CN110820941A - Emergency system building method under synchronous construction of horizontal structure and top formwork of core barrel - Google Patents

Emergency system building method under synchronous construction of horizontal structure and top formwork of core barrel Download PDF

Info

Publication number
CN110820941A
CN110820941A CN201910960401.4A CN201910960401A CN110820941A CN 110820941 A CN110820941 A CN 110820941A CN 201910960401 A CN201910960401 A CN 201910960401A CN 110820941 A CN110820941 A CN 110820941A
Authority
CN
China
Prior art keywords
construction
emergency system
horizontal structure
horizontal
synchronous construction
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201910960401.4A
Other languages
Chinese (zh)
Inventor
张志华
张步月
田喜胜
冯吉
杨鑫
王军
甘晓琴
王福彪
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Third Construction Co Ltd of China Construction Third Engineering Division
Original Assignee
Third Construction Co Ltd of China Construction Third Engineering Division
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Third Construction Co Ltd of China Construction Third Engineering Division filed Critical Third Construction Co Ltd of China Construction Third Engineering Division
Priority to CN201910960401.4A priority Critical patent/CN110820941A/en
Publication of CN110820941A publication Critical patent/CN110820941A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B1/00Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
    • E04B1/34Extraordinary structures, e.g. with suspended or cantilever parts supported by masts or tower-like structures enclosing elevators or stairs; Features relating to the elastic stability
    • E04B1/3404Extraordinary structures, e.g. with suspended or cantilever parts supported by masts or tower-like structures enclosing elevators or stairs; Features relating to the elastic stability supported by masts or tower-like structures
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B1/00Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
    • E04B1/35Extraordinary methods of construction, e.g. lift-slab, jack-block
    • E04B1/3505Extraordinary methods of construction, e.g. lift-slab, jack-block characterised by the in situ moulding of large parts of a structure
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G21/00Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
    • E04G21/32Safety or protective measures for persons during the construction of buildings

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Physics & Mathematics (AREA)
  • Electromagnetism (AREA)
  • Mechanical Engineering (AREA)
  • Buildings Adapted To Withstand Abnormal External Influences (AREA)

Abstract

The invention discloses an emergency system building method under synchronous construction of a horizontal structure of a core barrel and a top mold. When the core section of thick bamboo vertical structure is under construction to the top mould, select one or polylith horizontal floor and core section of thick bamboo vertical structure synchronous construction in the outside round within range of core section of thick bamboo to reserve the entrance to a cave of setting up sparse stair in the horizontal floor of construction, communicate from top to bottom through setting up the stair between each layer horizontal structure, thereby another passageway of the upper and lower top mould outside the construction elevator has been formed, the personnel of being convenient for are sparse when emergency, also can strengthen core section of thick bamboo vertical structure's stability.

Description

Emergency system building method under synchronous construction of horizontal structure and top formwork of core barrel
Technical Field
The invention belongs to the field of high-rise building construction, and particularly relates to an emergency system building method under synchronous construction of a horizontal structure of a core barrel and a top formwork.
Background
The super high-rise structure is mainly an outer steel frame and a core tube structure, the super high-rise structure adopts a top mould to construct a core tube vertical structure in advance, a horizontal structure in a core tube and an outer frame horizontal structure are constructed together, and the construction of the horizontal structure is usually lagged behind the core tube vertical structure by 10-15 layers;
the current construction mode is for only carrying out the vertical structure construction, and the constructor passes through the elevator loading from top to bottom the mould, and when emergency, after stopping power supply, constructor will be unable to evacuate from the mould, constitutes very big potential safety hazard.
Disclosure of Invention
The invention aims to provide an emergency system building method for overcoming the defects in the prior art that a horizontal structure of a core barrel and a top die are constructed synchronously. In order to achieve the technical purpose, the technical scheme adopted by the invention is as follows:
a method for building an emergency system under synchronous construction of a horizontal structure and a top formwork of a core tube is characterized in that when the core tube structure rises to the height of each floor of a main building, the horizontal structure corresponding to each floor is synchronously poured, platforms are built between any two or more vertical structure intervals at the edges of the core tube, and the time of every two adjacent layers of platforms is communicated through evacuation stairs.
Further limiting, the evacuation stairs are formed by erecting steel pipes or are formed by single-run shaped steel stairs.
Further limiting, holes are reserved on each layer of platform, and the evacuation stairs are communicated with the next layer of platform through the reserved holes of the upper layer of platform.
Further inject, every layer of platform is convenient for all be provided with the protection rail.
Further limiting, the holes are covered with protective nets.
Compared with the prior art, 1, under the working condition of top formwork construction, the construction of the horizontal structure of the local core barrel does not occupy the construction period of the vertical structure, and the construction efficiency of the top formwork system is improved.
2. The evacuation stair is erected by utilizing the synchronously constructed platform, the problem that constructors escape from the top die in an emergency is solved, and the evacuation stair has the advantages of simplicity and convenience in operation, low cost and the like.
3. The evacuation stair can be used as an upper channel and a lower channel outside the construction elevator, and even if the construction elevator fails, the evacuation stair can keep smooth traffic between the upper steel platform and the lower large flat layer.
4. And part of horizontal structures and vertical structures are constructed synchronously, so that the structural stability of the core barrel in the construction process is enhanced.
Drawings
In order to more clearly illustrate the detailed description of the invention or the technical solutions in the prior art, the drawings that are needed in the detailed description of the invention or the prior art will be briefly described below. In the drawings, like elements or portions are generally identified by like reference numerals. In the drawings, elements or portions are not necessarily drawn to scale.
Fig. 1 is a schematic view of the position structure of the platform and the core barrel according to the present invention.
FIG. 2 is a schematic diagram of the construction process.
Detailed Description
Embodiments of the present invention will be described in detail below with reference to the accompanying drawings. The following examples are only for illustrating the technical solutions of the present invention more clearly, and therefore are only examples, and the protection scope of the present invention is not limited thereby.
It is to be noted that, unless otherwise specified, technical or scientific terms used herein shall have the ordinary meaning as understood by those skilled in the art to which the invention pertains.
As shown in fig. 1, in the emergency system building method under the synchronous construction of the horizontal structure and the top formwork of the core tube, when the core tube structure rises to the height of each floor of the main building, the horizontal structure corresponding to each floor is synchronously poured, platforms are built between any two or more vertical structure intervals at the middle part of the core tube and the edges of the core tube, and the time of the adjacent two layers of platforms is communicated through evacuation stairs. The evacuation stairs are constructed by erecting steel pipes. Holes are reserved on each layer of platform, and the evacuation stairs are communicated with the next layer of platform through the reserved holes of the previous layer of platform. Each layer of platform is convenient to be provided with a protective fence. And each layer of platform is provided with a vertically corresponding hoisting port. The hoisting opening is covered with a protective net.
The technical scheme is as follows:
1. under the top mould construction working condition, the construction of the horizontal structure of the local core barrel does not occupy the construction period of the vertical structure, and the construction efficiency of a top mould system is improved.
2. The evacuation stair is erected by utilizing the synchronously constructed platform, the problem that constructors escape from the top die in an emergency is solved, and the evacuation stair has the advantages of simplicity and convenience in operation, low cost and the like.
3. The evacuation stair can be used as an upper channel and a lower channel outside the construction elevator, and even if the construction elevator fails, the evacuation stair can keep smooth traffic between the upper steel platform and the lower large flat layer.
4. And part of horizontal structures and vertical structures are constructed synchronously, so that the structural stability of the core barrel in the construction process is enhanced.
Finally, it should be noted that: the above embodiments are only used to illustrate the technical solution of the present invention, and not to limit the same; while the invention has been described in detail and with reference to the foregoing embodiments, it will be understood by those skilled in the art that: the technical solutions described in the foregoing embodiments may still be modified, or some or all of the technical features may be equivalently replaced; such modifications and substitutions do not depart from the spirit and scope of the present invention, and they should be construed as being included in the following claims and description.

Claims (5)

1. A method for building an emergency system under synchronous construction of a horizontal structure of a core barrel and a top mold is characterized in that: when the core tube vertical structure is constructed by the top die, one or more horizontal floor slabs are selected within a circle of range outside the core tube to be synchronously constructed with the core tube vertical structure, and the horizontal structures of all layers are communicated up and down by erecting evacuation stairs.
2. The emergency system building method under the synchronous construction of the horizontal structure of the core cylinder and the top mold according to claim 1, characterized in that: the evacuation stairs are formed by erecting steel pipes or are formed by single-run shaped steel stairs.
3. The emergency system building method under the synchronous construction of the horizontal structure of the core cylinder and the top mold according to claim 2, characterized in that: holes are reserved on each layer of platform, and the evacuation stairs are communicated with the next layer of platform through the reserved holes of the previous layer of platform.
4. The emergency system building method under the synchronous construction of the horizontal structure of the core cylinder and the top mold according to claim 3, characterized in that: each layer of platform is convenient to be provided with a protective fence.
5. The emergency system building method under the synchronous construction of the horizontal structure of the core cylinder and the top mold according to claim 4, characterized in that: the holes are covered with protective nets.
CN201910960401.4A 2019-10-10 2019-10-10 Emergency system building method under synchronous construction of horizontal structure and top formwork of core barrel Pending CN110820941A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201910960401.4A CN110820941A (en) 2019-10-10 2019-10-10 Emergency system building method under synchronous construction of horizontal structure and top formwork of core barrel

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201910960401.4A CN110820941A (en) 2019-10-10 2019-10-10 Emergency system building method under synchronous construction of horizontal structure and top formwork of core barrel

Publications (1)

Publication Number Publication Date
CN110820941A true CN110820941A (en) 2020-02-21

Family

ID=69549102

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201910960401.4A Pending CN110820941A (en) 2019-10-10 2019-10-10 Emergency system building method under synchronous construction of horizontal structure and top formwork of core barrel

Country Status (1)

Country Link
CN (1) CN110820941A (en)

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE1278712B (en) * 1963-08-01 1968-09-26 Hochtief Ag Hoch Tiefbauten skyscraper
CN106013450A (en) * 2016-07-14 2016-10-12 中国建筑第八工程局有限公司 Core tube skip-floor construction method
CN106869489A (en) * 2017-03-21 2017-06-20 中建三局第建设工程有限责任公司 Super High Core Walls Structure level and vertical synchronous construction top module system and construction method
CN107246073A (en) * 2017-06-14 2017-10-13 中建三局集团有限公司 Core Walls Structure crossbar structure synchronous construction structure and method
CN209353688U (en) * 2018-11-30 2019-09-06 中建八局第三建设有限公司 An early demolition formwork system for super high-rise building core tube with outer steel and inner aluminum composite

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE1278712B (en) * 1963-08-01 1968-09-26 Hochtief Ag Hoch Tiefbauten skyscraper
CN106013450A (en) * 2016-07-14 2016-10-12 中国建筑第八工程局有限公司 Core tube skip-floor construction method
CN106869489A (en) * 2017-03-21 2017-06-20 中建三局第建设工程有限责任公司 Super High Core Walls Structure level and vertical synchronous construction top module system and construction method
CN107246073A (en) * 2017-06-14 2017-10-13 中建三局集团有限公司 Core Walls Structure crossbar structure synchronous construction structure and method
CN209353688U (en) * 2018-11-30 2019-09-06 中建八局第三建设有限公司 An early demolition formwork system for super high-rise building core tube with outer steel and inner aluminum composite

Similar Documents

Publication Publication Date Title
CN108033367B (en) Synchronous lifting device and lifting method for steel column and cylinder frame alternately supported steel platform and tower crane
CN106437130A (en) Inner roof external climbing type formwork construction platform for super high-rise building construction
US10550566B2 (en) Structure and method of making the same
CN106150079A (en) Make building machine in the air
CN108331336B (en) Integral lifting steel platform system for synchronous construction of floor slabs and construction method thereof
CN103352580A (en) Construction method for internally added elevator structure in multilayer masonry house
CN110805259A (en) Integral steel platform formwork equipment for synchronous construction and construction method
CN107100361A (en) Inner support aluminum dipping form device and its installation method are climbed outside a kind of
CN217175692U (en) Intelligent hydraulic lifting formwork system for super high-rise core tube construction
CN203547125U (en) Column type overall steel platform hydraulic creeping formwork
CN104131706B (en) The construction method of the two-layer connection structure of vertical reinforcement of concrete frame structure
CN114809689A (en) After-loading elevator and aerial courtyard type corridor with old building reinforcing function
CN204850469U (en) Commercial building construction system
CN110820941A (en) Emergency system building method under synchronous construction of horizontal structure and top formwork of core barrel
CN106193586A (en) Elevator Telescopic folding Integral lifting core
CN110905204A (en) Method for transferring formwork supporting materials of wood formwork of building outer frame column
CN117569607A (en) Super high-rise adduction variable-section climbing frame construction method
CN215671063U (en) Roofing high altitude structure template supporting platform that encorbelments
CN214885380U (en) Portable tower crane construction platform passageway
CN213328707U (en) Thin-wall pier high-altitude operation combined platform
CN103352579A (en) Reinforcement and reconstruction masonry structure using externally-added gallery bridge and externally-added elevator and construction method
CN107642241A (en) The stress supporting construction and construction method of a kind of prefabricated balcony
CN109138499B (en) Prefabricated staircase shaping construction protection frame
CN101705675B (en) High tower structure convenient for the emergent evacuation of people and construction method thereof
CN208870379U (en) The integrated lifting steel plateform system of floor synchronous construction

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20200221

RJ01 Rejection of invention patent application after publication