CN106760069A - A kind of prefabricated board wall fixed installation technique and construction - Google Patents

A kind of prefabricated board wall fixed installation technique and construction Download PDF

Info

Publication number
CN106760069A
CN106760069A CN201710020709.1A CN201710020709A CN106760069A CN 106760069 A CN106760069 A CN 106760069A CN 201710020709 A CN201710020709 A CN 201710020709A CN 106760069 A CN106760069 A CN 106760069A
Authority
CN
China
Prior art keywords
board wall
groove
bolt
fixed installation
prefabricated
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201710020709.1A
Other languages
Chinese (zh)
Inventor
徐琳
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Nantong Textile Vocational Technology College
Original Assignee
Nantong Textile Vocational Technology College
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Nantong Textile Vocational Technology College filed Critical Nantong Textile Vocational Technology College
Priority to CN201710020709.1A priority Critical patent/CN106760069A/en
Publication of CN106760069A publication Critical patent/CN106760069A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B2/00Walls, e.g. partitions, for buildings; Wall construction with regard to insulation; Connections specially adapted to walls
    • E04B2/74Removable non-load-bearing partitions; Partitions with a free upper edge
    • E04B2/82Removable non-load-bearing partitions; Partitions with a free upper edge characterised by the manner in which edges are connected to the building; Means therefor; Special details of easily-removable partitions as far as related to the connection with other parts of the building
    • E04B2/821Connections between two opposed surfaces (i.e. floor and ceiling) by means of a device offering a restraining force acting in the plane of the partition

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Physics & Mathematics (AREA)
  • Electromagnetism (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Finishing Walls (AREA)

Abstract

The invention discloses a kind of prefabricated board wall fixed installation technique and construction, it is adaptable to which prefabricated assembled board wall is fixedly connected with building stratum.Mainly including prefabricated assembled board wall, building stratum, angle cleat with holes, split bolt, pre-embedded bolt, reserved groove etc..Prefabricated assembled board wall is concentrated by factory and made, reserved groove is held being connected with building stratum, equally, flooring and the prefabricated assembled board wall place of being connected also reserve groove, it is fixedly connected by split bolt, pre-embedded bolt with angle steel with holes, installation deviation is flexibly controlled with adjusting gasket.After installing, exposed groove is filled into covering in reserved groove cement mortar, complete fixed installation.The present invention is rational in infrastructure, and speed of application is fast, and installation accuracy is high, and in place, without repeatedly adjustment deviation, fixation is finished and covers connecting node using cement mortar achievable once mounting, and good concealment does not influence structure overall appearance.

Description

A kind of prefabricated board wall fixed installation technique and construction
Technical field
The present invention relates to a kind of board wall fixed installation technique, and in particular to a kind of prefabricated board wall fixed installation technique And construction.
Background technology
As new building technology and continuing to develop for material are widely used with progress, prefabrication. In the country that many building industrializations are flourishing, prefabrication experienced long-term experiment and application, modernization it is prefabricated Assembled architecture product can be with the various functions of highly integrated building, and the form and component of building are very exquisite.I State's construction demand amount is big, construction speed fast, necessary development prefabrication, then to prefabricated construction node Detailing requiments also more and more higher.
The content of the invention
Goal of the invention:The invention aims to solve deficiency of the prior art, there is provided a kind of reasonable in design, Speed of application is fast, and installation accuracy is high, and in place, without repeatedly adjustment deviation, fixation is finished and uses cement bonded sand achievable once mounting Slurry covering connecting node, good concealment, do not influence structure overall appearance a kind of prefabricated board wall fixedly mount technique and Construction.
Technical scheme:A kind of prefabricated board wall fixed installation technique of the present invention, comprises the following steps:
(1)Structure sheaf is constructed:Structure sheaf construction reserves groove and bolt embedment according to design requirement, and groove size uses 160mm × 160mm × 30mm, the deviation of pre-embedded bolt is not more than 2mm, and ensures that pre-embedded bolt top must not exceed the mark of structure surface layer It is high;
(2)Prefabricated assembled board wall factorial praluction:The size of reserved groove, the reserved groove in position Ying Yu buildings stratum are corresponding, And strictly controlling the deviation of pre-embedded bolt and split bolt, it is ensured that fixed angle steel can be easily installed;
(3)Transport, lifting:Transported from factory into lifting field process in board wall, the protection to sheet material groove should be strengthened, kept away Exempt to cause sheet material local damage because protection is improper, influence lifts quality with lifting speed;
(4)Fixed installation:High-strength bolt is selected in fixed installation;
(5)Groove is covered:Sealing groove is covered using mortar;
(6)Maintenance.
Further, step(4)Fixed installation should be greater than spiral shell from the high-strength bolt for being not less than M12, the size of bolt hole Bolt nominal diameter 2-3mm, bolt pitch of holes should be not more than 500mm.
Further, step(5)The mortar is using the cement mortar for being not less than M15.
The invention also discloses a kind of prefabricated board wall fixed installation construction, including assembled board wall, building stratum, company Angle steel, the reserved groove in building stratum, the reserved groove of board wall are connect, the reserved groove of the board wall is separately positioned on the two of assembled board wall Side, the reserved groove of board wall and the junction of the reserved groove in building stratum of both sides are connected by angle cleat, the assembling Formula board wall connects two angle cleats by split bolt, and the angle cleat is connected solid with building stratum by pre-embedded bolt simultaneously It is fixed.
Further, the small 3-5mm of depth of the length that the split bolt two ends are stretched out groove more reserved than board wall.
Further, the angle cleat and assembled board wall, building are equipped with adjusting gasket between stratum.
Further, the adjusting gasket uses rubber or steel plate washer.
Beneficial effect:The present invention is rational in infrastructure, and speed of application is fast, and installation accuracy is high, achievable once mounting in place, without Deviation is repeatedly adjusted, fixation is finished and covers connecting node using cement mortar, and good concealment does not influence structure overall appearance.
Brief description of the drawings
Fig. 1 is prefabricated board wall fixed installation organigram of the invention.
Specific embodiment
A kind of prefabricated board wall fixed installation construction as shown in Figure 1, including assembled board wall 1, building stratum 2, company Angle steel 3, the building stratum reserved groove 9 of reserved groove 6, board wall are connect, the reserved groove 9 of the board wall is separately positioned on assembled board wall 1 Both sides, the junction that the reserved groove 9 of the board wall of both sides reserves groove 6 with building stratum is connected by angle cleat 3, institute State assembled board wall 1 and two angle cleats 3 are connected by split bolt 4, the angle cleat 3 passes through pre-embedded bolt 5 and building simultaneously Stratum 2 is connected.
The small 3-5mm of depth of the length that the two ends of the split bolt 4 are stretched out groove 9 more reserved than board wall.
Adjusting gasket 7 is equipped between the angle cleat 3 and assembled board wall 1, building stratum 2, the adjusting gasket 7 is adopted With rubber or steel plate washer.
Prefabricated assembled board wall 1 is concentrated by factory and made, and the reserved groove in reserved building stratum is held being connected with building stratum 2 6, equally, the reserved groove 9 of board wall is also reserved on building stratum 2 with the place of being connected of prefabricated assembled board wall 1, with angle cleat with holes 3 are fixedly connected by split bolt 4, pre-embedded bolt 5, installation deviation are flexibly controlled with adjusting gasket 7, finally with nut 8 It is fixed.After installing, exposed groove is filled into covering with cement mortar at the reserved groove 6 in building stratum, complete fixed peace Dress.
Two ends set the reserved groove 6 in building stratum when the described bottom of prefabricated assembled board wall 1 is prefabricated in the factory, and are easily installed Fixed rear enclosed treatment;Corresponding groove is also left on the building stratum 2 when structure sheaf is constructed in advance, and pre- according to installation site Bury bolt 5;The angle cleat 3 with holes determines angle steel size according to the reserved size of groove 6 in building stratum, and meets design It is required that.
A kind of above-mentioned prefabricated board wall fixed installation technique, specifically includes following steps:
(4)Structure sheaf is constructed:Structure sheaf construction reserves groove and bolt embedment according to design requirement, and groove size uses 160mm × 160mm × 30mm, the deviation of pre-embedded bolt is not more than 2mm, and ensures that pre-embedded bolt top must not exceed the mark of structure surface layer It is high;
(5)Prefabricated assembled board wall factorial praluction:The size of reserved groove, the reserved groove in position Ying Yu buildings stratum are corresponding, And strictly controlling the deviation of pre-embedded bolt and split bolt, it is ensured that fixed angle steel can be easily installed;
(6)Transport, lifting:Transported from factory into lifting field process in board wall, the protection to sheet material groove should be strengthened, kept away Exempt to cause sheet material local damage because protection is improper, influence lifts quality with lifting speed;
(4)Fixed installation:High-strength bolt is selected in fixed installation;
(5)Groove is covered:Sealing groove is covered using mortar;
(6)Maintenance.
The present invention is rational in infrastructure, and speed of application is fast, and installation accuracy is high, and achievable once mounting in place, is adjusted without multiple Deviation, fixation is finished and covers connecting node using cement mortar, and good concealment does not influence structure overall appearance.
The above, is only presently preferred embodiments of the present invention, and any formal limitation is not made to the present invention, though So the present invention is disclosed above with preferred embodiment, but is not limited to the present invention, any to be familiar with this professional technology people Member, without departing from the scope of the present invention, when making a little change or modification using the technology contents of the disclosure above It is the Equivalent embodiments of equivalent variations, as long as being the content without departing from technical solution of the present invention, according to technical spirit of the invention Any simple modification, equivalent variations and the modification made to above example, still fall within the range of technical solution of the present invention.

Claims (7)

1. a kind of prefabricated board wall fixed installation technique, it is characterised in that:Comprise the following steps:
(1)Structure sheaf is constructed:Structure sheaf construction reserves groove and bolt embedment according to design requirement, and groove size uses 160mm × 160mm × 30mm, the deviation of pre-embedded bolt is not more than 2mm, and ensures that pre-embedded bolt top must not exceed the mark of structure surface layer It is high;
(2)Prefabricated assembled board wall factorial praluction:The size of reserved groove, the reserved groove in position Ying Yu buildings stratum are corresponding, And strictly controlling the deviation of pre-embedded bolt and split bolt, it is ensured that fixed angle steel can be easily installed;
(3)Transport, lifting:Transported from factory into lifting field process in board wall, the protection to sheet material groove should be strengthened, kept away Exempt to cause sheet material local damage because protection is improper, influence lifts quality with lifting speed;
(4)Fixed installation:High-strength bolt is selected in fixed installation;
(5)Groove is covered:Sealing groove is covered using mortar;
(6)Maintenance.
2. a kind of prefabricated board wall fixed installation technique according to claim 1, it is characterised in that:Step(4)Gu From the high-strength bolt for being not less than M12, the size of bolt hole should be greater than bolt diameter 2-3mm, bolt pitch of holes to Dingan County's dress No more than 500mm.
3. a kind of prefabricated board wall fixed installation technique according to claim 1, it is characterised in that:Step(5)Institute Mortar is stated using the cement mortar for being not less than M15.
4. a kind of prefabricated board wall fixed installation technique according to claim 1, it is characterised in that:A kind of dress Structure with the prefabricated board wall fixed installation of formula includes assembled board wall(1), building stratum(2), angle cleat(3), building stratum reserve Groove(6), the reserved groove of board wall(9), the board wall reserves groove(9)It is separately positioned on assembled board wall(1)Both sides, both sides The reserved groove of board wall(9)Groove is reserved with building stratum(6)Junction pass through angle cleat(3)It is connected, the dress With formula board wall(1)By split bolt(4)Connect two angle cleats(3), the angle cleat(3)Pass through pre-embedded bolt simultaneously (5)With building stratum(2)It is connected.
5. a kind of prefabricated board wall fixed installation technique according to claim 4, it is characterised in that:Described pair of drawing spiral shell Bolt(4)The length that two ends are stretched out reserves groove than board wall(9)The small 3-5mm of depth.
6. a kind of prefabricated board wall fixed installation technique according to claim 4, it is characterised in that:The joint angle Steel(3)With assembled board wall(1), building stratum(2)Between be equipped with adjusting gasket(7).
7. a kind of prefabricated board wall fixed installation technique according to claim 6, it is characterised in that:The spacer Piece(7)Using rubber or steel plate washer.
CN201710020709.1A 2017-01-12 2017-01-12 A kind of prefabricated board wall fixed installation technique and construction Pending CN106760069A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710020709.1A CN106760069A (en) 2017-01-12 2017-01-12 A kind of prefabricated board wall fixed installation technique and construction

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710020709.1A CN106760069A (en) 2017-01-12 2017-01-12 A kind of prefabricated board wall fixed installation technique and construction

Publications (1)

Publication Number Publication Date
CN106760069A true CN106760069A (en) 2017-05-31

Family

ID=58947824

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710020709.1A Pending CN106760069A (en) 2017-01-12 2017-01-12 A kind of prefabricated board wall fixed installation technique and construction

Country Status (1)

Country Link
CN (1) CN106760069A (en)

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108360564A (en) * 2018-04-17 2018-08-03 中国冶集团有限公司 A kind of foundation bolt fixes the piping lane port temporary plugging method of prefabricated board
CN108505538A (en) * 2018-04-17 2018-09-07 中国冶集团有限公司 A kind of city integrated piping lane temporary plugging method
CN108532627A (en) * 2018-04-17 2018-09-14 中国冶集团有限公司 A kind of bolt fixes the piping lane port temporary plugging method of prefabricated board
CN110241954A (en) * 2019-06-19 2019-09-17 江苏华特建筑装饰股份有限公司 Assembled architecture inner partition plate mounting assembly
CN110258808A (en) * 2019-05-31 2019-09-20 郑州航空工业管理学院 A kind of assembled architecture reinforcement assembly and assembled architecture
CN111519757A (en) * 2020-04-16 2020-08-11 闫旺升 Assembled concrete building connection structure
CN112282071A (en) * 2020-09-11 2021-01-29 中国建筑第八工程局有限公司 Mounting structure of external wall panel and construction method thereof

Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
SU1788173A1 (en) * 1990-03-22 1993-01-15 Ilya A Rokhlin Wall enclosure of framed building
DE29608828U1 (en) * 1996-05-17 1996-09-26 Moos Gerold Wall element
KR20110092934A (en) * 2010-02-11 2011-08-18 주식회사 극동피유테크 Insulation pad for supporting partitions at cold storage and method of building partitions using the pad
CN203174770U (en) * 2013-04-19 2013-09-04 深圳海龙建筑制品有限公司 Connection structure of prefabricated column and construction site base and building
EP2905393A1 (en) * 2014-02-05 2015-08-12 Zurecon AG Device for the subdivision of spaces and metal support
CN205063032U (en) * 2015-10-27 2016-03-02 文登蓝岛建筑工程有限公司 Wall connection node structure
CN205502243U (en) * 2016-03-04 2016-08-24 文登蓝岛建筑工程有限公司 Steel I -column with built -in fitting rigid coupling
CN106193328A (en) * 2016-08-25 2016-12-07 初明进 A kind of interlayer connection node

Patent Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
SU1788173A1 (en) * 1990-03-22 1993-01-15 Ilya A Rokhlin Wall enclosure of framed building
DE29608828U1 (en) * 1996-05-17 1996-09-26 Moos Gerold Wall element
KR20110092934A (en) * 2010-02-11 2011-08-18 주식회사 극동피유테크 Insulation pad for supporting partitions at cold storage and method of building partitions using the pad
CN203174770U (en) * 2013-04-19 2013-09-04 深圳海龙建筑制品有限公司 Connection structure of prefabricated column and construction site base and building
EP2905393A1 (en) * 2014-02-05 2015-08-12 Zurecon AG Device for the subdivision of spaces and metal support
CN205063032U (en) * 2015-10-27 2016-03-02 文登蓝岛建筑工程有限公司 Wall connection node structure
CN205502243U (en) * 2016-03-04 2016-08-24 文登蓝岛建筑工程有限公司 Steel I -column with built -in fitting rigid coupling
CN106193328A (en) * 2016-08-25 2016-12-07 初明进 A kind of interlayer connection node

Cited By (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108360564A (en) * 2018-04-17 2018-08-03 中国冶集团有限公司 A kind of foundation bolt fixes the piping lane port temporary plugging method of prefabricated board
CN108505538A (en) * 2018-04-17 2018-09-07 中国冶集团有限公司 A kind of city integrated piping lane temporary plugging method
CN108532627A (en) * 2018-04-17 2018-09-14 中国冶集团有限公司 A kind of bolt fixes the piping lane port temporary plugging method of prefabricated board
CN110258808A (en) * 2019-05-31 2019-09-20 郑州航空工业管理学院 A kind of assembled architecture reinforcement assembly and assembled architecture
CN110258808B (en) * 2019-05-31 2024-05-14 郑州航空工业管理学院 Assembly type building reinforcing component and assembly type building
CN110241954A (en) * 2019-06-19 2019-09-17 江苏华特建筑装饰股份有限公司 Assembled architecture inner partition plate mounting assembly
CN111519757A (en) * 2020-04-16 2020-08-11 闫旺升 Assembled concrete building connection structure
CN112282071A (en) * 2020-09-11 2021-01-29 中国建筑第八工程局有限公司 Mounting structure of external wall panel and construction method thereof

Similar Documents

Publication Publication Date Title
CN106760069A (en) A kind of prefabricated board wall fixed installation technique and construction
CN104060853B (en) Lightweight steel construction modularization house
CN205153114U (en) Lightweight steel structure modularized residential building
CN108824632A (en) A kind of prefabricated assembled bay window constructing structure of residential building and method
CN104153495A (en) Multifunctional lightweight concrete curtain wall connecting structure
CN206873673U (en) A kind of assembling type steel structure out-hung panel node
CN206468008U (en) Outer wall of basement one side formwork support system
CN206157955U (en) External connecting device of prefabricated wallboard
CN204001309U (en) A kind of syndeton of Multi-function light concrete curtain wall
CN207829207U (en) Steel construction assembled architecture unit combined wall
CN206916990U (en) Assembled cast-in-place concrete sandwiched thermal-insulating wall steel skeleton template system and connector
CN201474110U (en) Heat insulation system in compound heat insulation keel
CN204983237U (en) Framework composition outer wall system
CN205024843U (en) Joint construction of prestressing force hollow floor and H shaped steel roof beam
CN208996190U (en) A kind of profile steel house
WO2014117719A1 (en) Light composite floor slab
CN201099982Y (en) Rotating arc stairway joist assembly model
CN206448403U (en) Construction is fixedly mounted in a kind of prefabricated board wall
CN209082681U (en) A kind of prefabricated assembled bay window constructing structure of residential building
CN205063146U (en) Stiff and straight line furred ceiling turning structure of gypsum of preventing ftractureing
CN111809792B (en) Assembled precast concrete wallboard
CN210857779U (en) Assembled stair cladding structure
CN206512893U (en) A kind of prefabricated assembled board wall I-steel bolt joint construction
CN209457195U (en) A kind of outer waterproof inside holding Side fascia of half external hanging type
CN203821685U (en) Building component

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20170531

RJ01 Rejection of invention patent application after publication