CN106869483A - Combination foot palm and its installation method - Google Patents

Combination foot palm and its installation method Download PDF

Info

Publication number
CN106869483A
CN106869483A CN201611158460.2A CN201611158460A CN106869483A CN 106869483 A CN106869483 A CN 106869483A CN 201611158460 A CN201611158460 A CN 201611158460A CN 106869483 A CN106869483 A CN 106869483A
Authority
CN
China
Prior art keywords
flange
hole
plate body
breast board
plate
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201611158460.2A
Other languages
Chinese (zh)
Other versions
CN106869483B (en
Inventor
岳齐贤
王兴康
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Zhejiang 20 Smelter Construction Co ltd
China MCC20 Group Corp Ltd
Original Assignee
NINGBO MCC20 CONSTRUCTION CO Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by NINGBO MCC20 CONSTRUCTION CO Ltd filed Critical NINGBO MCC20 CONSTRUCTION CO Ltd
Priority to CN201611158460.2A priority Critical patent/CN106869483B/en
Publication of CN106869483A publication Critical patent/CN106869483A/en
Application granted granted Critical
Publication of CN106869483B publication Critical patent/CN106869483B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G5/00Component parts or accessories for scaffolds
    • E04G5/08Scaffold boards or planks
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G7/00Connections between parts of the scaffold
    • E04G7/02Connections between parts of the scaffold with separate coupling elements
    • E04G7/28Clips or connections for securing boards

Abstract

The invention provides a kind of combination foot palm, including:The first mounting hole is offered on plate body, the first hole latch structure is provided with the edge of plate body;Breast board is connected on the side of plate body, and the second mounting hole is provided with breast board, and the lower end and both sides of breast board are provided with the second hole latch structure;Foot guard plate is connected on the opposite side of plate body vertically, and the 3rd mounting hole is provided with foot guard plate, and the downside and both sides of foot guard plate are provided with the 3rd hole latch structure;Attachment fastener described in three groups is separately fixed on the first mounting hole, the second mounting hole and the 3rd mounting hole, and plate body, breast board and foot guard plate are connected by attachment fastener with scaffolding steel pipe, and its installation method is comprised the following steps:The foot guard plate is installed, the assembled plate body installs the breast board;Beneficial effects of the present invention are:Dismounting is facilitated very much, and scaffold connection is reliable, and plate body be able to will reliably be connected with foot guard plate and railing.

Description

Combination foot palm and its installation method
Technical field
The invention belongs to construction material and technical field of construction, it is related to combination foot palm, and also relate to the group The installation method of box-like scaffold board.
Background technology
Scaffold board is layed on scaffold, crosshead, is easy to workman to walk above it, is transported material and construction operation A kind of interim construction material being used in turn;The conventional scaffold board of construction site have punching press Steel scaffold board, wooden scaffold board, Bamboo scaffold board.
Fastener type steel pipe scaffold is set up flexibly, highly versatile, the advantages of both economical with being convenient to mount and dismount, it has also become Currently used amount at most, using a kind of most common scaffold.
Due to the property of construction, scaffold board turnaround speed is very fast, thus, scaffold board should have enough intensity, steady It is qualitative, and should have light weight, convenient disassembly, the features such as being hardly damaged.
Such as the Chinese invention patent of Application No. 201410746085.8, a kind of scaffold board, including scaffold board sheet are disclosed Body, the scaffold board body includes base plate and quarter bend, and base plate bottom is provided with some reinforcements, in the relative both sides of the base plate The quarter bend is equipped with along floor length direction, some pilot holes are disposed with each quarter bend, above-mentioned patent structure is simple, Low cost, easy installation and removal, and with larger compression strength.
The steel scaffold board for largely using in recent years, realizes the convenience of dismounting, but lack reliable with scaffold Connection, also lacks with foot guard plate, railing and is reliably connected, if paid no heed to during use, can also produce safety problem.
Consult pertinent literature to find, the research to scaffold board is concentrated mainly on convenience, and the research of security more lacks.
The content of the invention
The purpose of the present invention is directed to the above mentioned problem of prior art presence, it is proposed that combination foot palm and its installation side Method.
The purpose of the present invention can be realized by following technical proposal:A kind of combination foot palm, including:
Plate body, it is be arranged in parallel, and the first mounting hole is offered on the plate body, and first is provided with the edge of the plate body Hole latch structure;
Breast board, it is connected on the side of the plate body vertically, and the second mounting hole, the breast board are provided with the breast board Lower end and both sides be provided with the second hole latch structure;
Foot guard plate, it is connected on the opposite side of the plate body vertically, and the 3rd mounting hole, institute are provided with the foot guard plate The downside and both sides for stating foot guard plate are provided with the 3rd hole latch structure;
Attachment fastener, its quantity is three groups, and attachment fastener described in three groups is separately fixed at first mounting hole, the second peace On dress hole and the 3rd mounting hole, the plate body, the breast board and the foot guard plate pass through the attachment fastener and scaffold Fastener for connection.
Preferably, the attachment fastener includes fixed plate, fastening bolt, nut, two fastening snap fingers and respectively with two Individual fastening corresponding two connecting rods of snap finger, the fixed plate is used for and first mounting hole or the second mounting hole or the 3rd Mounting hole clamping, the fastening bolt is located in the fixed plate, and the nut is threaded in the fastening bolt, and two The individual fastening snap finger is respectively hinged at the both sides of the fixed plate, and two one end of the connecting rod are hinged another with the nut End is hinged with the fastening snap finger.
Preferably, being respectively arranged with the forward edge of the plate body, posterior edges, left side edge and right side edge One flange, the second flange, the 3rd flange and the 4th flange, first hole latch structure include the first connecting hole and the first company Pin, first connecting pin is arranged on first flange and the 3rd flange, and first connecting hole is arranged on described On second flange and the 4th flange.
Preferably, the left side edge and right side edge of the breast board are respectively arranged with the 5th flange and the 6th flange, Second hole latch structure includes the second connecting pin and the second connecting hole, and second connecting pin is arranged on the 5th flange And on the bottom surface of the breast board, second connecting hole is arranged on the 6th flange.
Preferably, the left side edge of the foot guard plate, right side edge and lower edge are respectively arranged with the 7th flange, the 8th Flange and the 9th flange, the 3rd hole latch structure include the 3rd connecting pin and the 3rd connecting hole, the 3rd connecting pin It is arranged on the 7th flange, the 3rd connecting hole is arranged on the 8th flange and the 9th flange.
Secondly, a kind of installation method of combination foot palm is disclosed, is comprised the following steps:
Step 1, the installation foot guard plate, are connected with each other, institute between each foot guard plate by the 3rd hole latch structure State and connected by second hole latch structure and first hole latch structure between foot guard plate and the plate body, each gear pin Plate is fixedly connected by the attachment fastener with scaffolding steel pipe;
Step 2, according to the assembled plate body of scaffold size, mutually interconnected by the first hole latch structure between each plate body Connect, each plate body is connected by the attachment fastener with scaffolding steel pipe;
Step 3, the installation breast board, are connected with each other, the column between each breast board by second hole latch structure Plate is connected by the attachment fastener with scaffolding steel pipe, and each breast board passes through second hole latch structure and described first Hole latch structure is connected on the plate body vertically.
Preferably, the 4th flange of the adjacent plate body of the 3rd flange correspondence of the plate body, described first Connecting hole is plugged in first connecting pin so that adjacent plate body connection, the first flange correspondence the described 9th Flange, and first connecting pin is plugged in the 3rd connecting hole so that the foot guard plate is connected to the plate body On, the bottom surface of second flange correspondence breast board, second connecting pin be plugged in first connecting hole so that The breast board is connected on the plate body.
Preferably, the 6th flange of the adjacent breast board of the 5th flange correspondence of the breast board, and described second Connecting pin is plugged in the second connecting hole so that the adjacent breast board is connected.
Preferably, the 8th flange of the adjacent foot guard plate of the 7th flange correspondence of the foot guard plate, and 3rd connecting pin is plugged in the 3rd connecting hole so that the adjacent foot guard plate is connected.
Compared with prior art, beneficial effects of the present invention are:
1st, dismounting is facilitated very much, and scaffold connection is reliable, and plate body be able to will reliably be connected with foot guard plate and railing.
2nd, fastening clip has connection reliable, the advantage of convenient disassembly, and structure is also very ingenious.
3rd, by setting first, second, third, fourth flange, alignment and positioning when being easy to plate body to install, and make Obtain overall structure compacter firm, and the first hole latch structure can play extraordinary connection effect.
4th, by described installation method can be quickly scaffold board is assembled on scaffold, can so greatly improve Efficiency of construction, is convenient in dismounting, very quick during installation.
Brief description of the drawings
Fig. 1 is the structural representation of plate body of the invention;
Fig. 2 is the cross-sectional view of plate body of the invention;
Fig. 3 is the structural representation of breast board of the invention;
Fig. 4 is the structural representation of foot guard plate of the invention;
Fig. 5 is the cross-sectional view of foot guard plate of the invention;
Fig. 6 is the structural representation of attachment fastener of the invention;
Fig. 7 is the structural representation of fixed plate of the invention;
Fig. 8 is the structure diagram of combination foot palm of the invention;
Fig. 9 is the flow chart of the installation method of combination foot palm of the invention.
In figure, 100, plate body;110th, the first mounting hole;120th, the first flange;130th, the second flange;140th, the 3rd flange; 150th, the 4th flange;160th, the first connecting hole;170th, the first connecting pin;200th, breast board;210th, the second mounting hole;220th, the 5th turn over Side;230th, the 6th flange;240th, the second connecting pin;250th, the second connecting hole;300th, foot guard plate;310th, the 3rd mounting hole;320、 7th flange;330th, the 8th flange;340th, the 9th flange;350th, the 3rd connecting pin;360th, the 3rd connecting hole;400th, osculum; 500th, attachment fastener;510th, fixed plate;520th, fastening bolt;530th, nut;540th, snap finger is fastened;550th, connecting rod.
Specific embodiment
The following is specific embodiment of the invention and with reference to accompanying drawing, technical scheme is further described, But the present invention is not limited to these embodiments.
As shown in Figure 1, Figure 2, shown in Fig. 3, Fig. 4, Fig. 5, Fig. 6, Fig. 7, Fig. 8, a kind of combination foot palm, including:Plate body 100, Breast board 200, foot guard plate 300 and attachment fastener 500, are used to build on scaffold, are stood for workmen and constructed.
Wherein, plate body 100 is exactly the platy structure be arrangeding in parallel, is mainly used in trampling standing for people, and in reality Plate body 100 is typically made with punching press shape steel plate, and upper surface sets strip male-type tread plate and osculum 400.
The first mounting hole 110 is offered on the plate body 100, the first mounting hole 110 is used to install attachment fastener 500, and And first the quantity of mounting hole 110 can be adjusted according to actual demand, typically in order to reach preferably fixed installation effect, lead to One row, four the first mounting holes 110 can be often set.
The first hole latch structure is provided with the edge of the plate body 100, the first pin-and-hole structure is mainly used in adjacent plate body 100 Assembling and plate body 100 and arm-tie and foot guard plate 300 assembling.
Breast board 200 is connected on the side of the plate body 100 vertically, herein what deserves to be explained is, breast board 200 is actually It is connected to the outside of plate body 100.
Actual breast board 200 is made by punching press shape steel plate, and the second mounting hole 210 is provided with the breast board 200, Second mounting hole 210 is used for installing attachment fastener 500, so that breast board 200 can be fixed together with scaffolding steel pipe.
The lower end and both sides of the breast board 200 are provided with the second hole latch structure, herein it is worthy of note that, breast board 200 It is vertically arranged, so its lower end is the edge of correspondence plate body 100, the both sides of breast board 200 pass through the second hole latch structure and phase Adjacent breast board 200 is connected.
Foot guard plate 300 is connected on the opposite side of the plate body 100 vertically, and the interior of plate body 100 is preferably connected to herein Side, and actual foot guard plate 300 is made by punching press shape steel plate.
The 3rd mounting hole 310 is provided with the foot guard plate 300, the 3rd mounting hole 310 is used to install attachment fastener 500, So that foot guard plate 300 is fixed together with scaffolding steel pipe.
The downside and both sides of the foot guard plate 300 are provided with the 3rd hole latch structure, and the downside of foot guard plate 300 passes through the 3rd Hole latch structure is plugged on the inside edge of plate body 100, and plate body 100 is by the 3rd hole latch structure and the plate body 100 of both sides Connection.
It is applied on plate body 100, breast board 200 and foot guard plate 300 attachment fastener 500, and quantity is at least three, so It is divided into three groups, and each group of quantity is several, and herein it is worthy of note that, each group of quantity of attachment fastener 500 Quantity with corresponding mounting hole is identical.
Attachment fastener 500 described in three groups is separately fixed at first mounting hole 110, the second mounting hole 210 and the 3rd On mounting hole 310, the plate body 100, the breast board 200 and the foot guard plate 300 are by the attachment fastener 500 and pin hand Frame fastener for connection.
The operation principle of attachment fastener 500 is the then other end by through mounting hole, making its body and mounting hole clamping Clip lives scaffolding steel pipe, this makes it possible to realize fixing purpose.
As shown in Fig. 6, Fig. 7, Fig. 8, on the basis of above-mentioned implementation method, the attachment fastener 500 includes fixed plate 510th, fastening bolt 520,530, two, nut fasten snap fingers 540 and respectively fastening snap finger 540 corresponding two described with two Individual connecting rod 550.
The fixed plate 510 is used to block with the mounting hole 210 of first mounting hole 110 or second or the 3rd mounting hole 310 Connect, fixed plate 510 is exactly a discoideus structure, size is just greater than mounting hole.
The fastening bolt 520 is located in the fixed plate 510, herein it is worthy of note that, fastening bolt 520 is axially It is fixed in fixed plate 510, and can rotates.
The nut 530 is threaded in the fastening bolt 520, and two fastening snap fingers 540 are respectively hinged at The both sides of the fixed plate 510, two one end of the connecting rod 550 are hinged the other end with the tightening buckle with the nut 530 Pawl 540 is hinged, herein it is worthy of note that, fastening snap finger 540 and connecting rod 550 be one-to-one, that is to say, that left side it is tight Gu the connecting rod 550 on the left of the connection of snap finger 540, the connecting rod 550 on the right side of the connection of fastening snap finger 540 on right side.
Attachment fastener 500 operationally, first passes through mounting hole, because the rear end for fastening snap finger 540 is to be hinged on fixation On plate 510, so two fastening snap fingers 540 can close up or open, one end of connecting rod 550 is hinged on fastening snap finger 540 Middle part is biased against on rear position, and the other end is hinged on nut 530, so turning fastening bolt 520, now nut 530 is along tight Fixing bolt 520 is moved, the rotation of drivening rod 550, can thus drive fastening snap finger 540 to close up.
The fastening clip of this structure has connection reliable, convenient disassembly, and structure is also very ingenious.
As shown in Figure 1 and Figure 2, on the basis of above-mentioned implementation method, the forward edge of the plate body 100, posterior edges, The first flange 120, the second flange 130, the 3rd flange 140 and the 4th is respectively arranged with left side edge and right side edge to turn over Side 150, herein it is worthy of note that, the first flange 120 and the 3rd flange 140 are upper overturnings, the second flange 130 and the 4th The lower flange of flange 150, upper overturning can be fastened with lower flange, and in actually splicing, positioned at the plate body 100 in left side, it the 4th Flange 150 is lower flange, and positioned at the plate body 100 on right side, its 3rd flange 140 is upper overturning, so the 3rd flange 140 can be detained Gone on to the 4th flange 150, similarly, the first flange 120 and the second flange 130 are also upper and lower turnup structure, are easy to breast board 200 And the installation settings of foot guard plate 300.
By setting first, second, third, fourth flange 150, alignment and positioning when being easily installed, and cause Overall structure is compacter firm.
First hole latch structure includes the first connecting hole 160 and the first connecting pin 170, first connecting pin 170 It is arranged on the flange 140 of first flange 120 and the 3rd, first connecting hole 160 is arranged on second flange 130 And the 4th on flange 150, in simple terms, directed downwardly first is provided with exactly the first flange 120 and the 3rd flange 140 and is connected Pin 170, the first connecting hole 160 is provided with the second flange 130 and the 4th flange 150.
Herein it is worthy of note that, when mounted, the 3rd flange 140 is anchored to when on the 4th flange 150, the first connecting pin 170 are just plugged in the first connecting hole 160, this makes it possible to make linking together for the stabilization of two boards body 100.
As shown in figure 3, on the basis of above-mentioned implementation method, the left side edge and right edge fate of the breast board 200 The 5th flange 220 and the 6th flange 230 are not provided with, wherein the 5th flange 220 can be anchored on the 6th flange 230, are easy to Positioning and installation.
In simple terms, the 6th turnover panel exactly on the breast board 200 in left side can be anchored on the 5th flange 220, so that two The adjacent breast board 200 of block is positioned together, and is easy to the connection of the second connecting pin 240 and the second connecting hole 250.
Second hole latch structure includes the second connecting pin 240 and the second connecting hole 250, second connecting pin 240 It is arranged on the bottom surface of the 5th flange 220 and the breast board 200, second connecting hole 250 is arranged on the described 6th On flange 230.
Herein it is worthy of note that, the second connecting pin 240 is distributed on the bottom surface of breast board 200, this makes it possible to make breast board 200 are plugged on the second flange 130 by the second connecting pin 240, so that breast board 200 is fixed together with plate body 100.
As shown in Figure 4, Figure 5, on the basis of above-mentioned implementation method, the left side edge of the foot guard plate 300, right side edge And lower edge is respectively arranged with the 7th flange 320, the 8th flange 330 and the 9th flange 340, wherein the 7th flange 320 pairs Another piece of the 8th flange 330 of adjacent foot guard plate 300 is answered, is linked together this makes it possible to make the left and right of two pieces of foot guard plates 300; The first flange 120 of correspondence of 9th flange 340, the first flange 120 can be snapped onto on the 9th flange 340, so that foot guard plate 300 Fix on the panel body 100.
The 3rd hole latch structure includes the 3rd connecting pin 350 and the 3rd connecting hole 360, the 3rd connecting pin 350 It is arranged on the 7th flange 320, the 3rd connecting hole 360 is arranged on the 8th flange 330 and the described 9th turns over On side 340.
Herein what deserves to be explained is, the 3rd connecting pin 350 is used to be plugged on the 3rd connecting hole 360 and the first connecting hole In 160, connected with plate body 100 and adjacent foot guard plate 300 this makes it possible to make foot guard plate 300.
As shown in Fig. 1, Fig. 3, Fig. 4, on the basis of above-mentioned implementation method, the plate body 100, the breast board 200 and Osculum 400 is offered on the surface of the foot guard plate 300, is easy to, in rainy day draining, prevent from producing ponding on scaffold board.
As shown in Figure 1, Figure 2, shown in Fig. 3, Fig. 4, Fig. 5, Fig. 6, Fig. 7, Fig. 8, Fig. 9, secondly, a kind of combination foot palm is disclosed Installation method, comprise the following steps:
Step 1, the installation foot guard plate 300, are mutually interconnected between each foot guard plate 300 by the 3rd hole latch structure Connect, connected by second hole latch structure and first hole latch structure between the foot guard plate 300 and the plate body 100 Connect, each foot guard plate 300 is fixedly connected by the attachment fastener 500 with scaffolding steel pipe;
Step 2, according to the assembled plate body 100 of scaffold size, the first hole latch structure is passed through between each plate body 100 It is connected with each other, each plate body 100 is connected by the attachment fastener 500 with scaffolding steel pipe;
Step 3, the installation breast board 200, are connected with each other between each breast board 200 by second hole latch structure, The breast board 200 is connected by the attachment fastener 500 with scaffolding steel pipe, and each breast board 200 is sold by second hole Structure and first hole latch structure are connected on the plate body 100 vertically.
By the above method can be quickly scaffold board is assembled on scaffold, can so greatly improve construction effect Rate, is convenient to, it is only necessary to reversely turn fixing bolt in dismounting, so that fasten snap finger 540 open, this makes it possible to make Attachment fastener 500 is separated with scaffolding steel pipe, then pushes down on foot guard plate 300, and the first connecting pin 170 is from the 3rd connecting hole Exited in 360, the 9th flange 340 is separated with the first flange 120, then successively dismantle down breast board 200, and by adjacent plate body Taken apart between 100, it becomes possible to take away, it is very convenient, it is quick during installation.
As shown in Figure 1, Figure 2, shown in Fig. 3, Fig. 4, Fig. 5, on the basis of above-mentioned implementation method, described the of the plate body 100 4th flange 150 of the adjacent plate body 100 of the correspondence of three flange 140, first connecting hole 160 is plugged on described first So that the adjacent plate body 100 is connected in connecting pin 170, the correspondence of the first flange 120 the 9th flange 340, and And first connecting pin 170 is plugged in the 3rd connecting hole 360 so that the foot guard plate 300 is connected to the plate body On 100, the bottom surface of the correspondence of the second flange 130 breast board 200, second connecting pin 240 is plugged on described first and connects Connect in hole 160 so that the breast board 200 is connected on the plate body 100.
Because the 3rd flange 140 and the 4th flange 150 are respectively upper and lower turnup structure, when some pieces of plate bodys 100 are combined Afterwards, can make to limit each piece of free degree of plate body 100, prevent it from loosening or fixed insecure;First flange 120 and Nine flange 340 and the second flange 130 and the bottom surface of breast board 200 are also after mounting, substantially upper and lower turnup structure, such energy The stability of enough holding scaffold boards from structure, then only needing to hole pin connection just can be by breast board 200, plate body 100 and gear Sole 300 is fixed together, very convenient practicality.
On the basis of above-mentioned implementation method, the adjacent breast board 200 of the 5th flange 220 correspondence of the breast board 200 6th flange 230, and second connecting pin 240 is plugged in the second connecting hole 250 so that the adjacent column Plate 200 is connected.
On the basis of above-mentioned implementation method, the adjacent gear pin of the 7th flange 320 correspondence of the foot guard plate 300 8th flange 330 of plate 300, and the 3rd connecting pin 350 is plugged in the 3rd connecting hole 360 so that phase The adjacent foot guard plate 300 is connected.
Specific embodiment described herein is only to the spiritual explanation for example of the present invention.Technology neck belonging to of the invention The technical staff in domain can be made various modifications or supplement to described specific embodiment or be replaced using similar mode Generation, but without departing from spirit of the invention or surmount scope defined in appended claims.

Claims (9)

1. a kind of combination foot palm, it is characterised in that including:
Plate body, it is be arranged in parallel, and the first mounting hole is offered on the plate body, and the first hole pin is provided with the edge of the plate body Structure;
Breast board, it is connected on the side of the plate body vertically, the second mounting hole is provided with the breast board, under the breast board End and both sides are provided with the second hole latch structure;
Foot guard plate, it is connected on the opposite side of the plate body vertically, and the 3rd mounting hole, the gear are provided with the foot guard plate The downside and both sides of sole are provided with the 3rd hole latch structure;
Attachment fastener, its quantity is three groups, and attachment fastener described in three groups is separately fixed at first mounting hole, the second mounting hole And the 3rd on mounting hole, the plate body, the breast board and the foot guard plate pass through the attachment fastener and scaffolding steel pipe Connection.
2. combination foot palm as described in claim 1, it is characterised in that:The attachment fastener includes fixed plate, fastening Bolt, nut, two fastening snap fingers and fastening corresponding two connecting rods of snap finger described with two respectively, the fixed plate are used for With first mounting hole or the second mounting hole or the 3rd mounting hole clamping, the fastening bolt is located in the fixed plate, The nut is threaded in the fastening bolt, and two fastening snap fingers are respectively hinged at the both sides of the fixed plate, Two one end of the connecting rod are hinged the other end and are hinged with the fastening snap finger with the nut.
3. combination foot palm as described in claim 2, it is characterised in that:The forward edge of the plate body, posterior edges, The first flange, the second flange, the 3rd flange and the 4th flange, described are respectively arranged with left side edge and right side edge One hole latch structure includes the first connecting hole and the first connecting pin, and first connecting pin is arranged on first flange and the On three flange, first connecting hole is arranged on second flange and the 4th flange.
4. combination foot palm as described in claim 3, it is characterised in that:The left side edge and right edge of the breast board Edge is respectively arranged with the 5th flange and the 6th flange, and second hole latch structure includes the second connecting pin and the second connection Hole, second connecting pin is arranged on the bottom surface of the 5th flange and the breast board, and second connecting hole is arranged on On 6th flange.
5. combination foot palm as described in claim 4, it is characterised in that:The left side edge of the foot guard plate, right edge Edge and lower edge are respectively arranged with the 7th flange, the 8th flange and the 9th flange, and the 3rd hole latch structure includes the 3rd Connecting pin and the 3rd connecting hole, the 3rd connecting pin are arranged on the 7th flange, and the 3rd connecting hole is arranged on On 8th flange and the 9th flange.
6. according to the installation method of any described combination foot palm in claim 1 to 5, it is characterised in that including following Step:
Step 1, the installation foot guard plate, are connected with each other, the gear between each foot guard plate by the 3rd hole latch structure Connected by second hole latch structure and first hole latch structure between sole and the plate body, each foot guard plate leads to The attachment fastener is crossed to be fixedly connected with scaffolding steel pipe;
Step 2, according to the assembled plate body of scaffold size, be connected with each other by the first hole latch structure between each plate body, Each plate body is connected by the attachment fastener with scaffolding steel pipe;
Step 3, the installation breast board, are connected with each other between each breast board by second hole latch structure, and the breast board leads to Cross the attachment fastener to be connected with scaffolding steel pipe, each breast board is sold by second hole latch structure and first hole Structural vertical is connected on the plate body.
7. the installation method of combination foot palm as described in claim 6, it is characterised in that:The described 3rd of the plate body 4th flange of the flange adjacent plate body of correspondence, first connecting hole be plugged in first connecting pin so that Adjacent plate body connection, the first flange correspondence the 9th flange, and first connecting pin are plugged on described So that the foot guard plate is connected on the plate body in 3rd connecting hole, the bottom surface of the second flange correspondence breast board, Second connecting pin is plugged in first connecting hole so that the breast board is connected on the plate body.
8. the installation method of the combination foot palm as described in claim 1 or 7, it is characterised in that:The breast board it is described 6th flange of the 5th flange adjacent breast board of correspondence, and second connecting pin be plugged in the second connecting hole so that The adjacent breast board is connected.
9. the installation method of combination foot palm as described in claim 8, it is characterised in that:Described the of the foot guard plate 8th flange of the adjacent foot guard plate of seven flange correspondence, and the 3rd connecting pin is plugged on the 3rd connecting hole It is interior so that the adjacent foot guard plate is connected.
CN201611158460.2A 2016-12-15 2016-12-15 Combined scaffold board and mounting method thereof Active CN106869483B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201611158460.2A CN106869483B (en) 2016-12-15 2016-12-15 Combined scaffold board and mounting method thereof

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201611158460.2A CN106869483B (en) 2016-12-15 2016-12-15 Combined scaffold board and mounting method thereof

Publications (2)

Publication Number Publication Date
CN106869483A true CN106869483A (en) 2017-06-20
CN106869483B CN106869483B (en) 2020-09-15

Family

ID=59164670

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201611158460.2A Active CN106869483B (en) 2016-12-15 2016-12-15 Combined scaffold board and mounting method thereof

Country Status (1)

Country Link
CN (1) CN106869483B (en)

Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US4624342A (en) * 1985-03-22 1986-11-25 Anderson Carl E Scaffolding platform
CN1133386A (en) * 1995-04-14 1996-10-16 小野辰雄 Scaffold plate
CN203034785U (en) * 2012-12-31 2013-07-03 中建海峡建设发展有限公司 Reinforcement mesh scaffold board
CN203183024U (en) * 2013-04-21 2013-09-11 徐建民 Bone nail taking-out device
CN203412278U (en) * 2013-06-25 2014-01-29 吴建常 Metal scaffold board for building
CN203878970U (en) * 2014-02-25 2014-10-15 中国建筑第八工程局有限公司 Construction scaffold board structure
CN205224572U (en) * 2015-11-19 2016-05-11 中国十七冶集团有限公司 A ledger board for fastener -style steel pipe scaffold
CN105908963A (en) * 2016-06-08 2016-08-31 苏州莲敬机械工程科技有限公司 Standing board of scaffold

Patent Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US4624342A (en) * 1985-03-22 1986-11-25 Anderson Carl E Scaffolding platform
CN1133386A (en) * 1995-04-14 1996-10-16 小野辰雄 Scaffold plate
CN203034785U (en) * 2012-12-31 2013-07-03 中建海峡建设发展有限公司 Reinforcement mesh scaffold board
CN203183024U (en) * 2013-04-21 2013-09-11 徐建民 Bone nail taking-out device
CN203412278U (en) * 2013-06-25 2014-01-29 吴建常 Metal scaffold board for building
CN203878970U (en) * 2014-02-25 2014-10-15 中国建筑第八工程局有限公司 Construction scaffold board structure
CN205224572U (en) * 2015-11-19 2016-05-11 中国十七冶集团有限公司 A ledger board for fastener -style steel pipe scaffold
CN105908963A (en) * 2016-06-08 2016-08-31 苏州莲敬机械工程科技有限公司 Standing board of scaffold

Also Published As

Publication number Publication date
CN106869483B (en) 2020-09-15

Similar Documents

Publication Publication Date Title
DE102013207827A1 (en) Device for fixing solar modules and roof
CN106869483A (en) Combination foot palm and its installation method
CN206418758U (en) A kind of scaffold board
CN206418587U (en) A kind of easy-to-dismount prefabricated balcony
CN206753009U (en) One kind building fabricated scaffold
CN209457352U (en) Portable stable type scaffold
CN201964100U (en) Hanging and connecting device
CN209119730U (en) A kind of outdoor use cable testing bridge for stablizing installation
CN214169883U (en) Construction elevator adheres to frame
CN209704028U (en) A kind of assembled architecture standardization protection system
DE102007028746A1 (en) Load u. Spacer support for supplementing the lightweight support for solar systems on flat roofs.
CN211622593U (en) Modular floor formwork device
KR200404035Y1 (en) A fixed frame for food- plate, and a fixed inspection equipment for bridges
CN108978487B (en) A easily set up quick detachable protection rack for bridge construction
CN209211854U (en) A kind of disk buckle scaffold that can quickly assemble
CN207332311U (en) A kind of building template securing device
CN108060782B (en) The installation method and auxiliary mounting tool of girder steel element
CN206110640U (en) A scalable scaffold frame plate for scaffold frame
CN106285066A (en) A kind of speed patch background frame
CN217711373U (en) Large-scale component installation bent
CN215211527U (en) Steel constructs component convenient to connect
CN216661335U (en) Multilayer guipure vaulting pole device
CN215926662U (en) Wall body external assembly type climbing frame suitable for tower crane
CN219548386U (en) Civil building construction post mould fastener convenient to equipment
CN211007597U (en) Attached lifting scaffold

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
CB02 Change of applicant information
CB02 Change of applicant information

Address after: 315 800 Pearl River Road 429 Xindan Street, Beilun District, Ningbo City, Zhejiang Province

Applicant after: Zhejiang 20 Smelter Construction Co.,Ltd.

Address before: 315 800 Pearl River Road 429 Xindan Street, Beilun District, Ningbo City, Zhejiang Province

Applicant before: NINGBO MCC 20 CONSTRUCTION Co.,Ltd.

TA01 Transfer of patent application right
TA01 Transfer of patent application right

Effective date of registration: 20190531

Address after: 315 800 Pearl River Road 429 Xindan Street, Beilun District, Ningbo City, Zhejiang Province

Applicant after: Zhejiang 20 Smelter Construction Co.,Ltd.

Applicant after: CHINA MCC20 GROUP Corp.,Ltd.

Address before: 315 800 Pearl River Road 429 Xindan Street, Beilun District, Ningbo City, Zhejiang Province

Applicant before: Zhejiang 20 Smelter Construction Co.,Ltd.

GR01 Patent grant
GR01 Patent grant