CN105298114A - Aluminum alloy formwork and climbing frame matched construction method - Google Patents

Aluminum alloy formwork and climbing frame matched construction method Download PDF

Info

Publication number
CN105298114A
CN105298114A CN201510071392.5A CN201510071392A CN105298114A CN 105298114 A CN105298114 A CN 105298114A CN 201510071392 A CN201510071392 A CN 201510071392A CN 105298114 A CN105298114 A CN 105298114A
Authority
CN
China
Prior art keywords
aluminum alloy
climbing frame
construction
formworks
layer
Prior art date
Application number
CN201510071392.5A
Other languages
Chinese (zh)
Inventor
王加鑫
杨广海
王电
Original Assignee
中建四局第三建筑工程有限公司
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 中建四局第三建筑工程有限公司 filed Critical 中建四局第三建筑工程有限公司
Priority to CN201510071392.5A priority Critical patent/CN105298114A/en
Publication of CN105298114A publication Critical patent/CN105298114A/en

Links

Abstract

The invention discloses an aluminum alloy formwork and climbing frame matched construction method. The method includes that a climbing frame is adopted for constructing a building exterior wall, and aluminum alloy formworks are adopted for formwork erecting and pouring of the building exterior wall; when being demounted, the aluminum alloy formworks are flatwise laid on a scaffold plate of the climbing frame according to an assembling sequence; when the climbing frame ascends, the aluminum alloy formworks are transported to a previous operation layer vertically, and then mounting construction of the aluminum alloy formworks on the previous layer is performed. Through ascending of the climbing frame, the aluminum alloy exterior wall formworks can be transported to an operation face on the previous layer vertically, so that manual transportation quantity is reduced, convenience is brought to construction, labor force can be saved, and construction progress can be accelerated. In the process of formwork demounting on a lower layer, the aluminum alloy formworks are stacked on the climbing frame according to the assembling sequence, so that when the formworks on the upper layer are mounted, the aluminum alloy formworks can be directly picked up for assembling, and construction is simple, convenient and efficient.

Description

A kind of aluminum alloy mould plate and climbing frame coordinative construction method
Technical field
the present invention relates to a kind of aluminum alloy mould plate and climbing frame coordinative construction method, belong to building engineering shuttering technical field of construction.
Background technology
traditional pin hand cradle outrigger is fixed on outside exterior wall, cannot vertically movement.Therefore, after the lower template for concreting is removed, need, by manpower, the template removed is removed supreme layer operation face, and then carry out the construction of last layer exterior wall.Template is very large to the workload of last layer vertical transport, and is difficult to guarantee that the order of template can not be upset in vertical transport process, makes troubles to the template assembly on upper strata.Affect efficiency of construction.
Summary of the invention
the object of the invention is to, a kind of aluminum alloy mould plate and climbing frame coordinative construction method are provided.To reduce the workload of artificial vertical transport template, convenient construction, save labour, accelerating construction progress.
technical scheme of the present invention:
a kind of aluminum alloy mould plate and climbing frame coordinative construction method, the method adopts climbing frame to carry out external wall construction, and external wall adopts aluminum alloy mould plate to carry out taking mould and builds; When removing aluminum alloy mould plate, aluminum alloy mould plate is lain on climbing frame scaffold floor according to assembled order; When climbing frame rises, simultaneously by supreme for an aluminum alloy mould plate vertical transport operation layer, and then carry out the installation of last layer aluminum alloy mould plate.
compared with prior art, the present invention can by the rising of climbing frame, simultaneously by aluminium alloys outer wall template vertical transport to last layer operating surface, decrease hand haulage's amount, convenient construction, can save labour, accelerating construction progress.Because aluminum alloy mould plate overlays on climbing frame according to assembled order in lower floor's form removal process, therefore when carrying out last layer model sheetinstallat, directly aluminum alloy mould plate can be picked up from climbing frame and carrying out assembled, constructing simple, convenient, efficient.
Accompanying drawing explanation
fig. 1 is method schematic diagram of the present invention.
being labeled as in accompanying drawing: the template that 1-major structure of construction, 2-climbing frame, 3-stack by assembled order.
Detailed description of the invention
below in conjunction with drawings and Examples, the present invention is described in further detail, but not as any limitation of the invention.
a kind of aluminum alloy mould plate and climbing frame coordinative construction method, the method adopts climbing frame to carry out external wall construction, and external wall adopts aluminum alloy mould plate to carry out taking mould and builds; When removing aluminum alloy mould plate, aluminum alloy mould plate is lain on climbing frame scaffold floor according to assembled order; When climbing frame rises, simultaneously by supreme for an aluminum alloy mould plate vertical transport operation layer, and then carry out the installation of last layer aluminum alloy mould plate.
Embodiment
fig. 1 is the method schematic diagram of this example, and the climbing frame 2 in Fig. 1 is arranged on outside major structure of construction 1, and climbing frame upwards can climb along major structure of construction.Climbing frame in figure mono-once covers two floors, template can be set up by conventional construction method for first and second layers and carry out external wall construction, then traditional construction mode scaffold used is removed, climbing frame is installed, the template of the second layer is removed again after climbing frame installs, when noting stripping, aluminum alloy mould plate is lain on climbing frame scaffold floor according to assembled order; After the form removable of the second layer, start climbing frame climbing device, climbing frame stops climbing after rising to third layer operating surface with the template 3 stacked by assembled order.When carrying out the installation of third layer outer wall template, can directly by template from climbing frame pick up carry out assembled, centre eliminates artificial operation template being vertically transported to third layer from the second layer, due to when removing the template of the second layer, template stacks by assembled order, therefore also without the need to selecting template, directly taking up just can be assembled, substantially increases efficiency of construction.In order to alleviate the load that climbing frame climbs, all templates adopt the aluminum alloy mould plate of lighter in weight.

Claims (1)

1. aluminum alloy mould plate and a climbing frame coordinative construction method, is characterized in that: the method adopts climbing frame to carry out external wall construction, and external wall adopts aluminum alloy mould plate to carry out taking mould and builds; When removing aluminum alloy mould plate, aluminum alloy mould plate is lain on climbing frame scaffold floor according to assembled order; When climbing frame rises, simultaneously by supreme for an aluminum alloy mould plate vertical transport operation layer, and then carry out the installation of last layer aluminum alloy mould plate.
CN201510071392.5A 2015-02-11 2015-02-11 Aluminum alloy formwork and climbing frame matched construction method CN105298114A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201510071392.5A CN105298114A (en) 2015-02-11 2015-02-11 Aluminum alloy formwork and climbing frame matched construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201510071392.5A CN105298114A (en) 2015-02-11 2015-02-11 Aluminum alloy formwork and climbing frame matched construction method

Publications (1)

Publication Number Publication Date
CN105298114A true CN105298114A (en) 2016-02-03

Family

ID=55195863

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201510071392.5A CN105298114A (en) 2015-02-11 2015-02-11 Aluminum alloy formwork and climbing frame matched construction method

Country Status (1)

Country Link
CN (1) CN105298114A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106869489A (en) * 2017-03-21 2017-06-20 中建三局第建设工程有限责任公司 Super High Core Walls Structure level and vertical synchronous construction top module system and construction method
CN110528739A (en) * 2019-09-05 2019-12-03 中国建筑第二工程局有限公司 FS keeps the temperature the integrated construction technique of exterior sheathing, aluminum alloy mould plate and climbing frame

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2001193278A (en) * 2000-01-07 2001-07-17 Kajima Corp Construction method for structure having inside space, and climbing scaffolding
CN201507113U (en) * 2009-09-25 2010-06-16 北京星河人施工技术有限责任公司 Electric climbing-formwork device used for building and construction
CN102016199A (en) * 2008-03-25 2011-04-13 Peri有限公司 Track-guided self-climbing shuttering system with climbing rail extension pieces
CN104131703A (en) * 2014-05-16 2014-11-05 中国建筑第四工程局有限公司 Method for constructing core tube wall through self-climbing formwork and adopted self-climbing formwork

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2001193278A (en) * 2000-01-07 2001-07-17 Kajima Corp Construction method for structure having inside space, and climbing scaffolding
CN102016199A (en) * 2008-03-25 2011-04-13 Peri有限公司 Track-guided self-climbing shuttering system with climbing rail extension pieces
CN201507113U (en) * 2009-09-25 2010-06-16 北京星河人施工技术有限责任公司 Electric climbing-formwork device used for building and construction
CN104131703A (en) * 2014-05-16 2014-11-05 中国建筑第四工程局有限公司 Method for constructing core tube wall through self-climbing formwork and adopted self-climbing formwork

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106869489A (en) * 2017-03-21 2017-06-20 中建三局第建设工程有限责任公司 Super High Core Walls Structure level and vertical synchronous construction top module system and construction method
CN110528739A (en) * 2019-09-05 2019-12-03 中国建筑第二工程局有限公司 FS keeps the temperature the integrated construction technique of exterior sheathing, aluminum alloy mould plate and climbing frame

Similar Documents

Publication Publication Date Title
CN100351484C (en) Liftable hydraulic climbing template and construction method thereof
CN101435276B (en) Cabin top steel beam hydraulic hoisting and positioning apparatus of cylinder cabin structure building and construction method thereof
CN1738952A (en) Concrete slab form system
CN201865054U (en) Hydraulic climbing formwork device for high bridge pier
CN201158933Y (en) High-rise maintaining scaffold device with extruding structure
CN201695681U (en) Integral self-elevating type elevator hoistway tube mold
CN102505845B (en) Quick construction method for high-rise buildings
CN102953546B (en) Construction method for mounting deformation joint template at double walls
Kannan et al. Constructability assessment of climbing formwork systems using building information modeling
WO2011002120A1 (en) Composite cage for construction
CN102213033A (en) Method of building a hybrid tower for a wind generator
CN104032967B (en) Prefabricated assembled frame structure component construction method for hanging
CN106400691B (en) Anti-collision wall mould bases integrated construction technique
CN102251664A (en) One-time forming construction method for cast-in-place stair tread template
CN106013192A (en) Method of constructing cofferdam after integrally lowering multiple layers of inner bracings of steel sheet pile cofferdam
CN106320691B (en) Aluminum wood template construction method
CN107435438B (en) Chimney rollover construction device
CN103935911B (en) Tower crane attached wall supporting construction and construction method thereof
CN101858119B (en) Reinforced concrete hollow floor slab and construction method
CN102587645A (en) Climbing supporting mechanism having expansion and automatic meshing functions, and construction method thereof
CN104131703A (en) Method for constructing core tube wall through self-climbing formwork and adopted self-climbing formwork
CN104947926B (en) A kind of Core Walls Structure inner core top formwork system hard protection device and its construction method
CN105908777A (en) Comprehensive pipe gallery sliding mold and application method thereof
CN105133833B (en) Stair template and the stair construction method using the stair template
CN101413341B (en) Elevator well internal formwork construction method and elevator well internal formwork construction support

Legal Events

Date Code Title Description
PB01 Publication
C06 Publication
SE01 Entry into force of request for substantive examination
C10 Entry into substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20160203

RJ01 Rejection of invention patent application after publication