CN106884529A - A kind of high-altitude long-span steel vestibule underplate concrete suspends steel form and construction method in midair - Google Patents

A kind of high-altitude long-span steel vestibule underplate concrete suspends steel form and construction method in midair Download PDF

Info

Publication number
CN106884529A
CN106884529A CN201710152132.XA CN201710152132A CN106884529A CN 106884529 A CN106884529 A CN 106884529A CN 201710152132 A CN201710152132 A CN 201710152132A CN 106884529 A CN106884529 A CN 106884529A
Authority
CN
China
Prior art keywords
steel
vestibule
section steel
span
steel beam
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201710152132.XA
Other languages
Chinese (zh)
Inventor
蔡超
曾鹏
倪坤林
张仕江
殷本林
罗元江
朱昌权
陈宁
李成伟
金大鑫
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Sinohydro Bureau 7 Co Ltd
Original Assignee
Sinohydro Bureau 7 Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Sinohydro Bureau 7 Co Ltd filed Critical Sinohydro Bureau 7 Co Ltd
Priority to CN201710152132.XA priority Critical patent/CN106884529A/en
Publication of CN106884529A publication Critical patent/CN106884529A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G9/00Forming or shuttering elements for general use
    • E04G9/02Forming boards or similar elements
    • E04G9/06Forming boards or similar elements the form surface being of metal
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G11/00Forms, shutterings, or falsework for making walls, floors, ceilings, or roofs
    • E04G11/36Forms, shutterings, or falsework for making walls, floors, ceilings, or roofs for floors, ceilings, or roofs of plane or curved surfaces end formpanels for floor shutterings
    • E04G11/38Forms, shutterings, or falsework for making walls, floors, ceilings, or roofs for floors, ceilings, or roofs of plane or curved surfaces end formpanels for floor shutterings for plane ceilings of concrete
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G17/00Connecting or other auxiliary members for forms, falsework structures, or shutterings
    • E04G17/18Devices for suspending or anchoring form elements to girders placed in ceilings, e.g. hangers

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Mechanical Engineering (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

The present invention relates to building engineering construction, a kind of high-altitude long-span steel vestibule underplate concrete suspends steel form and construction method in midair.Particularly high-altitude, large-span steel vestibule baseplate reinforcing bar concrete construction, belong to building auxiliary equipment field.It includes section steel beam and steel form, and section steel beam is the steel truss structure of the H profile steel composition for intersecting vertically in length and breadth, and section steel beam two ends are fixed in high building agent structure, and steel form is laid between section steel beam.The construction method of the invention includes:Section steel beam integrally lifts a height after the completion of installation on ground using the hydraulic lifting device in high building agent structure;It is by steel shutterings between section steel beam and steel form periphery full weld is suitable for reading in section steel beam;Continue to lift up steel vestibule and reach designed elevation, and complete mating operation;Casting concrete plate.The invention has the advantages that:Using a kind of steel form being welded directly together with steel vestibule, solve high-altitude, large-span steel vestibule concrete board constructions operation platform and set up problem, fill up a blank of high-altitude steel vestibule concrete board constructions construction technology.

Description

A kind of high-altitude long-span steel vestibule underplate concrete suspends steel form and construction method in midair
Technical field
The present invention relates to building engineering construction, particularly high-altitude, large-span steel vestibule baseplate reinforcing bar concrete construction, belong to Building auxiliary equipment field.
Background technology
Although relatively common building construction technology, construction process requirement will be higher for high-rise connected buildings structure, but Today of engineering technology prosperity, it can meet people to the diversified requirement of construction style.On the one hand by setting vestibule by phase Neighboring buildings are connected, and facilitate contact between two block domains;On the other hand, due to the profile that conjoined structure is unique, bring strong Strong visual effect, makes building more characteristic.Therefore more and more skyscrapers for being provided with vestibule are widely used in all kinds of In public building and commercial building.
Gallery structure form, it is generally the case that armored concrete or Structural Steel Reinforced Concrete are used when span is little more, Steel construction is typically chosen when span is larger.But when high-altitude, large-span corridor use Structural Steel Reinforced Concrete, conventional at present falls Ground scaffold, the stability of high building body side overhanging support shuttering supporting scheme and scaffolding height all hardly result in guarantee, The construction period is also substantially prolongs simultaneously, the vestibule concrete slab construction turns into prominent problem.For this reason, it may be necessary to simplify support knot Structure.
The content of the invention
The problem to be solved in the present invention is not enough aiming at more than and a kind of safe and reliable, economical rationality, operable is provided The strong concrete-pouring template system of property, to solve high-altitude, large-span steel vestibule concrete slab construction problem.Its technical scheme is such as Under:
A kind of high-altitude long-span steel vestibule underplate concrete suspends steel form in midair, and its key technology is to include section steel beam and steel Template, section steel beam is the steel truss structure of the H profile steel composition for intersecting vertically in length and breadth, and section steel beam two ends are fixed on high building agent structure On, steel form is laid between section steel beam.
Under steel form stiffener is fixed along long span direction.
Above-mentioned high-altitude long-span steel vestibule underplate concrete suspends the construction method of steel form in midair, and its key technology is to include Following steps:
1) section steel beam integrally lifts one after the completion of installation on ground using the hydraulic lifting device in high building agent structure Individual height;
2) it is by steel shutterings between section steel beam and steel form periphery full weld is suitable for reading in section steel beam;
3) steel form and stiffener are prevented fires, antirust treatment;
4) continue to lift up steel vestibule and reach designed elevation, and complete mating operation;
5) colligation Bars In Poured Concrete Slab reinforcing bar;
6) casting concrete plate.
Compared with prior art, the invention has the advantages that:
1st, the present invention is solved high-altitude, large-span steel and is connected using a kind of steel form being welded directly together with steel vestibule Corridor concrete board constructions operation platform sets up problem, has filled up a sky of high-altitude steel vestibule concrete board constructions construction technology In vain.
2nd, steel template system reduces bottom place usage amount compared with form bracing system is landed, there is provided solid is handed over Fork working space.
3rd, most of operations of the present invention is all carried out on ground, reduces work high above the ground, reduces construction safety risk, safety Reliable, economical rationality is workable.
Brief description of the drawings
Fig. 1, is overlooking the structure diagram of the present invention;
Fig. 2, is Figure 1A-A cross-sectional views;
Fig. 3, is Figure 1B-B cross-sectional views;
Fig. 4, is dimensional structure diagram of the present invention.
Specific embodiment
The present invention is described further below in conjunction with the accompanying drawings.
Referring to Fig. 1-Fig. 4, the present invention includes section steel beam 2 and steel form 3, and section steel beam 2 is the H profile steel group for intersecting vertically in length and breadth Into steel truss structure, the two ends of section steel beam 2 are fixed in high building agent structure 1, and steel form 3 is laid between section steel beam 2.
Under steel form 3 stiffener 4 is fixed along long span direction.
Above-mentioned high-altitude long-span steel vestibule underplate concrete suspends the construction method of steel form in midair, and its key technology is to include Following steps:
1) section steel beam 2 is integrally lifted after the completion of installation on ground using the hydraulic lifting device in high building agent structure 1 One height, this highly depends on the circumstances, and can be 1.5 meters, can be 2 meters, can also be 2.5 meters etc.;
2) according to size between section steel beam, steel form 3 is processed using 5-7mm steel plates;To ensure that concrete slab amount of deflection meets Code requirement, stiffener 4, the spacing 700- of stiffener 4 are set under steel form 3 along long span direction using 8-10mm steel plates 900mm, 90-100mm high;
3) steel form 3 is arranged between section steel beam 2, and the periphery full weld of steel form 3 is suitable for reading in section steel beam 2;
4) do not removed after steel form 3, belong to a part for building, it is necessary to prevent steel form 3 and stiffener 4 Fire, antirust treatment;
5) continue to lift up steel vestibule and reach designed elevation, and complete mating operation;
6) colligation Bars In Poured Concrete Slab reinforcing bar;
7) casting concrete plate 5.

Claims (3)

1. a kind of high-altitude long-span steel vestibule underplate concrete suspends steel form in midair, it is characterised in that including section steel beam (2) and punching block Plate (3), section steel beam (2) is the steel truss structure of the H profile steel composition for intersecting vertically in length and breadth, and section steel beam (2) two ends are fixed on high building In agent structure (1), steel form (3) is laid between section steel beam (2).
2. high-altitude long-span steel vestibule underplate concrete suspends steel form in midair according to claim 1, it is characterized in that in steel form (3) stiffener (4) is fixed under along long span direction.
3. a kind of high-altitude long-span steel vestibule underplate concrete suspends the construction method of steel form in midair, it is characterised in that including following step Suddenly:
1) section steel beam (2) is integrally lifted after the completion of installation on ground using the hydraulic lifting device in high building agent structure (1) One height;
2) it is by steel form (3) between section steel beam (2) and steel form (3) periphery full weld is suitable for reading in section steel beam (2);
3) steel form (3) and stiffener (4) are prevented fires, antirust treatment;
4) continue to lift up steel vestibule and reach designed elevation, and complete mating operation;
5) colligation Bars In Poured Concrete Slab reinforcing bar;
6) casting concrete plate (5).
CN201710152132.XA 2017-03-15 2017-03-15 A kind of high-altitude long-span steel vestibule underplate concrete suspends steel form and construction method in midair Pending CN106884529A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710152132.XA CN106884529A (en) 2017-03-15 2017-03-15 A kind of high-altitude long-span steel vestibule underplate concrete suspends steel form and construction method in midair

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710152132.XA CN106884529A (en) 2017-03-15 2017-03-15 A kind of high-altitude long-span steel vestibule underplate concrete suspends steel form and construction method in midair

Publications (1)

Publication Number Publication Date
CN106884529A true CN106884529A (en) 2017-06-23

Family

ID=59181021

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710152132.XA Pending CN106884529A (en) 2017-03-15 2017-03-15 A kind of high-altitude long-span steel vestibule underplate concrete suspends steel form and construction method in midair

Country Status (1)

Country Link
CN (1) CN106884529A (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108915245A (en) * 2018-06-20 2018-11-30 清华大学 Casting method without supporting steel plate device and concrete water flat structure
CN112392139A (en) * 2020-11-25 2021-02-23 中交第二航务工程局有限公司 Large-span combined building structure and construction method thereof
CN114059656A (en) * 2021-11-18 2022-02-18 泰宏建设发展有限公司 Large-span suspension type steel reinforced concrete multi-layer combined corridor integrated construction method

Citations (16)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
GB1332372A (en) * 1970-05-28 1973-10-03 Hambro Structural Systems Ltd Cold rolled sheet steel joist
WO2003076095A1 (en) * 2002-03-14 2003-09-18 Bhp Steel Limited Profiled steel decking sheets
CN2617859Y (en) * 2003-05-14 2004-05-26 上海市第七建筑有限公司 Truss supporting template systems
CN1534154A (en) * 2003-04-01 2004-10-06 勇 滕 Construction method of steel-concrete composite storey
JP2005105766A (en) * 2003-10-02 2005-04-21 Nippon Steel Corp Removable support beam
CN101230678A (en) * 2007-01-28 2008-07-30 邱则有 Force-bearing type template component
CN201809971U (en) * 2010-09-28 2011-04-27 杨峰 Floor formwork erecting system with large plate-span precast beam
CN202672713U (en) * 2012-06-08 2013-01-16 云南建工水利水电建设有限公司 Keel modifying device of cast-in-situ floor
JP5532468B1 (en) * 2013-11-25 2014-06-25 美藤 雅康 Formwork support member in the slab
CN203755678U (en) * 2014-01-26 2014-08-06 中铁建工集团有限公司 Upper suspension hoisting type hoisting device for reinforced concrete floor construction
WO2014191959A1 (en) * 2013-05-31 2014-12-04 Tecnotelai Components S.R.L. System and method for constructing a superstructure
CN204112714U (en) * 2014-08-12 2015-01-21 金天德 Detachable template system
CN105492708A (en) * 2013-08-29 2016-04-13 株式会社葵 Deck plate and manufacturing method for same
CN105625711A (en) * 2014-10-27 2016-06-01 葛丹丹 Construction-purpose roof template
CN105649314A (en) * 2016-03-15 2016-06-08 中国建筑第六工程局有限公司 Suspension platform for high and long-span corridor construction
CN206581588U (en) * 2017-03-15 2017-10-24 中国水利水电第七工程局有限公司 A kind of high-altitude long-span steel vestibule underplate concrete suspends steel form in midair

Patent Citations (16)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
GB1332372A (en) * 1970-05-28 1973-10-03 Hambro Structural Systems Ltd Cold rolled sheet steel joist
WO2003076095A1 (en) * 2002-03-14 2003-09-18 Bhp Steel Limited Profiled steel decking sheets
CN1534154A (en) * 2003-04-01 2004-10-06 勇 滕 Construction method of steel-concrete composite storey
CN2617859Y (en) * 2003-05-14 2004-05-26 上海市第七建筑有限公司 Truss supporting template systems
JP2005105766A (en) * 2003-10-02 2005-04-21 Nippon Steel Corp Removable support beam
CN101230678A (en) * 2007-01-28 2008-07-30 邱则有 Force-bearing type template component
CN201809971U (en) * 2010-09-28 2011-04-27 杨峰 Floor formwork erecting system with large plate-span precast beam
CN202672713U (en) * 2012-06-08 2013-01-16 云南建工水利水电建设有限公司 Keel modifying device of cast-in-situ floor
WO2014191959A1 (en) * 2013-05-31 2014-12-04 Tecnotelai Components S.R.L. System and method for constructing a superstructure
CN105492708A (en) * 2013-08-29 2016-04-13 株式会社葵 Deck plate and manufacturing method for same
JP5532468B1 (en) * 2013-11-25 2014-06-25 美藤 雅康 Formwork support member in the slab
CN203755678U (en) * 2014-01-26 2014-08-06 中铁建工集团有限公司 Upper suspension hoisting type hoisting device for reinforced concrete floor construction
CN204112714U (en) * 2014-08-12 2015-01-21 金天德 Detachable template system
CN105625711A (en) * 2014-10-27 2016-06-01 葛丹丹 Construction-purpose roof template
CN105649314A (en) * 2016-03-15 2016-06-08 中国建筑第六工程局有限公司 Suspension platform for high and long-span corridor construction
CN206581588U (en) * 2017-03-15 2017-10-24 中国水利水电第七工程局有限公司 A kind of high-altitude long-span steel vestibule underplate concrete suspends steel form in midair

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108915245A (en) * 2018-06-20 2018-11-30 清华大学 Casting method without supporting steel plate device and concrete water flat structure
CN112392139A (en) * 2020-11-25 2021-02-23 中交第二航务工程局有限公司 Large-span combined building structure and construction method thereof
CN114059656A (en) * 2021-11-18 2022-02-18 泰宏建设发展有限公司 Large-span suspension type steel reinforced concrete multi-layer combined corridor integrated construction method

Similar Documents

Publication Publication Date Title
CN107060275B (en) Modular elevator shaft construction process
CN100587206C (en) Steel pillar supporting type integral self-lifting steel platform scaffold template system
CN205025074U (en) Elevator well steel bracing promotes double -deck scaffold operation platform of formula
CN102535845A (en) Construction method of bearing frame of corridor structure
CN105863253A (en) Integral formwork-supporting type asynchronous casting stairwell wall column formwork supporting system and construction method
CN106884529A (en) A kind of high-altitude long-span steel vestibule underplate concrete suspends steel form and construction method in midair
CN113550578A (en) High-altitude overhanging structure formwork support and upper protection system construction method
CN110512719A (en) A kind of high residential building large span compartment vestibule high-altitude formwork steel platform construction
CN108331336A (en) The integrated lifting steel plateform system and its construction method of floor synchronous construction
CN105220766A (en) The syndeton of a kind of concrete prefabricated beam and cast-in-place post and construction technology thereof
CN209723438U (en) A kind of novel coagulation body precast stair plate
CN206581588U (en) A kind of high-altitude long-span steel vestibule underplate concrete suspends steel form in midair
CN106499211B (en) Newly-increased outrigger frame Baogang anchor daraf(reciprocal of farad) structure
CN206503378U (en) Newly-increased outrigger constructing structure
CN108775084A (en) Steel-concrete combines precast beam and prefabricated post connection structure and construction method
CN208363666U (en) It is a kind of for build face side construction safety protection frame
CN102108783A (en) Operation platform in control tower overhanging structure and construction method thereof
CN108019040B (en) A kind of high-rise building transfer floor Bailey bracket platform construction method
CN205348390U (en) Connection structure of precast concrete roof beam and cast -in -place post
CN112359860B (en) Construction method for non-support type open caisson capping
CN211714541U (en) Special handling frame for installing shear wall template in elevator shaft
CN206844680U (en) Steel vestibule installation on ground load transfer device
CN208088151U (en) A kind of plate girder bridge jacking auxiliary steel member
CN115075604B (en) Reinforcing method for old plate type balcony bearing structure
CN206220484U (en) A kind of template suspension centre spandrel girder of steel platform

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20170623