CN106759294B - 钢筋混凝土灌注桩与充气预应力钢管桩结合的复合桩 - Google Patents
钢筋混凝土灌注桩与充气预应力钢管桩结合的复合桩 Download PDFInfo
- Publication number
- CN106759294B CN106759294B CN201710105810.7A CN201710105810A CN106759294B CN 106759294 B CN106759294 B CN 106759294B CN 201710105810 A CN201710105810 A CN 201710105810A CN 106759294 B CN106759294 B CN 106759294B
- Authority
- CN
- China
- Prior art keywords
- pile
- steel
- pipe
- reinforced concrete
- air
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D5/00—Bulkheads, piles, or other structural elements specially adapted to foundation engineering
- E02D5/22—Piles
- E02D5/34—Concrete or concrete-like piles cast in position ; Apparatus for making same
- E02D5/38—Concrete or concrete-like piles cast in position ; Apparatus for making same making by use of mould-pipes or other moulds
- E02D5/42—Concrete or concrete-like piles cast in position ; Apparatus for making same making by use of mould-pipes or other moulds by making use of pressure liquid or pressure gas for compacting the concrete
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D5/00—Bulkheads, piles, or other structural elements specially adapted to foundation engineering
- E02D5/66—Mould-pipes or other moulds
- E02D5/665—Mould-pipes or other moulds for making piles
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D2250/00—Production methods
- E02D2250/0007—Production methods using a mold
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D2250/00—Production methods
- E02D2250/0046—Production methods using prestressing techniques
Landscapes
- Engineering & Computer Science (AREA)
- Structural Engineering (AREA)
- Life Sciences & Earth Sciences (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Mining & Mineral Resources (AREA)
- Paleontology (AREA)
- Civil Engineering (AREA)
- General Engineering & Computer Science (AREA)
- Piles And Underground Anchors (AREA)
Abstract
Description
Claims (1)
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201710105810.7A CN106759294B (zh) | 2017-02-27 | 2017-02-27 | 钢筋混凝土灌注桩与充气预应力钢管桩结合的复合桩 |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201710105810.7A CN106759294B (zh) | 2017-02-27 | 2017-02-27 | 钢筋混凝土灌注桩与充气预应力钢管桩结合的复合桩 |
Publications (2)
Publication Number | Publication Date |
---|---|
CN106759294A CN106759294A (zh) | 2017-05-31 |
CN106759294B true CN106759294B (zh) | 2018-09-14 |
Family
ID=58960679
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201710105810.7A Active CN106759294B (zh) | 2017-02-27 | 2017-02-27 | 钢筋混凝土灌注桩与充气预应力钢管桩结合的复合桩 |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN106759294B (zh) |
Families Citing this family (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN113898174A (zh) * | 2021-02-13 | 2022-01-07 | 朱彦达 | 地下室管线管道减震结构 |
CN113981959A (zh) * | 2021-12-03 | 2022-01-28 | 中交第二航务工程勘察设计院有限公司 | 气囊式钻孔灌注空心桩结构及其施工方法 |
Family Cites Families (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN2517782Y (zh) * | 2002-01-15 | 2002-10-23 | 于陵 | 内部设置有内芯的砼建筑基桩 |
CN100363563C (zh) * | 2005-02-05 | 2008-01-23 | 王常青 | 钻孔预制复合桩的方法 |
CN201162224Y (zh) * | 2007-11-27 | 2008-12-10 | 贵阳铝镁设计研究院 | 钢桩桩顶锚固结构 |
KR20140001554A (ko) * | 2012-06-27 | 2014-01-07 | 반석기초이앤씨(주) | 로타리 파일의 강관 연결구조를 이용한 말뚝 시공 방법 |
CN104452749B (zh) * | 2014-11-17 | 2016-06-08 | 杭州江润科技有限公司 | 一种钢筋混凝土现浇管桩的施工方法 |
CN204570668U (zh) * | 2015-05-06 | 2015-08-19 | 上海航鼎建设工程有限公司 | 一种抗拔灌注桩结构 |
-
2017
- 2017-02-27 CN CN201710105810.7A patent/CN106759294B/zh active Active
Also Published As
Publication number | Publication date |
---|---|
CN106759294A (zh) | 2017-05-31 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN102383418B (zh) | 抗震型预制混凝土实心方桩及其生产方法 | |
CN106759294B (zh) | 钢筋混凝土灌注桩与充气预应力钢管桩结合的复合桩 | |
CN106836463A (zh) | 承台及地梁结构的施工装置和施工方法 | |
CN101761089B (zh) | 纤维筋混凝土抗拔桩 | |
CN104929278A (zh) | 一种装配式密柱空心剪力墙结构 | |
CN105604190A (zh) | 一种预制装配式气膜混凝土壳及其制作方法 | |
KR102158522B1 (ko) | Phc파일 제작용 거푸집을 활용한 고강도 원심성형 각형보의 제조장치 및 이에 의해 제조되는 원심성형 각형보 | |
CN100513704C (zh) | 工程改造用叠合桩的成桩方法 | |
CN106480878A (zh) | 一种上、下部扩大型水泥土复合管桩 | |
JP2018003361A (ja) | 可縮部材 | |
CN102839608B (zh) | 钢混叠合塔的叠合段施工方法 | |
CN107059843B (zh) | 一种充气预应力钢管桩及施工方法 | |
CN104264659A (zh) | 一种预制空心抗拔桩及其制备方法 | |
CN102561360B (zh) | 一种深基坑支护方法 | |
KR101196631B1 (ko) | 지반 개량 공법 | |
CN207829298U (zh) | 一种预制装配式内嵌钢套管连接混凝土柱 | |
CN207331709U (zh) | 深厚填土边坡的网状支挡结构 | |
CN106759272B (zh) | 一种混凝土护壁的充气预应力钢管桩 | |
CN104711979B (zh) | 一种水下桩柱加固自锁板及其加固方法 | |
CN106760213B (zh) | 碳纤维布预约束超高性能混凝土柱的制造方法 | |
CN106894411B (zh) | 一种液压预应力钢管桩 | |
CN212027206U (zh) | 一种高压弹性管内充填固化材料环向预应力加固的装置 | |
CN106638733A (zh) | 一种增设水平钢筋的风机基础加固方法 | |
Zhang et al. | A hydrostatic test study on the waterproofing of an underground ecological granary using a plastic-concrete system | |
CN106836324A (zh) | 一种增设斜向抗拉钢筋的风机基础加固方法 |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
TA01 | Transfer of patent application right | ||
TA01 | Transfer of patent application right |
Effective date of registration: 20180802 Address after: 448000 69 Jingmen Road, Dugao District, Jingmen high tech Zone, Jingmen, Hubei Applicant after: Hubei Zexin Energy Technology Co Ltd Address before: 448000 401 6 Hai Hui Road, Dongbao District, Jingmen, Hubei, 6 Applicant before: Jingmen Chuangjia Machinery Technology Co., Ltd. |
|
GR01 | Patent grant | ||
GR01 | Patent grant | ||
TR01 | Transfer of patent right | ||
TR01 | Transfer of patent right |
Effective date of registration: 20191227 Address after: 226200 west side of wucang port, Qidong Marine Industrial Park, Nantong City, Jiangsu Province Patentee after: Qidong Nihui New Material Technology Co., Ltd Address before: 448000 Hubei province Jingmen city Jingmen high tech Zone and Duodao District Road No. 69 Patentee before: Hubei Zexin Energy Technology Co Ltd |
|
PE01 | Entry into force of the registration of the contract for pledge of patent right | ||
PE01 | Entry into force of the registration of the contract for pledge of patent right |
Denomination of invention: Composite pile composed of reinforced concrete cast-in-place pile and aerated prestressed steel pipe pile Effective date of registration: 20220602 Granted publication date: 20180914 Pledgee: Bank of China Limited by Share Ltd. Qidong branch Pledgor: Qidong Nihui New Material Technology Co.,Ltd. Registration number: Y2022320010194 |