19 | 荆门市佰思机械科技有限公司 | Self-elevating Climbing Formwork for Transportable Personnel |
| CN110821151A (en) * | 2019-12-06 | 2020-02-21 | 荆门市佰思机械科技有限公司 | Self-elevating Climbing Formwork for Transportable Personnel |
| CN110863649B (en) * | 2019-12-09 | 2021-08-27 | 中建七局第四建筑有限公司 | Lightweight hydraulic jacking formwork system for super high-rise construction |
| CN110863649A (en) * | 2019-12-09 | 2020-03-06 | 中建七局第四建筑有限公司 | Lightweight hydraulic jacking formwork system for super high-rise construction |
| CN110905189A (en) * | 2019-12-24 | 2020-03-24 | 荆门市佰思机械科技有限公司 | Climbing system of climbing formwork device |
| CN111550052A (en) * | 2020-05-30 | 2020-08-18 | 深圳市建工集团股份有限公司 | Exposed buried type steel bar reservation and chiseling-free construction method for floor slab outside super high-rise core tube |
| CN113982115A (en) * | 2021-11-12 | 2022-01-28 | 中建科工集团有限公司 | Frame-core tube construction method |
| CN113982115B (en) * | 2021-11-12 | 2022-12-13 | 中建科工集团有限公司 | Frame-core tube construction method |
| WO2023102592A1 (en) * | 2021-12-07 | 2023-06-15 | Fabquip Holdings Pty Ltd | A climbing formwork assembly and associated method |
| CN114427295A (en) * | 2021-12-31 | 2022-05-03 | 中国建筑第二工程局有限公司 | Pre-buried ground anchor pulling connection and holding column combined ultrahigh and ultralimit formwork system and construction method thereof |
| CN115288407B (en) * | 2022-07-25 | 2023-08-22 | 上海建工集团股份有限公司 | Construction method for immediately following vertical structure by using horizontal structure of super high-rise core tube |
| CN115288407A (en) * | 2022-07-25 | 2022-11-04 | 上海建工集团股份有限公司 | Construction method for horizontal structure of super high-rise core tube following vertical structure |
| CN115288414B (en) * | 2022-09-13 | 2023-09-01 | 中国建筑第八工程局有限公司 | Construction method of hydraulic climbing operation frame of super high-rise core tube special-shaped shaft |
| CN115288414A (en) * | 2022-09-13 | 2022-11-04 | 中国建筑第八工程局有限公司 | Construction method of hydraulic climbing operation frame for super high-rise core barrel special-shaped shaft |
| CN116170564A (en) * | 2022-12-26 | 2023-05-26 | 中建三局第一建设工程有限责任公司 | Image acquisition system and method for core tube floor reinforcement in top formwork construction |
| CN116170564B (en) * | 2022-12-26 | 2023-10-27 | 中建三局第一建设工程有限责任公司 | Method for acquiring reinforced bar image of core tube floor slab in top mold construction |
| CN116497946A (en) * | 2023-05-05 | 2023-07-28 | 中建三局集团(深圳)有限公司 | Tower separated synchronous growth construction method |
| CN119711620A (en) * | 2025-01-15 | 2025-03-28 | 上海建工集团股份有限公司 | Core tube hanging type modularized building |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| CN105143570B (en) | Building structure and construction method thereof | |
| CN105971276B (en) | Integral aluminum formwork stair one-step continuous pouring forming structure and construction method | |
| CN115233960B (en) | Integral construction platform structure and method for adding core tube wall in air | |
| CN110485553A (en) | A kind of assembled architecture and its assembly method on prefabricated assembled basis | |
| CN202627506U (en) | Formwork for cast-in-place concrete connecting beams | |
| CN103089004A (en) | Combination frame module, component frame module and tool set structure and installing and dismantling method thereof | |
| CN105804395B (en) | Stair continuously poured in one molding construction method based on monoblock type typified form | |
| CN102720360B (en) | Combination device of secondary high building supported lifted and poured cement formwork and building material lifting and lifting box | |
| CN110847050A (en) | Large-span prefabricated corrugated steel web composite beam top and bottom plate synchronous pouring template and application method thereof | |
| CN114541740A (en) | Integral steel platform formwork equipment for inclined wall construction and construction method thereof | |
| CN206722250U (en) | A kind of precast stair of lightweight | |
| CN112832368A (en) | Quick construction process for cantilever beam at ultrahigh position | |
| CN206487087U (en) | A kind of scissor stairs of sectional | |
| CN106042173A (en) | bridge production system | |
| CN115247498A (en) | Fixed bolster of prefabricated wallboard and contain braced system of this support | |
| CN202064281U (en) | Slip form frame | |
| CN115538678A (en) | Construction method for large-angle overhanging landscape platform side small platform | |
| CN112359965B (en) | Prefabricated concrete assembled structure with ribbed formwork and construction method thereof | |
| CN204982776U (en) | A plurality of large -scale concrete buttress synchronous construction slipform systems | |
| CN107152112A (en) | A kind of modularization Prefabricated stacking floor and its construction method for being used to drop plate region | |
| CN118257414A (en) | A formwork quick disassembly construction method | |
| CN107965193B (en) | Roof construction method for large diameter silo structure | |
| CN108019040B (en) | A construction method for the Bailey frame platform of the transfer floor of a high-rise building | |
| CN109877940A (en) | The production of prefabricated board, lifting and secondary pour integrated apparatus and construction method | |
| KR100697302B1 (en) | Bridge Formwork Removal and Multistage Formwork |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| PB01 | Publication | ||
| PB01 | Publication | ||
| SE01 | Entry into force of request for substantive examination | ||
| SE01 | Entry into force of request for substantive examination | ||
| RJ01 | Rejection of invention patent application after publication |
Application publication date: 20170620 |
|
| RJ01 | Rejection of invention patent application after publication |