CN106760492A - A kind of one-shot forming post-cast strip concrete construction process - Google Patents

A kind of one-shot forming post-cast strip concrete construction process Download PDF

Info

Publication number
CN106760492A
CN106760492A CN201611132441.2A CN201611132441A CN106760492A CN 106760492 A CN106760492 A CN 106760492A CN 201611132441 A CN201611132441 A CN 201611132441A CN 106760492 A CN106760492 A CN 106760492A
Authority
CN
China
Prior art keywords
post
cast strip
template
concrete
side body
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201611132441.2A
Other languages
Chinese (zh)
Inventor
李英章
李保彦
韩春涛
任杰
尚海
豆志周
刘鑫
杨光
黄超轶
吴叔于
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Zhonghangtian Construction Engineering Co Ltd
Original Assignee
Zhonghangtian Construction Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Zhonghangtian Construction Engineering Co Ltd filed Critical Zhonghangtian Construction Engineering Co Ltd
Priority to CN201611132441.2A priority Critical patent/CN106760492A/en
Publication of CN106760492A publication Critical patent/CN106760492A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G11/00Forms, shutterings, or falsework for making walls, floors, ceilings, or roofs
    • E04G11/36Forms, shutterings, or falsework for making walls, floors, ceilings, or roofs for floors, ceilings, or roofs of plane or curved surfaces end formpanels for floor shutterings
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B1/00Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
    • E04B1/62Insulation or other protection; Elements or use of specified material therefor
    • E04B1/66Sealings
    • E04B1/68Sealings of joints, e.g. expansion joints
    • E04B1/6801Fillings therefor

Abstract

A kind of one-shot forming post-cast strip concrete construction process is by when post-cast strip left and right sides major project concrete blinding is laid, one cuboid template is set, the Special controlling to the major project concrete moulding of the post-cast strip left and right sides is realized, the one-shot forming for realizing post-cast strip is then built by template and the special of scaffold.The beneficial effect of technical scheme of the present invention is:Using seven steps of the present invention, be capable of achieving one-shot forming post-cast strip concrete, it is to avoid the later stage needs to carry out the step of modification and treatment attractive in appearance to post-cast strip and major project concrete surface, with it is time saving and energy saving the characteristics of, the engineering time can be effectively saved, reduce construction cost.

Description

A kind of one-shot forming post-cast strip concrete construction process
Technical field
The present invention relates to a kind of building and architectural engineering construction technique, more particularly to the mould bases Construction of Supporting with post-cast strip Technique.
Background technology
Since reform and opening-up, especially since last decade, Chinese society economy is developed rapidly, and construction scale is increasingly grand, Structure type is more complicated various, particularly overlength, ultra-deep basement structure and high-rise main tower and low layer or multilayer annex phase The structure type of connection is a lot.In order to ensure the differential settlement between the globality and main group building of structure, design would generally be adopted Post-cast strip form is used, as the provisional movement joint of indwelling in cast-in-place integral reinforced concrete structure.Treat agent structure completion one In fixing time, after sedimentation is basicly stable, then post-cast strip is closed with slightly expanded concrete, structure is formed continuous entirety.
Existing form of construction work generally comprises two kinds:The first is main body concrete works template and post-cast strip concrete works Template holistic conformation;Second is that main body concrete works template and post-cast strip concrete works template are built respectively, pours master During body concrete, main body concrete works template is only built, after the maintenance of main body concrete works meets regulation, building post-cast strip Concrete works template.
That mode, post-cast strip concrete works template no matter is used to be required between building to main body concrete works side Face(That is two sides of post-cast strip concrete works)Coarse treatment of polishing is carried out, in the process, under main body concrete works Thus portion's flat appearance degree is caused to have poured post-cast strip concrete and is found main body concrete after removing alter-pouring strips mould plate by broken ring There is any excess concrete slurry stream in engineering bottom, and this needs to cut concrete by snap the line, is then beautified scraping cement mortar, such as The treatment of this later stage needs to spend substantial amounts of human and material resources and financial resources.
The content of the invention
The present invention is in view of the shortcomings of the prior art, it is proposed that a kind of one-shot forming post-cast strip concrete construction process, this is applied The application of work technique causes to beautify again after the completion of the concreting of post-cast strip, can effectively save the engineering time, reduces Construction cost.
A kind of one-shot forming post-cast strip concrete construction process of the present invention includes as follows:
Step one:Template is built using three-stage process
Build post-cast strip end template section, post-cast strip left side body engineering concrete bottom template section, post-cast strip respectively using three-stage process Right side body engineering concrete bottom template section;
Band both sides are poured respectively backward and extends 5 to 10 centimetres in the post-cast strip end template two ends;
The post-cast strip left side body engineering concrete bottom template and post-cast strip right side body engineering concrete bottom template are prolonged respectively Build post-cast strip end template both sides;
The post-cast strip end template, post-cast strip left side body engineering concrete bottom template, post-cast strip right side body engineering concrete End template is respectively adopted independent scaffold structural support;
Step 2:
Poured with after along post-cast strip end template and the seam of post-cast strip left side body engineering concrete bottom template, and post-cast strip end template Seam with right side body engineering concrete bottom template lays a cuboid template respectively;
The length of the cuboid template is equal to the post-cast strip end template and post-cast strip left side body engineering concrete bottom die The length of plate seam, is also equal to the length of post-cast strip end template and post-cast strip right side body engineering concrete bottom template seam; The width of the cuboid template 8 is twice of the post-cast strip end template one end to post-cast strip side development length, i.e., 10 to 20 lis Rice;The height of the cuboid template is 15 to 25 millimeters;
The cuboid template outer lateral side is in same plane with major project concrete side;
Step 3:Post-cast strip left side body engineering concrete blinding section and post-cast strip right side body engineering are built according to common process Concrete blinding section;
Step 4:To post-cast strip left side body engineering concrete and post-cast strip right side body engineering concreting and support Shield;
Step 5:After post-cast strip left side body engineering and post-cast strip right side body engineering concrete strength reach 5Mpa, first remove Remove the cuboid template in alter-pouring strips mould plate and template;Dabbing cleaning treatment is carried out to post-cast strip left and right sides construction joint, this step Alter-pouring strips mould plate is carried out into secondary formwork after the completion of work.
When post-cast strip end template is laid, post-cast strip end template width need to be completely covered post-cast strip left side body engineering coagulation Breach after soil, post-cast strip right side body engineering concrete end face cuboid form removable, and post-cast strip end template both sides are outside Respectively extend over 5 to 10 centimetres of major project concrete bottom;
In alter-pouring strips mould plate and major project concrete contact position, foam-rubber cushion is set;
Step 6:When design strength numerical value is reached to post-cast strip both sides major project concrete strength, by post-cast strip both sides master Body template is removed, only template at indwelling post-cast strip;
Step 7:After the post-cast strip technological requirement time reaches, post-cast strip inner concrete is poured;
Pour post-cast strip concrete and conserved, conserve rear i.e. dismountable post-cast strip concrete blinding up to standard.
The beneficial effect of technical scheme of the present invention is:Using seven steps of the present invention, you can realize once Shaping post-cast strip concrete, it is to avoid the later stage needs to carry out modification and place attractive in appearance to post-cast strip and major project concrete surface The step of reason, with it is time saving and energy saving the characteristics of, can effectively save the engineering time, reduce construction cost.
Brief description of the drawings
Pin hand in major project work progress in a kind of Fig. 1 one-shot forming post-cast strip concrete construction process of the present invention The schematic diagram of frame building structure;
Scaffold is built during post empiricism in a kind of Fig. 2 one-shot forming post-cast strip concrete construction process of the present invention The schematic diagram of structure;
In figure:1 post-cast strip left side body engineering concrete, 2 post-cast strip right side body engineering concrete, 3 post-cast strip left side bodies Engineering concrete sideform, 4 post-cast strip right side body engineering concrete sideforms, 5 post-cast strip left side body engineering concrete bottoms Template, 6 post-cast strip right side body engineering concrete bottom templates, 7 post-cast strip end templates, 8 cuboid templates, 9 scaffolds, 10 sponges Pad.
Specific embodiment
In order that those skilled in the art more fully understand technical scheme, with reference to specific embodiment to this Invention is described in further detail.
A kind of one-shot forming post-cast strip concrete construction process includes as follows:
As shown in figure 1, integrated engineering template is built using three-stage process, specially:
Build post-cast strip end template 7, post-cast strip left side body engineering concrete bottom template 5, post-cast strip respectively using three-stage process right Side major project concrete bottom template 6.
The post-cast strip end template two ends are poured band both sides and extend 5 to 10 centimetres respectively backward, even if post-cast strip end template spreads If to post-cast strip left side body engineering concrete 1, post-cast strip right side body engineering concrete 2.
The post-cast strip left side body engineering concrete bottom template 5 and post-cast strip right side body engineering concrete bottom template 6 Prolong the both sides of post-cast strip end template 7 respectively to build.
The post-cast strip end template 7, post-cast strip left side body engineering concrete bottom template 5, post-cast strip right side body engineering Concrete bottom template 6 is respectively adopted the structural support of independent scaffold 9.
Along post-cast strip end template 7 and the seam of post-cast strip left side body engineering concrete bottom template 5, and post-cast strip end template 7 lay a cuboid template 8 respectively with the seam of post-cast strip right side body engineering concrete bottom template 6.
The length of the cuboid template 8 is equal to the post-cast strip end template 7 and post-cast strip left side body engineering coagulation The length of the seam of native end template 5, is also equal to post-cast strip end template 7 and is connect with post-cast strip right side body engineering concrete bottom template 6 The length of seam;The width of the cuboid template 8 is twice of the one end of post-cast strip end template 7 to post-cast strip side development length, I.e. 10 to 20 centimetres;The height of the cuboid template 8 is 5 to 10 centimetres.
The outer lateral side of cuboid template 8 is in same plane with major project concrete side.
Post-cast strip left side body engineering concrete blinding and post-cast strip right side body engineering coagulation are built according to common process Clay model plate;Post-cast strip between post-cast strip left side body engineering concrete blinding and post-cast strip right side body engineering concrete blinding Left side body engineering concrete sideform 3,4 post-cast strip right side body engineering concrete sideforms pass through they sup-port, to protect Card concrete structural strength.
Post-cast strip left side body engineering concrete 1 and post-cast strip right side body engineering concrete 2 are poured and conserved.
Post-cast strip left side body engineering concrete 1 and post-cast strip right side body engineering concrete 2 conserve it is up to standard after, first remove Cuboid template at post-cast strip and in template carries out coarse treatment of polishing to post-cast strip both sides major project concrete surface.Treatment Finish and rear secondary install alter-pouring strips mould plate.
As shown in Fig. 2 building post-cast strip concrete blinding.Build scaffold and post-cast strip concrete blinding is set.After pour When band end template 7 is laid, post-cast strip end template width need to be completely covered post-cast strip left side body engineering concrete, post-cast strip right side Breach after major project concrete end face cuboid form removable, and post-cast strip end template both sides outwards respectively extend over main body 5 to 10 centimetres of engineering concrete bottom.In alter-pouring strips mould plate and major project concrete contact position, foam-rubber cushion 10 is set.After pouring Pour band concrete and conserved, conserve rear i.e. dismountable post-cast strip concrete blinding up to standard.
A kind of one-shot forming post-cast strip concrete construction process provided by the present invention is described in detail above, this Apply embodiment in text to be set forth the principle and implementation method of the application, the explanation of above example is only intended to side Assistant solves the present processes and its core concept;Simultaneously for those of ordinary skill in the art, according to the think of of the application Think, will change in specific embodiments and applications, in sum, it is right that this specification content should not be construed as The limitation of the application.

Claims (1)

1. a kind of one-shot forming post-cast strip concrete construction process, it is characterised in that the construction technology comprises the following steps:
Step one:Template is built using three-stage process
Build post-cast strip end template section, post-cast strip left side body engineering concrete bottom template section, post-cast strip respectively using three-stage process Right side body engineering concrete bottom template section;
Band both sides are poured respectively backward and extends 5 to 10 centimetres in the post-cast strip end template two ends;
The post-cast strip left side body engineering concrete bottom template and post-cast strip right side body engineering concrete bottom template are prolonged respectively Build post-cast strip end template both sides;
The post-cast strip end template, post-cast strip left side body engineering concrete bottom template, post-cast strip right side body engineering concrete End template is respectively adopted independent scaffold structural support;
Step 2:
Poured with after along post-cast strip end template and the seam of post-cast strip left side body engineering concrete bottom template, and post-cast strip end template Seam with right side body engineering concrete bottom template lays a cuboid template respectively;
The length of the cuboid template is equal to the post-cast strip end template and post-cast strip left side body engineering concrete bottom die The length of plate seam, is also equal to the length of post-cast strip end template and post-cast strip right side body engineering concrete bottom template seam; The width of the cuboid template is twice of the post-cast strip end template one end to post-cast strip side development length, i.e., 10 to 20 lis Rice;The height of the cuboid template is 15 to 25 millimeters;
The cuboid template outer lateral side is in same plane with major project concrete side;
Step 3:Post-cast strip left side body engineering concrete blinding section and post-cast strip right side body engineering are built according to common process Concrete blinding section;
Step 4:To post-cast strip left side body engineering concrete and post-cast strip right side body engineering concreting and support Shield;
Step 5:After post-cast strip left side body engineering and post-cast strip right side body engineering concrete strength reach 5Mpa, first remove Remove the cuboid template 8 in alter-pouring strips mould plate and template;Dabbing cleaning treatment is carried out to post-cast strip left and right sides construction joint, this step Alter-pouring strips mould plate is carried out into secondary formwork after the completion of work.
When post-cast strip end template is laid, post-cast strip end template width need to be completely covered post-cast strip left side body engineering concrete, after Pour and outwards respectively extend with the breach after right side body engineering concrete end face cuboid form removable, and post-cast strip end template both sides 5 to 10 centimetres of covering major project concrete bottom;
In alter-pouring strips mould plate and major project concrete contact position, foam-rubber cushion is set;
Step 6:When design strength numerical value is reached to post-cast strip both sides major project concrete strength, by post-cast strip both sides master Body template is removed, only template at indwelling post-cast strip;
Step 7:After the post-cast strip technological requirement time reaches, post-cast strip inner concrete is poured;
Pour post-cast strip concrete and conserved, conserve rear i.e. dismountable post-cast strip concrete blinding up to standard.
CN201611132441.2A 2016-12-09 2016-12-09 A kind of one-shot forming post-cast strip concrete construction process Pending CN106760492A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201611132441.2A CN106760492A (en) 2016-12-09 2016-12-09 A kind of one-shot forming post-cast strip concrete construction process

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201611132441.2A CN106760492A (en) 2016-12-09 2016-12-09 A kind of one-shot forming post-cast strip concrete construction process

Publications (1)

Publication Number Publication Date
CN106760492A true CN106760492A (en) 2017-05-31

Family

ID=58875784

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201611132441.2A Pending CN106760492A (en) 2016-12-09 2016-12-09 A kind of one-shot forming post-cast strip concrete construction process

Country Status (1)

Country Link
CN (1) CN106760492A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110359586A (en) * 2019-07-25 2019-10-22 华神建设集团有限公司 Late poured band structure and construction method

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH0525934A (en) * 1991-07-22 1993-02-02 Taisei Corp Construction method for pressure-proof concrete placing joint part
KR100875488B1 (en) * 2007-07-13 2008-12-22 김범준 Non-support form system and construction method using the same
CN101871262A (en) * 2010-06-25 2010-10-27 中天建设集团有限公司天津分公司 Method for constructing beam plate supporting system having post-cast strip
CN202850485U (en) * 2012-03-30 2013-04-03 江苏南通六建建设集团有限公司 A simple and practical building surface post-cast strip framework support system
CN205476458U (en) * 2016-01-29 2016-08-17 中国建筑第八工程局有限公司 Post -cast strip high formwork structure

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH0525934A (en) * 1991-07-22 1993-02-02 Taisei Corp Construction method for pressure-proof concrete placing joint part
KR100875488B1 (en) * 2007-07-13 2008-12-22 김범준 Non-support form system and construction method using the same
CN101871262A (en) * 2010-06-25 2010-10-27 中天建设集团有限公司天津分公司 Method for constructing beam plate supporting system having post-cast strip
CN202850485U (en) * 2012-03-30 2013-04-03 江苏南通六建建设集团有限公司 A simple and practical building surface post-cast strip framework support system
CN205476458U (en) * 2016-01-29 2016-08-17 中国建筑第八工程局有限公司 Post -cast strip high formwork structure

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110359586A (en) * 2019-07-25 2019-10-22 华神建设集团有限公司 Late poured band structure and construction method

Similar Documents

Publication Publication Date Title
CN105297982B (en) Laminated plate floor construction system and preparation method based on the prestress baseboard with truss
CN109403458A (en) Novel pre-fabricated one
CN101144328A (en) Construction method for after-pouring band beam-slab template
CN108638324A (en) A kind of construction method of prefabricated case beam
CN204343459U (en) The parapet node structure of overlaid plate type concrete shear wall system
CN103774561B (en) The job execution of speedway prefabricated small box girder frock method streamlined
CN102251674A (en) Bunker-skipping type seamless construction method of ultra-long concrete structure
CN108708394A (en) A kind of tunneling boring exempts from the overlapping assembled comprehensive pipe gallery structure and construction method of support
CN106968352A (en) Wall construction stitches construction method
CN109797969B (en) Construction method of post-cast strip tool type advanced formwork lifting system
CN201386392Y (en) Concrete hollow supporting body used for wall body construction technique
CN106760492A (en) A kind of one-shot forming post-cast strip concrete construction process
CN203270627U (en) Construction joint structure of shear wall
CN110042743A (en) The hydraulic climbing die block system of twin legged thin wall hollow pier with synchronize climb construction technology
CN208056338U (en) A kind of no mortar joint building-block insulated wall
CN203256930U (en) Connection structure for concrete wall body and masonry wall face
CN108589970A (en) The construction method of prefabricated window frame shear wall
CN210194695U (en) Double-wall waterproof structure is pour successively to underground building
CN210633836U (en) Grouting pipeline structure of prefabricated shear wall
CN114607140A (en) Concrete structure free of formwork construction and construction method
CN204112586U (en) A kind of building operations precast plate formwork
CN210766280U (en) Curb prefabricated assembly side form
CN207646941U (en) A kind of Constructional Col-umn Construction combination tool
CN205777491U (en) A kind of building body beam-column joint connecting structure
CN207513153U (en) The beam column cast-in-place node dedicated aluminium alloy template of assembly concrete frame structure

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
WD01 Invention patent application deemed withdrawn after publication

Application publication date: 20170531

WD01 Invention patent application deemed withdrawn after publication